Nancy, Per my conversation this morning with Greg Allmon with AT&T they had planned to start boring in the new fiber line starting on Monday June 6th. However, as I explained to Greg this was not what we had agreed to in the meeting last Thursday nor in the onsite meeting that I had with him earlier in the week. NTC needs to have the sidewalk complete (poured and cured) prior to any work being performed by AT&T. NTC cannot afford to wait on any franchise utility as we are the only ones with LD’s if this job is not completed on time. Furthermore, AT&T said that the entire line will be bored so NTC will not be installing any sleeves under the sidewalk. I will know tomorrow what the schedule is for pouring the sidewalks as the Superintendent for Axis should be back on site. I told Greg to anticipate being able to perform his work at the end of next week and I will let you know what the actual date will be once I know. Let me know if you have any questions. Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com