Once the ROW is all in place, and contractor has barricades up, we should let ATMOS get going. This work probably needs to be coordinated with the contractor, also I have not seen any drawings for what they are proposing – has he sent them to you? From: Barbier, Michael Sent: Monday, November 01, 2010 2:52 PM To: Romanowski, Mike Subject: FW: Vitruvian Way and Spring Valley ________________________________ From: Woolsey, Gary [Gary.Woolsey@atmosenergy.com] Sent: Monday, November 01, 2010 9:32 AM To: Barbier, Michael; Joel Massey Cc: Kuhlmann, Rodney D Subject: Vitruvian Way and Spring Valley I have the final estimates in to set up a project and begin construction. When, do you expect to be ready to begin your constructions on Vitruvian and Spring Valley projects. I will be breaking into streets for tie-ins and breaking sidewalks so reasonably I don’t want to start way to early before you guys are ready. Let me know when you are ready to begin so I can let Rodney schedule our contractors. Thanks Gary Woolsey Sr Project Manager Atmos Energy Corporation 5420 LBJ Freeway Suite 1714A Dallas, Tx 75240 214-206-2717