Nancy Please see the attached pricing for the temp asphalt change. Notice that this is an increase over the original bid item amount of approximately $70k. We have been giving some thought to not installing the temp asphalt and instead, paving the north lanes after we install the storm laterals. While there would be some cost increase on certain items to do that, it would overall save the town money. Please give me a call to discuss this as soon as you can so that we can get tomorrow scheduled with the placing of temp asphalt (or not if we choose not to do it). Thanks Andy Nord Cell: 817.819.4117 Email: anord@ntexcon.com From: Zach Fusilier [mailto:zfusilier@ntexcon.com] Sent: Tuesday, March 08, 2011 5:25 PM To: 'Josh Hodsdon' Cc: anord Subject: REVISED Zach Fusilier North Texas Contracting 4999 Keller Haslet Road Keller, Texas 76248 Office - 817-430-9500 Cell - 817-819-6691