Clay, My comments are below. Sheet 8 – Utility & Storm Sewer Plan Fire hydrant and bollards appear to be located inside the 24’ wide striped fire lane on the east side of the building. Sheet 9 – Utility Plan Revise the orifice opening to 14.5” to match the calculations. Chris Robinson, P.E. Grantham & Associates 6570 Naaman Forest Blvd. Suite #200, LB 2 Garland, TX 75044 972-864-2333 ext. 121 972-342-5351 cell 972-864-2334 fax From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Wednesday, February 23, 2011 9:46 AM To: 'Lynn Kadleck' Cc: Bill Leggett; Chris Robinson; Frank O. McIllwain Subject: RE: Million Air Phase 2 Lynn, Attached is the documents you forwarded with the plan submittal received yesterday afternoon. We will review the plan submittal and return comments today as was agreed to in our meeting at the first of the year. In regards to the pavement design, the geotechnical report provides a pavement section that was performed utilizing the FAARFIELD software and is in accordance with FAA Advisory Circular 150/5320-6E. The geotechnical report recommends a 9” pavement section over a 10” base. The letter that was received recommends a 7” pavement section over a 6” base. Additionally, the letter does not address anticipated aircraft loads nor does it address expected life spans. Finally, it does not state what standards were used to design the pavement section. I have attached a recap of our conversation on January 25, 2011 in which we discuss the importance of utilizing the FAA Advisory Circular for civil Airport paving guidelines and standards in the design of optional ramp paving specifications. In the absence of any additional data, the pavement design provided in the geotechnical report shall be utilized for the ramp area pavement. It is our goal to continue to work with you to make this a successful project. If you have any questions, please feel free to contact me. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Lynn Kadleck [mailto:lkadleck@verizon.net] Sent: Wednesday, February 23, 2011 7:08 AM To: Clay Barnett Subject: Million Air Phase 2 Clay, I noticed a couple of drafting items that did not get changed on the drainage area map (inlets numbers) and storm sewer profile (some of the HG numbers and the detention outlet opening size). I am having new Sheets 4 and 9 sent to you this morning to replace the ones in the sets sent yesterday. They should be there by 9:00 AM. Sorry about that. Please call with any questions. Regards, L. Lynn Kadleck, PE, RPLS Kadleck & Associates 555 Republic Drive, Suite 115 Plano, Texas 75074 972-881-0771 lkadleck@verizon.net