Josh, When we switched out the water fountains in change order #1.2, I asked Andy to price the new one with the double check and meter that was needed. That is why the new item was called "Drinking Fountain and Associated Connection." If there are additional items that we need beyond this then we will need to change order that in. Michael Barbier, P.E. Civil Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-217-6643 Fax 214-739-0095 www.halff.com From: Josh Hodsdon [mailto:josh@ntexcon.com] Sent: Monday, August 29, 2011 7:16 AM To: Barnett, Clay; Cline, Nancy S.; Barbier, Michael Cc: 'Andy Nord' Subject: Additional water meter and backflow Clay, Dave mentioned the installation of a 1-inch water meter, a ½-inch double check, and cans for the drinking fountain. However, these are not called for on the plans. How would you like to proceed with the installation of these items? Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com