Good Morning, In the weekly project meeting on June 2nd, we discussed a clarification of special provision 22.1 for contractor incentive on Spring Valley Road. The provision states that the contractor must " Reach a level of substantial completion so that all proposed travel lanes are permanently open to the public no later than July 15th 2011." After discussion, this clarification was agreed upon. - All Spring Valley Road lanes shall be substantially complete and open to traffic to include all permanent paving, vehicular pavers, striping, signing, and driveways. - The intersection of Spring Valley and Vitruvian Way shall be in the final proposed configuration with at least one lane open to traffic in each direction on Vitruvian Way. - It is acceptable for the intersection to be in a non signalized four way stop controlled configuration for this deadline. The contractor shall maintain all necessary temporary traffic control devices to navigate the intersection until the signal is functional. - Completion of this requirement will be subject to inspection and approval by the Town of Addison. Please inform me of any changes or additions to this clarification before 8:00 AM Thursday June 9th 2011. Sincerely, Michael Barbier, P.E. Civil Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-217-6643 Fax 214-739-0095 www.halff.com