Josh,
This assumes that additional time will not be requested for the additional white buttons that we have been discussing. Also, Brandon Graham is going to conduct an in-depth inspection
of all of the thermoplastic and bring us a map of the areas that need to be replaced. The thermoplastic repair on those areas needs to be completed at the same time.
If you have any questions, please let me know.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Josh Hodsdon [mailto:josh@ntexcon.com]
Sent: Thursday, August 18, 2011 1:24 PM
To: Clay Barnett; Nancy Cline; 'Barbier, Michael'
Cc: 'Andy Nord'
Subject: Striping work
Clay,
As discussed in our meeting this morning, all of the remaining striping and button work will no longer be part of the incentive completion date due to cleaning of the parking lots and
concrete flatwork this weekend at the school. However, NTC will get this work done in a timely manner with cooperation from the school irrigator as well as American and the school operations.
I anticipate this work being complete by the end of next week and I will let you know when it is scheduled.
Thanks,
Josh Hodsdon
Project Manager
North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248
M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com