1 . 1 ; r & Waldbauer Engineers, Inc. January 13, 1999 John Baumgartner, P.E. City Engineer Town ofAddison 16801 Westgrove Drive Addison, Texas 75001 Ref: Agreement for Update of Study for Two Proposed Union Pacific Railroad Crossings Dear Mr. Baumgartner: GBW Engineers, Inc. (GBW) is pleased to provide this agreement to update a study for two proposed Union Pacific railroad crossings in the Town ofAddison. GBW has prepared the following Scope of Services for this project: • Edit the existing report to incorporate comments from the Town of Addison including more recent traffic numbers. • Review the report and make any other appropriate revisions. • Incorporate color graphics in the report exhibits. • Prepare ten final copies ofthe final report including any City comments on a draft submittal. GBW proposes to complete the aforementioned Scope ofServices for a fixed fee of$900. Ifyou have any questions or would like to discuss this proposal further, please do not hesitate to call. Very truly yours, APPROVED BY: ruce Grantbam, P.E. President Town of Addison Date BG/gg C,IWPDOCS\PROPOSALIADDISONIRR·R!'TUR Tel (972) 84()'1916 Fax (972) 8-10·2156 1919 S. Shiloh Road. Suite 530. LB. 27. Garland. Texas 75042 (ftat:; +vifj-􀁦􀁾􀀴􀁴􀁲􀁾􀁴􀀭􀁥􀀠IZ. 􀁾􀁾􀁾􀁦􀁊􀀱I-􀁻􀀧􀁾􀁦􀀠/1tat(;(f-ft1r4 􀁾􀁾􀁾H-i-&ds · 􀁾􀁾􀀱􀀭􀀱􀁴􀀷􀁾􀀠: 􀁡􀀴􀁾􀀠'r .",---􀁾􀀢􀀢􀀢􀀻􀀻􀁲􀁮􀀠􀁉􀀬􀀻􀁾􀀠􀁾􀀮􀀠. 􀀰􀁾􀁶􀁦􀁾􀁾􀁾􀀠· 􀁦􀀡􀁶􀁬􀀮􀀭􀁾􀀠􀁾J?I"-. 􀁾􀀠if 􀁾􀁾+L 􀁾􀀩􀀮􀁊􀁨􀀠􀁉􀁲􀀭􀀭􀁌􀁕􀁦􀁬􀀭􀁴􀁬􀁾􀁲􀁩􀀴􀁕􀀠􀁦􀁾􀀷􀀠6f4(t 􀁾􀁬􀁴􀀮􀀬􀀠􀁾􀀱􀁁􀀮􀁾􀀠b 􀀫􀁾􀁾􀀠? fGt5J 􀁾􀁾􀁾􀁗􀁵􀁲􀁾􀁾􀀭􀁾􀀠'Du-g.N\-0\;1/1. 􀁰􀁾􀀮􀁊􀀮􀀼􀀾􀀠'v- 􀁾􀁻􀁕􀁶􀁜􀁪􀀴􀀠;li.0: I􀁾􀁉􀀠{)].aIL 􀁾􀀯􀀴􀀠􀁕􀁁􀁾􀀱􀀮􀀮􀀠+ilL klJ--V .•• 􀁾􀁲􀁾􀁾􀁾􀁾􀁦􀁯􀁾􀀠􀁾􀀠􀁾􀁾􀁐􀁾􀁉􀀠.,Ifwk.-􀁾􀁾􀁾;L{;. 􀁾􀀠􀁁􀁊􀁾􀀫􀀠· 􀁾􀀠􀁜􀁾􀁬􀁕􀀭􀁁􀀯􀁾􀀠. @􀁾􀀭􀀱􀁁􀀧􀁾􀀠P(BN/1􀁾bJA. P.. 􀁾􀀭􀀭􀀭􀀭􀁊􀁶􀀭􀀭􀁺􀀮􀀮􀀺􀀺􀀺􀀺􀀬􀀺􀀻􀀻. fd fn-zJ(;3-£J&5'/3;/'trr /" Due to extensive utility relocations in a tight construction corridor, the viability of Alternative 6 is questionable at this point. If the Town of Addison wishes to pursue this alternative, further coordination would be necessary with Dallas Area Rapid Transit (DART) and DWU prior to developing an Opinion of Probable Cost. HNTB Corporation Page 7 of 10 December 14, 1998 A discussion of the issues described in the attached matrix are provided below: • Charter Furnirure Building Take -Moving the alignment south of the railroad provides space between Arapaho Road and the railroad right-of-way (ROW) for the existing 60-inch DWU water line and the proposed double 9'x5' box culverts. • MNBA Building Take -Without taking the MNBA building, there is insufficient room to create a safe merge condition for the westbound entry ramp onto Arapaho Road. The lack of sight distance at the merge is more severe with the overpass than the underpass, due to the additional distance for merging the vertical alignment. The underpass alternative is not recommended without a stop condition oil the ramp traffic. • Relocate DWU Water Line -There is 81 feet from the railroad ROW to the face of the Charter Fumirure building. Consequently, the DWU water line, which is located approximately seven feet off the railroad ROW, would need to be relocated with Alternative 6 (underpass). Using a four-lane undivided roadway with 11-foot lanes for Alternative 5 (overpass), and providing a IS-foot easement for DWU. The south overpass wall would be located approximately nine feet from the Charter Fumirure building. If a sidewalk were provided across the ramp for emergency access, the separation from the curb to the furnirure building would be reduced to four feet. Noise -Although truck traffic is likely to be low on the Arapaho Road extensions, noise may still be a source of complaint from affected business owners if an overpass is constructed. " Realign Midway for Construction Sequence 1 If the underpass were selected, a probable construction sequence would require the removal of one half of Midway Road at a time. In conjunction, Midway Road would have to be realigned and narrowed to four lanes through the construction zone on two occasions. The underpass construction could affect Midway Road in this manner for up to a year. • Sump Storm Sewer -All the underpass options would require the draining of the roadway under under Midway Road. There appears to be sufficient grade to install a 􀁾􀁯􀁲􀁭􀀠sewer from inlets . , . m the depressed roadway to the concrete channel west of Surveyor. . • Move Box Culvert to North Side of Railroad Right-of-Way -Alternative 6,(underpass) would require the installation of double 9'x5' box culverts on the north side ofthe railroad. If a minimal separation were to be provided from the box culverts to an existing I2-inch sanitary sewer line, the edge of the boxes would be approximately five feet from several existing buildings. In addition, multiple drainage utility relocations would be required under the railroad tracks at Midway Road, and the box culverts would need to cross back under the railroad further to the west. HNTB Corporation Page 8 of 10 December 14, 1998 Other Project Issues Two other issues of note have been discussed, outside the limits of the Midway Road section. 1. Railroad Spur Crossings The two railroad spur crossings just west of Addison Road could prove difficult and timeconsuming to obtain. We recommend that coordination begin with DART as soon as a final alignment has been selected. 2. Realty Road Section The traffic volumes indicate that a four-lane undivided roadway would be adequate along the existing Realty Road alignment. Omitting a median from most of this section of the project would minimize the impact on adjacent parking lots and driveways. The roadway could still be widened for turn lanes at Midway Road and Surveyor Boulevard. Conclusions and Recommendations The primary goal, which has been expressed by Town of Addison staff for this project, is to relieve congestion on Belt Line Road. All the alternatives will provide some relief to Belt Line Road, however, no one alternative clearly stands out as preferred. The attached matrix presents presents a comparison associated with each alternative. Three overpass and three underpass alternatives were evaluated, and in each case, the corresponding underpass alternative was more expensive given that the extensive utility relocations required for Alternative 6 would result in its cost exceeding that of Alternative 5. An underpass would be more visually appealing than an overpass, however, the narrowing of Midway Road would increase traffic delays during the estimated 12 months of construction. Although a tunnel would create less noise impact, only five commercial buildings are located within the overpass limits on both sides of the railroad, including Charter Furniture. , :,.. If Town of Addison staff are comfortable with an overpass at this location, we would recommend that one of the overpass aiternatives be'selected. >" Of the three overpass alternatives analyzed, Alternative 5 pushes the south overpass wall within nine feet of the Charter Furniture building without a sidewalk for emergency access on the overpass. In addition, it would require DWU to accept 15 feet for maintenance of their 60" water line. This is their normal easement width for a much smaller service line. Alternative 3, like Alternative 5, has no ramps. Although it would require the purchase of the Charter Furniture building, this extra cost would be largely offset by construction cost savings. In addition, the purchase of this property would make for less constricted construction in this area. HNTB Corporation Page 9 of 10 December 14,1998 Alternative 1 requires the purchase of the Charter Furniture and MNBA buildings in order to make the entry ramp onto Arapaho Road safe at the merge point. Alternative 3 could be constructed with an exit ramp only, and no entry ramp. Therefore, the benefit of the entry ramp may be compared with the cost of the MNBA building to determine its justification. HNTB Corporation Page 10 of 10 December 14, 1998 .. ADDISON ALIGNMENT ALTERNATIVES Midway Road Section -Matrix of Issues ALTERNATIVE 1 Overpass with ramps on north DESCRIPTION OF side ISSUE Separated from Alignment railroad right-of-Description way Charter furniture Yes building take MBNA building take Yes (for ramp safety) Relocate DWU No water line Noise Yes Realign Midway for construction No sequence (4 lanes) Sump storm sewer No Move box culvert to north side of RIR; No other utility .. relocations Opinion of Probable $19.708.065 Cost (with 20% ( + buildings) contingencyl ALTERNA TIVE 2 ALTERNATIVE 3 ALTERNATIVE 4 Underpass with Overpass Underpass ramps on north without ramps without ramps side Same as 1 Same as 1 Same as 1 Yes Yes Yes Probably No No No No No . No Yes No Yes No Yes Yes No Yes . /-, No No No $21.920.110 $19.669.785 $21.881.830 ( + buildings) ( + building) ( + building) --ALTERNATIVE 5 ALTERNATIVE 6 Overpass Underpass without ramps; without ramps; without building without building take take Adjacent to railroad right-of-Same as 5 way No No No No No Possibly Yes Yes No Yes No No Yes Yes No $21.809.772 N/A ----------I . HNTB Corporation Page 1 of 1 December 14, 1998 I:I􀁾i i -J LETTER OF Job No, 25768 , The HNTB Companies TRANSMITTAL Date S!.I1e630, 14114Dalas Parkway, OeltasTe:ms 15240 (972)661-5626 December 17,1998 Arapaho Road Ext. To: James C. Pierce Jr., P.E. Re: Asst. City Engineer Town of Addison 16801 Westgrove Dr. Addison Texas 75001 0144 WE ARE FORWARDING TO YOU: NO. OF COPIES SHEET NO. LAST DATED DESCRIPTION ..".".".""1::".,,., .. 1.......,',.".".".,..,...........,. ,.. 􀀱􀀿􀁥􀀮􀁾􀀺􀀢􀀬􀀱􀁓􀀮􀀬􀀩􀀿􀀿􀁾􀀮􀀠􀀮􀀬􀀮􀀱􀀢􀀬􀀬􀀺􀀬􀀺􀀬􀀬􀀺􀀻􀁑􀁾􀁾􀁣􀀮􀀨􀁬􀁉􀀮􀁥􀀮􀁁􀁲􀀨􀁬􀁾􀁩􀀧􀀮􀀱􀁾􀁉􀀨􀀩􀁦􀁾􀁾􀁥􀀮􀀮􀁁􀁲􀀮􀁡􀀬􀁰􀀮􀁡􀀮􀁨􀀨􀀩􀀬􀁾􀁸􀀮 􀁴􀀺􀁡􀁬􀁍􀀮􀁩􀁾􀁾􀁬􀁬􀀺􀁹􀀮􀁒􀀬􀀬􀁾􀀺􀀮􀀬􀀬.. """""""""""•.""+"."'".".".,,.,,''',.,,.. , .".....".".".".".".".".".".".".".."."."....".".".".." ..,,' '''''"..."."."."''."."."...,, ....."."..... ..."..""""""""""".""..".".".".".."",,,,....,,'" .."..."...".""."....... I .. " .. ".. "·""..""....·..,,·· ....·,,·,,·,,·,,·," . ,.... .""......."........,......,."'".. "."".""""".."."".,,.,, """ ...."""."!."".""... ",... .."..".""""."."."... ",,.. ,,,, ... " ... THESE ARE TRANSMmED: D For approval 􀁾􀀠For your use D As requested 􀁾􀀠For review & comment PLEASE NOTE: c ......... .....".".,.., ........ , ... "."."..... -....... , .. ,., ................................. "".................. , .... " ....... · ........... H.H «. ,..,. ,. ................ iCenterline Of60" DWU water line shown in relationship to a Tangent alignment of Arapaho. We are having :ARS field check the distance between the RR RfW and the Charter furniture warehouse. We should have this ,iby 12/22/98 COPVTO: Dan Becker P.E, 2 I:I􀁾i i -) The HNTB Companies &tte 630, 14114 Datas f'a1kWey, Delas: Tams 7524{) (972) 561-562& LETTER OF TRANSMITTAL Job No. 25768 Date December 15, 1998 To: James C. Pierce, Jr., P.E. Asst. City Engineer Town ofAddison iP Box 144 Addison, Texas 75001-0144 Re: Arapaho Road Extension Phase II & III WE ARE FORWARDING TO YOU: NO. OF COPIES SHEET NO. LAST DATED DESCRIPTION .,,-" .. ,.. . ...................-..-,.-".-".-.. -"...............................................................................,......,. ..·.· ....· ...·.·.. 1.·.··.··.:::..···.•••••............: .................................... :..:..:..:..:..::.............................................................................................:..:......:..:......... THESE ARE TRANSMITTED: o For approval o For your use o As requested 􀁾􀀠For review & comment PLEASE NOTE:··························........................................................................................... .... I,Ifyou need additional copies, please let me knDw. ,I COPYTO: GBW Engineers Inc. Bruce Grantham P.E....,.... Jack Hatchell P.E. Daniel F. Becker P.E. ALIGNMENT STUDY CONCLUSIONS AND RECCOMENDATIONS ARAPAHO ROAD EXTENSION Town of Addison, Texas PROJECT DESCRIPTION The project consists of alignment studies, determination of right-of-way needs, meetings with property owners, and the preparation of right of way documents for Arapaho Road, from Addison Road to Marsh Lane. HISTORY OF STUDIED ALIGNMENTS The Town of Addison and our project team defined a 􀁤􀁥􀁳􀁩􀁧􀁾􀀠corridor earlier this year for the Arapaho Road extension. This corridor generally runs near or adjacent to the railroad track from Addison Road to just east of Surveyor Boulevard. The corridor angles toward the southwest as it crosses Surveyor Boulevard, then turns back to the west to follow the existing Realty Road to the Marsh Lane intersection. Within the design corridor, a preferred horizontal alignment has been established, with the exception of a 2,500 ±Joot section of roadway centered around the Midway Road intersection. Alternatives Considered for tbe Midway Road Section In recent months, the following alternatives have been evaluated for the Midway Road section: 1. Overpass with ramps on the north side requiring building acquisition(s) in this section. 2. Underpass with ramps on the north side (same horizontal alignment as Alternative 1). 3. Overpass without ramps (same horizontal alignment as Alternative 1). 4. Underpass without ramps (same horizontal alignment as Alternative 1). 5. Overpass without ramps requiring no building acquisition in this section. 6. Underpass without ramps (same horizontal alignment as Alternative 5). 7. Overpass with ramps on the south side (same horizontal alignment as Alternative 1). 8. Underpass with ramps on the south side (same horizontal alignment as Alternative 1). 9. Intersection at-grade. HNTB Corporation Page 1 of 10 December 14, 1998 CORRIDOR DESCRIPTIONS There are six alternates being pursued at the present. From these six alternates, one will be chosen to implement for the project. The alternates are described in detail below, with a brief list of major issues associated with each alternate. Alternate names in the following section only correspond to the roll plot drawings that were submitted to the Town of Addison, Texas. 1. ALTERNATE 1 -OVERPASS AT MIDWAY ROAD WITH RAMPS ON TIlE NORTH SIDE OF PROPOSED ARAPAHO ROAD Alternate 1 has the same beginning and ending points as all of the alternates. The corridor begins at the Marsh Lane and Realty Lane intersection on the west end. From this point, the corridor remains on the existing alignment of Realty Road, to a point of curve south of the existing substation west of Surveyor Boulevard. From there, the alignment follows on an angle south of the existing pump station and elevated storage tank, to a point of curve on the south and west side of the elevated storage tank. The alignment then parallels the railroad right-of-way to a point in front of the MBNA Building fronting on Centurion Way. The corridor then curves to the right and proceeds east, perpendicular with Midway Road, approximately 200' south of the existing at-grade crossing with the railroad. Once through Midway Road, the corridor curves to the left and follows parallel to the railroad right-of-way. The corridor then makes two at-grade crossings with wye tracks south of the east-west rail corridor, just west of Addison Road. Once on the east side of the tracks, the corridor ties into the future intersection of Arapaho Road and Addison Road on the east end. The proposed roadway would essentially be placed at existing grade for most of its entire length, except for the potential condition at Midway Road. The overpass at Midway Road would be a three-span precast prestressed I-beam bridge. The ramps associated with this alternate would be on the north side of this alternate between the proposed roadway and the railroad right-of-way. The ramps would be at-grade and would tie into the proposed roadway at a point where the project grade line returns to the existing grade. This alternate has several major issues of importance. • GEOMETRY -Geometrically the only issue is the ramp geometry. In order to tie-in with the proposed roadway, the ramp speed is controlled by the vertical alignment to a design speed of 25mph, resulting in a differential of more than IOmph between the ramp and the mainline. • SAFETY -A major safety issue is associated with the merge area for the westbound on ramp from Midway Road. The conditions may not allow for desired design speed, due to AASHTO guidelines for stopping sight distance and intersection sight distance. The taper rates from the Manual on Uniform Traffic Control Devices are also possible areas where HNTB Corporation Page 20f 10 December 14, 1998 deficiencies may occur with this corridor. But, the issues can be improved by lowering design speeds on the ramp or by creating a stop or signaled condition at the on ramp terminal. • RIGHT-OF-WAY -Impacts include the purchase of one and probably two buildings at Midway Road. The corridor also requires that a building at Addison Road be purchased as well as some of the mini storage facility at Surveyor Boulevard. • CONSTRUCflBILITY -The issues include construction sequencing for the overpass erection and relocation of the concrete surface ditch. This alternate does not affect the 60" Dallas Water Utilities transmission main. There are no foreseen impacts to the underground franchise utilities at Midway Road. • COST -This corridor is predicted to be the most costly alternate excluding the cost of right-of-way acquisition. 2. ALTERNATE 2 -UNDERPASS AT MIDWAY ROAD WITH RAMPS ON THE NORTH SIDE OF PROPOSED ARAPAHO ROAD The underpass horizontal alignment is the same as its overpass counterpart. Vertically, the corridor will underpass existing Midway Road. The corridor will require that Midway Road traffic be placed on a precast prestressed concrete structure. This alternate has several major issues of importance. • GEOMETRY -The issues are the same as the previous alternate. • SAFETY -The issues are the same as the previous alternate. • RIGHT-OF-WAY -The issues are the same as the previous alternate. • CONSTRUCTIBILITY -The issues include construction sequencing for the underpass construction and relocation of the concrete surface ditch. This alternate does not affect the 60" Dallas Water Utilities transmission main, but would require that it be placed behind the retaining walls along the depressed section of roadway_ The underground franchise utilities at Midway Road will require relocation and have to be maintained with temporary. • COST -This corridor is predicted to be one the most economic alternates excluding the cost of right-of-way acquisition and any lane-hour charges for reducing the number of lanes on Midway Road while the bridge is being constructed. HNTB Corporation Page 3 of 10 December 14, 1998 3. ALlERNAlE 3 -OVERPASS AT MIDWAY ROAD WITHOUT RAMPS ON THE NORTH SIDE OF PROPOSED ARAPAHO ROAD The overpass corridor follows the same horiwntal and vertical alignment alternates with ramps. This alternate has several major issues of importance. • GEOMETRY -There are no negative geometric issues with this corridor. • SAFETY -There are no negative safety issues with this corridor. • RIGHT-OF-WAY -The issues are the same as the alternate with ramps. • CONSTRUCTIBILITY -The issues are the same as the alternate with ramps. • COST -This corridor is predicted to be one the most economical alternatives, excluding the cost of right-of-way acquisition costs and any traffic congestion cost for reducing the number of lanes on Midway Road while the bridge is being constructed. 4. ALlERNAlE 4 -UNDERPASS AT MIDWAY ROAD WITHOUT RAMPS The underpass corridor follows the same horizontal and vertical path as its counterpart with ramps. This alternate has several major issues of importance. • GEOMETRY -The only negative geometric issue is the sag condition under Midway Road will most likely require the structure to be lighted. • SAFETY -The only safety issue is the underpass lighting. • RIGHT-OF-WAY -The issues are the same as the alternate with ramps. • CONSTRUCTIBILITY -The issues are the same as the alternate with ramps. • COST -This corridor is predicted to be the most economical alternate excluding the cost of right-of-way acquisition and any costs related to the reduction of traffic for reducing the number of lanes on Midway Road while the bridge is being constructed. HNTB Corporation Page 40f 10 December 14, 1998 5. ALTERNATE 5 -OVERPASS WITHOUT RAMPS -NO TAKING OF CHARTER FURNITURE WAREHOUSE The alignment of Arapaho Road for this alternative would parallel the railroad tracks at project crossing of Midway Road. The issues related to this alternate are: • GEOMETRY -The alignment would be on straight tangent, parallel to tracks. • SAFETY -No safety issues except sight distance of vertical geometry. • RIGHT-OF-WAY -The issues are the same as the alternate with ramps. • CONSTRUCTIBILITY -Same as Alternate 1, except retaining walls would require relocation of Dallas Water Utilities (DWU) 60" water line. • COST -The cost of this alternative is essentially the same as underpass alternative, Alternate 1. 6. ALTERNATE 6 -UNDERPASS WITHOUT RAMPS -NO TAKING OF CHARTER WAREHOUSE The alignment for Alternate 6 is the same as Alternate 5. The issues related to this alternate are: • GEOMETRY -Same as Alternate 5. • SAFETY -Sight distance in sag vertical curve-Flooding in Heavy Rainfall. • RIGHT-OF-WAY -Same as Alternate 5. • CONSTRUCTIBILITY -Requires construction and placement of retaining wall very close to and below the elevation of DWU 60" water line. Relocation of the water line is recommended. • COST -The cost of this alternate is approximately 5-percent greater than Alternate 5. HNTB Corporation Page 5 of 10 December 14, 1998 7. ALTERNATE 7· UNDERPASS WITHOUT RAMps· NO TAKING OF CHARTER WAREHOUSE The other alternatives considered in preliminary designs have been dropped from further consideration due to drainage and utility conflicts. Traffic Analysis The North Central Texas Council of Governments (NTCOG) prepared traffic assignments for the year 2020 for the five alternatives for the Arapaho Road Extension. These alternatives are described below. • "No Build" Alternative -What is the impact on adjacent streets if Arapaho Road is not extended? • "At-Grade" Alternative -Arapaho Road extended with its intersection with Midway Road at-· grade. • "Grade-Separated" Alternative· Arapaho Road Extended with a grade separation at Midway Road without ramps. • "Ramps on the North Side" Alternative -Arapaho Road extended with a grade separation at Midway Road and ramps on the north side of Arapaho Road. • "Ramps on the South Side" Alternative· Arapaho Road extended with a grade separation at Midway Road and ramps on the south side of Arapaho Road. Projected Traffic Volumes The table below presents a summary of projected traffic impacts for the extension of Arapaho Road with its intersection at Midway Road grade separated without ramps. Roadway Section Projected Daily Traffic Volumes by Year 2020 "No Build" "Grade Separated" Arapaho Road Addison Road to Midway Road 17,000 Midway Road to Marsh Lane 13,000 Belt Line Road Addison Road to Midway Road 58,000 54,000 Midway Road to Surveyor 47,000 42,000 Midway Road North of Arapaho Road 52,000 44,000 South of Arapaho Road 58,000 46,000 HNTB Corporation Page 60f 10 December 14, 1998 As shown in the above table, the extension of Arapaho Road from its current terminus to Marsh Lane reduces projected traffic on Belt Line and Midway Roads. Year 2020 volumes on Belt Line Road are projected to be approximately S,OOO vehicles per day (vpd) less with Arapaho Road extended. Volumes on Midway Road are projected to be reduced 8,000 to 12,000 vpd. Arapaho road is projected to carry 17,000 vpd east of Midway Road and 13,000 vpd west of Midway Road. The section of Arapaho Road, east of Midway road, should be constructed as a four-lane divided facility based on projected traffic volumes. West of Midway Road, Arapaho Road can be constructed as a four-lane undivided roadway. In summary, traffic projections prepared by NTCOG indicate that the extension of Arapaho Road to Marsh Lane will aid in reducing the projected future traffic on Belt Line and Midway Roads. Evaluation of Final Alternatives for Midway Road Section The alignment names in the following sections are as follows: 1. Overpass with ramps on on the north side requiring building acquisition(s) in this section. 2. Tunnel with ramps on the north side (same horizontal alignment as Alternative 1). 3. Overpass without ramps (same horizontal alignment as Alternative 1). 4. Tunnel without ramps (same horizontal alignment as Alternative 1). 5. Overpass without ramps requiring no building acquisition in this section. 6. Tunnel without ramps (same horizontal alignment as Alternative 5). 7. Overpass with ramps on the south side (same horizontal alignment as Alternative 1). 8. Tunnel with ramps on the south side (same horizontal alignment as Alternative 1). 9. At-grade. Horizontal and vertical alignments, along with Opinions of Probable Cost, were prepared for Alternatives 1 through 5. These costs are included in a matrix of issues related to these alternatives, in addition to Alternative 6. Due to extensive utility relocations in a tight construction corridor, the viability of Alternative 6 is questionable at this point. If the Town of Addison wishes to pursue this alternative, further coordination would be necessary with Dallas Area Rapid Transit (DART) and DWU prior to developing an Opinion of Probable Cost. HNTB Corporation Page 7 of 10 December 14, 1998 A discussion of the issues described in the attached matrix are provided below: • Charter Furniture Building Take -Moving the alignment south of the railroad provides space between Arapaho Road and the railroad right-of-way (ROW) for the existing 6O-inch DWU water line and the proposed double 9'xS' box culverts. • MNBA Building Take -Without taking the MNBA building, there is insufficient room to create a safe merge condition for the westbound entry ramp onto Arapaho Road. The lack of sight distance at the merge is more severe with the overpass than the underpass, due to the additional distance for merging the vertical alignment. The underpass alternative is not recommended without a stop condition on the ramp traffic. • Relocate DWU Water Line -There is 81 feet from the railroad ROW to the face of the Charter Furniture building. Consequently, the DWU water line, which is located approximately seven feet off the railroad ROW, would need to be relocated with Alternative 6 (underpass). Using a four-lane undivided roadway with 11-foot lanes for Alternative S (overpass), and providing a IS-foot easement for DWU. The south overpass wall would be located approximately nine feet from the Charter Furniture building. If a sidewalk were provided across the ramp for emergency access, the separation from the curb to the furniture building would be reduced to four feet. • Noise -Although truck traffic is likely to be low on the Arapaho Road extensions, noise may still be a source of complaint from affected business owners if an overpass is constructed. • Realign Midway for Construction Sequence -If the underpass were selected, a probable construction sequence would require the removal of one half of Midway Road at a time. In conjunction, Midway Road would have to be realigned and narrowed to four lanes through the construction zone on two occasions. The underpass construction could affect Midway Road in this manner for up to a year. • Sump Storm Sewer -All the underpass options would require the draining of the roadway under Midway Road. There appears to be sufficient grade to install a storm sewer from inlets in the depressed roadway to the concrete channel west of Surveyor. • Move Box Culvert to North Side of Railroad Right-of-Way -Alternative 6 (underpass) would require the installation of double 9'xS' box culverts on the north side of the railroad. If a minimal separation were to be provided from the box culverts to an existing 12-inch sanitary sewer line, the edge of the boxes would be approximately five feet from several existing buildings. In addition, multiple drainage utility relocations would be required under the railroad tracks at Midway Road, and the box culverts would need to cross back under the railroad further to the west. HNTB Corporation Page 8 of 10 December 14, 1998 Other Project Issues Two other issues of note have been discussed, outside the limits of the Midway Road section. 1. Railroad Spur Crossings The two railroad spur crossings just west of Addison Road could prove difficult and timeconsuming to obtain. We recommend that coordination begin with DART as soon as a final alignment has been selected. 2. Realty Road Section The traffic volumes indicate that a four-lane undivided roadway would be adequate along the existing Realty Road alignment. Omitting a median from most of this section of the project would minimize the impact on adjacent parking lots and driveways. The roadway could still be widened for turn lanes at Midway Road and Surveyor Boulevard. Conclusions and Recommendations The primary goal, which has been expressed by Town of Addison staff for this project, is to relieve congestion on Belt Line Road. All the alternatives will provide some relief to Belt Line Road, however, no one alternative clearly stands out as preferred. The attached matrix presents presents a comparison associated with each alternative. Three overpass and three underpass alternatives were evaluated, and in each case, the corresponding underpass alternative was more expensive given that the extensive utility relocations required for Alternative 6 would result in its cost exceeding that of Alternative 5. An underpass would be more visually appealing than an overpass, however, the narrowing of Midway Road would increase traffic delays during the estimated 12 months of construction. Although a tunnel would create less noise impact, only five commercial buildings are located within the overpass limits on both sides of the railroad, including Charter Furniture. If Town of Addison staff are comfortable with an overpass at this location, we would recommend that one of the overpass alternatives be selected. Of the three overpass alternatives analyzed, Alternative 5 pushes the south overpass wall within nine feet of the Charter Furniture building without a sidewalk for emergency access on the overpass. In addition, it would require DWU to accept 15 feet for maintenance of their 60" water line. This is their normal easement width for a much smaller service line. Alternative 3, like Alternative 5, has no ramps. Although it would require the purchase of the Charter Furniture building, this extra cost would be largely offset by construction cost savings. In addition, the purchase of this property would make for less constricted construction in this area. HNTB Corporation Page90flO December 14, 1998 Alternative 1 requires the purchase of the Charter Furniture and MNBA buildings in order to make the entry ramp onto Arapaho Road safe at the merge point. Alternative 3 could be constructed with an exit ramp only, and no entry ramp. Therefore, the benefit of the entry ramp may be compared with the cost of the MNBA building to determine its justification. HNTB Corporation Page 10 of 10 December 14, 1998 --------------ADDISON ALIGNMENT ALTERNATIVES Midway Road Section -Matrix of Issues AL TERNA TIVE 1 Overpass with ramps on north DESCRIPTION OF side ISSUE Separated from Alignment railroad right-of-Description way i Charter furniture Yes , building take M BNA building take Yes (for ramp safety) Relocate DWU No water line Noise Yes , Realign Midway forI􀀢􀀢􀀮􀁾􀀬􀀬􀀬􀀠No 􀁾􀁬􀁩􀁥􀁱􀁵􀁥􀁮􀁣􀁥􀀠(4 lanes) Sump storm sewer No 􀁾􀁾􀁾􀁾􀁾􀀭􀀭􀀭􀀭----I Move box culvert to north side of RIR; No other utility relocations Opinion of Probable $1 9,708,065 Cost (with 20% (+ buildings) contingency) ALTERNA TIVE 2 ALTERNATIVE 3 ! ALTERNATIVE 4 Underpass with Overpass Underpass ramps on north without ramps without ramps side Same as 1 Same as 1 Same as 1 Yes Yes Yes Probably No No -------------No No No No Yes No Yes No Yes Yes No Yes No No No $21,920,110 $19,669,785 $21,881,830 ( + buildings) (+ building) (+ building) ALTERNATIVE 5 Overpass without ramps; without building take Adjacent to railroad right-ofway No No Possibly Possibly Yes No No No $21,809,772 ALTERNATIVE 6 Underpass without ramps; without building take ----------------Same as 5 No No Yes No Yes Yes Yes N/A .' HNTB Corporation " Page 1 of 1 December 14, 1998 􀁨􀁾􀀱􀁉􀀯􀁬􀁔􀁃􀀠􀀨􀁾􀁉􀁲􀀯􀁾􀀡􀀠􀁾􀁉􀀠􀁾􀀯􀁆􀀠Mw-􀁾􀁾􀀠􀀦􀁪􀀭􀁾􀀠􀁘􀁾􀁦􀀠􀁴􀁊􀀨􀀩􀁶􀁕􀁾􀀠 NOIIh Central' TeJCaS 􀁃􀁯􀁵􀁮􀁣􀁾􀀠Or Governments November 24, 1998 Mr. Jack Hatchell Jack Hatchell & Associates P.O. Box 2660119 Plano, Texas 75026'()119 Dear Mr. Hatchell: Per your request of October 22, 1998, enclosed are the projected 2020 volumes for Arapaho Road, provided with six volume maps for various ·scenarios. Each map presents the volumes on the Addison Airport Tunnel. Listed below are the scenarios that have been modeled: • No-Build -Arapaho Road terminates at Addison Road (Airport Tunnel) • AI Grade -Arapaho Road extends 10 Marsh Lane (Airport·Tunnel) • Grade Separated -Arapaho Road extendS 10 Marsh LSne (no interchange with Midway Road) (Airport Tunnel) . • .Grade Separated with Full Ramps at Midway Road -Arapaho Road extends to Marsh Lane (full interchange at Midway Road) (Airport T urinel) • Grade Separated With Ramps at Midway Road -Arapaho Road extends to Marsh Lane (ramps exiting westbound Arapaho Road to northbound Midway Road and ramps exiling southbound Midway Road to westbound Arapaho Road (Airport Tunnel) • Grade Separated with Ramps al Midway Road -Arapaho Road extends to 􀁾􀀡􀁩􀁬􀁲􀁳􀁨􀀠Lane (ramps exiling westbound Arapaho Road to northbound Midway Road and ramps exiting southbound Midway Road 10 westbound Arapaho Road (No Airport Tunnel) If you have any questions regarding the Iraffic forecasts for Arapaho Road, please contact Mitzi Ward or me at (817) 695-9240. Sincerely, 􀁨􀀡􀀮􀀻􀀡􀁴􀀡􀁾􀀠􀀯􀁾􀁲􀁲􀁩􀁳􀀮P.E.· Director of Transportation . MW:ez Enclosures co: 1998-99 UPWP Element 5.03 Project File . 6'6 Six Fi&gs Drive, centerpoint Two P. O. Box 5888, Mlnglon ...... 76005·Sa8a 1817) 649·3300 FAX: 817·640·7609 (i)_d ..... ItJUUJ/UOlj 􀁾􀀠 􀁩􀁾􀀠 􀁩􀁾􀀱􀀠 􀁉􀁾􀁾􀀠 􀁾􀁾􀀠 􀁾􀀠QOORUMDR • 12 ... Iii AODISOIIRD 2J lit i 􀁾􀀠􀁾􀀠II N i Hi MlDWAYRD .. 18 42 12 MARSHtANE § 􀁾􀀠iiB 􀁾􀀬􀀬􀁾 􀁾􀀠 􀁾􀀠aUORUMDR 10 13 '" N 􀁾􀀠ADDISONRD N MIDWAYRD 42 36 57 52 'i 0 0:: (/) G 4:z [ 􀁾􀀠II) 0:: LJJ ..... ..J LJJ 􀁾􀀠MARSH LN 40 42 41 "., .. " -""........,,, ..... --􀁾􀀠r-____􀁾􀁑􀁕􀁾􀁏􀁬􀁬􀁩􀁒􀁾􀁕􀁍􀁾􀁄􀁾􀁒􀁾􀀭􀀫􀁾􀀭􀀭􀁊􀁭10 13 N MIDWAYRD1/􀁾􀀠I l 4 SURVEVOR BLVD ) \ 2 " \ \ 􀁍􀀬􀁎􀁊􀁾10 ROAD EXTENSION GRADE SEPARATED @MlrNVAYW/FULL RAMPS 2020 VOLUMES 11000 KELLER SPRINGS RD 'Z1 7 20 􀁾􀀠:r: 􀁾􀁜􀁾r-C/Jz a z􀁾􀀠􀁾􀀠;:0;:0 0,0[ 􀁾___1 r 13 ullD8ERG lilt!.. :: :: II 􀁉􀁾.) N EE.TLlERD 41 III Sl-71 "A41'!!l 8)􀁖􀀭􀁾􀀠-.tICMlnI'f_ . 􀁾􀁾􀁣􀁁...􀁉􀁏􀁲􀀻􀁬􀁾􀀠􀁾􀀠􀁾􀁾􀀠􀀮􀁾􀀽􀀭􀀭c c '"'. c c " ... 􀁾􀀠QUORUM DR 10 13 '" 􀁾􀀠N 􀁾􀀠AODISONRO 21 \MIDWAYRD §.... 􀁾􀁩􀀳􀀠 􀁾􀁾􀁾􀀠 !;( 3642 57 52 􀁾􀀠CDQex: C/lC) 4Z ir D. R (/) ex: w -' ....I W lI' « MARSHLN 40 42 41 , •• -,•• "" ",' •• d _ ............1'<'_.. Ii II!I 1,If 111' . ,I.' I ' ;' ',' 􀁾􀀠􀁦􀁓􀁾􀀠􀁾􀂧􀁓􀁾􀀠@.... 􀁾􀀠QUORUM DR 10 13 .... 􀁾􀀠AODISONRD N MIOWAYRD 42 44 '" 􀁾􀀠0c::: Y5 Z 4 If /'ij SURVEYOR BLVD III III 􀁾􀀠􀁾􀀠􀁾􀀠MARSH LN 42 I ARAPAHO ROAD EXTENSION GRADE SEPARAlED @MDWAYW/FULL RAIVIPS 2020 VOLUMES 11000 ;: 􀁾􀀠en ::t r-z "'"., '" '" r KELLER SPRINGS RO􀁾􀁾􀁾􀁾􀁜􀁾􀀭􀀭􀀭􀀭􀁾􀀷􀀭􀀭􀀭􀀭􀀭􀀧􀀱􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀱􀀬􀀱􀁾􀀱􀁪􀀬20 17 } g 0c: 􀁾􀀠en 􀁾􀀠0fl'l ?( c: z ;: ,jg jg C ;:􀁩􀁾􀁾􀁾􀀠 􀁩􀁾􀁆􀀽@) ; tn •􀁾􀀠I iliI 􀁺􀁾􀀠iH􀁳􀁬􀁊􀁾􀁬􀁩􀀠U7j 􀁾􀁌􀁌􀁪􀁦􀁳􀁂f««< R , ••.. 15 • .. .. ..M.. .. a 􀁾􀀠.. i 􀁲􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀁭􀁾􀁌.. 1f!IJ;'" .. ARAPAHO ROAD GRADE SEPARAlED@MJDVVAYWRAIVIPS (AIRPORT 1l.INNEL) 2020 Va..tJMES 11000 z ..J 􀁾􀀻􀀱􀀱􀀠i .. 7 :10 17 = .l; III: t !i! let Ii!! 􀁾􀀠arap & tunnel NFreewayN Principal, HOV NMnorN Collector, FrontageN Rarl1JS :107 17 :;; 11 l 􀁉􀁾􀀠1= N c 􀁾􀀠="r: ----\ Z .. ·􀁡􀁾􀀠A BELTUNERO 􀁾tiallMl T...as COl/MIDI' 􀁇􀁣􀁟􀁾T__ 􀁾􀁃􀁖􀁏􀁌􀁕􀁍􀁅􀁃􀁏􀁍􀁆􀁁􀁒􀁦􀁦􀁩􀁏􀁎􀀠Grade Separated Grade With Ramps No Build At Grade Separated South Side North Side No Tun ARAPAHO Addison to Midway Midway to Surveyor 24,000 6,000 17,000 13,000 28,000 17,000 18,000 17,000 18,000 17,000 BELTLlNE Addison to Midway Midway to Surveyor 58,000 47,000 53,000 46,000 54,000 42,000 50,000 45,000 46,000 42,000 46,000 42,000 MIDWAY North ofArapaho South ofArapaho South ofBelt Line 52,000 58,000 36,000 57,000 52,000 44,000 46,000 32,000 60,000 52,000 44,000 50,000 47,000 47,000 52,000 47,000 KELLER SPRINGS East ofAddison Tunnel West ofMidway 20,000 2,000 31,000 19,000 2,000 33,000 20,000 2,000 31,000 20,000 7,000 27,000 20,000 7,000 36,000 19,000 36,000 􀁾􀁾􀀠ALTERNATE TOWN OF ADDISON, TEXAS ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST SUMMARY OF COSTS FOR EACH ALTERNATE HNTB 1 GBW Engineers 12103198 DESCRIPTION ENGINEER'S ESTIMATED COST 􀁦􀁾􀀠ALTERNATE 4AU ALTERANTE 4AO ALTERANTE 4BU ALTERANTE 480 ALTERANTE 5 ALTERNATE 4· UNDERPASS CONDITION AT MIDWAY ROAD WITH RAMPS ALTERNATE 4· OVERPASS CONDITION AT MIDWAY ROAD WITH RAMPS ALTERNATE 4· UNDERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS ALTERNATE 4 ·OVERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS ALTERNATE 5· OVERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS $ 19,708,065.60 $ 21,920,109.60 $ 19,669,785,60 $ 21,881,829.60 $ 21,809,772.00 U􀁾􀀺􀁜􀁈􀀠'tVio;; '" '. 􀁾􀀠􀁩􀁲􀁾􀀠lL 12!gjq8 TOWN OF ADDISON, TEXAS HNTB I GBW Engineers 12103198 ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE , ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATE 4 -UNDERPASS CONDITION AT MIDWAY ROAD WITH RAMPS ITEM NO ITEM DESCRIPTION UNIT QUANTITY ENGINEERS ESnMATE , ROADWAY UNIT PRICE AMOUNT 100 PREP. & MAINT. OF RIGHT-Of-WAY STA 78.0 $ 2,500.00 $ 195,000.00 . 104 REMOVE OLD CONCRETE (PVMT.) SY 7,200 $ 2.00 $ 14,400.00 110 EXCAVATION (ROADWAy) CY 35,500 $ 3.20 $ 113,600.00 132 EMBANKMENT (ORDINARY COMPACTION) CY 21,000 $ 8.50 $ 178,500.00 . 260 LIME TREATED SUBGRADE (6 in) (Ramp') SY 19,430 $ 1.60 S 31,088.00 260 LIME TREATED SUBGRADE (8 in) (Mainline) SY 380,300 $ 1.60 $ 608,480.00 360 CONCRETE PAVEMENT (10 in) (Mainline) SY 380,300 $ 24.00 $ 9,127,200.00 360 CONCRETE PAVEMENT (10 in) (Ramps) SY 19,430 , $ 24.00 $ 466,320.00 360 MONOLITHIC CURB (TYPE A) (6 in) LF 28,450 $ 2.00 $ 56,900.00 423 RETAINING WALL (CAST IN PLACE) SF 30,000 $ 40.00 $ 1,200,000.00 500 MOBILIZATION LS 1 $ 20,000.00 $ 20,000.00 502 BARRICADES, SIGNS AND TRAFFIC HANDLING LS 1 $ 20,000.00 $ 20,000.00 666 REFLECT PAVE MARKINGS LF 80,000 $ 1.50 $ 120,000.00 · LIGHTING LF 12,000 $ 35,00 S 420,000,00 , · TRAFFIC SIGNALS (PER INTERSECnON) EA 3 $ 80,000.00 S 240,000.00 681 TEMPORARY TRAFFIC SIGNAL EA 2 $ 10,000.00 $ 20,000.00 · ROADWAY STRUCTURE SF 6,150 $ 45.00 $ 276,750.00 • INLETS EA 30 $ 2,500.00 $ 75,000.00 MANHOLES EA 5 $ 5,000.00 S 25,000.00 LATERALS LF 1,230 $ 50,00 $ 61,500.00 24" RCP LF 3,000 $ 50.00 $ 150,000.00 30"RCP LF 1,530 $ 65,00 $ 99,450,00 ' 3S"RCP LF 500 $ 80,00 $ 40,000,00 i 6'X S' RCBC IF 260 $ 220.00 $ 57,200.00 7'X S'RCBC LF 400 $ 250.00 $ 100,000,00 : 9'X 5' RCBC LF 500 $ 300,00 $ 150,000.00 ' 2-7'XS'RCBC LF 800 S 500.00 5 400,000.00 2 -9' X 5' RCBC LF 1,460 $ 630.00 $ 919,800,00 10' X 6' RCBC LF 920 $ 720.00 $ 662,400.00 la' X 7' RCBC LF 130 $ 760.00 $ 98,800.00 HEADWALL CONCRETE CY 60 $ 600.00 $ 36,000.00 REMOVE CONCRETE CHANNEL LINING SY 11,200 $ 10.00 $ 112,000.00 REMOVEIREPLACE CONCRETE CHANNEL LINING SY 1,300 $ 60.00 $ 78,000,00 OTHER UTILITY RELOCATIONS LS 1 $250,000.00 $ 250,000.00 $ 16,423,388.00SUBTOTAL $ 3,284,677.6020% CONTINGENCY TOTAL CONSTRUCTION COST $ 19,708,065.60 TOWN OF ADDISON, TEXAS HNTB I GBW Engineers 12103198 ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATE 4 -OVERPASS CONDITION AT MIDWAY ROAD WITH RAMPS ITEM NO ITEM DESCRIPTION 􀁩􀁾􀀧􀁾􀀧􀀠ENGINEERS ESTIMATE ROADWAY UNT 100 PREP. & MAINT. Of RIGHT·Of·WAY STA 78.0 $ 2,500.00 $ 195,000.00 104 REMOVE OLD CONCRETE (PVMT.) SY 7,200 $ 2.00 $ 14,400.00 110 EXCAVATION (ROADWAY) CY 9,650 $ 3.20 $ 30,880.00 132 EMBANKMENT (ORDINARY COMPACTION) CY 202,540 $ 8.50 $ 1,721,590.00 􀁾􀁄SUBGRADE (6 in) (Ramps) SY 19,430 $ 1.60 $ 31,088.00 D SUBGRADE (6 in) (Mainline) SY 360,300 $ 1.60 $ 608,460.00 AVEMENT (10 in) (Mainline) SY 360,300 $ 24.00 $ 9,127,200.00 360 CONCRETE PAVEMENT (10 in) (Ramps) SY 19,430 $ 24,00 $ 466,320.00 360 MONOLITHIC CURB (TYPE A) (6 in) LF 28,450 􀁾􀀠56,900.00 423 RETAINING WALL (CAST IN PLACE) SF 45,000 $ $ 1,800,000.00 500 MOBILIZATION LS 1 20,000,00 502 BARRICADES, SIGNS AND TRAFFIC HANDLING LS 1 $ 20,000.00 $ 20,000,00 886 REFLECT PAVE MARKINGS LF 80,000 $ 1.50 $ 120,000,00 • LIGHTING Lf 12,000 $ 35,00 $ 420,000.00 • TRAFFIC SIGNALS (PER INTERSECTION) EA 3 $ 80,000.00 $ 240,000.00 681 TEMPORARY TRAFFIC SIGNAL EA 4 $ 10,000,00 $ 40,000,00 · ROADWAY STRUCTURE SF 9,550 $ 45,00 $ 429,750,00 INLETS EA 30 I$ 2,500,00 $ 75,000.00 LATERALS LF 1,230 I$ 50,00 $ 61,500.00 30" RCP LF 530 $ 34,450.00 36" RCP LF 500 $ 40,000.00 6'X5' RCBe LF 260 $ 220.00 $ 57,200.00 7'X5'RCBC LF 400 $ 250.00 $ 100,000.00 LF 500 $ 300.00 $ 150,000.00 2· 7'X 5' ReBC LF 800 $ 500,00 $ 400,000.00 2·9' X 5' RCBC LF 1,460 $ 630.00 $ 919,800.00 10' X6' ReBC LF 920 $ 720.00 $ 662.400.00 10' X 7' RCBC LF 130 $ 750.00 $ 98,800.00 HEADWALL CONCRETE CY 60 $ 600.00 $ 36,000,00 REMOVE CONCRETE CHANNEL LINING SY 11,200 $ 10.00 $ 112,000.00 REMOVE/REPLACE CONCRETE CHANNEL LINING SY 1,300 $ 60.00 $ 78,000,00 OTHER UTILITY RELOCATIONS LS 1 $100,000.00 $ 100,000.00 SUBTOTAL $ 18,266,75ROO 20% CONTINGENCY $ 3,653,351,60 TOTAL CONSTRUCTION COST $ 21,920,109,60 TOWN OF ADDISON, TEXAS HNTB I GBW Englne.rs 12103198 ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATE 4 -UNDERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS ITEM NO ITEM DESCRIPTION UNIT QUANTITY ENGINEERS ESTIMATE ROADWAY UNIT PRICE AMOUNT 100 PREP. & MAINT. OF RIGHT-OF-WAY STA 7B.0 $ 2,500.00 S 195,000.00 104 REMOVE OLD CONCRETE !PVMT.) SY 7,200 $ 2.00 $ 14,400.00 110 EXCAVATION (ROADWAY) CY 35,500 $ 3.20 $ 113,600.00 132 EMBANKMENT (ORDINARY COMPACTION) CY 21,000 $ B.50 $ 178,500.00 260 LIME TREATED SUBGRADE (6 In) (Ramps) SY 19,430 $ 1.60 $ 31,08B.00 260 LIME TREATED SUBGRADE (6 in) (Mainline) SY 380,300 $ 1.60 $ 608.480.00 360 CONCRETE PAVEMENT (10 in) (Mainline) SY 380,300 $ 24.00 $ 9,127,200.00 360 CONCRETE PAVEMENT (10 in) (Ramps) SY 19,430 $ 24.00 $ 466,320.00 360 MONOLITHIC CURB (TYPE A) (6 in) LF 25,000 $ 2.00 S 50,000.00 423 RETAINING WALL (CAST IN PLACE) SF 30,000 $ 40.00 $ 1,200,000.00 500 MOBIUZATION LS 1 $ 20,000.00 $ 20,000.00 ; 502 BARRICADES, SIGNS AND TRAFFIC HANDLING LS 1 $ 20,000.00 $ 20= 666 REFLECT PAVE MARKINGS LF 75,000 $ 1.50 $ 112,50 · LIGHTING LF $ 3MO $ 402,500.00 · TRAFFIC SIGNALS (PER INTERSECTION) EA 3 $ 80,000.00 S 240,000.00 6Bl TEMPORARY TRAFFIC SIGNAL EA 2 $ 10,000.00 $ 20,000.00 · ROADWAY STRUCTURE SF 6,150 $ 45.00 $ 276,750.00 EA 30 $ 2,500.00 $ 75,000.00 EA 5 $ 5,000.00 $ 25,000.00 LATERALS LF 1,230 $ 50.00 $ 61,500.00 24" RCP LF 3,000 $ 50.00 $ 150,000.00 30"RCP LF 1,530 $ 65.00 $ 99,450.00 36"RCP LF 500 $ 80.00 $ 40,000.00 6' X 5' RCBC LF 260 $ 220.00 $ 57,200.00 7'X5' RCBC LF 400 $ 250.00 $ 100,000.00 S'X S' RCBC LF 500 $ 300.00 $ 150,000.00 2-7' X 5' RCBC LF BOO $ 500.00 $ 400,000.00 2 -9' X S' RCBC LF 1,460 $ 630.00 $ 919,800.00 LF 920 $ 720.00 $ 662,400.00 la' X 7' RCBC LF 130 $ 760.00 $ 98,800.00 HEADWALL CONCRETE CY 60 $ 600.00 $ 36,000.00 REMOVE CONCRETE CHANNEL LINING SY 11,200 $ 10.00 $ 112,000.00 REMOVE/REPLACE CONCRETE CHANNEL LINING SY 1,300 $ 60.00 $ 78,000.00 OTHER UTILITY RELOCATIONS LS 1 $250.000.00 $ 250,000.00 SUBTOTAL $ 16,391,488.00 20% CONTINGENCY $ 3,278,297.60 TOTAL CONSTRUCTION COST $ 19,669,785.60 ----.. TOWN OF ADDISON, TEXAS HNTB /GBW Engineers 12103198 ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATE 4 -OVERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS ITEM NO ITEM DESCRIPTION GINEERS ESTIMATE ROADWAY UNIT PRICE AMOUNT 100 PREP. & MAINT. OF RIGHT-OF-WAY .0 $ 2.500.00 $ 195.000.00 104 REMOVE OlD CONCRETE (PVMT.) 2.00 $ 14,400.00 110 EXCAVATION (ROADWAY) 3.20 $ 30.880.00 132 EMBANKMENT (ORDINARY COMPACTION) C $ 8.50 $ 1.721.590.00 􀀬􀁾􀀠􀁉􀀢􀁍􀀢􀀧􀁾􀀢􀀢􀀢􀁾'" 􀀮􀀢􀁾􀀮􀀬􀀬􀀬􀀠S 19.430 $ 1.60 $ 31.08B.OO SUBGRADE (6 in) (MainlineJ SY 380.300 $ 1.60 $ 606,480.00 360 PAVEMENT (10 in) (MainlineJ SY 380.300 $ 24.00 $ 9.127.200.00 360 TE PAVEMENT (10 in) (Ramps) SY 19.430 $ 24.00 $ 466.320.00 360 MONOLITHIC CURB (TYPE A) (6 in) LF 25.000 $ 2.00 $ 50.000.00 423 RETAINING WALL (CAST IN PLACE) SF 45.000 $ 40.00 $ 1.800.000.00 500 MOBILIZATION LS 1 $ 20.000.00 $ 20.000.00 502 BARRICADES. SIGNS AND TRAFFIC HANDLING LS 1 $ 20.000.00 $ 20.000.00 666 REFLECT PAVE MARKINGS IF 75.000 $ 1.50 $ 112.500.00 · LIGHTING IF 11.500 $ 35.00 $ 402.500.00 · TRAFFIC SIGNALS (PER INTERSECTION) EA 3 $ 80.000.00 $ 240.000.00 681 TEMPORARY TRAFFIC SIGNAL EA 4 $ 10.000.00 $ 40.000.00 • ROADWAY STRUCTURE SF $ 45.00 $ 429.750.00 INLETS EA 30 $ 􀁾􀀷􀀵􀀧􀀰􀀰􀀰􀀧􀀰􀀰􀀠LATERALS IF 1.230 $ 61.500.00 30" RCP IF 530 $ 34.450.00 36" RCP IF 500 $ 80.00 $ 40.000.00 S'XS' RCBC IF 260 $ 220.00 $ 57.200.00 7'X 5' RCBC IF 400 $ 250.00 $ 100.000.00 9'X 5' RCBC IF 500 $ 300.00 $ 150.000.00 2· 7'X 5' RCBC LF aoo $ 500.00 $ 400,000.00 2-9'XS'RCBC LF 1.460 $ 630.00 $ 919.800.00 10' X 6' RCBC LF 920 $ 720.00 $ 662,400.00 10' X 7' RCBC LF 130 $ 760.00 $ 98.800.00 HEADWALL CONCRETE CY 60 $ 600.00 $ 36.000.00 REMOVE CONCRETE CHANNEL LINING SY 11.200 $ 10.00 $ 112.000.00 REMOVE/REPLACE CONCRETE CHANNEL LINING SY 1.300 $ 60.00 $ 78.000.00 OTHER UTILITY RELOCATIONS lS 1 $100.000.00 $ 100.000.00 SUBTOTAL 858.00 20% CONTINGENCY $ 3.646.971.60 TOTAL CONSTRUCTION COST $ 21.881.829.60 TOWN OF ADDISON, TEXAS HNTB 1GBW Engineers 12/03198 ARAPAHO ROAD EXTENSION FROM ADDISON ROAD TO MARSH LANE ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST ALTERNATE 5· OVERPASS CONDITION AT MIDWAY ROAD WITHOUT RAMPS ITEM NO QUANTITYITEM DESCRIPTION UNIT ENGINEERS ESTIMATE ROADWAY UNIT PRICE AMOUNT 100 STAPREP. & MAl NT. OF RIGHT-OF-WAY 78.0 $ 2,500.00 $ 195,000.00 104 REMOVE OLD CONCRETE IPVMT.) SY 7,200 $ 14,400.00 110 $ 2.00 EXCAVATION (ROADWAY) CY 6,035 $ 19,312.00 132 $ 3.20 EMBANKMENT (ORDINARY COMPACTION) CY 86,360 $ 734,060.00 260 $ 8.50 LIME TREATED SUBGRADE 16 in) (Ramps) SY 19,430 $ 31,088.00 260 $ 1.60 LIME TREATED SUBGRADE (6 in) (Mainline) SY 380,300 $ 1.60 $ 608,480.00 360 CONCRETE PAVEMENT (10 in) (Mainline) SY 380,300 $ 24.00 $ 9,127,200.00 360 CONCRETE PAVEMENT (10 in) (Ramps) SY 19,430 $ 466,320.00 360 $ 24.00 MONOLITHIC CURB (lYPE A) (6 in) LF 24,750 $ 2.00 $ 49,500.00 423 RETAINING WALL (CAST IN PLACE) SF 45,000 $ 40.00 $ 1,800,000.00 500 MOBILIZATION LS 1 $ 20,000.00 $ 20,000.00 502 LS LS 1 $ 20,000.00 666 BARRICADES, SIGNS AND TRAFFIC HANDLING $ 20,000.00 1-::LF 75,000 $ 112,500.00REFLECT PAVE MARKINGS $ 1.50 · ¢"'􀀡􀀵􀀧􀀷􀁲􀀢􀀧􀁃􀁾•11,500 $ 402,500.00LIGHTING LF $ 35.00 · 􀀧􀁜􀀴􀁾􀀺􀀧􀀻􀀮􀀠 􀁩􀀮􀀭􀁣􀀭􀀺􀁾􀀻􀀬 $ 240,000.00TRAFFIC SIGNALS (PER INTERSECTION) EA 3 $ 80,000.00 􀁾􀁾􀀮􀁾􀀢􀁾􀀠EA is 40,000.00681 TEMPORARY TRAFFIC SIGNAL 4 is 10,000.00 􀁾􀁾􀁾􀁾􀀺􀀠• t.o:;; 􀀮􀁾􀁾􀀧􀀠􀁾􀀧SF is 429,300.00ROADWAY STRUCTURE (Ii'/'",:'􀀹􀀧􀁾􀀰􀀰􀀠INLETS EA .00 $ 75,000.00 Cii'/,.' t'!,'l:i7'.:.MANHOLES EA 0.00 $ 25,000.00 LATERALS LF 1,230 is 50.00 $ 61,SOO.00 {P" ,:' 􀁾. 24"RCP $ 150,000.00 1LF 3,000 is 50.00 I t; .:.".:.:;3 ,LF30"RCP 1,530 $ 65.00 $ 99,450.00 , I t}:M$ 40,000.00 6'XS' RCBC 36" RCP LF 500 $ 80.00 $ 57,200.00 7'XS'RCBC LF 260 is 220.00 LF is 2S0,00 $ 100,000.00 9'XS'RCBC 400 $ 150,000.00 2-7' X 5' RCBC LF 500 is 300.00 $ 400,000.00 2-9' X S' RCBC LF 800 $ 500.00 is 919,800.00 10' X6' RCBC LF 1,460 $ 630.00 $ 662,400.00 10'X7' RCBC LF 920 $ 720.00 $ 98,800.00 HEADWALL CONCRETE LF $ 760.00130 $ 36,000.00 REMOVE CONCRETE CHANNEL LINING CY $ 600.0060 SY 11,200 $ 10.00 $ 112,000.00 REMOVEJREPLACE CONCRETE CHANNEL LINING $ 60,00SY 1,300 $ 􀀷􀁾􀀬􀀰􀀰􀀰􀀮􀀰􀀰􀀠$ 700,000.00 OTHER UTILITY RELOCATIONS RELOCATE 60" WATER MAIN 2,000 $ 350.00LF 1 $100,000.00 $ 100,000.00LS $ 18,174,810.00SUBTOTAL $ 3,634,962.0020% CONTINGENCY TOTAL CONSTRUCTION COST $ 21,809,772.00 Eoopcc.xls 12/2/98 􀁔􀁒􀁁􀁾􀁃􀁖􀁏􀁌􀁕􀁍􀁅􀁃􀁏􀁍􀁐􀁁􀁒􀁦􀁦􀁩􀁏􀁎􀀠Grade Separated Grade With Ramps No Build At Grade Separated South Side ARAPAHO Addison to Midway 24,000 17,000 28,000 Midway to Surveyor 6,000 13,000 17,000· BELT LINE Addison to Midway 58,000 53,000 54,000 50,000 Midway to Surveyor 47,000 46,000 42,000 45,000 MIDWAY North ofArapaho 52,000 36,000 . 44,000 32,000 South ofArapaho 58,000 57,000 60,000 South ofBeh Line 52,000 46,000 52,000 􀁾􀁾􀁾􀂭􀁻􀀱􀀭􀁾􀀠􀁰􀁾􀁻􀁲􀀭􀁾􀀠 ---ARAPAHO ROAD NO BUILD ALTERNATIVE 2020 VOLUMES /1000 '" 􀁾􀀠::t '" >% m 􀁾􀀠􀀩􀁾􀀠'" _____V 􀁾􀀠KELLER SPRINGS RD '" I(l !ii 􀁾􀀠47 47 -J N 􀁾􀀠0 􀁾􀀠0c: A0s:: el c: '" s::􀁾􀀠0􀁾􀀠'" Arap_Nobuild'" 0 !ll ./<0 /\/Freeway 13 I\/.Principal, HOV􀁾􀁦I\RAPAI-OR LINDBERG DR 8 I\/.Mnor1\/Q)lIector, Frontage8l 􀁾􀀠-/\/Ramps'" BELT UNE AJ 58 '5/' 71 ;Jp :......."""T_ ",;W -== Cc",!ldJIlfOo_=-. n-lID'fIMkalta􀁾􀀠 ARAPAHO ROAD EXTENSION AT GRADE 2020 VOLUMES 11000 􀁾􀁅􀁌􀁌􀁅􀁒SPRINGS RD I:;; \;;0 lCJ) s:: :J: 5 r Z I:E 􀀺􀁾􀀠:::0 o o c: o :::0 c:s:: o;;0 -o 􀁾􀁟􀀭􀀭􀀧􀁊􀀢􀀢􀀧􀀠21 w -BELT LINE RD 46 ... '" 􀁾􀁌􀀭-S \ Arap_ag.shp NFree.vay IV Principal IVMnorN Collectors, FrtgIVRarrps 􀀭􀁾􀀠N jJt W*E ARAPAHO ROAD EXTENSION GRADE SEPARATED @MIDWAY RD 2020 VOLUMES 11000 KELLER SPRINGS RD s: » "Is: » 106l \_ 0 Ie::J: 0 0r 1 􀁾􀀠0U5 :;0z 􀁾􀀠􀁾􀀠es: 0 :;0t!> Jel el I 􀁾il i 􀁾􀀠;0 !Xl 􀁾􀀠RAPAHORD .. 􀀧􀁾􀀭􀀧􀀷􀀺13 13... (J) I 42 54 55 tl9BELT LINE RD 5'; 􀁉􀁾􀀠43 􀁾􀁜􀀠Arap..9S.shp NFreewayNAincipal NMnorN Collectors, Frtg IVRarT1Js􀁾􀀠NW*E L....-S I ARAPAHO ROAD EXTENSION GRADE SEPARATED @MIDWAYW/RAMPS 2020 VOLUMES 11000 \ KELLER SPRINGS RD 􀁾􀀠. \ -" 􀁾􀀠\' Zr \ I g􀁾􀀧i \§ (\) i?< \0; 010 •"I 􀀮􀁾􀀠,z·o0 􀁾􀀠• 􀁉􀁾􀀠􀁾􀀠" 10 ° I.' ' 􀁾􀁾􀁁􀁈􀁏􀁒􀁄􀀠􀁾􀀠• UNDBE"GOR_A " A++)8\ 1-" • -j--,.-f-'"24 28 • BElTUNERO I ..' "I 􀁾􀁾􀀠􀁾􀀮􀀮􀀭􀀭􀀭􀀭􀀭􀀭􀀧􀀠'" -.. I III , 􀁾􀀠.. .' ., '" J ' AraP.-9SfTlll·shpIVFIVPri";IVMnorIV Collectors. FrtgIV Rarll:ls NW+E S PROJECT #92-094 Arc::l.pc::l.ho Roc::l.c1. Extension UTILITIES COORDINATION IS' MANAGER: 13ruce Grc::l.nthc::l.m Print Date: October H', 1992 (4:29pm) UTILITY COMPANY CONTACT PHONE &FAX PATE ACTIlI'ITY /RESPONSE: FOLLOW 0'1' NOTES LODe Star Gas Co. 1015 Hutton St. Carrollton, TX 75006 Howanllewis Ph: 972-323·8936 h: 10/15/98 Sent letter and map to Howard lewis. TU Electric 1015 Hutton St. Carrollton, TX 75006 Todd Guinn Ph: 972-323·8928 Fx: 9]2.323·8925 10/15/98 Senllelter and map to Todd Guinn. Southwestern Bell 275 N. Greenville, 2nd Floor Richardson, TX 75081 Tim Beidelman Ph: 214·46404095 Fx: 10[15/98 Sent letter and map to Tim Beidelman. TCI 327 Gross Road Mesquite, TX 75149 Don Burkhart Ph: Fx: 10/15/98 Sent leiter and map to Don Burkhart. MCI Tech Support Dept. 28551642 2250 lakeside Drive Richardson, TX 75082 Michael White Ph: 972-498·6041 Fx: 10/15/98 Sent letter and map to Michael White. WorldCom 2477 Gateway Drive Irving, TX 75063 Theresa Hardin or Jim Dunn Ph: 972-753·1900 Fx: 10/15/98 Sent leiter and map to Jim Dunn. Harron Cable TV P. D. Box 2628 Waxahachie, TX 75165 Dennis Anderson Ph: fl: 10115198 Sent leiter and map to Dennis Anderson. .t::\.•. v·· p.l 􀁏􀁯􀁾􀀠15 98 10:332 Jaok Hat-ohe1l 972-424-13S8 Jack HatcheD & Associates P.O. Box 260119 Plano, Texas 75026-0119 (972424-1368) Telephone & FAX FAX To: James C. Pierce, Jr., P.E., DEE Assistant City Engineer Town ofAddison (972)450.2837 From: Jack Hatchell, P.E. Date: October IS, 1998 James· Please find attached the traffic assignments for the "No Build" alternative for Arapaho Road. As you can see, the extension ofArapaho Road does provide relief to Belt Line and Midway Roads. I will have a comparison ofthe alternatives to include ''No Build" for our meeting next week. Please do not hesitate to can me ifyou have any questions or need additional information. Number ofpages inchlding this sheet '2. p.2 Oot15 S8 10.33a Jaok Hatohell 972-424-1368 § I lit 􀁚􀁾􀀠􀁾􀁉􀀧􀁾􀁪􀁬􀀠ilJ 􀁾􀁌􀁌􀁪􀁦􀁾􀁃􀀹􀀠,f««< IE \ '" 􀁾􀀭-;: QUORUM OR II 12 '" iii AODISOIIRD 25 24 I , i 􀁾􀀠III!i V 􀁾􀀠􀁍􀁉􀁄􀁗􀁁􀀩􀀧􀁾􀁄 􀀠58 52 􀁾􀀠Ii 􀁾...vo \If 2:B I z ~ ' V J-q 􀁾􀀠􀁾􀁾􀁾􀁾􀀠u/vc,U.--f-- i v:j 􀁾􀁾􀁾􀁾􀁾􀁲􀂭􀁾􀀨􀀩􀁾􀁾􀁾􀁾􀀠 􀂷􀁦􀁣􀁾􀁾􀀠􀀬􀁶􀁴􀁕􀁌􀁾 􀁜􀁾􀁾􀀬􀁾􀀩􀀠 􀀯􀁾􀁾􀀠􀁉􀁜􀁇􀀭􀁆􀁾􀀱􀁊􀀬􀁻􀀭􀀸􀁫􀀮􀀠 '3 t:t 􀁾􀁾􀀠B.Jf hI\11 e /e) 􀁾􀁴􀁴􀁌􀀵􀀠􀁾􀀺􀁉􀀠'31 tf/) 􀁾􀁾􀂻􀁗􀀧􀁩􀀧􀀭􀀧vL-1nA&rr1M yJuJJJ 􀁾􀀠v1 􀁃􀂣􀁊􀁾􀀠􀁶􀁶􀁦􀁾i 􀁲􀁾􀁾􀀡􀁊􀁾􀀠('for> &:.d􀁾J2,() North Central Texas Council Of Governments July 14, 1998 Mr. Jack Hatchell Jack Hatchell & Associates P.O. Box 2660119 Plano, TX 75026-0119 Dear Mr. Hatchell: Enclosed are maps of the projected 2020 volumes for Arapaho Road per your May 29, 1998, request. Twenty-four hour volumes were developed for Arapaho Road using the Dallas-Fort Worth Regional Travel Model. Three scenarios were modeled for the facility with each alternative extending Arapaho from its current terminus at Addison Road to Marsh Lane as a four-lane facility. Arapaho was mOdeled at grade in the first alternative. The second alternative modeled Arapaho grade separated at Midway Road with no connections at Midway. The last alternative also modeled a grade separation at Midway Road, but ramps with connecting the two roads. If you have any questions regarding the Arapaho Road assignments, please contact me or Mitzi Ward of my staff at (817) 695-9240. Sincerely, 􀁾􀁦􀁾􀀠Michael Morris, P.E. Director of Transportation MM:db Enclosure 616 Six Flags Flags Drive, Centerpoint Two P. O. Box 5886, Mington, Texas 76005·5668 (817) 640·3300 FAX: 817-640·7806 (i)recycled paper ARAPAHO ROAD EXTENSION AT GRADE 2020 VOLUMES 11000 KELLER SPRINGS RD I Arap_ag.shp IVFreevvayIVPrincipal0􀁾􀀠IVMnorc:::r: 􀁉􀁾􀀠\g 0 /\/Collectors, Frtg 􀁾􀀠IVRarrpss:: 0 ;:u.... •z 􀁾􀁉􀀠􀀭􀀭􀀭􀁜􀁾􀀠􀀯􀁾􀀧􀁉􀁾􀀠+H-+-......... '" 􀁾􀀮􀀠;' Ie􀁾􀀠1/1 [---8RAPAHO R 􀁾􀀠􀁲􀁕􀁎􀁄􀁂􀁅􀁒􀁾􀁾􀀭1 0/rc: rI. ' D! • I _./•.' N 6 􀁤􀂷􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀽􀀱􀀠-::-:---L-􀁾􀀠'4 I I J 24 '" '" 􀁾􀀠'" ././46 s3--------.....L/54 NBELT LINE RD 􀀮􀁾􀀠 46 N\ j...-􀁾􀀭􀀭􀀭􀀭68 W*E S --i 􀁌􀁾􀀠4 SURVEYOR BLvO"-l􀁾􀀱􀀠 ADDISONRD 􀀭􀀬􀁾􀀬􀀬􀀭􀀭􀀭􀀭􀀧􀀭􀀢􀀧􀀢􀀠\, IL! o i o MIDWAYRD 57-'I --21 ) \ '--53 􀁾􀁃􀁖􀁏􀁌􀁕􀁍􀁅􀁃􀁏􀁍􀁐􀁁􀁲􀁵􀁦􀁦􀁩􀁏􀁎􀀠At Grade Grade Separated Grade Separated tJv tkrnp 5 With Ramps South ARAPAHO Addison to Midway 24,000 17,000 28,000 Etvd-Midway to Surveyor 6,000 13,000 17,000 W€5!BELT LINE Addison to Midway 53,000 54,000 50,000 Midway to Surveyor 46,000 42,000 45,000 MIDWAY North ofArapaho 36,000 44,000 32,000 South ofArapaho 57,000 60,000 South ofBeIt Line 52,000 46,000 52,000 North Central Texas Council Of Governments July 14,1998 Mr. Jack Hatchell Jack Hatchell & Associates P.O. Box 2660119 Plano, TX 75026-0119 Dear Mr. Hatchell: Enclosed are maps of the projected 2020 volumes for Arapaho Road per your May 29, 1998, request. Twenty-four hour volumes were developed for Arapaho Road using the Dallas-Fort Worth Regional Travel Model. Three scenarios were modeled for the facility with each alternative extending Arapaho from its current terminus at Addison Road to Marsh Lane as a four-lane facility. Arapaho was modeled at grade in the first alternative. The second alternative modeled Arapaho grade separated at Midway Road with no connections at Midway. The last alternative also modeled a grade separation at Midway Road, but ramps with connecting the two roads. If you have any questions regarding the Arapaho Road assignments, please contact me or Mitzi Ward of my staff at (817) 695-9240. Sincerely, 􀁾􀁊􀀲􀁾􀀠Michael Morris, P.E. Director of Transportation MM:db Enclosure 616 Six Flags Drive, Centerpoint Two P. O. Box 5686, Arlington, Texas 76005·5886 (817) 640·3300 FAX: 617·640·7806 ®recycled paper ARAPAHO ROAD EXTENSION AT GRADE 2020 VOLUMES 11000 \. --------KELLER SPRINGS RD 􀁾􀀠I .!Z c::ui1i ----0"" 􀁾::u􀁾􀁲􀀭------)' I 􀁾􀁩􀁬􀁬􀁾􀀠 0s::-» c􀁾􀀠c c 0::u cs::􀁾􀀠􀁾􀀠Arap_ag.shp NFreeway/V PrincipalNMnor /v Collectors, Frtg NRan1ls iI! 1 "/-< /􀁾􀁉􀀠... 􀁾􀀠C -0 I) I--:;----1􀁾􀀠21􀀯􀁴􀀬􀀭􀁾􀁁􀀯􀁩􀁏RD 1 •r􀁌􀁬􀁎􀁄􀁂􀁅􀁾􀁦􀁩􀀢􀁭􀀠-'" /I 6 􀀮􀁾􀀠I " Ir J , ,􀀭􀀭􀀭􀀭􀀯􀁌􀀬􀀭􀁾� �􀁾􀀭􀀭􀁾􀁾􀁾􀁾􀀭!( BELT UNE RD/" ·1" ,I N • 46·"\ "J'" II 􀁜􀁟􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭W*E S ARAPAHO ROAD EXTENSION GRADE SEPARATED @MIDWAY RD 2020 VOLUMES /1000 􀁾􀀭􀀧􀀩􀀠KELLER SPRINGS RD , 􀁾􀀠(J) :s:: »-8:I: 􀁾􀀠_ 􀁾􀀠1􀁾􀀧􀁾􀁉􀁾! " 􀁾􀁉􀁩􀀠I I 􀁾􀁟􀀠.... €l 􀁉􀁾􀀠 􀁾􀀠ARAPAHOR 􀁾􀁉􀀠􀁌􀁬􀁎􀁯􀀮􀁅􀁒􀁾􀀢􀁉􀂷􀀱􀀠 􀁩􀁾􀀠o c .0,;;0 ·c :s:: '\ I ;" 13 0 i 13 • ___________--T 17 •􀁩􀁾􀀠BELT LINE RD 􀁾􀀠42 I 􀁾􀀠C;;iL 􀀭􀀭􀀮􀁲􀀭􀁾􀀠􀁩􀀵􀀵􀀵􀀵􀀭􀀮􀀮􀀮􀁌􀀮􀀭􀀭􀀻􀀶􀀹􀁾􀀨􀁾􀁉􀁊􀁊􀁉􀁉􀁾 􀁾􀀠. 􀁾􀁜I "\ ." I Arap..Q8.shp /\/FreeNaYIV PrincipalIVMnor 1\/Collectors, FrtgIVRaJlllS NW+E s ARAPAHO ROAD EXTENSION GRADE SEPARATED @MIDWAYW/RAMPS 2020 VOLUMES 11000 "-􀁾􀀡􀀠KELLER SPRINGS RD I I , 1 I ! I, I 􀁉􀁾􀀠\ . 'i8 I IIx ;;; I;!:: 10 Izr 0 '10 jC, :1E -0I »!gs i::tli ,'-< 􀁩􀁺􀀮􀁾􀀠... I ::tl : ::tl 00' 0 <0 􀁾􀀠._::tl􀁾􀁉􀀠1􀁾􀁾􀁉1 J:zii ) I, I XlLlND6ER§Jl.13_J􀁾􀀠ARAPAHo RO I --------1 􀁾"r24 17 '" 􀁟􀁾􀀲􀀸􀀠'" 25 '" i 81 􀀭􀀭􀀭􀀭􀀯􀁾􀀡􀀠 ;m I' //' 􀁾􀀠􀁾􀀠0l BELT LINE RD . 45 "'I 50 􀀭􀀭􀁾􀁏􀁏􀀠I?I 45 \ '" 64I,w '" ___J L-,/-------\\ \ I \I . II I . \ \ i T I Arap-9Sfl11>.shp NFreewayAJPrincipal AJMnor /\/Collectors, FrtgIVRafll)S NW*E S 􀁾􀁃􀁖􀁏􀁌􀁕􀁍􀁅􀁃􀁏􀁍􀁐􀁾􀁏􀁎􀀠At Grade Grade Separated Grade Separated With Ramps South ARAPAHO Addison to Midway 24,000 17,000 28,000 Midway to Surveyor 6,000 13,000 17,000 BELT LINE Addison to Midway 53,000 54,000 50,000 Midway to Surveyor 46,000 42,00045,000 MIDWAY North ofArapaho 36,000 44,000 32,000 South ofArapaho 57,000 60000/, South ofBelt Line 52,000 46,000 52,000 MEMO Engineers. Inc. 1919 S. SblIob Rd., Suit. 530, LB 27, Garland, TX 75042 Date: September 23, 1998 To: Mr. Jim Pierce, Town ofAddison From: Bruce Grantham Re: Arapaho Road Extension Please find enclosed an updated schedule for the Arapaho Road project. Ifyou have any qoo,,,,", ,1,_giw m, ,..n.􀁾􀀠1'e/.: (972) 840·1916 f FAX: (972) 840·2156 fE-mail: Jofu@gbwengineers.com 14114 DallasI : I 􀁾i i =1ARCHITECTS ENGINEERS PLANNERS Parl!way, Suite 630 􀁄􀁡􀁊􀀯􀁡􀁳􀀬􀁔􀁾􀀠7524()'438J (972) 661-5626August 25, 1998 FAX (972) 661-5614 Town of Addison 5300 Beltline Road P.O. Box 144 Addison, Texas 75001 Attn: James E. Pierce, Jr., P.E. Assistant City Engineer ARAPAHO ROAD EXTENSION Dear Mr. Pierce: During the month of July, Dallas Aerial Surveys continued the development of mapping for the Arapaho Road extension project and digital files for the mapping were delivered on August 13, 1998. We are beginning the study of alignments just south of the railroad and along Centurion and Realty. Electronic files will be furnished to GBW Engineers, Inc. to begin plotting of utilities. Jack Hatchell has collected available traffic data and has received traffic counts at Midway Road with and without connections to the extension from the North Central Texas Council of Governments. ARS Engineers, Inc. has completed their control traverse and established panel points for use by Dallas Aerial Surveys for aerial photography control. They have also assembled deed sketches for approximately 90% of the property primarily between Addison Road and Surveyor. Very truly yours, HNTB CORPORATION Daniel F. Becker, P.E. Vice President, Central Division DFBllnb The HNTB Companies OFFlCES: ALEXANDRlA, VA; ATlANTA, GA: AUSTIN, TX: DATON ROUGE, 1..11, DOSTON, lolA, CHARlESTON. VIV, CHIo,GO. IL; CLEVElIIND, OH; DAlL'.S, TX: DENVER, CO, DETROIT, M[: FAIRFIElD, NJ: fT. WORm, lX: HARTFORD, CT: HOUSTON, lX: INDIANAPOUS. IN: IRVINE, 0.: KANSAS on', MO, lIINS1NG, ).II: u.s VEGAS, NV: LOS ANGElJ'.S, 0., LOUISVILLE, KY: MIAMI, FL; MILWAUKEE, WI; MINNEAPOLIS. MN: NASHVILLE, TN: NEW YORK. NY; OAKLAND, CA; OKlIIHDMA CIIT. OK: ORLANDO. n. QVERlIIND PARK. K5; PHOENIX, AZ, PLYMDlJn-I MEETING. PA; PORTIAND, ME; RIILElGH, NC; ROCKLAND COUNTY. NY; SAN ANTONIO, TX; 􀁓􀁾􀁁􀀱􀁔􀁉􀀮􀀮􀁅􀀬􀀠WA: TAMPA, FL; TUlSA, OK: WICHITA, KS 25768 􀁾􀀠II;: 􀁾􀀠). I 􀁾􀁉􀀠II 'IIII $% uuuale WAW = 􀁉􀁾􀁾􀀠􀁾􀀠CITY OF DAlLAS .... BEl. 􀁾􀁏􀁄􀀠RES£'R\It1IRI 􀁾􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠.... i .... 􀁾􀀠I ).. ::s I 􀁾􀀠~ 1 PROfESSIONAL AUTOBODY & GLASS 2 ,RAILROAD RIGHT-OF-WAY C:I j 􀁾􀀠J MACARONI GRILL 4 GRADY'S GRILL􀁾􀀠 􀁾􀀠 􀁾􀀠􀁾􀀠ARAPAHO ROAD ALIGNMENT BARTON-ASCHMAN ASSOCIATES. INC. s..a Il(I,T \.M: 10. " .. ., QIiJ.W. m.o 1n4O" (114 􀁍􀀱􀁾􀁉􀁍􀀠PARSONSIpll!:J TAA.NaPOftTATION GRQUP ® --q> @􀁾􀀠@® ST. LOUIS t!t SOUlHltFSTFRN CD __ RAILROAD II 􀀬􀀫􀀽􀀭􀀭􀀭􀀭􀁾􀁾􀀠® 􀁰􀁾􀀠---®:: • , 0P0SE1J ARAPAiiO c --􀁾􀀮􀁾􀀠LJ 􀁾􀁾􀁾􀀧􀀺􀀠RaAO 􀀭􀀭􀁾􀀭􀁾􀀬􀀠i􀁾􀀠􀁾􀀠L /l..􀁾􀀠􀁾􀀠􀁾􀀠􀁾__ ea.r UNE ROAfJ 􀁾􀀠--' :: t-A. ol""A.'J /B L. $.e."","-r ,-h1 15101 MIDWAY ROAD I ,., +e.x <..; p r.2 4139 CENnJRION WAY 3 4131 CENnJRION WAY 4 4125 CENnJRION WAY 5 4101 CENnJRION WAY 6 lilT SLAB MINI-WAREHOUSES ARAPAHO ROAD AliGNMENT7 GROUND MOUNT WATER TANK 8 VACANT PROPERTY BARTON-ASCHMAN ASSOCIATES, INC. IS4e!I iIQ]' UIE 1Itl. "". IWJ.AS, TDIo.S 􀁬􀁾􀁗􀀮􀀠(114) "'-,_ PARSONSIp1􀁾􀀠TRANSPORTATION GROUP ® -----//----􀁾􀀠I :d I "/r----------/l --qD -@3 I􀁾􀁾ARAPAHO RO @AO 􀁾􀀭􀀭􀁾􀀭􀀭􀁾􀀭I?£"AL.lY L.AN£" , 􀁾􀁟􀁟􀁟􀀠__ " ___::_ 􀁾􀀭􀀭􀁾􀁦i i 􀁾@, Y)I 􀁾􀁉I,t3 ,I: 􀁾􀀺􀀠' , ® :!lfll 􀁾􀀠􀁾􀁾􀀠-􀁾􀀧􀁉􀀠I Vj' 􀁾􀀠I . '" :I􀁾􀀠"',i􀁾􀁉􀁩􀀠􀁾􀀠Ii 􀁾􀀠,I: '.) ,I' 􀁾􀀠: I ; !s! 􀁾􀀠Vj BEL n.INE ROAD 1 15107 SURVEYOR BLVD. 2 15109 SURVEYOR BLVD. ARAPAHO ROAD AliGNMENT 3 15115 SURVEYOR BLVD. 4 3801 REALTY LANE BARTON-AaCHMAN 5 3799 REALTY LANE ASSOCIATES, INC.6 VACANT 14M atll' ..lID, 11ft. 􀁾􀁾)$U(,\. ttJ'l m..,_ iil PAASONS'l!!:J TRAN"""""ATION GROUP ® 1)f\.Jt (" /' 􀁻􀁜􀁾􀁬􀁾􀁾􀀠􀁾􀀠􀁾􀁾􀀠"I 􀁾􀀠􀁉􀀺􀁾􀀠\poq Wj..,.f'-L ,I 􀁾􀀠).. l .n: UiIIIB it $,11. lIWiii4i1 ___ Iif.; I I ---"ti..... BEl. TWOOO RESERIIOIR􀁾􀀠􀁾􀀠Cl:x' 􀁾􀀠..... 􀁾􀀠􀁾􀀠􀁾} ).. :s ">J I 􀁾􀀠1 PROFESSONAL AUTOaOOY &GLASS 2 RAILROAD RIGHT-OF-WAY􀁜􀁾􀀠􀁾􀀠j 􀁾􀀠J :5 MACARONI GRill 4-GRADY'S GRILLQ; "\~~~ y\.{'-, It"" c:i L.[1'1.(' "I'; 􀁾􀀠􀀮􀁜􀁾􀁖􀀨􀀧􀁴􀀭􀁾􀀧� �ARAPAHO ROAD ALIGNMENT 􀁌􀁾􀀧􀁜􀁜􀀠BARTON-ASCHMAN, u'(I'l!. 􀁾()4P. (..-....-􀁾V" f(\eL15 P)(I,.(I el-f----wdw 􀁾􀁉􀁁􀀠􀁾􀁾􀀠1 15107 SURVEYOR BLVD. 2 15109 SURVEYOR BLVD. 3 15115 SURVEYOR BLVD. 4 3801 REALlY LANE 5 3799 REALlY LANE 6 VACANT &1'1. )., \.. oJ t. \􀀢􀀧􀁾􀁊􀀠IV \)rt)V 10-' 􀁾􀀠I 􀁾􀀠, J..::-------® 'a'i m 􀁾􀀠􀁾􀁾􀁬􀁻 I. I I lil 􀁾􀀠I 􀁾􀀠􀁾􀀠􀁾􀀠(i') ARAPAHO ROAO ALIGNMENT BARTON-ASCHMAN ASSOCIATES, INC. tI4UI Ml.f tM... "M.1!4U$. '!'tIiU 'mAO. Ctl4} ""'-1_ Ijil p""8ONa 􀁾􀀠TRANIIfI"'O\IITA.T1ON GROUP if\. @ TOWN OF ADDIsoN 􀁔􀁏􀀺􀁾􀁾􀁾􀀠Company: GBuJ FAX#: 􀁴􀁴􀀷􀀻􀁺􀀮􀀭􀁋􀁴􀁦􀁯􀁾􀀱􀀴􀁦􀁴􀀠Date: 1.A fiA d -􀁾􀀠.,t/AA 􀁾JJ :L I' IT r ( i THESE ARE TRANSMITTED as checked below: o For approval 0 Approved as submitted o Resubmit ____copies for approval 􀀮􀀬􀁾􀁆􀁯􀁲􀀠your use 0 Approved as noted o Submit copies for distribution J'd As requested 0 Retumed for corrections o Retum corrected prints o For review and comment C o FOR 81DS DUE __________ 19____ 0 PRINTS RETURNED AFTER LOAN TO US REMARKS 􀁟􀀱􀀭􀁾􀁾􀁾􀀽􀀭􀀢􀀧􀁁􀁡􀀯􀀺􀀻􀀧􀀭􀀽􀀭􀀧􀀭􀀢􀁾􀀽􀀮􀀽􀀺􀀺􀀮􀀮􀁌􀀡􀀧􀀽􀀽􀀭􀀭􀀮􀀮􀁌􀀮􀁾􀀮􀀮􀁌􀀽􀀾􀀽􀀽􀀭􀀭􀀽􀁾􀀺􀀮􀀮� �􀁉􀁌􀀮􀀺􀀺􀀮􀀻􀀻􀀺􀀮􀀽􀁰􀁾􀀽􀀭􀀢􀀧􀀽􀁾􀀺􀀮􀀮􀀮􀀺􀀮􀀬􀀭􀀧􀀭􀀭􀀭􀀧􀁾􀀧􀀭􀀭􀀢􀀢􀀽􀀽􀀢􀀢􀀭􀀭􀀭COPyTO_________________ _ /) SIGNED: 􀁾􀀼􀀭􀁴􀀺􀀻􀁺􀀻􀀻􀀼􀀭􀀼􀀺􀀮" If enclosures are not as noted, please 􀁮􀁯􀁴􀁾􀀠 R4.,j 6 -IS"-rr 11111 Dallas I : I 􀁾i i =JARCHITECTS ENGINEERS PLANNERS Parkway, Sulle 630 Dallas, Texas 73210-1381 June 2,1998 (972) 661-5626FA}{ (972) 661-5614 Town of Addison P.O. Box 144 Addison, Texas 75001-0144 Attn: Mr. James C. Pierce, Jr., P.E., DEE Assistant City Engineer ARAPAHO ROAD EXTENSION Dear Mr. Pierce: We are proceeding with the Phase 1 services for the extension of Arapaho Road, and this is to provide you with the status of activities in progress. Our surveyor, ARS Engineers, Inc. (ARS), began work setting panel points for Dallas Aerial Surveys (DAS) and is continuing their design survey activities. Benchmark data and horizontal controls have been furnished to ARS for their use in setting controls for DAS. Written agreements with subcontractors have been executed and insurance certificates issued. Jack Hatchell & Associates has compiled the available traffic data and has requested traffic projections from the North Central Texas Council of Governments for streets in the vicinity of the project. In cooperation with GBW, we have updated the schedule to reflect the delay in starting work with no change in the completion dates and a copy has been furnished to the Town of Addison. During June, we expect to continue the traffic studies, design surveys, aerial mapping, and collection of utility information. We will submit brief status reports to you monthly to keep you abreast of project develoj}ment activities. Ifyou have any questions, please call. Very truly yours, HNTB CORPORATION 􀀻􀁴􀀯􀁾􀁾Dattiel F. Becker, P.E. Vice President, Central Division DFB/lnb 25768 Tbe HNTH Companies OFFICES; AI.EIC",.,'J)KlA, VA; ATtANTA, Gt.; AUSTIN, TX; BATON Rovet:. LA. nOSTON. 1>1 ... ; CHAIU..I:1'1'ON. 􀁷􀁶􀁾􀀠cwC\co. It; 􀁃􀁴􀀮􀁅􀁖􀁅􀁬􀀮􀁁􀁾􀀮􀀠OH; DALLAS. n, DEl'iVER. co; D£rROrT, MI; FA1RFIEJ.D, I'll: f'T. WOIll11. TX: HARTFORD, CT; HOUSTON, TX; lNDJAlil,POLlS, IN: IR\'lNE, CA, KA....SJ,$ OTY. MO. LANSING, !>II; I.M VEO!>S. NV; LOS ANGffi£S. 0\; l.O!JISVtl.U:, K'f; 􀁾􀁉􀁊􀁁􀁍􀀱􀀮􀀠I'L: MILWAUKEE, WI; M!NNEAVOUS. MN; NASHVIl.LE, TN, NEW YORK. NY; OAKLAND. Ck OKLAHOMA CITY, OK: OlU.Al'lOO, Fl.; OVERlAND PARK XS; l'HOENfX, AZ·, I'LYMOUTH MrumNG, PA; 􀁐􀁑􀁾􀀧􀁲􀁌􀁁􀁎􀁏􀀮􀀠Me: RIILElGH, I'o'Cl ROCKLAND COONn', NY, SAN A."mJNIO. TX; 5EATTt£, \VA< TAMPA. Fk 1't11SA, OX; WlCUITIL KS. Engineers. Inc. Date: 6/4198 To: Jim Pierce From: Bruce Grantham Re: Arapaho Road Extension I have enclosed the revised Arapaho Road Extension Project Schedule per our discussion. Please call ifyou have any questions. Tel.: (972) 􀁧􀀴􀀰􀁾􀀱􀀹􀀱􀀶􀀯FAX: (972) 840-2156/E-mail: lnfo@gbwengineers.com _________________________ _ JOB NODATE ATTENTION REPublic Works /Engineering 16801 Westgrove. P.O. Box 144 Addison, Texas 75001 Telephone: (214)450-2871 • Fox: (2141931·6643 GENTLEMAN: WE ARE SENDING YOU V:< iii ..; ;Z; G) :D 0 0" :;: -< " 0 0 Z " iii c .. :D Ci" ..; c: 5 '" rn [00 Z 􀁾􀀠􀁾􀀠•􀁾• ,<"..,0.' , •..••» 􀁾􀀠..􀁾.""," » 􀁾􀀠􀀢􀀢􀀢􀀢􀁾􀁾􀁵􀁶􀀠Ln. Ktlllyewd. :. IdU1lJ) LJ'\. Wal,rvl, Pili",,.. DALLAS 􀁾􀀠FARMERS BRANCH 􀁩􀁾􀀠Q' L.. ..____,CARROLLTON "·""""1: , " e J • 􀁾􀁻􀀮􀀠(; 􀁾􀀠"-o n , •,•􀁾􀀠;; ;: ,. 􀁌􀀮􀁟􀁾􀀠DALLAS h:i 􀀧􀁾􀀠􀀭􀀻􀀧􀀧􀀧􀀧􀀧􀀧􀀢􀀭􀁾􀀠, . o • '>---.... ri 􀁾􀁉I 􀁾Quorum Pro . lade·mC!!! In_.J; ; ,; •􀁾􀀠􀁾􀀠e "AddlaOM Rd• 􀁾􀀠, 11 ] 􀁾􀁴􀁬􀀠r:1 IL ., ell, 􀁵􀁭􀁬􀁾􀀠, . 􀁾􀀠• 􀁾􀀠;; >, 􀁾􀀠􀁾􀀠<􀀭􀀭􀀽􀀽􀁾􀀬1!:..2Z_ ,i.., No, '0 Scala 􀀮􀁾􀀠,, 􀀬􀀭􀁾􀀭􀀮􀀭􀀭􀀭􀀮" FHlURE 2 CONCEPTUAL ROAOWAY CONFIGURATION 􀁾􀀠 ________________________ _ DATe J.j.-,3-7'r IJOB NO. ATTENTION Public Works I Engineering 16801 Weslgrove. P.O. Box 144 Addison, Texas 75001 RE" O/lAAA d --£P { 􀁐􀁾􀀮􀀮􀁺􀁺􀀺􀀯􀀷􀀷􀀱􀀠 Telephone: (214J 450-2871 • Fox: (2141931-6643 : GENTLEMAN: WE ARE SENDING YOU )(Attached o Under separate cover via ______the following items: o Shop Drawings o Prints o Plans 0 Samples 0 Specifications o Copy of letter o Change order 0 ________________________ COPIES DATE NO_ DESCRIPTION J 􀀧􀁪􀀩􀁾􀀱􀁬􀀭I h2n., A J. 􀁨􀁾􀀠Pld-M 􀁾􀀠􀁪􀀯􀁾􀀠􀁾􀀠􀁾􀁙􀀷􀀢􀂣􀀩􀁲􀁾􀁾􀁾􀀠-I/O -PiUjA-. 4'-0 ...t.-Jt () AdA/! bA4 􀁦􀀬􀀧􀁾􀀠I P v I I , THESE ARE TRANSMITTED as checked below: o For approval o Approved as submitted o Resubmit ____copies for approval ;fFor your use o Approved as noted o SubmH copies for distribution o As requested o Returned for corrections o Return corrected prints o For review and comment 0 o FOR BIDS DUE 0 PRINTS RETURNED AFTER LOAN TO US SIGNED: 􀁟􀀭􀀭􀀭􀀭􀀻􀀾􀁴􀀭􀀧􀀡􀀴􀁦􀀺􀀡􀀺􀀽􀀮􀀽􀀭􀁉􀀮􀁾􀁾􀀺􀁓􀀺􀀺􀀽􀀽􀁟􀁟__ If If enclosures are not as noted, please noli _________________________ _ Public Works I Engineering 16801 Weslgrove' P,O, Box 1M Addison, Texas 75001 Telephone: [214) 450-2871 • Fax: [214)931-6643 DATE IJOBNQ,3-2.'" ''"If..PATTENTION RIi": " !/(NArlJ .... /4..J :o::./ill,I i : GENTLEMAN: WE ARE SENDING YOU 􀁾􀁴􀁴􀁡􀁣􀁨􀁥􀁤􀀠o Under separate cover via ______the following items: o Shop Drawings o Prints o Plans 0 Samples 0 Specifications 0 __________________________o Copy of letter o Change order , COPIES :5 DATE NO, ! 􀁾-#-" J-... 7Ad ./..,b' //f DESCRIPTION /JP7j J; J.A THESE ARE TRANSMITTED as checked below: o For approval 0 Approved as submitted o Resubmit _____ copies for approval o For your use o Approved as noted o Submit copies for distribution o As requested o Returned for corrections o Return corrected prints o For review and comment 0 o FOR BIDS DUE __________ 19____ o PRINTS RETURNED AFTER LOAN TO US . REMARKS 􀁟􀀭􀀭􀀭􀀭􀁉􀁅􀁾􀁙􀀭􀀭􀀭􀀭􀀲􀀺􀀺􀁉􀀭􀀭􀀽􀀭􀀭􀀽􀁾􀀽􀀭􀀽􀀽􀁾􀁾􀁾􀂷􀀭􀀢 􀀭􀀽􀁬􀀺􀀺􀀺􀀺􀀮􀀮􀀮􀀮􀀺􀀺􀀻􀀽􀀭􀀭􀀺􀀺􀀮􀀮􀀭􀀮􀀮􀀮􀀺􀀽􀀭􀀬􀀭􀁾􀀭􀀢􀀢􀀬􀀭􀀧_______ COPYTO _________________________________ SIGNED: 􀁾􀁾􀁾􀁾􀀽􀀽􀀽􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀧􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭 ,r ,/Town of AddisonJ\J uV1996 Daily Traffic Volume Summary :. 􀁾􀁾􀁟􀀢􀀧􀁾􀁷􀀮􀀠􀁗􀁾􀀠---.􀁾􀀠-99S-D.iiy -rratiicvoJumes 􀁾􀀽􀀢􀁾􀁬􀀠--l:illlerence__ _, "I. cnange Street Location -·,NB SB EB WB _ ---Total VPD 1986 1989 1993 1996 --;-1996·1993'-_ -From-1993 IMidway "oad i "IO,ly Mills 10 ;:,ojourn 18011 20771 􀁾􀁾􀁾􀁾􀁾􀀠NR 􀀲􀀷􀁾􀁾􀀷􀀠341Uli 38782 4674 􀁾􀁾􀀺Sojourn to Keller Springs 18298 16754 25655 34203 35052 849 Keller Sprin9S to Lindbergh 19946 20707 40653 32137 30562 44065 40653 ·3412 -8% Lindbergh 10 Belt Line 20474 20816 41290 36166 29138 40179 41290 1111 3% Belt line 10 Beliway 23413 21584 44997 31975 35831 43665 44997 1332 3% Beltway to Proton 29051 23163 52214 36915 37383 47484 52214 4730 10% Proton \0 Spring Valley 30024 23755 53779 40689 39699 46836 53779 6943 15% South of SEring Valley ___________ 31969 26836 58805 48051 44042 54508 58805 4297 8% Montfort Drive Verde Valley to Sakowilz --􀀭􀁾􀀭-NR_........ -----NR------16477 --1594-5--""_ .. -"NR-----NA 􀁾􀀭NR Sakowitz to Belt Line 10151 7372 17523 16332 12225 15500 17523 2023 13% Paladium Road -East of Montfort---518 -497 1015 -·"NR----NR--135S--'1015 ·343 ·25% Pebble Beach Wesl,,! Marsh 1350 t-Ji'_62 3012 NfC-NR r-IR 3012 NA NA Proton Road Midway to Bell Line 2147-1998 4145 NR NR 2651 ---;ri45 1494 56% Beltway to les Lacs 1312 1639 2951 NR NR NR 2951 NA NA les Lacs to Azure 1583 1450 3033 NR NR NR 3033 NA NA Quorum Drive Dallas Parkway to Landmark 5396 5669 11067 11198 10510 9987 mist 1080 "ii% landmark to Belt line 5879 5511 11390 8120 9271 8739 11390 2651 30% Belt line to Arapaho 5339 4804 10143 10107 8182 10261 10143 -118 􀁾􀀱􀀥􀀠Arapaho to Airport Parkway 2381 1893 4274 5247 4769 6262 4274 -1988 ·32% Airport Pkwy _to Keller Springs 2533 1977 4510 4925 4625 5946 4510 ·1436 ·24% Keller Springs to Westgrove 1525 1531 3056 2907 2708 􀀳􀀵􀁾􀁾􀀠3056 -462 ·13% Realty Marsh to Business 1289--1519 280S Nie-NR NR --;2808 NA NA Runlon Road North of Belt Une 1014 1431 -2445 Nff NR 2446 *0%2445 ·1 ?akowi12 Parkway Bell Line 10 Montfort 700 2977 3677 􀁟􀀴􀁾􀀴􀁟􀀲􀀠2482 2258 3677 1419 63% Sojourn Midway Road to Voss Road 􀁾􀁾􀁾􀁾􀀠5602 􀁾􀁾􀁾􀀺􀀠􀁾􀁾􀁾􀁾􀀠7088 10047 11489 1442 14% Voss Road to Addison Road 2985 4001 6079 5365 ·714 -12% Addison Road 10 DaUas Pkwy_ 2380 2985 5365 3847 1073 NR 5365 NA NASpe-ctrum----I> i':\"ailiiPk,,;y: to-Arapaho -Road -_.1761 "" 1968 -_. 2628 --2382----3101·'-:372-9--􀁦􀀭􀀭􀀭􀀦􀁾􀀳􀀱􀁾􀁾􀀠20% Spring Valley Rd_ Marsh lane to Brookhaven 16444 '15750 31194 10171'-16254 12349 31194 18845 153% Brookhaven to Midway 11234 12264 23496 16187 12017 21927 23498 1571 7% East of Midway 6922 7149 14071 26892 26536 27902 14071 -13831 -50% Surveyor Blvd. North of Beit line Road 3022 3436 6458 7310 4961 NR 6458 NA NA Sel! line to Beltway '1453 2037 3490 2191 2222 NR 3490 NA NA Weslgrove Dallas Pkwy. to Addison Road -4080 4448 8528--·-gr2·64--. 6291 8055-852-8473 6% Addison Road to Sunbell 5779 5245 11024 12578 7924 9366 11024 1658 18% Bent Tree Plaza to Sojourn 6070 6530 12600 11151 8491 10287 12600 2313 22% Trinity Mills to Sojourn ..___ 4280 4105 8385 9030 5407 6520 8385 1865 29% Winwood Drive South at 􀁂􀁥􀁬􀁾line ____ .._______ 310 354 -664--.--iffi.__-=-_ 􀀭􀀭􀀭􀁾􀀭-609-664 55 9%-- ,. Town of Addison 1996 Daily Traffic. Volume Summary ---I 5620 10391 10867 11356 11529 11352 8985 Lane 10 Surveyor to Midway Road Road to Beltway to Addison Road Road to Quorum Road to Dalias Pkwy, Pkwy. to Montfort to White Rock Creek 􀀭􀁾􀁾􀁁􀀢􀀧􀁁􀀠--." 􀁔􀁲􀁡􀀭􀁦􀁦􀁉􀀨􀁻􀀢􀁜􀁩􀁯􀁬􀁾􀁭􀁥􀁳􀁣􀀺􀂷􀂷􀁾􀂷􀀮􀀺􀀺􀀺􀁲􀀠E13-'-we-Total vpif' 4815 􀁂􀁬􀁾􀀬􀁬􀀠10435 9706 20097 11167 22034 11904 23260 11902 23431 12018 23370 10088 19073 25951 28895 54846 28092 24617 52709 30825 28323 59148 34316 35275 69591 32401 36356 68757 31488 35291 68777 25069 24836 49905 24740 26305 51045 "7838 8909 5925 5908 5225 3163 1249r5537 1986 5195 8751 NIA NIA 19693 NR 20468 NR 41411 38435 46249 54442 42387 38084 34862 32612 6315 5607 4985 4946 3980 1i23--8359 2422 . ---..􀀭􀀭􀁾􀀭1989 5293 7546 13491 14884 15826 NR 17490 NR 36171 36396 41928 44772 42340 40788 37332 43037 5987 4500 3463 3415 4919 , 31503 32980 37942 35382 1993 6832 9359 18076 17130 17505 18526 20949 NR 41054 40010 54199 52243, 49026 44949 42046 42192 6927 4346 4822 4965 4603 33987 37196 32621 I 199$ 1996·1993 ' From 1 9131 2299 340/0 10435 1076 11% 20097 2021 11% 22034 4904 29% 23260 5755 33% 23431 4905 26% 23370 2421 12% 19073 NA NA 54846 13792 34% 52709 12699 32% 59148 4949 9% 69591 17348 33% 68757 19731 40% 68777 21828 49% 49905 7859 19% 51045 8853 21% S909 4563 105% 5925 1103 23% 5908 943 19% 􀀭􀀭􀁾􀁅􀁾􀁾􀀠-------1 􀁾􀁾􀀺􀀻----1----.--53467 39526 35518 41517 19480 2330 2897 4639 57% 6% 9% MINUTES OF MEETING Project: Arapaho Road Extension Meeting Date: March 10, 1998 HNTB Attendees: Ron Whitehead, Town ofAddison GBWNo.: 98-094 John Baumgartner, Town ofAddison Jim Pierce, Town ofAddison Dan Becker, HNTB Bruce Grantham, GBW Engineers, Inc. • The Town has 60 reet of right-of-way (ROW) dedicated on the City ofDallas Reservoir and Addison Restaurant Park properties, adjacent to the railroad. . • The Roadway Inn Addition property has a tennis court in the rear which should not significantly impact the property's functionality if it is acquired as ROW. • The Yoplait Yogurt property is already pressed for parking space. If a portion of the rear ofthis property is acquired for ROW, replacement parking space will need to be acquired nearby. • The racquet club facility on Centurion Way is vacant at the present time. • The City-owned pump station can be relocated, ifnecessary, according to a previous study performed for the Town. • If a portion of the mini-warehouse tract is taken, the remainder of the tract will need to be evaluated for its functionality . • The Midway Road intersection is a key element ofthe project design. The following issues were discussed regarding this intersection: Jack Hatchell will study the traffic implications ofan at-grade crossing on other intersections in the neighborhood, particularly the one at Belt Line Road. Mr. Hatchell's study should help determine the viability ofan at-grade crossing. If an elevated crossing is selected, no access at Midway should be considered as an alternative, along with access on lyon ramps. • A two-way couplet will be evaluated between Midway Road and Surveyor Boulevard as widening the existing Centurion Way may have a significant impact on parking and access to the adjoined tracts, partiCUlarly on the north side. • Property acquisition costs for an at-grade alignment should be compared with a more extensive elevated roadway alignment. 1919 S. Shiloh Road, Suite 530, LB 27 Garland. Texas 75042 Phone: 972-·840-1916 Engineers. Inc. Fax: 972-840-2156 MINUTES OF MEETING Page 2 Project: Arapaho Road Extension Meeting Date: March 10, 1998 HNTB • It is not possible to elevate the roadway over the railroad crossings near Addison Road due to clearance requirements at Addison Airport. • Dan Becker will check on the property acquisition cost for a commercial tract recently acquired for the Keller Springs project. • The Town will consider bond financing to build a section ofthe roadway if it is feasible to obtain the necessary ROW while other issues are resolved on the balance ofthe project. • The section from Marsh Lane to Surveyor Boulevard may be the most straightforward to fast track. • The HNTB tearn should investigate all the construction and design alternatives for this corridor in order to select the most cost effective alignment which is feasible. 14111 D<1Jtm; 􀀱􀀧􀁖􀁲􀁾SuIre 630 DoJlas. Tt:Q'U I : It:-i i =) ARCHITECTS ENGINEERS PLANNERS 7524()4j81 (972) ()(;i·5626 FAX (972) 6(;1·5614 April 2, 1998 Mr. James C. Pierce, Jr., P.E., DEE Assistant City Engineer Town of Addison P.O. Box 144 Addison, Texas 75001 TOWN OF ADDISON Arapaho Road Extension -Phase IIIm Dear Mr. Pierce: As requested in your letter dated March 9, 1998 authorizing us to proceed with the referenced project, we are enclosing Certificates of Insurance as required. Should you have any questions following review of these certificates, please let us know. Very truly yours, HNTB CORPORATION 􀀱􀁦􀁬􀁾􀁱􀀷􀁾􀀠Daniel F. Becker, P.E. Vice President, Central Division DFB/cec Enclosures 25768 Tbe HNTB Compantes OfI'lCES: A1..EXANDRlA, VA; ATl..ANTA. GA; AUSTIN, TX; DATON ROUGE. LA; BOSTON, MA, O'ARU5TO.s, wv: CHtCo'.GO, IL\ CU!V(ll,I,NI), OM: DAU.A$, TX; tmNV£It, co; DETROIT, MI; FAIRI'IE1.0, N), "T, WORTH. '0(; HARTFORD, CT: HOUSTON, i"X; INDIANAPOLIS. IN; IRViNE, CA; KANSAS crrr, 1010; [.ANS,lt-