>> Leave comment << Response to RFI No. 2 As of 27-Apr-2011 9:17 AM CT Vitruvian Infrastructure Phase 2A - Bella Lane 3900 Vitruvian Way Addison, Texas 75001 Project Number: 1308 - 2A Status: Outstanding Overdue Subject off site soil disposal Reason Code None Question Cost impact of off site haul of exc ess materials Proposed Solution See attached pricing Attached Files EXCESS MATERIALS CHANGE ORDER.pdf Section: 2 - Sitework Int. Tracking #: Days Elapsed: 8 From: Robert Farrow Originated: 19-Apr-2011 4:34 PM CT To: Eric Little (First Recipient) Requested By: 26-Apr-2011 12:00 AM CT (Original 26-Apr-2011 4:28 PM CT) Copy to: Lauren Williams Joel Massey Nick Jacob Scott Hale Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Cost Increase of US $12,599 Time Change: Increase of 2 days Discipline Code: N/A Drawing Numbers: Needs Drawing Change? Yes History (Chronological Order) Type Routed Billable n/a Memo Clay - please take a look at the attached change request for Bella. This is a result of our direction yesterday to remove all excess spoils from the site. ICON and I will review the pricing as well. Thanks, Attached Files (none) From: Eric Little Sent: 20-Apr-2011 8:11 AM CT To: Clay Barnett Requested By: 26-Apr-2011 4:28 PM CT Copy to: Lauren Williams Joel Massey Nick Jacob Scott Hale Robert Farrow Type Response Billable n/a Memo Additional fill may be needed in other areas in the southeast portion of Vitruvian Park. We will not know until our survey work comes in in a few days. I also need time to review the previous RFI concerning the dirt work. The original topo survey was done in 2007. We did new cross sections of Bella Lane on the day of the Pre-construction meeting. I will review the two new surveys to make sure we are on the same page. Attached Files (none) From: Joel Massey Sent: 20-Apr-2011 8:28 AM CT To: Eric Little Requested By: 26-Apr-2011 12:00 AM CT Copy to: Lauren Williams Nick Jacob Scott Hale Robert Farrow Bruce Dunne Clay Barnett Type Routed Billable n/a Memo Please give us some direction when you get the results of the new survey. Attached Files (none) From: Eric Little Sent: 27-Apr-2011 8:19 AM CT To: Joel Massey Requested By: 26-Apr-2011 12:00 AM CT Copy to: (none) Type Response Billable n/a Memo The survey of the fill area south of the park indicates, we do not need any more dirt, however, since the contract was setup to accept excess material, I recommend we identify a location(s) for CPSCivil to "place" (scarify, place & compact) any excess material. This work will need to be coordinated with what NTC will be required to do to complete the park excavation and placement work. We will need to have a site visit and a decision for the completion of the NTC dirt work scope before a location for CPSCivil can be identified. We will provide a grading plan for the placement area(s). I have reviewed the two surveys (our's & Hudson's) and responded to RFI #3 that we are different. I requested bench mark information under RFI #3. This is pertinent to this RFI only if haul-off is chosen and additional costs are to be determined. Attached Files (none) From: Joel Massey Sent: 27-Apr-2011 9:17 AM CT To: Eric Little Requested By: 26-Apr-2011 12:00 AM CT Copy to: Lauren Williams Joel Massey Nick Jacob Scott Hale Robert Farrow Bruce Dunne Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software