Nancy/Clay, I have attached the latest version of change order 1.2 and 2.2. This should include pricing, as of now, for everything extra that has been added. Also, on the final contract days issue, I noticed that both change order 1.1 and 2.1 included sections that specified "Revised Contract time". Change order 1.1 for Spring Valley specified 277 Days and 2.1 specified 285 days. This might help prove our case that split schedules were the intention. We would still need to figure out how the bonus days for each project would be calculated. Please let me know if you have any questions or need anything else. Thank you, Michael Barbier, P.E. Civil Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-217-6643 Fax 214-739-0095 www.halff.com