Joel, I went ahead and reviewed the change order. The only item I noticed was that it shows removing 13lf more than what remains in the contract for Item 90. If it is agreed that this was overpaid, we can deduct it on the next pay application. Please send over the final CO when it is ready. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Tuesday, June 28, 2011 12:05 PM To: Clay Barnett Cc: Eric T. Little; Bruce Dunne Subject: RE: Bella Lane - Change Order #1 Clay, I believe we will have an additional item for the Bella Lane CO 1. We are going to need to add some 2” electric conduit for a revised electric service route. I am confirming the route with Oncor Electric Delivery. I will let you know as soon as I know. Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com From: Bruce Dunne Sent: Monday, June 27, 2011 8:11 AM To: 'Clay Barnett' Cc: 'Eric T. Little'; Joel Massey Subject: Bella Lane - Change Order #1 Attached is Change Order No. 1 for CPS Civil. Please review and give me your comments. I wasn’t sure on the date of the contract so please check that. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711