Michael, I checked the bid book and he is correct. However the bid tab shows 52. Could you let me know which is correct? Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Josh Hodsdon [mailto:josh@ntexcon.com] Sent: Friday, July 29, 2011 8:04 AM To: Clay Barnett Cc: 'Andy Nord' Subject: Pay Application item discrepancy Clay, Please review your spreadsheet and see if you have the correct quantity for item 1.88 – Drill shaft traffic pole (36 Inches). We have been using 52 in our SOV but the Bid Quantity was 60. I have made this change in our SOV so please let me know if you concur. We are working on finalizing the pay app so that I can review it with Dave, Eric and Wade and get it in your hands no later than Monday August 1st. The total contract value that you show on the pdf you sent for the second change orders also does not match the pay application you sent out last month. Once the quantity for item 1.88 is agreed upon everything will match between your pay application and our schedule of values. Let me know if you have any questions or comments. Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com