I’m meeting with Oncor tomorrow. I’ll verify their requirements this morning. Thanks, Eric From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Thursday, February 24, 2011 8:11 AM To: Clay Barnett Cc: Joel Massey; Eric T. Little Subject: RE: Bella Lane To my knowledge, Oncor has no requirements that the contractor be pre-qualified to install the duct bank. Their requirements and specifications, which include approval of the materials to be used and the right to inspect the work, is listed in the duct bank notes shown on Sheet 35 of the drawings. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Wednesday, February 23, 2011 6:22 PM To: Bruce Dunne Cc: Joel Massey; 'Eric Little (elittle@udr.com)' Subject: Bella Lane Bruce, Could you send the section from the spec book that requires that the contractor be qualified by Oncor to install the duct bank? Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 ****************************************************************************************************************** This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. *******************************************************************************************************************