Special comments by author: The updated schedule has been uploaded to PM. Thanks, Eric Schedule Task List For Construction As of 03-Jun-2011 07:48 AM CT Vitruvian Infrastructure Phase 2A - Bella Lane 3900 Vitruvian Way Addison, Texas 75001 Project Number: 1308 - 2A # WBS Description Duration Start Finish %Complete Pred. 1 1 VITRUVIAN PHASE 2 175 CALENDAR DAYS 102d 18-Apr-2011 06-Sep-2011 53% 2 1.1 PRECONSTRUCTION ITEMS 6d 18-Apr-2011 25-Apr-2011 100% 3 1.2 PRECONSTRUCTION MEETING 1d 18-Apr-2011 18-Apr-2011 100% 4 1.3 SWPPP PAPERWORK 1d 18-Apr-2011 18-Apr-2011 100% 5 1.4 TRENCH SAFETY PLAN 1d 18-Apr-2011 18-Apr-2011 100% 6 1.5 LINE LOCATES 3d 18-Apr-2011 20-Apr-2011 100% 7 1.6 INSTALL SILT FENCING AND CON ENTRANCE 2d 21-Apr-2011 22-Apr-2011 100% 6 8 1.7 INITIAL DUCT BANK STAKING 1d 21-Apr-2011 21-Apr-2011 100% 6 9 1.8 PLACE DUCT BANK 20d 22-Apr-2011 19-May-2011 100% 10 1.8.1 EXCAVATE & PLACE MHOLE STA 24+57 2d 22-Apr-2011 25-Apr-2011 100% 8 11 1.8.2 EXCAVATE TIE LOCATION STA 20+69 ET-D 1d 26-Apr-2011 26-Apr-2011 100% 10 12 1.8.3 PLACE MHOLE STA 20+85 ET-D 1d 27-Apr-2011 27-Apr-2011 100% 11 13 1.8.4 PLACE DUCT ET-D 5d 28-Apr-2011 04-May-2011 100% 12 14 1.8.5 CONSTRUCT LATS ET-D 1d 05-May-2011 05-May-2011 100% 13 15 1.8.6 CONSTRUCT DUCT E-E 2d 06-May-2011 09-May-2011 100% 14 16 1.8.7 CONSTRUCT DUCT E-F 2d 10-May-2011 11-May-2011 100% 15 17 1.8.8 CONSTRUCT MHOLE E-G STA 0+75 1d 12-May-2011 12-May-2011 100% 16 18 1.8.9 CONSTRUCT DUCT E-G 5d 13-May-2011 19-May-2011 100% 17 20 1.9 PLACE SANITARY SEWER 6d 26-May-2011 02-Jun-2011 100% 21 1.9.1 ORDER SAN SEWER MATS 1d 26-May-2011 26-May-2011 100% 9 22 1.9.2 LAYOUT SANITARY 1d 26-May-2011 26-May-2011 100% 21 23 1.9.3 EXPOSE SSB2 STA 1+00 1d 27-May-2011 27-May-2011 100% 21 24 1.9.4 CONSTRUCT LINE SS2 1d 30-May-2011 30-May-2011 100% 23 25 1.9.5 CONSTRUCT LATERALS 1d 31-May-2011 31-May-2011 100% 24 26 1.9.6 CONSTRUCT MANHOLES 2d 30-May-2011 31-May-2011 100% 25 27 1.9.7 PRESSURE TEST AND VACUUM TEST 1d 01-Jun-2011 01-Jun-2011 100% 26 28 1.9.8 BACKFILL MANHOLES 1d 02-Jun-2011 02-Jun-2011 100% 27 30 1.10 PLACE STORM 9d 01-Jun-2011 13-Jun-2011 15% 31 1.10.1 ORDER STORM MATS 1d 01-Jun-2011 01-Jun-2011 100% 20 32 1.10.2 LAYOUT STORM 1d 02-Jun-2011 02-Jun-2011 100% 31 33 1.10.3 EXPOSE EX COND SD-A4 1d 03-Jun-2011 03-Jun-2011 0% 32 34 1.10.4 PLACE LINE SD A-4 AND LATS 2d 03-Jun-2011 06-Jun-2011 0% 33 35 1.10.5 PLACE MHOLE STA 1+00 SD A-4 1d 06-Jun-2011 06-Jun-2011 0% 34 36 1.10.6 EXPOSE EX COND SDC7 STA 0+61 1d 07-Jun-2011 07-Jun-2011 0% 35 37 1.10.7 CONSTRUCT SD-C7 STA 0+61-1+38 1d 07-Jun-2011 07-Jun-2011 0% 36 38 1.10.8 PLACE MHOLE STA 1+38 1d 08-Jun-2011 08-Jun-2011 0% 37 39 1.10.9 CONSTR. SD-C7 TO STA 4+11 2d 08-Jun-2011 09-Jun-2011 0% 38 40 1.10.10 PLACE MHOLE STA 4+11 1d 10-Jun-2011 10-Jun-2011 0% 39 41 1.10.11 CONSTRUCT LATS 2d 10-Jun-2011 13-Jun-2011 0% 40 42 1.10.12 CONSTRUCT INLET BOTTOMS 3d 08-Jun-2011 10-Jun-2011 0% 38 43 1.10.13 POUR INVERTS 2d 10-Jun-2011 13-Jun-2011 0% 40, 42 44 1.11 PLACE WATER 10d 13-Jun-2011 24-Jun-2011 0% 45 1.11.1 ORDER WATER MATS 2d 13-Jun-2011 14-Jun-2011 0% 30 46 1.11.2 LAYOUT WATER 2d 13-Jun-2011 14-Jun-2011 0% 30 47 1.11.3 EXPOSE EX COND STA 20+24 1d 13-Jun-2011 13-Jun-2011 0% 30 48 1.11.4 PLACE 10" LINETO STA 28+20 3d 13-Jun-2011 15-Jun-2011 0% 47 49 1.11.5 EXPOSE EX CASING 2d 15-Jun-2011 16-Jun-2011 0% 48 50 1.11.6 PUSH PIPE STA 30+10 TO STA 28+24 1d 16-Jun-2011 16-Jun-2011 0% 49 51 1.11.7 PLACE 10" STA 30+10 TO 31+84 2d 16-Jun-2011 17-Jun-2011 0% 50 52 1.11.8 PLACE LATS TO STA 20+24 3d 15-Jun-2011 17-Jun-2011 0% 48 53 1.11.9 PLACE HYDRANTS TO STA 20+24 1d 17-Jun-2011 17-Jun-2011 0% 52 54 1.11.10 PLACE LATS Sta 30+10 to 31+84 2d 17-Jun-2011 20-Jun-2011 0% 51 55 1.11.11 PRE-TEST 2d 20-Jun-2011 21-Jun-2011 0% 51, 52, 53, 54 56 1.11.12 TEST 2d 21-Jun-2011 22-Jun-2011 0% 55 57 1.11.13 CHLORINATE 3d 22-Jun-2011 24-Jun-2011 0% 56 58 1.12 PLACE ELECTRICAL CONDUIT ROUGH 16d 24-Jun-2011 15-Jul-2011 0% 59 1.12.1 LAYOUT ELECT 2d 24-Jun-2011 27-Jun-2011 0% 44 60 1.12.2 PLACE CONDUITS 7d 24-Jun-2011 04-Jul-2011 0% 44 61 1.12.3 PLACE LIGHT POLE BASES 8d 04-Jul-2011 13-Jul-2011 0% 60 62 1.12.4 ROUGH ELECTRICAL PANEL 3d 13-Jul-2011 15-Jul-2011 0% 61 63 1.13 DEMO ROUGH GRADING 2d 15-Jul-2011 18-Jul-2011 0% 64 1.13.1 STAKE CUT FILL 2d 15-Jul-2011 18-Jul-2011 0% 62 65 1.13.2 PLACE IRRIGATION SLEEVES 2d 15-Jul-2011 18-Jul-2011 0% 62 66 1.14 PAVING 26d 18-Jul-2011 22-Aug-2011 0% 67 1.14.1 LIME STABILIZE SUBGRADE 6d 18-Jul-2011 25-Jul-2011 0% 65 68 1.14.2 CONCRETE PAVE BELLE LANE 11d 25-Jul-2011 08-Aug-2011 0% 67 69 1.14.3 UTILITY FINISH OUT 6d 08-Aug-2011 15-Aug-2011 0% 68 70 1.14.4 ELECTRICAL FINISH OUT 6d 08-Aug-2011 15-Aug-2011 0% 68 71 1.14.5 INSTALL PAVERS 6d 08-Aug-2011 15-Aug-2011 0% 68 72 1.14.6 PLACE FLEXBASE FOR ASPHALT 4d 15-Aug-2011 18-Aug-2011 0% 71 73 1.14.7 PAVE ASPHALT TURN AROUND 3d 18-Aug-2011 22-Aug-2011 0% 72 74 1.15 LANDSCAPE 4d 22-Aug-2011 25-Aug-2011 0% 73 75 1.16 STRIPING PAVING MARKING SIGNAGE 4d 25-Aug-2011 30-Aug-2011 0% 74 76 1.17 PUNCH SELL 6d 30-Aug-2011 06-Sep-2011 0% 75 Show records by page .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software