Nancy, I met with our paving subcontractor this afternoon and it looks like we will need to take a good hard look at the possibility of shutting Spring Valley down to just one lane of east bound traffic for the duration of the concrete paving work. The track and “guide string” will need to be placed on the west bound lane and an additional 2-feet of concrete paving will need to be removed. This will only leave us with 20-feet of width for two lanes of traffic. Can you please review this over the weekend and on Monday to determine if this is really a viable option so that I can make some arrangements for saw-cutting and barricades. I think the only major concern is with the fire department but please let us know. Thanks, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com