Nancy, I left you a voicemail earlier today regarding the geotech lab for the Spring Valley project. I had spoken to Wade with Kleinfelder earlier today about picking up a proctor so that we can start with backfill activities this next week. Wade informed me that they have not received anything from the Town so they cannot pick up a proctor at this time. Is the Town using a different lab? Without a proctor NTC and its subcontractors cannot begin the backfill process. This is leaving both NTC and Inland exposed to a potentially bad situation with the open excavations along a busy street. The manhole at station 12+44 has already been placed and is ready for backfill. Please look into this hold up as this will have a major impact to our schedule if we cannot work due to this lapse. NTC cannot afford for this to delay the project nor can the Town. Please let me know the status of the situation so that I can schedule my subs accordingly. Thank you in advance for your prompt response. Regards, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com