Would whoever receives this first please send me a copy I could edit of the construction contract for Spring Valley? It is two pages. Someone wants me to add some information regarding the breakdown for DISD to it. Matt – I am trying to do this before you send contracts out to be signed. Thank you, Nancy From: Nancy Cline Sent: Tuesday, October 26, 2010 12:39 PM To: Lea Dunn; Tom Forrest Subject: Exhibit D Spring Valley Road Improvements.pdf - Adobe Reader Spring Valley : The breakdown for the amount owed by DISD is $1,079,317.81. This is the sum of one-half of 1A which is $760,222.19 and one-third of 1B which is $319,095.62. (see attached drawing) The one-third of 1B would be the same amount to be paid by UDR of $319,095.62. If you have any questions, please let me know. Thank you, Nancy