DWU -Farmers Branch 16" Water Line Interconnect Town of Addison, Texas Engineer's Opinion of Probable Cost Item No. Item Description Units Quantity Unit Cost Total Cost 1 Mobilization LS 1 $15,000.00 $ 15,000.00 16" Concrete Cylinder Pipe, including 2 appurtenances and necessary excavation and backfill, complete and in place LF 20 $ 125.00 $ 2.500.00 3 Concrete Thrust Blocking CY 2 $ 150.00 $ 300.00 4 60" x 16" Saddle & Service (per Hanson) EA 1 $ 9,560.00 $ 9,560.00 5 18" x 16" Saddle & Service (per Hanson) EA 1 $ 4,390.00 $ 4,390.00 6 16" Tappina Valve, complete and in place EA 2 $ 5,000.00 $ 10,000.00 10" Reinforced Concrete Paving Remove I 7 Replace, including subgrade preparation, complete and in place SY 30 $ 70.00 $ 2,100.00 8 Erosion Control LS 1 $ 1,000.00 $ 1,000.00 9 Traffic Control Plan preparation and implementation LS 1 $ 8,000.00 $ 8,000.00 10 Trench Safety Design and Implementation LS 1 $ 2,000.00 $ 2,000.00 11 Sod SY 30 $ 15.00 $ 450.00 Sub-Total $ 55,300.00 10% Contingency $ 5,530.00 Total Total Bid $ 60,830.00 OWU -Farmers Branch 16" Water Line Interconnect Town of Addison, Texas Dam: February 4. 2005 Senior Vice President Item No. Item DescrlDtion Units Quantitv Unit Cost Total Cost 1 Mobilization LS 1 $8.a:XUV 􀁾􀀮􀁦􀀮􀁘􀀧􀀩 2 16" Concrete Cylinder Pipe, including appurtenances and necessary excavation and backfill, comolete and in olace LF 20 $1,.()(lJ. tb $a2lhO.a> 3 Concrete Thrust Blockina CY 2 $2SO,l1':J $ Sau,t:) 4 60" x 16" Saddle & Service (oer Hanson) EA 1 $9,560.00 $ 9,560.00 5 18" x 16" Saddle & Service (oer Hanson) EA 1 $4,390.00 $ 4,390.00 6 16" Tappina Valve. comolete and in olace EA 2 $IStoLo $fUDJ.t:tJ 7 10" Reinforced Concrete Paving Remove I Replace, including subgrade preparation and curb and gutter, complete and in place SY 30 $ 2aJ.ct;) $ G.tnI>,m 8 Erosion Control LS 1 $ 7S0.otJ $ 7So•.::b 9 Traffic Control Plan implementation and maintenance LS 1 $2SiV.a $ '2.S70.lJ:) 10 Trench Safety Design and Implementation LS 1 $..,........ 􀁾 $ 3(Xtt..aJ 11 Sod SY 30 $ &1#00 $ 9 Additional Labor/Equipment(4.5 hrs@$350Ihr) 0203 Water. (+$1,575.00) Net change to estimate +$1,575.00 Project: 15001 Beltwood Parkway -Water Vaultfor AddisonIFarmers Branch Connection v Qty 1111I8 4.5 Date 1I14/2005 P.D.No. Rate 1,500.00 5,200.00 765.81 2,107.25 450.00 350.00 350.00 Total Payments/Credits Balance Due Invoice Invoice # 910-1 Terms Net 30 Amount 1,500.00 5,200.00 765.81 2,107.25 450.00 2,800.00 1,575.00 $14,398.06 $0.00 $14,398.06 HP LaserJet HP LASERJET 3200 3200se n v e n t JAN-17-2005 4: 19PM Fax Call Report Job 349 Date 1/17/2005 Time 4:19:05PM Type Send WatSl' Distribution §290.44 Identification 99722416305 Duration 0:47 Pages 1 Result OK §290.44(.f)(2) Special precautions must be taken when walCrlinc8 are laid under any flowing or intermittent Btream or semipermanent body ofwater such as marsb, bay, or estuary. 10 these cases, the waler main shaU be iDBtallcd in a separate watertight pijle ellcasement and valves must be provided on each side ofthc crossing witb"facilitics to allow the underwater portion ofthc system to be isolated and tested to determine tM, thcrll are DO leaks in the undcIW8ler line. Alternately. and with .the permission of tho 􀁥􀁸􀁣􀁣􀁵􀁾􀁥􀁬􀁱􀁩􀁲 􀁥􀁣􀁬􀁯􀁲􀀮 the watertight pipe encasement may be omitted. §29O.44(1)(3) New mains shall be thoroughly disinf 􀁾J1tp. 􀁾􀁾􀁊􀁶􀁕 ht)" tf7l lf1Vl 􀀤􀁾􀀬􀀮􀀣...... 􀀬U􀁴􀀩􀁾 Ff5, --H+--·-·-__4-􀀭􀀭􀁾􀁟􀀮􀀭􀀭􀀭 i ;1 I! I --,-i:,-.! -------,-----'􀀭􀀭􀀭􀀺􀀭􀀮􀀭􀁾􀀭􀁟􀀮􀁟􀀭􀀭􀀭 -----1----􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀀭􀀭􀀭􀁾􀀭􀁾􀀭 􀁾􀀭􀀭􀀭 􀀭􀀭􀀭􀀭􀀭􀁜􀁾􀀭-------------1----------------,􀀭􀀭� �􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭 -----.---._------------------fT; 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀮 -----------iii 􀀭􀁾􀁩􀁾􀀭􀀭􀀭 --􀁾􀀭----'-----=:------'---1 I 􀁾 ---.-,-----.--'--rn---' ------.---f i l 􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀼􀀭􀀭􀀭 --------,....:...\ ._------1: 1 ! II 􀀧􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀁟􀁟􀁟􀁟􀁟􀁟􀁦􀀫􀀭􀀭􀀭􀀭􀀺􀀾􀀭􀁾􀂭 I! : J i l -----------I-+.; ------:"--"--; i! !ii --------ttt .-HI ..􀁟􀁾􀀭􀀭􀀭􀀭􀀭􀁟􀀮􀁟􀀮􀀭 ----.:...------+ ,-b t! I 'I; :t J 􀀭􀁾􀀭 -"----,-------------􀀭􀀭􀀭􀁾􀀭􀀭􀀬􀀭􀀭􀀬􀀭 -----------,----------_. l.lL --iT!-;! j ! I 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀀭� �􀀭􀀭􀁾􀀭􀀭􀁟􀁩 !,[I /􀀬􀀮􀁾􀀭􀀭􀀭􀀭 􀀭􀀽􀀺􀀭􀀭􀀺􀀺􀀺􀀮􀀮􀀮􀀭􀀺􀀺􀀬􀀮􀀺􀀭􀀮􀁾􀀭􀀢􀀢􀀽􀀢􀀮􀀮􀀭􀀭􀀭􀁟􀀺􀁟􀁾􀁤􀀡􀀮􀁧􀁾􀁾􀁾􀁾􀁬 -i I '-----------------H+----------------------'---\-iii ' ' ---------1I1'i 1------I: ! "HP LaserJet HP LASERJET 3200 3200se n v e n t JAN-17-2005 4: 12PM Fax Call Report Job 347 Date 1/17/2005 T-ime 4:08:20PM Type Send Identification 92146722020 Duration 4:27 Pages 4 Result OK VI8 Fox 1-512-239-6972 January 17,2005 Assis1mlt Administrator . -cts Texas . sion on Environmental QuIllity Aus' Texas Rc: Water 􀁓􀁾 Interconnection Between Addison and Farmers Brnnch Dear Ms. Morgan: This is to describe the water system interconnection project that we have been working on with Farm"'" BrBlIch. The primaIy pwpose ofthis project is to allow shut down ofthe 60" Dallas Water Utilities walOr main that feeds the Farmers Brnnch Marsh Lane Pumping S18tion and to therefore furniSh a temporary supplementary supply of water from Addison to Farmers Branch. The 60" main needs to be shot down so that a portion ofthe main can be Iowored to aoeommodate the construction of Arapaho Road, Phase ill in Addison. The seeondaJ}' pwpose of this project is to make an interconnection between the two systems such that either City can supply .water 10 the. other in case ofemergency. Adellson has taken the lead and will bear the cost ofthe interconnection. Atapping sleeve and volve lias been installed on the 8" main on BellwOod Parkway in Farmers Branch, and • similar connection has been made on the nearby 8" main in Addison. An 8" turbine meter has been installed in a vaulllo measure Dow delivered to either municipality. Acopy ofthe piping ammgemenl and location map is attached. CollstNction of the interconnection was "!'II1p/eled on Friday January 14, 2005. The piping was disinfected and l1ushed. All wolk was done under the supervision ofTCEQ Licensed Operators from both municipalities, as well as Licensed Professional Engineen from Addison. Both municipalities sha1I share sanitary control of1bo interconnection. with Addison taking the lead. Testing has ahown tbatAddison ean.fumish 1,350 gpm to Farmers Branch with a differential prelll1lre of 4 psi. Ms. Wanda Morgan January 17, 2005 Page 2 Please call me at 972-450-2871 ifyou have any questions or require any additional information. 􀁶􀁥􀁲􀁹􀁴􀁲􀁵􀁬􀁹􀁹􀁯􀁵􀁲􀁳􀁾􀁾 J es C. Pierce, Jr. P.E. ssistant Director ofPublic Works Cc: Chris Terry, Assistant City Manager Jerry Davis, Utilities Superintendent John Hill, Cowles & Thompson Mark Pavageaux, P.E., Director ofPublic Wodcs, Farmers Branch :z= L? > ....... JE X15T:. g." C.Z" '. ( I.lPPI5Ptv) . '1' I' 􀁉􀁪􀀶􀀮􀁸􀁻􀁾􀁲􀀺 f . 􀁦􀁾􀁖􀀮 c. .. 􀀨􀁁􀀮􀁐􀀮􀁄􀀨􀀾􀁾􀀻􀁙􀀩􀀮 "!; . C(iil'cR,eT'E' T1f1Gvs-Y 13 (.I7CIC: IlVfi Pl!1J f· " FIe, p, ('t 􀁾􀁲􀁣􀁒 .Pte!!? 9'''X 8'.". 􀁾􀁣􀁲􀂣􀁒􀀮􀁟 VA.. _f/--.':"T) 􀀬􀁁􀁌􀁌􀁾􀀺􀁊􀀬􀀿 .. /. 􀁓􀀢􀀧􀁾􀀢􀀢􀀢􀀢 . , " . ,;/'. .\ . ,C􀁦􀁬􀁾􀁣􀀮􀀮􀁒􀁣􀁔􀀮􀁅 ., .. . PRPP. 8' P; l/, C. rHRf/5T' PtedP, 8'/1 . 1/. (AOOi.soill) . ·CoIIICRETe. ... 8t.lJlKfAdt. "'" P, VIC.:. ..fRt:1('•.8' .. . ItBAArDIJ{V t:X1'>T-TJ?I/JT. (!tfJOfSe'4/) 􀁾􀀺􀀺􀁾􀀻􀀻􀁣􀀺􀁾􀁔􀁃􀁉􀀧􀀱 8',"C,I. lEAST. (Jt..QQ::/(l/(,j e'F PRtJP. Tet: . "', S '.􀁾􀁦􀁒􀀺􀁴􀀧􀁐 .. 􀀳􀀧􀁾􀀧􀁋􀀸􀀮􀀢 .., . 􀁥􀀮􀁸􀀯􀁾􀁔􀁾􀁦􀁊􀁉 11, 􀁾􀀺􀀮􀀮 .. ..T/f.Pf'JtV.(i $L 􀁅􀀧􀀮􀁅􀁙􀁾 (F-1RI'1t:,gS .6RI.IA't;:H).. ¢ .... /(/.fL 1(6 "-+--14995 Beltwood Parkway . . "-.Proposed 8" Water Interconnection Addison/Farmers Branch " 􀁉􀁖􀁴􀁮􀂷􀁾􀂷􀁾 cPt'-'T/i-c,r ALl. .,'t.-.F.F..E.C..r;EO.-..... PI2.t?.Pt.£/C. .O""'IV!!=R$ pRIPR.n .5TAI?T ,oF. 􀁾􀀮􀁯􀁉􀁖􀀧􀀾T/?vCTI 01'1.-" Januarv 2005 izoCl􀁾Z􀁾ou : i SCAlf IN FEET 47 48 n 46 CEDAflBRUSH 􀁾 45 .... 42 CONTINUED ON MPJ>24 CONTINUED ON MAP 4 4 i'h -----------.•----,,!!,,!_--_.---_!!!!'!'!'!"'---.............􀀢􀀢􀀧􀀻􀀽􀀬􀀮􀀭􀀧􀁾􀀭 􀁾􀀮􀀭􀀭􀀮􀁾􀀬􀀧􀀧􀀭􀀽􀀭􀀭􀀭􀀭 --'---·-----:......_4 o wtEBURN HP LaserJet HP 􀁌􀁁􀁓􀁅􀁒􀁾􀁉􀁅􀁔 3200 3200se n v e n t JAN-17-2005 3:45PM Fax Call Report Job 345 Date 1/17/2005 Time 3:42: llPM Type Send Identification 915122396972 Duration 3:04 Pages 4 Result OK • J:. N ol-.ADDIsoN PUBLIC WORKS DEPARTMENT 􀁾􀁌 " .... .., POll omce BOll 9010 Iddlsoa. ftiU 7.5901.90111 J8Jl1lllIY 17, 2005 Ms. Wanda Morgan, Assistant Administrator Utilities and Districts Texas Commission on Environmenla1 Quality Austin, Texas (9'72) 450-2871 FAX (971).aSl).:zlIl7 16801 Wftt,rllVe Via Fax 1-512-239-6972 Re: Water System Interoooneclion Between Addison and Farmm BlBDch Dear Ms. Morgan: This is 10 descn1le the water system inte"",nn.ection project that "'" have been working on with Farmers BlBDch. The primary pUIJlOse oflhis project is 10 allow shut down ofthe 60" Dallas WBler Uillities water main that feeds the FllDDers BlBDch Marsh Lane Pumping Stalion and 10 th....fore furnish alempomry supplementary supply ofwater fiom Addison 10 Farmm Branch. The 60" main needs to be shut down so that a a portion of the main can be lowered to accommodale the construction ofArapaho Rtlad, Phase ill in Addison. The sec:ondaly pwposc ofthis project is to make an interoonneclion between the two systems such that either City can supply waler to the other in case of emergency. Addlson bas taken the lead and will bear the cost ofthe interoonncction. Atapping aleeve and valve has been installed on the 8" main on Beltwood Pukway in FllDDers Bmncb, and a similar COlUll:lCtion has been made on the nearby 8" main in Addison. An 8" turbine meier has been installed in a vault to measwe flow delivered to either municipality. Acopy of the piping anangement and location map is attached. Construction ofthe interoonnection was compleled on Friday JanllllIY 14,2005. The piping was diainfeeled and flushed. All work was dollC under the supervision ofTCEQ Licensed Operators from both municipalities, as well as Licensed Professional Engineers fiom Addison. Both municipalities sbaII share SllIIitary control ofthe interconnection, with Addison taking the lead. Testing has shown lItat Addison can furnish 1,350 gpm to Fwmers Branch with a differential preas"'" of4 psi. January 17,2005 Ms. Wanda Morgan, Assistant Administrator Utilities and Districts Texas Commission on Environmental Quality Austin, Texas (972) 450-2871 FAX (972)450.2837 16801 Westgrove Via Fax 1-512-239-6972 Re: Water System Interconnection Between Addison and Farmers Branch Dear Ms. Morgan: This is to describe the water system interconnection project that we have been working on with Farmers Branch. The primary purpose of this project is to allow shut down of the 60" Dallas Water Utilities water main that feeds the Farmers Branch Marsh Lane Pumping Station and to therefore furnish a temporary supplementary supply of water from Addison to Farmers Branch. The 60" main needs to be shut down so that a portion of the main can be lowered to accommodate the construction of Arapaho Road, Phase III in Addison. The secondary purpose ofthis project is to make an interconnection between the two systems such that either City can supply water to the other in case ofemergency. Addison has taken the lead and will bear the cost ofthe interconnection. A tapping sleeve and valve has been installed on the 8" main on Beltwood Parkway in Farmers Branch, and a similar connection has been made on the nearby 8" main in Addison. An 8" wbine meter has been installed in a vault to measure flow delivered to either municipality. A copy ofthe piping arrangement and location map is attached. Construction of the interconnection was completed on Friday January 14,2005. The piping was disinfected and flushed. All work was done under the supervision ofTCEQ Licensed Operators from both municipalities, as well as Licensed Professional Engineers from Addison. Both municipalities shall share sanitary control of the interconnection, with Addison taking the lead. Testing has shown that Addison can furnish 1,350 gpm to Farmers Branch with a differential pressure of4 psi. Ms. Wanda Morgan January 17,2005 Page 2 Please call me at 972-450-2871 ifyou have any questions or require any additional information. 􀁖􀁾􀁴􀁲􀁵􀀱􀁹􀁹􀁯􀁵􀁲􀁳􀁾􀁾􀁾 J es C. Pierce, Jr. P.E. ssistant Director ofPublic Works Cc: Chris Terry, Assistant City Manager Jerry Davis, Utilities Superintendent John Hill, Cowles & Thompson Mark Pavageaux, P.E., Director ofPublic Works, Farmers Branch :.;;;"" -...., :;;;"'. 􀁾 ....... .tExt!T-. 8'/1 􀁃􀁾􀁉􀀻 . . ((tPPI5p,v) '1' 'r .. " . r/􀁉􀁪􀀮􀁾􀁘􀀭􀀧􀀤􀀮􀁲􀀺 8' . f. V",.c. • '.. ( A. P{)(.$PIy) , 􀀧􀁜􀁥􀁯􀁾􀁾􀁾􂂬􀁾. .1f?I/Jt .-.. fJ/.. uC!< Wf; . ItBIM/DIJt;V ext.JT8'." c,.I, t=A.5T . (IF 􀁰􀁾􀁰􀁰􀀮 TC'E' . . PRt:lf'•..8''' .. RISllld, 􀁾􀁲􀁥􀁬􀀧􀀱 . 'v/fLV£".PRpP, 􀁴􀁦􀀱􀁾􀁲􀁥􀀭􀁾 vA(.,It:-T L 􀁾􀀯􀁉􀀧􀀩􀀨􀀬􀀵􀀧 11 ., 7 .PR."p, .,Il/.. o. .' 1'--'.'. '.' . . MSTd. 􀁾 I I .. 1 .. ··· . 􀁾􀀺􀀮􀁉􀀢􀁾. " . " . :/PRflP. If Po v, c . . (AO(>ISdiV) (!RI7 f·􀁾􀂣􀁔􀁅􀁒􀀧 If " 􀁄􀁾􀁾􀁰􀀬 5' X 8'. ' AiL M3.? .. ' "'/"fi ..' .. ' ., .. , --II .Cf2&CRETE .' . '''Rf3P, K rHRldT . . p, 􀁖􀀧􀀮􀀱􀀮􀁣􀀮􀀮􀀬􀁾􀀮 . .' 􀀸􀁴􀀮􀀮􀀢􀀨􀀮􀁫􀀯􀁁􀁬􀀮􀁾􀂷􀂷􀂷 .-(If-0 ()ISbIt/) . CCiif'7:Rc'fE·· T1ttzvs."r 8 t.. PC-it:: I/Vii , , , -L _. .., _ 􀁉􀁾􀁔􀀮􀂷61'S 􀀧􀁾􀁦􀁥􀀻􀁰􀀧􀀯􀁾􀀻􀁾􀀺 􀁾􀁾􀀻􀀻􀀮 C-'f. .' .. . .. ..... .. 􀀮􀀮􀀮􀁾􀀮 P.f'.. .. .., .' 􀀨􀁆􀀯􀁩􀁒􀀯􀀧􀀱􀁅􀁉􀀼􀀤􀀮􀀨􀀤􀁒􀀯􀁉􀁎􀁾􀀩.. ¢ . I(/.lL 􀁾􀁣 ...... 􀁾 14995 B·eltwood Parkway . ."-Proposed 8" Water InterconnectionAddison/Farmers Branch /VtPTlE: cplVTACT A-t:...L. _, ..... ".-.. -..' T······· -" f" . ," . f'tFFECT.EO 􀁰􀁾􀁰􀁐􀁅􀁉􀁃 . " ... -: .. 􀁾􀀮 ,-. ... .(?f,vIV!ER$ pRIPR.n 5TA:I?' .of. 􀁾􀁐􀀴􀀯􀀮􀁳􀁔􀁬􀀿􀁶􀁃􀁔􀁉􀁴􀀿􀀱􀀱􀀯 . Januarv 2005 . 􀁾zoo 􀁾z§ SCALE IN FEET .., n i : QQ 46 􀁾 3 45 47 48 􀁾 CEOAllBRUSH 􀁾 42 45 -CONTINUED ON MAP -24 CONTINUED ON MAP 4 4 -------_."!"!!....􀁾.. -"""-._--_..._"!!!_----........!--...,;.,..-,.... -.-..-,..􀁟􀁾􀀮-_..􀀺􀁾􀀭􀀬 SCALE IN MILES F!i􀀡􀀡􀀡􀀵􀁏􀀻􀁾􀀻􀀻􀁓􀀻􀀺􀁩􀁬􀀽􀁩􀁾􀁾􀀽􀀢􀀧􀁩 PI o l/e 11.. 3/.. 110, .... WEEB RN i8 T 0 W N 0 F .ADDIsoN PUBLIC WORKS DEPARTMENT !lIM.. w ® Post Office Box 9010 Addison, Texas 75001-9010 January 17, 2005 Ms. Wanda Morgan, Assistant Administrator Utilities and Districts Texas Commission on Environmental Quality Austin, Texas (972) 450-2871 FAX (972)450·2837 16801 Westgrove Via Fax 1-512-239-6972 Re: Water System Interconnection Between Addison and Farmers Branch Dear Ms. Morgan: This is to describe the water system interconnection project that we have been working on with Farmers Branch. The primary purpose ofthis project is to allow shut down of the 60" Dallas Water Utilities water main that feeds the Farmers Branch Marsh Lane Pumping Station and to therefore furnish a temporary supplementary supply ofwater from Addison to Farmers Branch. The 60" main needs to be shut down so that a portion ofthe main can be lowered to accommodate the construction of Arapaho Road, Phase III in Addison. The secondary purpose of this project is to make an interconnection between the two systems such that either City can supply water to the other in case of emergency. Adcfison has taken the lead and will bear the cost of the interconnection. A tapping sleeve and valve has been installed on the 8" main on Beltwood Parkway in Farmers Branch, and a similar connection has been made on the nearby 8" main in Addison. An 8" turbine meter has been installed in a vault to measure flow delivered to either municipality. A copy ofthe piping arrangement and location map is attached. Construction of the interconnection was completed on Friday January 14,2005. The piping was disinfected and flushed. All work was done under the supervision ofTCEQ Licensed Operators from both municipalities, as well as Licensed Professional Engineers from Addison. Both municipalities shall share sanitary control ofthe interconnection, with Addison taking the lead. Testing has shown that Addison can furnish 1,350 gpm to Farmers Branch with a differential pressure of4 psi. Ms. Wanda Morgan January 17, 2005 Page 2 Please call me at 972-450-2871 if you have any questions or require any additional information. 􀁖􀁥􀁲􀁹􀁴􀁲􀁵􀁬􀁙􀁙􀁯􀁵􀁲􀁳􀁾􀁾 J es C. Pierce, Jr. P.E. ssistant Director ofPublic Works Cc: Chris Terry, Assistant City Manager Jerry Davis, Utilities Superintendent John Hill, Cowles & Thompson Mark Pavageaux, P.E., Director of Public Works, Farmers Branch .............:::;:::::>' -.-.-.----. .. 􀁾 . J= 1/X(5r.. g. C,.r, '" ( ItPPl5PtV) '1' • ! +--(, 􀀮􀀮􀁾􀁘􀁻􀁳􀀮􀁲􀀺 􀁾 .. f,t/', .C-. . (A.PD(5PIf/) . "j; . prep p, ('f 􀁴􀀺􀀮􀁲􀁥􀀭􀁾 .PRp,P, 5' IfX3.". V 􀁾􀀷􀀨􀀯􀁴T􀀮􀀮 .ALL 􀁾􀀮􀁾􀀮􀀿 .... .... S ,-􀁾 .C:􀁡􀁁􀀨􀁃􀁾􀁾􀁔􀁬􀁩 . .' ...." . PRPP" 8" P, V, c.'7' \ '" .. jHRv,Sr 􀁐􀁦􀀿􀁾􀁐􀀮 8' . (AOt>i.50iV) ·eolVt.R(£17i. . . ... Bt."l/klA/li. P, ((,.e: . . fRPP, }i"'. ItBAArDPty /!EXI.>", . .TJ:?I/JT . '. (Aoo/St1t1/) 􀁒􀀺􀀺􀁾􀁾􀀺􀁣􀀮􀁾􀀷􀁃􀀱􀀧􀀱 3."C,I. cAST. 􀁦􀁊􀀯􀀮􀀮􀀨􀁽􀁾􀁉􀀯􀁬􀁩􀀶􀁩 &IF PRoP. TeE. . CtiNl:RerE·· THlii!tif,"T B t.oc-/c l,lVfi . " , , . "-' ... 􀁅􀁘􀀯􀁾􀁔􀀮 􀀻􀀯􀀻􀀺􀁊􀁾􀀡􀀻􀀺􀁐􀀧􀁾􀁾􀀻􀁾􀀺􀁅􀁅􀀧􀀻􀀢 ., .. .. £',,". . . .' r􀁆􀀱􀁒􀁮􀁅􀁆􀁓􀀸􀁒􀁉􀀮􀁉􀀢􀀢􀀧􀁾􀁈􀀩􀀮􀀮 ( .. I(--1 L .1("'; 14995 Beltwood Parkway . ..,--.Proposed 8" Water Interconnection Addison/Farmers Branch . 1VC1.TE'· 􀁴􀀻􀁯􀁾􀁔􀀯􀁦􀁣􀀮􀀬􀁔 ALL rt.rFE.Ct,E.'?: PR.0PlfR . 􀁴􀀿􀁾􀁉􀁖􀁆􀁒􀀤 pRloR.n STAg, ,CJF. CPA/"oS r/?vc. TI t'i1/Januarv 2005 . 􀁾zocw::lZ;:::z8 50 f 51 52 NORTH ODR J . 47 48 CEDAABRUSH :::; 45 .... 42 CONTINUED ON MAP 24 CONTINUED ON MAP 4 4 I1,<, 􀁍􀁾􀀫􀁾􀀡􀀡􀀡􀁗􀁾􀁃􀀭􀀭􀀭􀁉􀁉􀀢􀀬􀀬􀀭􀀭􀀭􀁴􀀭􀀭􀀱􀀭􀀭􀁟.... 45 ::: --------_.. 􀁾"'!!"'•. ""!"'..• "'!""'!""""""'!-"'..-- ---"=.•,,"""'-,.,.. -"-' 􀁾.•,.-,._,',._---_..: 􀁟􀁾 io weEBURN HP LaserJet HP LASERJET 3200 JAN-17-2005 4:01PM 3200S8 rQ® 􀁾invent Fax Call Report Job Date 346 1/17/2005 Time Type 3:57:38PM Send Identification 99722416305 Duration 3:20 Pages 5 Result OK From: Jim Pierce, P.E. Asst. Public Wks. Dir. Phone: 972/450-2879 FAX: 972/450-2837 jpiuce@ti.addisoD.lLU. ADDIsoN PUBLIC WORKS To: m,fk 81t,a􀁾􀀴􀀺 '" 2C Company: ffrrtt"", 8¥J FAX II: 911.-t. '11-C; 3'115" Date: 1-/7-05 16801 Westgrove P.O.Box 9010 1# of pages (including 􀁣􀁯􀁶􀁥􀁲􀀩􀀺􀁾 Addison, TX 75001-9010 􀁾􀁥􀀺 IlJoI,jtltl!FtJr"'''J'$ 􀁾􀁲􀀢􀁮􀁧􀁦 41a,fff-S,.t-hn 􀀮􀁊􀁨􀁢􀁲􀀦􀀨􀁬􀁊􀁮􀀮􀀬􀁾 . I . o Originl iD mail 0 Pu your request 0 FYI. 0 CaD me CommeDU' tJ1a.d .' 'um1·d"AA-t'tr2:z<􀁲􀀻􀁾 -*= TC£(p d&bcd.2 . TOWN OF From: Jim Pierce, P.E. Asst. Public Wks. Dir. Phone: 972/450-2879 FAX: 972/450-2837 jpierce@ci.addison.tx.us PUBLIC WORKS 16801 Westgrove P.O.Box 9010 # of pages (including cover): S Addison, TX 75001-9010 Re: fldohhlll/fiJOfll'l'f l!r RIDa 􀀸􀁾 'j 7z e.t50 ;l83 7 .,... 3 Inc. CCMII' Fax JI'V'V\ 􀁐􀀬􀁾􀀬􀀮􀁃􀀭􀁥 • Mr;)rtn11f1Vis ,.... Malt Brandenburg .... .... 12-Jan-05 -Quate-WIIlervaua/15001 E. BeItwoodCCl: ...-.C ....111 Mr. Davit. Th8nk you for gMng us lie ()ppOIIIftty fa woItl. for the iD'M'l OfAdelson once-. AUacbed for your I8View is ourQUClCelbrthe vauft inslallIIIIOn and W8l8f' ine connections 11115001 E. BeIwoad. Ifthis Is 8ale(.1CabIe__eIgn and lID( b8c:k our UIter of AIihoftz:IIIon and rI1II/I us the qif181. Onee the Faed copy is ftICl8MId we JAn to schedule and petfonn the WOI1l tamanow, 13-Jan-04. Please give US. all ifyau""" any commenIS or quesllaN concemirv ourquote. TOWN OF ADDIsoN To:---I1ttlrk 􀁢􀁬􀁡􀀬􀁊􀁾 􀁾􀁙􀁊 Company: J}&1J15 􀁅􀁸􀁣􀀬􀀱􀀯􀁾􀀴􀀭􀁾 FAX #: 2/4-733-2C>if3 PUBLIC WORKS From: Jim Pierce, P.E. Asst. Public Wks. Dir. Phone: 972/450-2879 FAX: 972/450-2837 jpierce@ci.addison.tx.us Date: 1-/1.-oS 16801 Westgrove P.O.Box 9010 # of pages (including cover): 12-Addison, TX 75001-9010 Re: 􀁉􀀱􀁊􀁊􀁴􀁾􀁁􀀯􀁲􀁡􀁴􀀧􀁦􀁉􀁻􀁦􀁲􀁾􀁾􀀢􀀮􀁊 kldn-¥M1 ;[irkvWHVltdinJ__ ./I.Original in mail . 0 Per yonr reqnest 0 FYI 0 Call me Comments: Ie /i-fY t9 I-􀁾􀀡􀀭􀀿􀁾 a.;f/aedPd HNTB Corporation The HNTB Companies Engineers Architects Planners Mr. David Robinson Operations Manager Pumping Division 2900 White Rock Road Dallas, TX 75214 15150 Surveyor Blvd. Addison. TX 75001 Telephone (972) 361 -0064 Facsimile (972) 361 -0065 www.hnlb.com HNTB Arapaho Road -Phase ill Project January 11,2005 Dear David: Three weeks ago, Archer Western Contractors, Ltd. scheduled a meeting with you on the procedures for the lowering ofthe 60"main and to schedule a test shutdown for the section ofthe DWU 60"main and the associated valves. During this preparation for the test shutdown ofthe 60"main that next day, DWU notified Archer Western Contractors, Ltd. that a issue had arose with the shutdown ofthe 60"main. DWU found that the water supply connection for the City ofFarmers Branch was on the closed side ofthe valve, which would turn off the water to the City ofFarmers Branch Marsh Lane Pumping Station. Since that time, The City ofFarmers Branch has been performing tests on their system to determine ifthey would be able to maintain pressure and volume when the 60" valve is closed on their system. The City of Farmers Branch has determined that they will not be able to maintain the required pressure beyond 48-hours. Upon the notification ofthis issue, the Town ofAddison and the City of Farmers Branch began working on an "interconnect" that would supply Farmers Branch during the work on the 60"main line. This "interconnect" must be installed and operational, prior to the shut down ofthe 60" main line. The Town ofAddison has requested Archer Western Contractors, Ltd. to reschedule the work on the 60" DWU main until the referenced "interconnect" can be completed. At the present time the Town ofAddison is attempting to expedite this work and anticipates this work to be completed on or about January 19,2005. We wanted to keep you informed ofthis matter. Thank you, Guy Van Baulen, EIT HNTB Corporation Cc: Steve Chutchian, Town ofAddison Erling Holey, Dallas Water Utilities Cassia Sanchez, Dallas Water Utilities Katura Curry, Grantham & Associates Jerry D. Holder, HNTB Corporation Michael Ebeling, HNTB Corporation DATE JrIF-O 5 NAME----M,Ord'---c...,------'-P_, HOME# _ ADDRESS WORK# _ 171 '-TJ 9-􀀲􀀮􀁾􀀱􀀳 t:',. A_7I-d IAf"11 REQUEST FOR I fJ ( 􀁾􀀢􀀢􀀢􀁐􀀧􀀢 F(.) Vl SERVICE , Jilt 6fvt It I Ltrrrz;{ 􀁾 t. 􀀢􀀧􀁲􀀭􀀭􀁉􀁾 () K-i;t-'-\. 􀁾 􀁾 vLk 􀁾 􀁾 􀀣􀀱􀁾􀁊􀁲􀁟􀁊􀀮􀀭􀀭 _ 􀀳􀀬􀁉􀁁􀁊􀁍􀀬􀁾 YIYi.I/14􀁾 􀁁􀁃􀁔􀁉􀁾 TAKEN--------------ROBIN _ AL------MITCH _ JAMES _ JEFF------JOHN----- HP LaserJet HP LASERJET 3200 JAN-11-2005 11:21AM Fax Call Report 3200S8 n v e n t Job 291 Date 1/11/2005 Time Type 11: 20: 19AM Send Identification 99722416305 Duration 0:51 Pages 2 Result OK 􀁾􀁌 MoisaN PUBLIC WORKS DEPARTMENT __, _ ....__ .. .. __ ...... _e olltomce 0'1:"10 ,Ttl•• 5 .".0 J8Iluary 11, 2005 Mark O. Pavageaux. P.E. Director ofPublic Works P.O. Box 819010 Fanners Branch, TX 75381-9010 19711 f,,50·2871 FAX ('71 51-2137 16101 Wullfon Re: Wak:r System Interconnection BetweenAddOOn and Farmers Branch DearMJ. Pavageaux: This is 10 describe the intercoonection project that we have been wolkin8 on with you JeCCIl11y. The primary pwpose oflhi. project i.1o allow shutdown ofthe 60"DWU water main thai feeds the Farmers Branch Marsh Lane Pumping Station and to therefore furnish a .upplementary IUJIIlly ofwaler fiom Addison to F&rmenI Branch. The 60" main need.o 10 be shut down so thai a portion ofthe main can be lowered to accommodale the constrlll:tion ofArepeho Road, Phase m. The second8ly pwpose ofthis project is to make au inten:oDJU:Ction between the two systems lOCh thai either City can supply water to the other in case ofemergency. Addison intends to take the lead and bear the cost ofthe inten:onnection. A tapping .leeve and wive will be installed on lIIe 8" main on BellWood Parl