Josh, That time works for me as long as you believe that everything on the walkthrough list will be completed by then. Here is the list again just to make sure we are on the same page. 1. Striping- Install all proposed and remove all temporary/existing from Spring Valley within project limits 2. Concrete- Complete all sections (driveways, intersection, etc.) along Spring Valley, driveway half that was poured incorrectly should be redone 3. Pavers- All vehicular pavers at the Vitruvian intersection should be in place, ensure that pavers do not inhibit flow of drainage 4. Signs- All proposed signing should be in place and operational along Spring Valley, all unnecessary temporary signs removed 5. Backfill all medians along Spring Valley 6. All joints should be sealed and finished. Several joints at the Vitruvian intersection need to be redone 7. All median noses should match detail on sheet 22 which shows a 6" to 3" taper down (this item can be completed after the deadline but is still very critical) 8. All lanes (2-each direction) should be open on Spring Valley, Vitruvian must have 1 lane each direction 9. Vitruvian intersection can still be four way stop sign controlled 10. Short term one lane closures on Spring Valley will still be allowed to complete work in the medians Michael Barbier, P.E. Civil Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-217-6643 Fax 214-739-0095 www.halff.com From: Josh Hodsdon [mailto:josh@ntexcon.com] Sent: Friday, July 15, 2011 8:00 AM To: Barbier, Michael; Barnett, Clay Cc: 'Andy Nord'; 'Zach Fusilier' Subject: Final walkthrough Michael, I would like to walk the Spring Valley portion of the job this morning at 11:30. Please let me know if this will work. Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com