Zach,
I do not see any issues with this approach. Please send us the pricing for the bore once it is available.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Zach Fusilier [mailto:zfusilier@ntexcon.com]
Sent: Sunday, July 24, 2011 5:56 PM
To: Clay Barnett; 'Josh Hodsdon'
Cc: 'Eric T. Little'; 'Andy Nord'; Nancy Cline
Subject: RE: Approved June 2011 Pay Application
Clay,
After looking at placing the telephone drop at the same location with the other project it appears it will require a bore under the school approach. American requested a drop close
to the other end of the project which would have avoided the requirement for them to install the telephone conduit the entire length of Spring Valley. They requested a change order
for this which we received as they were able to install with other irrigation trenching operations. The only item of note is the bore under the existing approach since the Ratcliff
sleeves will not be a viable option. I have asked them to price the work, but NTC is trying to see if we can secure a directional drill subcontractor to install the sleeve asap since
American has had trouble getting a sub to perform the bore. We can probably install turnkey for $ 30 per foot or less, but wanted to let you know that we are moving forward with it.
Having the items together is probably a good thing for the town and we have had nothing but trouble trying to secure our own drop much less at the other end of the project. Let me
know if acceptable and we will formalize the price as soon as we know who is available. Should be a very minimal amount of money as they have agreed to forfeit all costs for the conduit
and telephone wiring for the entire distance. Thanks again.
Zach Fusilier
North Texas Contracting
Office - 817-430-9500
Cell - 817-819-6691
Email - zach@ntexcon.com
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Thursday, July 14, 2011 3:52 PM
To: 'Josh Hodsdon'
Cc: 'Eric T. Little'; 'Andy Nord'; 'Zach Fusilier'; Nancy Cline; David Wilde
Subject: RE: Approved June 2011 Pay Application
Josh,
The pay application is attached. I had to make a couple of revisions:
1. Item 1.154 – Reduced by 6. I believe these were counted before Change Order 1.2 and we found that there were 34. If there were indeed 40, then we will need to document it
and process another change order to add the other 6.
2. Item 2.15 – Reduced by 2000. The quantity in the original bid is 265, not 2265. If there was an overage, then we need to get it documented and change ordered in.
If you do not have any objections, please execute the pay application and return for payment. If you have any questions, please let me know.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Josh Hodsdon [mailto:josh@ntexcon.com]
Sent: Tuesday, July 12, 2011 3:38 PM
To: Clay Barnett; Nancy Cline; David Wilde
Cc: 'Eric T. Little'; 'Andy Nord'; 'Zach Fusilier'
Subject: Approved June 2011 Pay Application
Clay,
Please see the attached approved pay application for June 2011. This has been reviewed by both UDR and the Town. Please let me know if you have any questions or comments.
Thanks,
Josh Hodsdon
Project Manager
North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248
M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com