I’m ok with that, but I don’t think NTC will accept it. That being said, no reason we can’t present it to them. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Monday, June 27, 2011 1:10 PM To: Eric T. Little Cc: Nick Jacob; Nancy Cline Subject: Days on Spring Valley/Vitruvian Way Eric, I have a solution to the per day value issue on the Spring Valley/Vitruvian Way project, but Nancy wanted me to run it past you before I send it to North Texas. I was going to offer to pay the $3,000 per day they complete early on Spring Valley and then $500 per day they complete Vitruvian Way early. This correspondences with the daily value we have for the Bella project. My thought was that we never envisioned paying $3,000 per day for early completion of the parallel parking on Vitruvian Way, but would be open to paying $500 per day for early completion similar to Bella. Please let me know if you see any issues with this proposal. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 ************************************************************ This e-mail and any files or attachments transmitted with it contain Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. ************************************************************