Nancy Attached is the change order for doing the paving operation being moved up into phase one for the north side of Spring Valley. We have incorporated the changes that we talk about in the meeting a few weeks ago. Please also note that we have included in this pricing 165 tons of flex base that was used for temp paving around / in driveways and block outs. We used flex base in those locations as it was quicker and easier than asphalt and since it was for such a short time with smaller amounts of traffic, full depth asphalt was not needed. One last thing is that the quantity of temp asphalt that NTC is removing from the contract is a little less than originally thought due to the fact that we have installed just short of 300 SY at this point. Thanks and please give me a call if you have any questions on this as I know I can ramble a little in my emails. Andy Andrew D. Nord North Texas Contracting | Estimator 4999 Keller Haslet Rd. Keller, TX 76248 Phone: 817.430.9500 Fax: 817.430.9207 Cell: 817.819.4117