Nick, I have talked through everything with Clay and here is what we worked out and still need so we can start Ponte: NTC Items: Impact Fees & ROW Permit Fee - Reviewed all taps and fees, total is $ 1,210 which NTC will cut and bring to Pre-con, UDR to reimburse without mark up. Pre-Con - first available date with Clay's Friday vacation and Monday holiday is Tuesday morning. Clay will schedule exact time and let us know asap. UDR / Icon Items: SWPPP information needs to be conveyed to Clay as I told him we worked out, but please give him exact information Proof of TDLR submission Clay needs a copy of our contract that shows the line items and totals 5 sets of plans for City need to be brought to pre-con If we do this we can start Tuesday morning. Thanks and please let me know. Zach Fusilier North Texas Contracting Office - 817-430-9500 Cell - 817-819-6691 Email - zach@ntexcon.com From: Nick Jacob [mailto:PJacob@udr.com] Sent: Friday, August 26, 2011 8:18 AM To: Zach Fusilier; 'Clay Barnett' Cc: 'Jamie Voris'; Deiadra Burns; Tom Lamberth; anord Subject: RE: Ponte Until we get some items flushed out I cannot give you an accurate start date. I would think we are a week to two weeks out. Items we need to discuss how to handle are: · New SWPPP · ROW permit · Impact Fees · 5 sets of plans from ICON · Precon meeting