Due to the storm event this week, Oncor Crews will not finis the removal of the poles and some incidental overhead construction and removals on the very east end of this project. We have removed the majority of the overhead lines and equipment off the wood structures. I understand that we have also picked up the materials that were removed Tuesday. The Oncor Crews plan to return next week to finish this project. Will this be a problem? If the pole located in the area of the storm drain connections is in the way, could you dig it up and move it out of your way? It has been cut off to about 10’ or so out of the ground. Let me know what we can do to maintain your schedule. Confidentiality Notice: This email message, including any attachments, contains or may contain confidential information intended only for the addressee. If you are not an intended recipient of this message, be advised that any reading, dissemination, forwarding, printing, copying or other use of this message or its attachments is strictly prohibited. If you have received this message in error, please notify the sender immediately by reply message and delete this email message and any attachments from your system.