I talked with Ronnie Free and he was going to get with Jeff Graves and the Distribution Operations Tech to schedule the switch-over. I will find out tomorrow when the switchover from overhead to underground will be made. Ronnie thought ot might be Monday but I will try to have a firm schedule tomorrow. ________________________________ From: Josh Hodsdon [mailto:josh@ntexcon.com] Sent: Wed 5/4/2011 4:04 PM To: Baldwin, Larry Cc: 'Nancy Cline'; 'Clay Barnett'; 'Andy Nord' Subject: Oncor Schedule Larry, I am being told in the field that Will Bros. will be finished with their work by the end of the day today. After speaking with Ronnie, it sounds like there is some internal scheduling that needs to take place before the underground cables can be energized and the overhead cables and poles taken down. Can you please provide me with a finish schedule for your work on Spring Valley. I have critical path items that need to take place once your work is complete and subs that need to be scheduled. Please let me know as soon as you can and I would also like to discuss this work in the meeting tomorrow with the Town. Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com Confidentiality Notice: This email message, including any attachments, contains or may contain confidential information intended only for the addressee. If you are not an intended recipient of this message, be advised that any reading, dissemination, forwarding, printing, copying or other use of this message or its attachments is strictly prohibited. If you have received this message in error, please notify the sender immediately by reply message and delete this email message and any attachments from your system.