-. -.' I • :..., SWV3B-n 􀁓􀁖􀁘􀀳􀁾􀀠 URS Corporation Arapaho Road Bridge at Midway Road Design Development and Contract Documents Change Order No. 03 to Work Order No. 001 ATTACHMENT M Revised Estimated S.nedule ITASK '''UN 􀁾􀀠􀁾􀁐􀁬􀀠􀁾􀁐􀁆􀁏􀁾􀁳􀀠􀁩􀁾􀀠• Review • ••• -.1& NTP REQ'D INFORMATION FROM TOWN'S CONSULTANT SUBMITTAL URS Corporation Arapaho Road Bridge at Midway Road Design Development and Contract Documents Change Order No. 03 to Work Order No. 001 ATTACHMENT M Revised Estimated Schedule TASK "Yo. 2 􀁏􀁾􀁬􀁯􀁾􀁥􀁲􀀠2 􀁾􀁉􀁏􀀠I (NTP) • Issues INTP For Prelim. DeSign 'Desiign I al Arch , Bridge 􀁾􀀠􀁾􀁐􀁬􀁡􀁮􀁳􀁬􀀠• Review , Town Council IRevise 􀁾􀀠• 10 Town Council , DeSign IFinal I Report IFinal I Plans 'inal Desion , Desion 􀁾􀁡􀁬(60% Plans) • Review •10 Town Council Bridge I Final Desig n & ' Final Desio n I (95% Plans) , • Review Signed and 􀁓􀁥􀁡􀁬􀁥􀁤􀁾􀀠2 002 • 2 002 1 2 􀁊􀁾􀁮􀁵􀁾􀁲􀁹3 2 0 0"3 12 􀁾􀁡􀁲􀁾􀁨􀀠3 􀁾􀀠2 􀁾􀁰􀁲􀁧􀀠3 12 􀁾􀁡􀁾􀀠3 12 􀁾􀁵􀁮􀁾􀀠3 2 􀁩􀁕􀁉􀁾􀀠3 12 􀁁􀁾􀀹􀁾􀁓􀁉􀀠3 2 '0 0 3 1 2 􀁏􀁾􀁬􀁯􀁾􀁥􀁲3 2 0 0 3 12 0 0 3 􀀯􀁡􀁾􀁵􀁾􀁲􀁹􀀠4 2 0 0"4 12 􀁾􀁡􀁲􀁾􀁨􀀠4 2 􀁾􀁰􀁾􀀠4 2 􀁾􀁡􀁹􀁯􀀠􀁾􀀠•􀁾􀀠• .. • • 􀁾􀀠-"I • 􀁾􀀠-􀁾􀀠• NTP • REQ'D INFORMATION FROM TOWN'S CONSULTANT • SUBMITTAL ", .Jk '1) 􀁾􀀠URS Cerperatien IS 􀁾􀀠Arapaho Road Bridge at Midway Road 􀁾􀀠"Design lDevelopment and Contract Documents 􀁾􀀠􀁾􀀠Change IIrder No, 03 to Work Order No, 001 .'C! '-l ATTACHMENT M 􀁾􀀠J-Revised Estimated Schedule 􀁾􀀠TASK "v.. 2 􀁯􀁾􀁴􀁯􀁾􀁥􀁲2 12 0 () 2 2()()2 12 􀁊􀁾􀁮􀁵􀁾􀁲􀁹􀀠3 12 () 0"'3 2 􀁾􀁡􀁲􀁾􀁨􀀠3 2 􀁾􀁰􀁾􀀠3 2 􀁾􀁡􀁾􀀠3 2 􀁾􀁵􀁮􀁾􀀠3 2 􀁾􀁕􀁉􀁾􀀠3 2 􀁁􀁾􀀹􀁾􀁴􀀠3 120()3 12 􀁯􀁾􀁴􀁯􀁾􀁥􀁲3 2 0 () 3 12 () 3 􀀲􀁊􀁡􀁾􀁵􀁾􀁲􀁹􀀠41200"'4 12 􀁾􀁡􀁲􀁾􀁨􀀠4 2 􀁾􀁰􀁲􀁾􀀠4 2 􀁾􀁡􀁹􀀨􀀩􀀠4 ii;eto I I 􀁾􀁾􀀺􀀾􀁥􀁳􀀠􀁾􀀠,For Prelim, Desion •rv Desion \, •1at Arch I. 0 , Bridge 􀀮􀀮􀁬􀁾􀀠IExpert ' , .j" IFin.1 , (-30% Plans) • I,v , Revlev ,'U Town • 'I {evise' ,10 Town • \ Revise , Design 􀁾Design 􀁾􀁥􀁰􀁯􀁲􀁴􀀠•• Design I 160% Plans) •, Review -,loTown , 􀁾􀁄􀁲􀁡􀁩􀁮􀁡􀁯􀁥􀀠•I Desion&' 􀁾Final Desion •,Review -,( ,Final PS&E -land Sealed PS&E (100%) • • NTP • REQ'D INFORMATION FROM TOWN'S CONSULTANT • SUBMITTAL AI [/£S 620 : : ---!-----,-----,----1-: : ---,-----1 ,, j' : : i :l :L: :;:.--,.------+--+.--<,------>__+__ 1;_____ ------I--·-I---+---!,---+------I ,---􀀭􀀭􀀭􀀭􀁾􀀬􀀭􀀭􀂷􀁩􀀭􀀭􀀭􀀬􀁾􀀭􀀭􀀫􀀭􀀭􀀮􀂷􀀭􀀭􀀭􀀱􀀭 􀀭􀂷􀀫􀀭􀀭􀁩􀁬􀀭􀀭􀀭􀀧􀀬􀀭􀀭􀀭􀂷􀀭􀁌􀀭􀀭􀀮􀀭􀁾􀀭􀀭􀀭􀀫􀀭􀀭􀀮􀀭􀀻􀀮􀀮􀀭􀀭􀁊􀁌___,,---+---------! i l: : : :: : : : --+: : I', " " :, : : :,+---+--..,----+--.+-.-.---,---r--+---1---+ --1---+--,,-----,. --+----􀁾􀀭􀀭􀀭􀀬􀀭􀀭􀀭"-----."------;---,--.-;---,􀀭􀀭􀀮􀀭􀁾􀀭􀀭􀀭􀁦􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀁾􀀭􀀫􀀭􀀭􀀭􀁾􀀭􀀫􀀭􀀭􀀭􀁾􀀭􀀭􀀱􀀠: 􀁾􀀠i : 􀁾􀀠: i :-r----1----1--· --+---+---,--. ---':"---__ +_+___ .: ___.__ <: ____1___., ___ ---1----11----'--"" 􀀭􀀭􀀭􀀭􀀮􀁾􀀭􀀭􀀭􀁉􀀭􀀭􀀭􀀭􀀡􀀾􀀭􀀭􀀭􀁩􀀺􀀠:i i-! :'-----+--!--i : ' ; ; " ::: : : :---:---􀀭􀀭􀀭􀀮􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀫􀀭􀂭---1--' ,---'--'-: ___ +__ _ ;:, : : ; , ii' : ' f----<' __._c_ -,---,. --.-_L__ --.; -__L_ ,-.,' -----+-+----i. --+---, -􀀭􀀭􀀭􀁾􀀠--+---1----., ---1--.-.----il---•.--1--.!---,-1----11--------r--+·--r':'--- ---+----1--·+----11---L--,----..'.--1---;'--1-----i---""--';.---.,..--t--L-iiii I I ! i -:,., __ ."; ___,.__ 1.:-+---+--+---i---+ __ .__ ; ; ! ! Ii ---..'.---t---,..---'---___ , --i----, ___ :___ 1__ . : __ _,i-.-!c---i----I----+--+---+--+--,e--+---i-!---/-'--'!---i---i----------I------tT----'--+--'----tT----r-: ... , ,-,_c,-c I I I I I I I I I I 􀁲􀀭􀀭􀀭􀁩􀀭􀀭􀀭􀁦􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀺� �􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀁦􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀬􀀭􀀭􀀭􀁾􀀭􀀭􀀫􀀭􀀭􀂭: ---.,--. ---,------+--+--i-:--cl---i-, -----+-----+-----+--.------'----􀀭􀀭􀀭􀁾􀀭􀀭􀂭􀀭􀀭􀀭􀁾􀀭􀀭􀂭􀀭􀀭􀀭􀁾􀀭􀂭,-------1---'---·,------1 ----;.--,·----;.---1---I I I I r II I I Ii,:: I J : : _+:__: : _L i _L :: : 􀁦􀀭􀀭􀀭􀁾􀀭􀀭􀀫􀀭􀁾􀀭􀀭􀀫􀀭􀀫􀀭􀀫􀀭􀀭􀀬􀀭􀀭􀀭􀀻􀁟􀀭􀀭􀁟􀁩􀀭􀀭􀀭􀀺􀀭􀀭􀀭􀀫􀀭􀀬􀀭􀁉􀀭􀀭􀀭􀀭􀁔􀀭􀀭􀀭􀀭􀁉􀂷􀀭􀀭􀀭􀂷􀁴􀀭􀀭􀀭􀀭� �􀀭􀁔􀀧􀀭􀀭􀀭􀀭􀀭􀀭􀀻􀀮􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀭􀀭􀀧􀀭􀀭􀀭􀁾􀀭􀀭􀀫􀂭-----+------1-------I i', 􀁉􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀬􀀠􀀭􀀭􀀭􀁾􀀭􀀭􀀭-----'1-'-+'---1---1'----1------+--,+-,+--1'---' I : I I I I! ! I I t I I !: I : I I I I I I I I ; ---:-,􀀭􀀫􀀭􀀭􀀭􀀺􀀺􀀬􀀺􀁩􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀮􀀻􀀧􀀮􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀁌􀀭􀀭􀀭􀀭􀀬􀀭􀀭􀀭􀁉􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀁉􀀭􀀭􀀭􀀭􀀭􀀫􀁣􀀭􀀭􀀭􀀭-+--:.--___;:___ .J___;. ___ 􀁾___ ;i___ +______ 1 ___ : __ ,; ______1---------1---+--1----11----------,.---,1---:------1---1------·1---1----,------1--' :--: ; , ---r ! ' : ! !! ! ::: : : : : : I I I I :, : : j ,I Iii : : : ; , -.'-----f---' , , 􀀫􀀧􀀭􀀭􀀭􀀧􀁉􀀭􀀭􀀭􀀭􀀢􀀧􀁾􀀭􀁦􀀭􀁾􀀧􀁾􀁾􀀭􀁾􀀧􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀀢􀁾􀀢􀀧􀀫􀁾􀁾􀀩􀁉􀀧􀁾􀁮􀀧􀁾􀁾􀁾􀁾􀀧􀀭􀀴__􀁾􀁾􀁾􀁾__􀁾􀁾􀀧􀁾􀀠, !, -, i-------·i'-------;-- ----, T", , , , , --'1---------, ': ': I I I I ! I I ,I I I I I I I:: : I ! I I I I I I I I I I l ! 1 1 􀁟􀁾􀁟􀀬􀀠i I : I! ! : : 1! 􀁾􀁉􀁊􀀽􀀠: --'-.',---1-, " "--+--", ----,,-,II ---,---[--:--I---t- --I---, ---1----·,--1---.-----------1-------:---;--1--+-1--+-----:---1---1'--11+1I I I I : I I I Ii: : : : : 􀁾􀀠__ C. -: 􀁷􀁾􀀭􀀧''''_ 11 '1t. 'mr II : , : I' 􀁾􀀠N : : : I;: :---I un" 􀀫􀀭􀀮􀀭􀀻􀀮􀀧􀁾􀁾􀀼􀀫􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀭􀀭􀀷􀀧􀀮􀀬􀀮􀁉􀀯􀀭􀀫􀀭􀀭􀀻􀀮􀀮􀀭􀀭􀀭􀁩􀀭􀀭􀀭􀀭􀀻􀂭-+,-l,!lr'2cr,l+5-=""b-----r-----i----'----r--I--f 􀁾􀀠Upl ---r-----r-----,:----I---,:--..􀁴􀀭􀀭􀀭􀁾􀀻􀀭􀀭� �-r--+---'---620 􀀶􀀠􀀧􀁾I;) --.---+--r-+----:--l=rn------,--I I i I I __1_____1___1___ 1_____1___ I I I I I I I I I I I I , 'l! 􀀱􀀭􀀭􀀭􀁾􀀭􀀭􀀱􀀭􀀭􀁾􀁲􀀭􀀭􀁬􀀭􀀭􀀭􀀬􀀠􀀭􀀭􀁬􀀭􀀭􀁟􀁾􀀭􀀭􀀫􀀬􀀠I I I I i'-'I I i --I I ! I I I I-1---:--􀀭􀀭􀁾􀀭􀀭􀀫􀀭􀀭􀁩􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀀡􀀭􀀭􀀫􀀭􀀭􀁩􀀭􀀭􀀫􀀭􀀭􀀧􀁴􀀭􀀭􀀭􀁲􀀭􀀭􀀬􀀭􀁾􀀭I I : I I I 􀁾􀀠I ;: j I I 􀀮􀁾.. 􀁾􀀭􀀭􀀭--i---I---1-'--t---'t---I---i---I---'t-----t--l I I I I I : I, :j; I􀀭􀁾􀀭􀀭􀀭􀀺􀀠4--+---,--+--+--+--+I I I I I I I :!i -c--!! : 􀁾􀀠: ----+--!---􀀭􀀭􀀭􀂷􀀡􀀭􀀭􀀭􀁲􀀭􀀭􀁾􀀠-----!--I ,􀁾􀀠:: 􀁾􀀠: 􀀭􀀭􀀬􀁴􀀭􀀭􀀭􀁉􀀭􀀭􀀭􀀡􀀭􀀭􀀭􀁉􀀭􀂷􀂷􀁾􀁾􀀭􀀭􀀭: I I I-----r--'---I , , I1-----.L--r--1---r--l-----1---HI I I I I. I :: 􀁾􀀠I ---i---􀁦􀁾􀀭􀀧􀀻􀀭􀀭􀀭--.--+--'t--+I 􀁾􀀠I I I [r I : : : ! I I1--------1 t----1---􀀭􀀭􀁔􀀭􀀭􀀭􀁾􀀭􀀭􀁔􀀭􀀭􀀭--1-----r--- +I "1I I I I I I------,--+--i-----t----T---i-TI I I .______ ____ J. iLl 1 J I I I I J I I I -------j-"----i-----i-----t----1-----1-----i--·-----+----1l ·---+----t--; ------􀀭􀂷􀀭􀀭􀁩􀀭􀀭􀀭􀁦􀁟􀀭􀀭􀀱� �􀀭􀁾􀀠􀀭􀀭􀁾􀀭􀀭􀀭􀁾􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭I I I I I I I I . ________.L_ . _______1____ I I! I I I I I ----􀀭􀁾􀁾􀀭􀀭􀀭􀁦􀁟􀀭􀀭􀁟􀀱􀀭􀀭􀁾􀀠􀀭􀀭􀁾􀀭􀀮􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭I I! 1 ! I Ii! I 􀁟􀁌􀁾􀁾􀁾􀀠􀁾􀁟􀁟􀀠I I I I I I I I I ! I !! I I I I I J------;---1--;'------;-----,------;-----,-----'1"--, "" ! I I ; 􀁾􀁾􀁾􀁾􀀡􀀠I I II I I!------r:􀀭􀀭􀁾􀀭􀀭􀀭.. --·i---􀀭􀀭􀁩􀀭􀀭� �􀀭􀀭􀂷􀂷􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀂷􀁲􀀭􀁾􀁾􀀠--i--, I I I;I 'I I I i 􀁟􀁾􀁾􀁾􀁾􀀠I I I I I I I I I I I I--l------i-----1-----1---' '--'r-----1---" --r-I ! I I I -T-----. I! I : : : t l .,---....._--'1-----.,.,---􀀭􀀭􀀢􀁩􀀭􀀭􀀭􀀭􀀭􀀭􀂷􀁲􀀭􀀭􀁾􀀠: ; : :: , I j I I I ! I I--i---L---i __ ---i-----i---r-I I ! I 1 II I, I' 1 I 1 -----1---,--, : I I I I I I II J--.---I---t-----,-----r ---,--I i I I J I ! I 1 I I -: I I II I I I I --i---''---t-----i-----i---􀀭􀁾􀁩􀀭􀀭􀀭􀀢􀀭􀀭􀁲􀀭I I;! I I! I , 1 : I ,I 1 .i I I 􀀭􀁾􀀭􀀭􀁾􀀭􀀭􀀭--i----i-----f--j 1 I I 1 ; I J ---􀀫􀀭􀀭􀁾􀀠i r---T-i----+----'------+---'"I J--r----r-----,--I I I I LO C\J \.0 􀁾􀀠\.0 \.0 D"􀁾\.0 I ,I 1-+-+-1--++ j 1±l __1_____1___L__1_____I__ ___􀁾􀀭􀀭􀁬􀀭􀀭. I I 1 I Ii: 1 : : ,, ---+-,,, , I'---.j.-I I, I 􀀭􀀭􀀭􀁾􀀭􀀭I ,: I!'--T 􀁾􀀠___ l---__ l______ l_____1_____1_____ l__ I I I I I I I J I I II I I I I "i I I I I --,----:-------;--1--------;--I I I I I I I I I I -: I I \ 1 I I I I--t------t----t-----t-----tIj I I I I I I I I 1 ,, -•. f. __ ,, f---1I----;,,___ .J. __ ,, I il'I'.:; I--"-m-----,----,--------+----..+ -..--1-----19 I I! I I I I.j... I I :: "1' .,.: -{I I _ I I :,'" II I I 1--+---!---i---!--+--+--+--+-----+-----+------+--+----+-I I I ! f 1 :: i I I I -I I I I I I I . I I ,-----+---t----+--j-----+-----+--,--r-'r--t' t I I I I I 1 I I I \ I I I I I \ II;: j-------t:: + +I j I I 1 I '"" -!-----􀀮􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀡􀀭􀀭---􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭---\--1-----I I 1 I [ I 1 I I I f I \ i J1-----1--' ,---1'----1-----L-􀁊� �􀁾􀀠-----! ' '/. 1 I! J ::::: : 􀁾􀀺􀀠I I I In -<;"$ 􀁾􀀭􀁴􀀭􀀭----t------t------t-P' 1'--1 f I I ' :. I I I I...L J j 􀁾􀀠: :: :: j I I I I Ir------T------r--l---r-----r-----r-, ---1-1 I I I I IIt:: I ILl I 􀀾􀀾􀁾􀀠I I I [IT------T-------t-----t-----T------t1------.0 􀁊􀁾􀀠I I I I! r--.. ru I I I [ i I '--J : I!J 􀁾􀀠Ii!I •. ),---T_l ---r-----t-􀀭􀀭􀀭􀁾􀀭􀀭---\TIl ::: 1 [ t--' 􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀭􀀭􀁾..􀀭􀀭􀀭􀁾􀀭􀀭---+-􀀭􀀭􀀭􀁾􀀭􀀭t= i I I I I' I I I I I _ __ AJ 1·I I I I I III r-l' -----1·--l---f-----1'-----.I I ! ' I' ; I I 􀁾􀀠.! I : --J---􀁾􀀬􀀬􀀭􀁊􀀭􀀭􀀭--1 ---􀀭􀀭􀁬􀀭􀁾􀀭--1-----1--.+--1---􀀭􀁬􀀭􀀭􀀭􀀭􀀭􀀭􀁬􀀭􀀭􀀭􀀭􀀭􀀭􀁬􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀁾􀀢􀀢􀁩􀀭􀀭􀀭􀁬􀀭􀀭---t--􀀭􀀭􀁾􀁩􀀭􀀭I ! I ! I I 11 ; I ! . __ 1 I I I I: I I 􀁾􀀭􀀭􀁬􀀠': I II Ic: I J -i I I I-T-r------T--·l ---T--􀀭􀀭􀁾􀁲􀀭􀀭􀁾􀀠􀁾􀀬􀀠! '! "if!' \\􀁾􀀠I I.. i L. I 􀁾􀀠V( \ \ I It! : I I I I I 􀁾􀀠')I I I I ! I.-+ 􀀮􀁾􀀬􀀠---i-----t··-----+-􀁾􀀭􀀭􀁾􀀭􀀭__ 􀁌􀁾__ 􀀭􀀭􀀭􀁾􀀭􀁬􀀻􀀻􀀻􀁁􀁟􀁾iii I I I \ t IV) F'""I!L I I I I ! 􀀡􀁾􀀠I I I I I I I I 15IAYM 0 mEW:! I I I I I I I Ivr vu I I -r-Ir--􀀭􀀭􀀭􀁾􀁊􀀠I I I I I' !::.t I I I I II Il.\j""::ji:: l: :: 􀀺􀁾􀁾.--T-----T----T----r--' ---"---jr-􀀭􀀭􀀭􀁾􀀭􀁯􀁊􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀠:: :: 􀀺􀁾􀁾.... I I I I ! " ,'" I I I! :" III--i---􀀭􀀭􀀫􀀭􀀭􀀭􀀬􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭--, --t+-___ 􀁾􀁣􀀺􀁩􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀠I I I I I 􀁉􀀡􀁾􀀠I, I I! I I rilS f..;;; I I I I i I '-t II i I---T-----,---r--,------T--,-,------T-J I I I'; I I . I I:---r-I: i---}---<----I I ; I I J I'I I j I I I +------+-----}------+--'-._-r--' ---}-􀀭􀀭􀀷􀁻􀀮􀀭􀀭􀁾􀀭􀀭􀀭􀁴􀀭􀀭􀀭􀀼􀀭􀀭􀀭􀀭􀀭􀀭I! I! I I I I I I " I' I I I I I---+----}----t}--􀀭􀁾􀀭􀁴􀀭􀀭I I I I : I I I I I I I I I I I 'j"I I I I--T------T---I-----r,--,---,-----I-T----r-I I I I I ! 1 I I 􀁾􀀠LO tr) I.D L()! f;5􀁾􀀠l() D--\.0 \.0 􀁾􀀠__lI I __I ! ___􀁾􀀭􀀭􀁴􀁴􀀭I I i I ------,--,: I I I I I I I I I I I -----1 I :I I I --+I I I __ -i-I I I I : i I! I: --+--: I I I I I I L____:...-......t I" I I I. I I I ---t------t-j I ' ..__ .H : : j I I I --+---t----\' I I l I --!: --i-----+ I! I I I _ __ L I I I --+----1---+'" I I I I I I I I I I 1 jI 1 ! I I I I I I I I :' 􀀮􀀭􀀭􀁾􀀠 : I I r--: ' I I I I I --r-I ! I : ' --+I I 1 I I I I I I, I I ' --I---r--l--I . I ,,__.1 __ _ ,, I ,, __ ..l. __ _ I,, 0 1 L[J IYj C\J ,0 \..0 fg 1..0􀁾􀀠􀁾􀀢􀁔􀀠I , II I I f----"----"----+---r--' .-+-􀁾􀀠I I lr)-<,£) _ __ 4. __ ,i :: : 􀀫􀂷􀂷􀂷􀂷􀂷􀁲􀀭􀀭􀀴􀁉􀀭􀀭􀁾􀂷􀂷􀂷􀂷􀀭􀀫􀂷􀂷􀂷􀂷􀁲􀀭􀀭􀀫􀀧􀀭􀀭􀀭􀁴􀂷.. 􀂷􀀫􀀭􀀭􀀭􀁲􀀭􀀭􀁔􀀭􀀭􀀭􀁲􀀭􀀭􀀫􀀭􀀭􀀫􀀭􀁾􀀭􀀭􀀭􀁴􀀭􀀭􀀭􀁲􀀠I I ---1--I I I I f I J I I I --_.!-􀁾􀀭􀀭􀁾􀀠􀀭􀀭􀁾􀀭􀀭􀀭􀁲􀀭􀀭􀁦:- __1___ --+-------+------: 􀂷􀀭􀀭􀂷􀂷􀁾􀀻􀀭􀀭􀀭􀁴􀀠􀁾􀀭􀀭􀀭---t-I I I I I 1I I :.....t--cr--1.....+-....t---+I---r....􀀭􀀧􀁲􀀭􀁾􀀭􀀭􀀭􀀫􀀧􀀭􀀭􀀭􀁴􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀁲􀀭􀀭􀀫􀀭􀀭􀀭􀁲􀀠, I'I o--. 1..0 --11--I I @L--l---;------􀀭􀀭􀁾􀀭􀀭􀁩􀀭􀀭􀀭􀀢􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭,IIi I I I I 1.1 I I ii I!! I I I I I-----i---1------ii--􀁴􀁾􀀭􀀭􀂷􀁾􀀭􀀭􀀭---i---i--l --t-----j---􀀭􀀭􀁴􀀭􀀭􀀭􀀭􀀭􀀭􀁴􀀭� �􀀭􀀭􀀭􀀭􀁴􀀭􀀭􀁾􀁬􀀭􀀺􀀠􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀱􀀧􀁾􀀭'___L_ I I I 1 I I I I __+ -I I J I I --I----+I I I I I I I i i I I I I j I I I--1----i--+--l--+--t--+-t--+--·--+--t------t------t--· ---t--1---,.-.---t -I I:: : i: 1: : I I 􀁟􀁾____ I___ 􀁾􀀠__ -__􀁾___􀁾___ 􀁾􀀠_____􀁾􀀠___ --*---r--".--__ +___ 􀁾􀀺􀀠___+___:_._+_ 􀀭􀀭􀀭􀁬􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀁉􀀠:1, .L I I I I I I I I I I---t:,. I! I I I I I I ...-+'---t---tr-------!I I I I I I I ; I 1 ' 􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭... -J----1---􀁾􀀭􀀡􀀭􀀭􀀭__1___ -i------l------l------l􀁾􀀭􀀭􀁬􀀭􀀭---l-----L_\.. 􀁬􀀭􀀭􀀭􀁾􀀭J I I I I I I I I I I I I I I: : : :: ::::::::J I I :: I -: ---r----:􀁦􀁾􀀠I: -----i I I I I I 1 I I =. I ,I I I ; j I I---l-----l---f--1----_·t-----+---._-... ---+---,---+------+------+---+-----i------+--i- -"c'-I I I I J I.. I I I I I 1 I \ I 􀁾􀀠I I I J;C I I I J ! I I :; ::-:: --1 --􀁾􀁦􀁾􀁾􀀠I I : ------t􀀭􀁬􀀭􀀭􀁾􀁾􀁾􀀠---J--􀀭􀀭􀁊􀀭􀀭􀀭􀁦􀀭􀀭􀀭􀁾􀀭􀀭􀀭--1--.1..----1---􀁾􀀠.. _l___ -1-----1------1-----}􀁾􀁾􀀭􀀭􀁬􀀭􀀭---1-----L--i-\-.. c'-I I I I I I 1 I I I I I I \ l: : I : I 􀁾􀀠􀁾􀀠:t I 􀁾􀀠I :: 1 f I -: : 􀁾􀀠: : : : : \ 1 I I j I I 1 I I I I I I--i----;--.. 􀁾􀀮􀀭􀀭􀀮􀀡􀀭􀀭􀀭􀀭􀀭􀀧􀁩􀀭􀀧􀁾􀀭--t-----1---I---t---t------r------t-----·.,:·---t--··_-t-----t--i "-'-'1: I IJ I I I I I 􀁾􀀠I I \ I I I 􀀭􀀭􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀁾􀀭+ I I i ----+·--1---1----/---1-'1: :: : c :: i: \--1----1---1---1-----1---1---t----t-t---t--------r------t--:--.-'I I I I I I I E 􀁾􀀠! I I I I I I I I . J I:: i: IiiI--1----1---f---"----..,-----1----,t ----1'£1 􀁾􀁴􀀠---...----r-f ; I i I Ei 􀁾􀀠I 1 II I I I I 􀁾􀀠l I I -j I { I I I ! 1 I I +I I I I-+-􀀭􀀫􀀭􀀭􀁾􀀭􀀭􀁾􀀭􀀭􀀭-+---+ _+_..1' -+ I---t---1--'-+---+---+ji"--"I j I I! I L__ I I I I : : 􀁾􀀠:: :: ::::j 􀀭􀀭􀁾􀀭􀀭􀀭--1-----1-----1---􀀭􀀭􀀱􀀭􀀭􀁾􀁾􀀭􀀭􀁴􀀺􀀭􀀭􀀮􀀠--1---t--l---T !: --+ r-----t-----+1 -: ---Q I I I I I J 􀁾􀀠Ll !! I '--J I : I J I I !! ....t---t,t,-t---t,--+----+-C\jI I I I j I 1 I 1 I I I I I I I II'􀁾􀀭􀀭􀀧􀀱􀀭􀀭􀁾􀀠---;---r--t--T----1---1---j-r-----r :---. ---r----r------eo I I I ell 1 I I 1 -, .... ___. .L ttt--+--t---I--r-1 1---1---+---, 􀀭􀀭􀀭􀀭􀀭􀁴􀀭􀀭􀀭􀁾� �.. 􀀬􀀭􀀭􀀭􀁾􀀭􀀭􀀭--1----1 1 L-􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀁬􀀠􀁾􀀭􀀭􀀬􀀠---1--􀀭􀀭􀁪􀁲􀀭􀁾􀁾􀀭􀀭􀀭􀁩􀀭􀀭1 I I : I 1 I I II 1 􀁉􀁾􀁾􀀭1-----+-: ----+ 1 I I I I I I : 'iJ---Ir--􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀧􀀧􀀧􀀧􀁾􀀭􀀭� �􀀭􀀭􀁾􀀭􀀭􀀭--t--"--1-----1---r--t---t---i---T------t------t----t-,I }-----}-J I I I I I I l I I I I! I I I 'I l -I-----t-; --I I J ! ,1;,..__-+____ : l: :: i I I d:':i /1 ::r--i-----1---·--·:------ 't--·, ---1-----1---T---􀀭􀀭􀁔􀀭􀀭􀀭􀀭􀁾􀀭􀁔􀀭􀀭􀀭􀀭􀀭􀀭􀂷􀀭􀁦􀀮􀀮􀀮􀀠L--T -r-r----r-1__-+!---f--_i I _____L I 1 I I 􀁾􀀠I i I_ : :: l: :: I : : 􀁬􀀭􀀭􀁾􀀠􀀬􀀬􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀧􀁲􀀭􀀭􀀭 --i----+-----i----·--+------+------i----r------i--􀀭􀀭􀁾􀁾􀀭􀀭􀁬􀁩􀀭􀀭􀀭􀁾􀀭􀀭I I I 1 I ! I I J I !+__+____t I I 1 I L,,__ 􀁾􀁟􀁟􀀠I I 􀁾I I --1-----J-----J-----J .. 􀀬􀀭􀁾􀀭􀀭􀁬􀀭􀀭􀀭--1--􀁩􀀭􀀭􀀭􀁾 􀀭􀀭􀀭􀀡􀀭􀀭􀀮􀀬􀀠--1-..----1 ! ! L}__ 􀁾􀁉􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀻􀀭􀀭􀀭􀀭􀀭􀀭I I I j I I > I i I I; "I I I I I J I I I i I I I I I 􀁬􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀁾􀀠I It---: ' J I I I I I I I I 􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀁬� �􀀭􀀭--i---􀂷􀀭􀀭􀁾􀀭􀀭􀀭􀀢􀀭􀀭􀀭􀀮􀁴􀀧􀁾􀀭􀀭--f-----i--t: f--i--,·---i I􀁴􀀭􀀭􀁾􀀠---f-_____ J", I I ___ __;_ __J! -I I IJ 1: ::: 6 1:: I 􀁾􀀠i J I I I I 􀁾􀀠I I I I I I I--1------r---􀀭􀀭􀀱􀀭􀀭􀀭􀁾 􀀭􀀭􀀱􀀭􀀭􀀭--i------· 􀀭􀁔􀀭􀀭􀀭􀀭􀀭􀀭􀁔􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀁔􀀭􀀭--'-y-----y-----r--' --tr------r-I 1__ 1 __ J I I l I I J Ii r : : -L :.::: : ':: I--1-----i---r--'! "-1---1-----1------t---t----1M"-􀁯􀀭� �􀀤􀁩􀁾---+-----t-t}-_· 􀀭􀀭􀀭􀁽􀀭􀀭􀁩􀁾􀀠􀁾􀀮􀀠I I I I I I I I I I I I I I ! I j 1 I 11 --4-----i----{-----i-----+---. --+------+------i-r--'---}-----}--1--, I : I I I I I I; r,,!􀀭􀀭􀀭􀀭􀀭􀁉􀀭􀀭􀀭� �􀀭􀀭􀀭􀁾􀀮􀀠,,,._-,--,, _!_ I I I j I I I _J[ I I 􀀭􀀭􀁾􀀭􀀭􀀭--J--􀁾􀀭􀀭􀁊􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀀡􀀠--t------+-·..---t-----t--􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀀭􀀭􀁾􀁾􀀭􀀭􀁾􀀭􀀭􀀭􀁾􀀭􀀭I I I 1 -t--I I I I I \ ! I J I I I I f I I I ! I : ! j: ;: : I:,---c--,-----4---.--,-----{------}--+--f--+--+-----t--r--,--1---,-----+ 1---,--. --tt--I---ti_•. +__..__ I ! I I I I I 􀁾􀀠I I I I I I J 􀁾􀀠J I I I! I j 1 I I J I I I I I I I! I j 1 ------i---r---·;----i---I---{-----+---r'--+------+------+------+􀀭􀁾􀁻􀀮􀀭􀀭---i--I I j I, I I I I 1 ___ +_J___ 􀁾􀀠r I 􀁟􀁾􀀠! I 1__ I 􀁟􀁾􀀠I I 1 􀁾􀀠<,£) lC) t2 􀁾􀀠l[J C\J <,£) 􀁾􀀠L[J-<,£) o--. <,£) @ AGREEMENT FOR PROFESSIONAL SERVICES I"Agreement") This Agreement between the Town of Addison, Texas ,C'CUen!") and URS Corporation (,URS,,). a Nevada corporation; Gravstone Centre, 3010 LBJ Freeway, Suite 1300 75234; 972.406,6950 C'URS"), is effective as of September 11.2002 . The parties agree as follows: It is tile expre®see iRleRt af the parties that Ihis I'!; from. any and all claims, actions. causes of action. demands. losses. harm. damages. liability. expenses, lawsuits. judgments, costs. and fees (including reasonable attorney fees and court costs). for any injury to or the death of any person. or any damage to or destruction of any property, or any other harm for which damages or any other form of recovery is sought (whether at law or in equity), resulting from, based upon. or ariSing out of any negligent. grossly negligent reckless, or intentionally wrongful act, error. or omission of URS. its Officer,;. employees, agents. engineers, consultants, contractors, subcontractors. or any person or entity for whom URS is leqa"y liable, under, in connection with, or in the performance of. this Agreement. The provisions of this paragraph shall survive Ihe expiration or termination of this Agreement. ARTICY; VII Consequential &Iamaqes. Neitller Pally shall be liaille te tile atller far G9ASe'lYeAtial damages. iAGllldiAg. witlleut limitatien, less af lise ar less af Ilfefils. iRGIlFFEld by aRe amltller SF their PSA-l.DOC 19-Mar.Q2 -3 􀁳􀁾􀁢􀁳􀁩􀁤􀁩􀁡􀁲􀁩􀁥􀁳􀀠SF 􀀵􀁾􀁓􀀶􀁥􀁳􀁳􀁳􀁆􀁓􀀬􀀠regarsles5 sf whether 􀁳􀁾􀁇􀁨􀀠damages are Gauged by breas" sf soRlrasl, 'A'illful mi5seRdllsl, RegligeRl asl or amissioF!, ar ether wroRgful asl sf either of them. ARTICLE VIII-Client Responsibility. Client shall: (1) provide URS, in writing, all information relating to Client's requirements for the project; (2) correctly identify to URS, the location of subsurface structures whiCh have been placed by Client, such as pipes, tanks, cables and utilities; (3) notify URS of any potential hazardous substances or other health and safety hazard or condition known to Client existing on or near the project site; (4) give URS prompt written notice of any suspected deficiency in the Services; and (5) with reasonable promptness, provide required approvals and decisions. In the event that URS is requested by Client or is required by subpoena to produce documents or give testimony in any action or proceeding to which Client is a party and URS is not a party, Client shall pay URS for any time and expenses required in connection therewith, including reasonable attomey's fees. ClieRl shall reimburse URa fer all falEeS, aGlies aRd le',ies S\lsh as Sales, Use, 'Jal\le MGeS Taxes, geeme9 F'rafiIs Taxes, aAIl ether Similar falEes whish are Bdllee la ar eeauGleS from the '..alue sf URal Servises. FaF the p\llf*lSe of this Artisle s\lsh taxes GRail Ret iRGluee falEes imposes OR URS Ret iRGeme, aRd empleyer aF employee payrell falEes levieS lily aRY UARed Slates taxiRIl aslharily, aF the taxiR!j aiJIMrities sf the seuR\ries aF BAY ageASY ar SU9ai'/isieR tReresf iF! '/Ihish URS sllllsiaiaFies, affiliates, aF ei'lisieAs are pofJAaReRtly aemiGileS. It is allreea aRd IlRaaFSteed IRat tRese Ret iRoome, _playar aF empleyee payroll falEes are iRsluaee iR the IlRit pAGes er lump S\lm te be paid URal IlAdsrthe respeGli'IB 'A'erk GRIer. ARTICLE VIIIX -Force Majeure. An event of "Force Majeure" occurs when an event beyond the control of the Party claiming Force Majeure prevents such Party from fulfilling its obligations. An event of Force Majeure includes, without limitation, acts of God (including floods, hunicanes and other adverse weather), war, riot, civil disorder, acts of terrorism, disease, epidemic, strikes and labor diSputes, actions or inactions of government or other authorities, law enforcement actions, curfews, closure of transportation systems or other unusual travel difficuHies, or Inability to provide a safe working environment for employees. In the event of Force Majeure, the obligations of URS to perform the Services and the obligations of the Client hereunder shall be suspended for the duration of the event of Force Majeure. In such event, URS 511ail be eEjuitably esmpensated IllF time e*pendea and Bl L. Addison, TX 75001-9010 -.-.-.' " "". .... ." .. ' .. '::.' ARAPAHO ROAD BRIDGE AT MIDWAY ROAD WORK ORDER NO. 001 ATTACHMENT A SCOPE OF SERVICES DESIGN DEVELOPMENT Al"ID CONSTRUCTION DOCUMENTS FOR THE ARAPAHO ROAD BRIDGE DRS will provide the engineering. architecturaJ, lighting design and noise study services including plans, specifications and estimates as it relates to Arapaho Road from approximate Station 40+67 to approximate Station 70+28 and as provided in the itemized scope. The construction will consist of an elevated four-lane roadway with sidewalk located within the proposed Arapaho Road right-of-way (ROW) on a tangent alignment. URS shall prepare plans, details and compute quantities for a steel arch bridge, the "blue-bridge concept", over Midway Road, with prestressed concrete beam approaches. Design and details will include all bridge details including any soundwalls located on the bridge. DRS will also provide all bridge drainage details to accommodate the drainage in accordance with the Town's Consultant's drainage requirements. URS will also prepare plans, details and compute quantities for any lighting & illumination, and traffic control for the areas under and immediately adjacent to the bridge and retained wall portion of Arapaho Road with the exception of those portions to be prepared by the Town of Addison's Consultant. URS will also prepare architectural details for the bridge, the mechanically stabilized earth (MSE) retaining walls and the sound walls. Additionally, URS will prepare a noise study including ambient noise measurements, modeling and noise analyses. URS will prepare and submit technical memorandums, preliminary plans and preliminary construction cost estimates at the end of the Design Development phase for the Town's review. After resolution of one set of comments, URS will provide all fmal detail plans, specifications, and estimates as previously described, to be included into one fmal construction package prepared by the Town's Consultant. DRS will submit four sets of plans for review to the Town for 65% review and 95% review and will incorporate the Town's comments (one set per submittal) in the next submittals. URS will also provide signed and sealed mylar plans at the 100% fmal submittal. DRS will coordinate with the Town of Addison andlor the Town's Consultant for all interface design issues as well as coordinate the format and consolidation of construction plans, specification and estimate into one final construction package. URS will coordinate with the Town andlor the Town's Consultant for revising the horizontal alignment and vertical' profIle of Arapaho Road to accommodate the proposed bridge structure. URS will coordinate with the Town andlor the Town's Consultant for the revised alignment of the proposed box-culvert under Arapaho Road as well as bridge drainage and bridge drain tie-ins. URS will coordinate with the Town andlor the Town's Consultant for all geotechnical information required for the foundation design for the bridge and retaining walls. 􀁾􀁬􀀭􀀻􀁾􀁾􀀠􀁾􀁲􀀠\ , .' The Town of Addison will provide to URS all available Arapaho Road geometries, including but not l @"<, MfY. limited to electronic files for horizontal alignment, vertical profIle, typical sections, topography ;r:ufo!> 11' survey, field survey, and utility information. The Town will also provide boring logs, soil parameters I'"'\f', 􀁾􀀮􀀠and foundation design recommendations (allowable bearing capacities, lateral load analysis, etc.) 􀁾􀀠, 􀀩􀁡􀁾􀀱􀀩􀀬􀀠required for the bridge foundation designs. The Town of Addison will provide to URS a field location \&M;I .' survey of the existing 60-in. diameter water main, locating the water main precisely, both vertically and horizontally, along the project limits and specifically in the vicinity of the arch-bridge's main foundations. Additionally the Town will provide any applicable noise regulations or ordinance information, obtain right of entry, and provide all traffic data including but not limited to, peak hourly volumes, average daily traffic, percentages of trucks, and design and posted speeds that may be required for the noise study. The Town will provide all landscape ordinances and guidelines as well as provide a copy ofthe Town's Consultant's schematic landscape masterplan and the streetscape design development package. All ROW documentation and plans, Arapaho Road geometries and roadway design, drainage, parking lot layout and design, retaining wall layout and design, survey, geotechnical engineering, design and details for sOWldwails on retaining walls or at grade, landscaping, hardscaping and irrigation for landscaping, permitting. and construction administration, inspection and record drawings are' outside the scope ofthis agreement and will be performed by others. URS August 7, 2002 Mr, Steven Z. Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P,O, Box 9010 Addison, TX 75001-9010 Re: Arapaho Road Bridge at Midway Road Phase II -Design Development, Contract Documeuts, and Construction Administration Conceptual Constructiou Cost Estimate -"TxDOT" Bridge Dear Mr. Chutchian: Enclosed please find a copy ofthe Conceptual Construction Cost Estimate for a standard "TxDOT" bridge for the referenced project for your review as you requested. This estimate in addition to a standard bridge includes minimal urban design & landscaping, roadway deck and parking lot lighting, lighting along the traffic rails, a rail to separate pedestrians from the roadway and some soundwalls, The conceptual cost is -$4.1 million. We trust that this will help in moving the process forward so we may proceed with finalizing Our scope and fee proposa\. Sincerely, URS Corporation 􀁾􀀯􀀿􀁤􀁦􀀠CliffR. Hall, PE Project Manager Enclosure URS Corporation Prestonwood Tower 5151 8eftline Road, Suite Suite 700 Dallas, TX 75254 Tel: 972,980,4961 Fax: 972.991.7665 ARAPAHO BRIDGE MEETING, 9125/02 OPENING COMMENTS RON WIDTEHEAD/CITY MANAGER PBASE DI STATUS REPORT HNTB BRIDGE DESIGN & CONSTRUCTION PROCESS DRS GENERAL DISCUSSION URS May 5, 2003 Mr. Steven Z. Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re: Arapaho Road Bridge at Midway Road Phase II -Design Development & Contract Documents Draft Noise Report Dear Mr. Chutchian: Enclosed please fmd three copies ofthe Draft Report for the Arapaho Road Bridge Noise and Vibration Analysis for your review. Please provide any comments at your earliest convenience. Upon receipt ofyour comments we will issue the final report. Sincerely, C;;;d/CliffR. Hall, PE Project Manager Enclosure URS Corporation Gtaystone Centre 3010 LBJ Freeway, Suite 1300 Dallas. TX 15234 Tel: 972.406.6950 Fax: 972.406.6951 FW: Arapaho Road Borings Page 1 of2 Steve Chutchian To: Elizabeth Matting Subject: RE: Arapaho Road Borings Liz -Please accept this correspondence as your approval to pelform the additonal borings. Thanks. Steve C. -----Original Message----From: Elizabeth Metting [mailto:EMETTING@HNTB.com] Sent: Monday, April 14, 2003 1:30 PM To: schutchian@ci.addison.tx.us Subject: FW: Arapaho Road Borings Steve, This is the estimate 10 get the additional two borings done. I would like to get the Town's approval 10 get this work underway ASAP. Please call me on my mobile 8t972-849-8023 Liz -----Original Message---From: Roger Southworth To: Elizabeth Melting Sent: 4fI412003 9: 11 AM Subject: Re: Arapaho Road Borings Good morning Liz, The additional oost for the bridge borings is $1,600.00. This includes re-clearing the utilities, re-mobilization of drilling equipment, rock coring (assumed boring depths of 40 feet), laboratory testing, and additional CAD. A large part ofthis budget is for re-clearing utilities since we will have to start from the beginning with the utility locates. Feel free to give me a call ifyou need more information. Roger »> "Elizabeth Melting" 04f09f03 01:30PM »> Here is a spreadsheet listing the borings that I show have been done, ." along with the ones that remain to be done. < , ItJerry Holder" . com> , SUbject: RE: Bridge footing 03/18/03 10:19 AM Cliff, I'm working on finishing up the pavement file now and can have that to you pretty soon. I haven't finalized the profile yet but I am hoping to have that done in the next day or so. Since the sidewalk is with in l2-ft of the edge of pipe, I will need 22-ft of clearance under the sidewalk. I will verify that you have the 16' 6" 1 under the bridge, but I think the sidewalk might control the vertical over Midway. I am working in SelectCad not GeoPak but can give you all the files you will need to the 4th decimal place. Would you want these files as I finish them or all together? I can get them all to you by the end of the week. Jenny Nicewander, P.E. HNTB Corp. 5910 W. Plano Parkway, Suite 200 Plano, TX 75093 main -972-661-5626 direct line -972-628-3164 fax -972-661-5614 -----Original Message----From: Cliff_Hall@URSCorp.com [mailto:Cliff_Hall@URSCorp.comJ Sent: Tuesday, March 18, 2003 9:07 AM To: Jenny Nicewander Cc: schutchian@ci.addison.tx.us; Jerry Holder Subject: Re: Bridge footing Jenny, I have just received a phone call from Luke Jalbert of the Town of Addison giving us notice-to-proceed with Option A for the Arapaho Road Bridge. In order to begin our work on the bridge, we will need the final alignment and profile of Arapaho Road bridge as soon as possible. In addition to any MicroStation files, we would appreciate a copy of the GeoPak files with all information (Sta, Elev, Grade, etc.) to four decimal places. To ensure that a minimum vertical clearance of 16 1 -6" over Midway Road is maintained to the bottom of the prestressed beam and diaphragm at the arch section, a superstructure depth of a minimum of 5'-6" is required. When verifying the vertical clearance, the cross slope of the deck must be taken into account. Please call if you have any questions. Cliff R. Hall, PE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 ******************************** ************************************** This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. ********************************************************************** 2 3 Steve Chutchian From: Jenny Nicewander [JNicewander@HNTB.com] Sent: Tuesday, March 18, 2003 10:19 AM To: Cliff_Hall@URSCorp.com Cc: schutchian@ci.addison.tx.us; Jerry Holder; Ijalbert@ci.addison.tx.u 5 Subject: RE: Bridge footing Cliff, I'm working on finishing up the pavement file now and can have that to you pretty soon. I haven't finalized the profile yet but I am hoping to have that done in the next day or so. Since the sidewalk is with in 12-ft of the edge of pipe, I will need 22-ft of clearance under the sidewalk. I will verify that you have the 16'6" under the bridge, but I think the sidewalk might control the vertical over Midway. I am working in SelectCad not GeoPak but can give you all the files you will need to the 4th decimal place. Would you want these files as I finish them or all together? I can get them all to you by the end of the week. Jenny Nicewander, P.E. HNTB Corp. 5910 W. Plano Parkway, Suite 200 Plano, TX 75093 main -972-661-5626 direct line -972-628-3164 fax -972-661-5614 -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.com] Sent: Tuesday, March 18, 2003 9:07 AM To: Jenny Nicewander Cc: schutchian@ci.addison.tx.us; Jerry Holder Subject: Re: Bridge footing Jenny, I have just received a phone call from Luke Jalbert of the Town of Addison glvlng us notice-to-proceed with Option A for the Arapaho Road Bridge. In order to begin our work on the bridge, we will need the final alignment and profile of Arapaho Road bridge as soon as possible. In addition to any MicroStation files, we would appreciate a copy of the GeoPak files with all information (Sta, Elev, Grade, etc.) to four decimal places. To ensure that a minimum vertical clearance of 16'-6" over 􀁾􀁤􀁷􀁡􀁹􀀠Road is maintained to the bottom of the prestressed beam and diaphragm at the arch section, a superstructure depth of a minimum of Sf-6ft is required. When verifying the vertical clearance, the cross slope of the deck must be taken into account. Please call if you have any questions. Cliff R. Hall, PE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 ! Fax: 972.406.6951 ********************************************************************** This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. ************************************************** ******************** 2 I Steve Chutchian From: ClifCHall@URSCorp.com Sent: Tuesday. March 18. 2003 9:07 AM To: Jenny Nicewander Cc: schutchian@ci.addison.tx.us; jholder@hntb.com Subject: Re: Bridge footing Jenny, have just received a phone call from Luke Jalbert of the Town of Addison glvlng us notice-to-proceed with Option A for the Arapaho Road Bridge. In order to begin our work on the bridge, we will need the final alignment and profile of Arapaho Road bridge as soon as possible. In addition to any MicroStation files, we would appreciate a copy of the GeoPak files with all information (Sta, Elev, Grade, etc.) to four decimal places. To ensure that a minimum vertical clearance of 16' -6" over Midway Road is maintained to the bottom of the prestressed beam and diaphragm at the arch section, a superstructure depth of a minimum of 5'-6" is required. When verifying the vertical clearance, the cross slope of the deck must be taken into account. Please call if you have any questions. Cliff R. Hall, FE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 1 Ret: 1 Fax: 'i·iMI"u IjjJ00201/29/2003 14:36 FAX URS Memorandum Date; January 28, 2003 To: ShW'on Bell. From: CliffR. Hall. P.E. 6t{li Subject: Arapaho Road Bridge -Concept Vrdeo FileJi A$ requested we have enclosed II copy ofthe computer animated video files ofthe Arapaho Road Bridge concept, developed for the design competition presentation last April. To view these files you will need to download the files onto a computer with a DVD player software. The DVD player software should be opened and from the DVD player open the file. Please feel free to call me ifyou have any problems. c,c, Steve Chutchian, PE Rece ax : 􀁁􀁾􀁊􀀠00 3:2 Fax St l' • a ISO 1 01/29/2003 14:36 FAX @OOl URS Facsimile To! Firm: -,;;,...., N '" F 􀀦􀁾􀀬...'" 􀁎􀁾__ Fi!a;;mile: '4,2 .YS;"O, "2.6 􀁾􀀷􀀠From! c....'FF r-h1-..... Date: \ /.. q 1t:P-=-';._...... Page 1 of: 􀁾􀀠Message: Subject: cc: .. URS Corporation . COl'FJI)ENrI!.J.,IT'II NOTICE ,3010 LBJ freeway, 􀁓􀁵􀁩􀁴􀁾􀀠1320 ! The information In ibis. (acJimile Irwmimon is. intended solely rortMDBfla.&. l'X 7$234 meed Teciplenl of Ihls: tlllJU'mlnion. If you have: rcqblcd IIlII !Q:': in error, Tal: 972.406.6950 􀁰􀁬􀁣􀁾􀁊􀁃􀀠notify the. 􀀮􀀡􀁾􀁾􀁴􀀠immediiitl)' b)' ItJephont". rr ),OLl &II!: nOllhcFall; 􀁮􀀺􀀲􀀢􀀬􀀴􀀰􀁇􀀮􀀶􀁾1 inttndcd redpient, plc&$c be 􀁾􀁖􀁩􀁬􀁃􀁤􀀠ths.1 diucminarion. diairibUliOll•.orWiNI.umeorpc.com copying of Ihl: infoonlltion contained in mil ru il sUi.:::tly prohibited. Steve Chutchian To: Jerry Holder Subject: RE: Data for Noise Study thanks. -----Original Message----From: Jerry Holder [mailto:JHolder@HNTB.com] Sent: Monday, December 16, 2002 11:06 AM To: schutchian@ci.addison.tx.us ec: jpierce@ci.addison.tx.us SUbject: RE: Data for Noise Study Actually Steve, I checked with Liz on #3 and it turns out that we spent a lot of time getting the COG photo's projected into the correct coordinate plane so that it lines up with our CAD drawings* So we're giving what we did to Cliff to save them the time and effort. He'll only need your CD's if for some reason he needs coverage outside of the roadway corridor. Jerry -----Original Message----From: schutchian@ci.addison.tx.us [mailto:schutchian@ci.addison.tx.us] Sent: Monday, December 16, 2002 11:04 AM To: Jerry Holder Subject: RE: Data for Noise Study Jerry -thanks for the help. I will check with Jim today. Steve C. -----Original Message----From: Jerry Holder [mailto:JHolder@HNTB.comj Sent: Wednesday, December 11, 2002 6:28 PM To: Cliff Hall@URSCorp.com; schutchian@ci.addison.tx.us Cc: Elizabeth Metting; Jenny Nicewander; Angela Stoddard Subject: RE: Data for Noise Study Steve, I think we can help with the following: Item #1: I believe Bruce Grantham has a contract on Midway Road, I will check to see if it covers this area. (Liz, I think you know the answer to this one, please let me know) Item #2: We can e-mail this to Cliff. {Jenny, please take care of this} Item #3: The Town has coverage through COG. Jim Pierce has the CD's from COG that have the aerial files on it. (Steve can you check with Jim on this?) Item #4a, b, and c: I will discuss this with Angela Stoddard. I know this data is limited and assumptions were made for the engineering report. We will provide what we have. (Angie, please get the engineering report and let's discuss what we can provide to Cliff} 1 Item #4d: Angela and I will send the design criteria to Cliff. Item 5: Jenny and I will send this to Cliff. Let's set a deadline of Monday to get this to Cliff. Thanks everyone. Jerry -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.comj Sent: Wednesday, December 11, 2002 4:21 PM To: schutchian@ci.addison.tx.us Cc: Jerry Holder; Elizabeth Metting Subject: Data for Noise Study Steve, In order to develop our model for the noise study, we will need the following information. We understand that some of this information (e.g. traffic data) may not be available to the extent that we are requesting; however, we would ask that you please provide as much information as is available. 1. Midway Road vertical profile and horizontal alignment in the vicinity of Arapaho Road. 2. Arapaho Road final vertical profile and horizontal alignment (when available). 3. Aerial map showing extent of project ROW plus 500' to cover all adjacent receptors. (It would be helpful if the aerial showed the proposed Arapaho Road). 4. Traffic Data: a. ADT: Future design year with project alternative b. Directional Peak hour traffic volumes (total, not turning movements) for level-of-service (LOS) C and DIE (link capacity data, not intersection capacity data) for the future design year with project alternative. c. Vehicle Mix: 5 types -automobiles, motorcycles, busses, medium trucks and heavy trucks (3 axles or greater) for peak-noise-hour, LOS C or DIE. d. Traffic speeds, design and posted. 5. Railroad: type and frequency of rail traffic. Cliff R. Hall, PE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 ********************************************************************** This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. ********************************************************************** 2 See answers below Page 1 of3 Steve Chutchian From: Jerty Holder [JHolder@HNTB.com] Sent: Thursday, December 12, 2002 9:26 AM To: clifChali@urscorp.com; schutchian@ci.addison.tx.us; Jenny Nicewander; Angela Stoddard; Elizabeth Metting; Rob Kouba; Katura Curry , Subject: See answers below Please see our responses to Cliff's requests, shown in red below. Thanks, Jerry steve, I think we can help with the following: Item #1: I believe Bruce Grantham has a contract on Midway Road, I will check to see if it covers this area. {Liz, I think you know the answer to this one, please let me know} Liz has sent an e-mail to Katura (Grantham & Associates) to send this information to Cliff. Item #2: We can e-mail this to Cliff. {Jenny, please take care of this} Jenny will e-mail the latest to Cliff by Friday. Item #3: The Town has coverage through COG. Jim Pierce has the CD's from COG that have the aerial files on it. {steve can you check with Jim on this?} Item #4a, b, and c: I will discuss this with Angela Stoddard. I know this data is limited and assumptions were made for the engineering report. We will provide what we have. (Angie, please get the engineering report and let's discuss what we can provide to Cliff) #4a: I will fax Cliff the traffic data from the engineering report and also the geotechnical report showing the percentage of trucks. will do this today. #4b: This is not available since this road is on a new alignment. You might be able to get some information from the traffic study the Town recently did on Beltline. #4c: See geotech report I will fax to you·. Item #4d: Angela and I will send the design criteria to Cliff. Design Speed = 40 mph and Posted Speed = 40 mph. Item 5: Jenny and I will send this to Cliff. There are four (4) freight trains per day that use the track. They are not on a set I 12/16/2002 See answers below Page 2 of3 schedule. Let's set a deadline of Monday to get this to Cliff. Thanks everyone. Jerry -----Original 􀁍􀁥􀁳􀁳􀁡􀁧􀁥􀀭􀀭􀀭􀁾From: Cliff_Hall@URSCorp.com [mailto:Cliff Hall@URSC0J:'p.com] Sent: Wednesday, December II, 2002 4:21 PM To: schutchian@ci.addison.tx.us Cc: Jerry Holder; Elizabeth Metting Subject: Data for Noise Study Steve, In order to develop our model for the noise study, we will need the following information. We understand that some of this information (e.g. traffic data) may not be available to the extent that we are requesting; however, we would ask that you please provide as much information as is available. 1. Midway Road vertical profile and horizontal alignment in the vicinity of Arapaho Road. 2. Arapaho Road final vertical profile and horizontal alignment (when available). 3. Aerial map showing extent of project ROW plus 500' to cover all adjacent receptors. (It would be helpful if the aerial showed the proposed Arapaho Road). 4. Traffic Data: a. ADT: Future design year with project alternative b. Directional Peak hour traffic volumes (total, not turning movements) for level-of-service (LOS) C and DIE (link capacity data, not intersection capacity data) for the future design year with project alternative. c. Vehicle Mix: 5 types -automobiles, motorcycles, busses, medium trucks and heavy trucks (3 axles or greater) for peak-noise-hour, LOS C or DIE. d. Traffic speeds, design and posted. 5. Railroad: type and frequency of rail traffic. Cliff R. Hall, PE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 12116/2002 I Steve Chutchian From: Elizabeth Metting [EMETTING@HNTB.comJ Sent: Monday, December 02, 2002 8:37 PM To: schutchian@ci.addison.tx.us; ClifCHall@URSCorp.com Cc: Jenny Nicewander; Jerry Holder; Mike Preston; David Boles Subject: RE: Arapaho Road Bridge Steve, understood that Slade would not be available this week. Whenever he is available, we would like to meet with him, you, Jim Pierce, Luke, and Cliff. Wednesday morning should be possible (as early as 8:30) or right after lunch. If he is out, then let both Cliff and me know several possible times early next week and we will find a time to meet. We have developed some sketches trying to fit a sidewalk/trail within the typical section while still accomodating DWU's desire to remain a minimum distance from the 6011 line. We would like to get everyone together to develop the concepts into a working plan. Liz -----Original Message----From: schutchian@ci.addison.tx.us [mailto:schutchian@ci.addison.tx.usl Sent: Monday, December 02, 2002 4:00 PM To: Cliff Hall@URSCorp.com Cc: Elizabeth Metting Subject: RE: Arapaho Road Bridge Cliff/Liz: we probably can meet on Wednesday or Thursday afternoon this week, or anytime on Monday or Tuesday of next week. Thanks. Steve C. -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.com] Sent: Monday, December 02, 2002 3:31 PM To: emetting@hntb.com Ce: sehutchian@ci.addison.tx.us Subject: Arapaho Road Bridge Liz, As we discussed the week before last, you were going to arrange a meeting with the Town of Addison to discuss the bridge and roadway typical sections that will provide the required clearance to the 60" water main. Please advise the time and location for this meeting if it has been arranged. This issue must be resolved before we can progress with the preliminary bridge design. Cliff R. Hall, PE Bridge Group Manager URS Corporation Greystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.4Q6.6951 I ********************************************************************** This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any usel dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. ********************************************************************** 2 PUBLIC WORKS DEPARTMENT (972) 450.Z871 FAX (972) 45{)·2837 ® Post Offiee Box 9016 Addison, Texas 75001-9010 16801 Westgrove November 18, 2002 Mr. CliffR. Hall. P.E. URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1320 Dallas, Texas 75234 Re: Arapaho Road Bridge at Midway Road Phase II Design Development & Contract Documents Agreement for Professional Services Dear Mr. Hall: Enclosed is a copy ofan executed original ofthe Agreement for Professional Services for the Arapaho Road Bridge at Midway Road. An original ofthis document was previously forwarded to your office by separate transmittal. Please accept this correspondence as your authorization to proceed with the Arapaho Road bridge design, as outlined in the Scope ofServices portion ofthe Agreement. Should you have any questions, please call me at 972-450-2878. Thank you. Sincerely, /t/t-(' 􀁾􀀠Michaelh{urphy,P.E. Director ofPublic Works Enclosure Steve Chutchian From: HILL, JOHN [jhill@cowlesthompson.coml Sent: Friday, November 01 , 2002 8:36 AM To: 'Nancy_Cole@URSCorp.com' Cc: 'mmurphy@ci.addison.tx.us'; 1pierce@ci.addison.tx.us'; 'schutchian@ci.addison.tx.us'; DIPPEL,KEN Subject: RE: Town of Addison-Revision!! Nancy--No problem with striking that 􀁰􀁲􀁯􀁶􀁾􀁳􀁾􀁯􀁮􀀠(that provision (with a modification) was included with the changes proposed by URS). I would appreciate it if you would please have URS execute two originals of the agreement and have the URS representative forward the signed originals to Jim Pierce at Addison. Thanks. John Hill Cowles « Thompson 901 Main St. 4000 Bank of America Tower Dallas, Texas 75202 (214) 672-2170 -----Original Message----From: Nancy Cole@URSCorp.com [rnailto:Nancy Cole@URScorp.com] sent: Thursday, October 31, 2002 2:34 PM To: HILL, JOHN Cc: 'jpierce@ci.addison.tx.us'; DIPPEL, KEN Subject: Re: Town of Addison-Revision!! John-Sorry to do this, but as per my phone message, we need to discuss Article XVI, 1tG" -!lIn the event Client and URS are unable to agree on an appropriate equitable adjustment in Estimated Costs and Schedule prior to the time the changes in the Services need to be performed, then Client shall authorize URS to proceed with the changes and URS will do so...• " • URS doesn't want to have the obligation to perform if we cannot reach an agreement prior to our starting work. We would like to strike that language. Regards, Nancy C. Cole Contracts Manager, Gulf Coast Region URS Corporation, Legal Department 8181 E. Tufts Avenue Denver, CO 80237 (303) 740-2737 (303) 930-6044 fax nancy_cole@urscorp.com ttHILL, JOHN" mpson.com> cc: 1 U1jpierce@ci.addison.tx.us flf , "DIPPEL, KEN" 10/30/2002 08:44 Subject: Town of Addison AM <. ludgments, costs. and fees "ncluding reasonable attorney fees and court costs), for any injury to or the death of any person. or any damage to or destruction of any property, or any other harm for which damages or any other form of recovery is SQught (whether at law or in equity). resulting from. based upon. or arising out of any negligent. grossly negligent. reckless, or intentionally wrongful act, error, or omiSSion of URS, its Officers. employees. agents, engineera, consultants. contractors. subcontractors. or any person or entity for whom URS is legally liable. under, in connection with. or in the performance of. this Agreement. The provisions of this paragraph shall survive the expiration or termination of this Agreement. ARTICbli '.'11 ConsegueRtial [)amages. 􀁾􀁬􀁥􀁩􀁴􀁒􀁥􀁲􀀠FlaFly sllall I;)e liable te Ille ather for 􀁇􀁓􀁁􀁳􀁥􀁅􀁬􀁾􀁥􀁁􀁬􀁩􀁡􀁬􀀠damages, iASIIll:IiRg, wilRawt IimltatieA, less af use eF less sf prefits, iASllrred Ily eRe aRetner aF tneir PSM.DOC 19-Mar'()2 -3 syllsi"'ial'ies er SysseSS9rs. 􀁲􀁡􀁾􀁡􀁲􀁤􀁬􀁥􀁳􀁳􀀠9f whether slleh 􀀢􀀧􀁡􀁭􀁡􀁾􀁥􀁳􀀠are eatlse'" By breach af CGR!raat. willflll mise9R"'tlat, 􀁒􀁥􀁾􀁬􀁩􀁾􀁥􀁒􀁬􀀠aat sr smissisFl, sr stJ:ler WFsA8f1l1 aat sf either ef them. ARTICLE VI" -Client Responsibility, Client shall: (1) provide URS. in W1iting, all information relating to Client's requirements for the project; (2) correctly identify to URS, the location of subsurface structures which have been placed by Client, such as pipes, tanks, cables and utilities; (3) notify URS of any potential hazardous substances or other health and safety hazard or condition known to Client existing on or near the project site; (4) give URS prompt W1itten notice of any suspected deficiency in the Services; and (5) with reasonable promptness, provide required approvals and deCisions. In the event that URS is requested by Client or is required by subpoena to produce documents or give testimony in any action or proceeding to whiCh Client is a party and URS is not a party. Client shall pay URS for any time and expenses required in connection therewith, including reasonable attorney's fees. GlieRl sllall raimsllrse 􀁕􀁾fer ailiaxes, "'uties an'" levies StlGA as Sales, Use. VallAe ,<\l:kIee Taxes, Oeemee pFGfits Taxes. aAe GIller similar \axes wilieR ara a£l£led la ar "'eduate!! from Ihe value at URS SeP,'ises. FeF the fltlfll9se af this I',FliGie SlAsh t_ shall Rsl iRGIude \axes imflese'" on URS nGl iAGOme. ane empleyer eF emllleyee 􀁰􀁾􀀧􀁲􀁥􀁬􀁬􀀠taJ(8S l&Vie'" 11)' aAY !JRiIed States laxiR!! authelity, eF the 􀁴􀁡􀁸􀁩􀁾􀀠autherilies elf the seuRlries elF any B!leRGY eF 􀁳􀁷􀁾􀁍􀁳􀁩􀁥􀁒􀀠theraaf iR '",hish !JRS subsidiaries. affiliates, or "'i"isioRS are permaReRlly !!omisile!!. It is B!lreed ane tlA"'eFSteoo that these Ret iASElme, emllleysr Elr emflloY88 payrell taxes are illsltldes iA tile tlAit PAGOS or lump Sllm Ie ge flSie URS Ynear the F8SflSsti'l1l 'NeFk OFEklF. ARTICLE VIIgc; -Force Majeure. An event of "Force Majeure' occurs when an event beyond the control of the the Party claiming Force Majeure prevents such Party from fulfilling its obligations. An event of Force Majeure includes, without limitation, acts of God (including floods, hunicanes and other adverse weather). war, riot, civil disorder, acts of terrorism, disease. epidemic. strikes and labor disputes, actions or inactions of govemment or other authOrities, law enforcement actions. curfews, closure of transportation systems or other unusual travel difficulties, or inability to provide a safe working environment for employees. In the event of Force Majeure, the obligations of URS to perform the Services and the obllgatjons of the Client hereunder shall be suspended for the duration of the event of Force Majeure. In such event, YRS sllall I:)e 8€111ilallly seml'l8nsatell fer lime eXl'leAdell all!! 9J(l'lsnsss iRBllrre'" StlRA8 tile 􀁥􀁾􀀧􀁥􀁒􀁬􀀠ef Feree Majewre aAd the Time SchedulesBlle!!Y[e shall be extended by a like number of days as the event of Force Majeure. If Services are suspended for 􀁾(lL03Q) consecutive days or more bv such Force Majeure, either URS or the Client may, iA its sole "'isereli911. upon at least 5 days prior Wlitten notice, terminate this Agreement ander the affected WorX Order. sr !lGlh. In the case of such termination. iR aeditieR 10 Ille seFApeRsatisR ana time elElaAsisA sGl feFlIl alleva, URS shall be compensated in accordance herewith for all worX properly performed to the date of terminationreasolla!lle IormillatillR eXflenses. In the event of such termination of this Agreement and the WorX Order, no amount shan be due for lost or anticipated profits. ARTICLE VIIgc; -Riaht of Entry. If Client is the owner of the project site, URS shall have access to the project sjte at all reaSQnable times for the puroose of providing the Services. If Client is not the owner of the project site, Client shall use its commercially reasonable efforts to obtain permission for URS to have access to the project site for such purooseGlieRl graRlS t9 URS. all"', if the prejeGl site is IIG1 9.....lIea Ily Ily GlieRl, '.'.-0.:::JO')ON J: C 􀁅􀁾􀀠􀁾􀀠•C) c ..J ° N I!! :::J C)u: ' .. 0 to 0 to 0 ID 0 ID ID 0,... ,... <0 <0 ID to ....'" '" '" b·'V8P 􀁏􀁏􀀺􀁓􀁾􀀠OO:vk 􀁏􀁏􀀺􀂣􀁾􀀠􀀰􀀰􀀺􀀱􀀺􀁾􀀠􀁏􀁏􀀺􀁾􀀾􀀠OO:Ok 00:6 OO:g OO:L 00:9 ,OO:g '" I-'OO:v N, 00:£ 'r!-I .50> l -' ' 00:(: I􀁾,OO:k I-'00:0 + 00:£1: 00:(:(: 00: k1: 00:01: 00:6> OO:gk OO:H 00:9k OO:Sk OO:vk Affected Environment 5.0 ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION MEASURES 5.1 THRESHOLDS OF SIGNIFICANCE The project would be considered to produce a noise impact if FHWNrxDOT NAC are approached or exceeded. Specifically, if the noise from the project equals or exceeds the NAC for Activity Category B or C of 66 dBA L", and 71 dBA L", respectively, or ifpredicted traffic noise levels exceed existing noise levels by more than 10 dBA,the project would be considered to have a significant noise effect and mitigation should be considered. 5.2 IMPACTS ANALYSIS AND MITIGATION MEASURES 5.2.1 Traffic Noise Modeling After ambient noise data were collected, the potential noise impacts to representative noise-sensitive receivers were modeled using the FHWA Traffic Noise Model (TNM®), TNM® is FHWA's most recent computer-based noise model for highway traffic noise prediction and analysis. TxDOT has approved the noise model for use in the analysis of their highway projects. TNM® incorporates features that make it a very good choice for accurate assessment of noise from the proposed project; specifically, the model allows the analyst to very accurately input and model the geometry of the proposed roadway, surrounding structures and receivers in three dimensions. Site-specific data used to model future noise impacts included: • Design year traffic data (traffic volumes, mix, direction, and speed) • Roadway design data (plan and profile) • Topographic data + Aerial photographs The site-specific data were used to create a digital model of the proposed project alternative in TNM@The TNM® runs used the same locations as those where measurements were conducted. Additionally, supplemental mode1locations were used in the TNM® model to more fully represent potential changes to the local noise environment. The model receiver locations are shown in Figure 1 and listed in Table 5. Year 2020 traffic volumes for the grade-separated alternative (13,000 ADT) were utilized for the noise modeling, as supplied by traffic and design information supplied by HNTB and Terra Mar, Inc. Modeled speed for the project was 40 miles per hour. Traffic mix (!be percentages of autos, light, medium and heavy trucks) was used as supplied by the traffic study. As shown in Table 5 (exterior noise impacts), the TNM® results were combined with the existing, ambient noise levels to obtain predicted future-with-project peak-noise-hour levels. The future-withproject noise levels were then compared with thc FHWNrxDOT NAC to identifY any representative ,' URS P:lArapahQ Road Bridge\Ooes\Noise & VlbratiOJ1\Oad't Noise Report\Oraft NOise rieport r1.docJ project No 51512003 5..1 Affected Environment noise-sensitive receivers that would have a noise impact from the proposed project. Interior noise levels were also predicted, using the results for the exterior noise modeling and then subtracting a 25 decibel exterior/interior noise reduction factor for shielding provided by the building structure. The 25 dB reduction factor is based upon guidance provided by TxDOT, as well as other agencies. This factor aSsumes a masoury structure of modern construction, with single glazing, with doors and windows closed. Most modern commercial structures would provide well over 25 dB of noise reduction with doors and windows closed; thus, the 25 dB assumption is conservative. The predicted interior noise levels were then compared to the FHW AlTxDOT NAC for noise-sensitive interior spaces, as shown in Table 6. URS P:lArapaho Road 8ridge\Oocs\Noise & Vibratlon\Oraft Noise Report\Oraft Noise Report r1.docf project No 51512003 5-2 I Table 5 -Predicted Exterior Noise Levels Receptor # Receptor Loeation Existing Ambient Level (based upon Noise Measurements) (dBA Lcq) Estimated' Futu re Noise Level (from Arapaho Bridge) (dBA Lcq) Combined Future Noise Level (Ambient plus Project) (dBA Leq) Estimated Increase Over Existing Noise Level (dBA Leq) Criterion Noise Levell (dBA Leq) Future Noise Level Exceeds Criterion Noise Level? Substantial Increase Criterion (Greater than 10 dBA) Exceeded? 1 WofCroueh Property -10' fin bridge 58 57 61 3 71 No No 2 W "fCrouch Property -35' fin bridge 58 58 61 3 71 No No 3 W of Crouch Property -60' fin bridge 58 57 61 3 71 No No 4 W of Crouch Property -85' fin bridge 58 56 60 2 71 No No 5 W of Crouch Property -110' fin bridge 58 54 59 I 71 No No 6 E "fCroueh Property -I0' fin bridge 58 55 60 2 71 No No 7 E of Crouch Property -35' fin bridge 58 56 60 2 71 No No g E of Crouch Property -60' fin bridge 58 56 60 2 71 No No 9 E of Crouch Property -85' fin bridge 58 56 60 2 71 No No 10 E of Crouch Properly -110' fin brid.. 58 55 60 2 71 No No II Outdoor Break Area 􀁾􀀠Furniture Stare 59 54 60 I 66 No No 12 Ice Rink in Parking Lot 66 56 66 0 71 No No 13 Adj to Motel 6 63 58 64 I 66 No No 14 Adi to Homewood Suite.q 59 57 61 2 66 No No 15 Mi to Comfort Suites 57 65 65 8 66 No No 16 Adj to E sideofFumiture Store 66 54 66 0 71 No No 17 Adj to Int.rvest 58 60 62 4 71 No No 18 Adi to Satorirrhc Harbor Group 58 62 63 5 11 No No 19 Adj. to Building near W sidcofProicct 58 62 63 5 71 No No Future noise level fu>m proposed project, derived from the FHWA's TNM® noise model. Activity Category B (which includes hotel/motell.nd uses). j Table 6 -Predicted Interior Noise Levels Rcceptor # Receptor Location Estimated Future Exterior Nobe Level (Ambient plus Project) (dBA L..) Estimated Future Interior Noise Levell (Ambient plus Projeet) (dBAL..) Criterion lntcriof Noise Level2 (dBA Loq) Future Noise Level Exceeds Criterion Noise Level? 1·10 Crouch Property 61 36 51 No 12 Icc Rink 66 41 51 No 13 Motel 6 64 39 51 NQ 14 Homewood Suites 61 36 51 No 15 Comfort Suites 65 40 51 No 16 Furniture Store 66 41 51 No 17 intervest 62 37 51 No 18 Satoriffho Harbor Group 63 38 51 No 19 􀂥􀀳􀀺􀁾􀁩􀁊􀀴􀁴􀁾􀁧􀁾􀁾􀁟􀁲 􀁗􀀠Side of Project 63 38 51 No I 􀁾􀀠Assuming a conservative interior/exterior noise reductlon factor of25 dBA, basoo upon TXDOT guidance, as well as eorroborating guidanee from other state and federal agencies. Assumes it masonry strueture with single-glazing, doors and windows closed, 2-Criterian noise levels based upon TxDOT I FHWA interior Noise Abatement Criteria for residences, motels, hotels, publie meeting rooms, sehools. churches. librarie.o;, hospitals and auditoriums. Affected Environment 5.2.2 Operational Noise Impacts As shown in Table 5, none of the 19 modeled representative receivers would have exterior noise impacts from the proposed project. Similarly, Table 6 shows that none of the modeled receivers would have interior noise impacts from the proposed project. 5.2.3 Construction Noise Impacts Construction phase noise would result from the use of motorized construction equipment. Other shortterm impacts from construction noise could result from construction traffic including materials delivery. Noise levels would vary depending on the type of equipment used, how it is operated, how well it is maintained, and its proximity to noise-sensitive uses. Standard excavation and installation equipment, such as graders, backhoes, loaders, tractors, drill rigs, welders, and heavy trucks would be used for construction of project facilities. Although construction would increase local noise levels, construction noise at anyone location would be of brief duration because of the linear nature of the project and because of the cyclical nature of construction activities. With implementation of recommended good practice measures (listed below), project construction noise would not result in significant noise effects. 5.2.4 Vibration Groundborne vibration from heavy equipment operations during project construction and from traffic using the proposed bridge was evaluated and compared with relevant vibration impact criteria. The Federal Transit Authority's (FTA's) Transit Noise and Vibration Impact Assessment Manual (1995) provides vibration impact criteria and recommended methodologies and guidance for assessment of vibration effects. Ground-borne vibration is a small, rapidly fluctuating motion transmitted through the ground. Groundborne vibration diminishes (or "attenuates") fairly rapidly over distance. Some soil types transmit vibration quite efficiently; other types (primarily "sandy" soils) do not. There are several basic measurement units commonly used to describe the intensity of ground vibration. The descriptor used by FT A is the velocity decibel, abbreviated V dB. The velocity parameter best correlates with human perception of vibration. Thus, the response of humans, buildings and sensitive equipment to vibration is described in this section in terms of the root-mean square (RMS) velocity level in V dB units. As a point of reference, the average person can just barely perceive vibration velocity levels below 70 VdB (typically in the vertical direction). For this project, FTA's more detailed, second-tier General Vibration Assessment was performed. In this analysis, adjustments to the impact criteria (level vs. distance) are used to account for vehicle speed, soil type, building/foundation type and roadway structural characteristics (i.e., roadway on bridge structure). For the General Vibration Assessment, the land-use-dependent criteria listed in Table 7 would apply. The most stringent vibration criteria is 65 VdB for land use Category I receptors. Project-specific variables included vehicle speed, soil type and building/foundation type. Vehicle speed used for the analysis was 40 miles per hour. The limestone sub-soil underlying the project site was accounted for by assuming URS P;\Arapaho Road Bridge\Docs\Noise & Vibration\Draft Noise Report\Oraft Noise Report r1.doc:l project No 51512003 5-5 Affected Environment highly efficient vibration propagation. The elevated roadway structure would act to diminish direct vehicle vibration. In contrast, potential amplification of vibration within the nearby buildings due to sympathetic resonance was assumed, as a conservative measure. Two cases were analyzed for this project: Case I was for the nearest building (The Crouch Property) which would be as near as 27 feet from the bridge piers following project construction; Case 2 was for the Motel 6 building which would be located approximately 100 feet from the roadway following project construction. For Case I, the predicted vibration level within the building would be approximately 59 VdB. For Case 2, the predicted vibration level would be approximately 55.5 VdB. Both vibration levels would be below the most stringent of the FTA vibration criteria for land uses in which low vibration levels are "essential". Both levels would also be below the human threshold ofperceptibility. Table 7-Criteria for Impact for for Human Annoyance and Interference to Use of Vibration-Sensitive Equipment' Ground-borne Vibration (VdB re 1 micro in/secl Events' Land Use Category Category Comment Frequent Infrequent 1 Low interior ambient is essential 65 65 2 Residential &sleep 72 80 3 Institutional &daytime 75 83 4 Concert hall, TV/Recording Studio H 65 65 5 Auditorium .. 72 80 6 Theatre H 72 80 • Frequent is defined as greater than or equal to 70 events per day 􀁾See section 12.2.2 of FTAManual re potential for structural damage to (rogUe structures if operational during transit events Source: FTA, 1995 Potential vibration effects from construction operations were also assessed using the FTA methodology contained in the Transit Noise and Vibration Innpact Assessment Manual. For Case I (the Crouch Property), in which project construction operations would take place within 25 feet of the building, drilling and other activities would be well below FTA criteria levels for potential damage to structures, even using the most stringent "extremely fragile historic buildings" category. The damage criterion for such structures is 0.12 inches per second, whereas the worst-case vibration level is predicted to be 0.09 inches per second. For Case 2 (the Motel 6 building), the construction vibration level would be substantially reduced by the additional distance between the project site and the building. The vibration level at the motel would be approximately 0.01 inches per second. Vibration from construction activities would be clearly perceptible at the Crouch Property when construction is underway near the building, but would not be damaging. Vibration from construction activities at the Motel 6 building is expected to be barely perceptible when construction is underway adjacent to the property. In summary, no significant impact would result from operational or construction activities associated with the proposed project. DRS p:\ArapahO Road Bridge\Oocs\Noise: &, Vibration\Draft Noise Report\Oraft Noise Report r1.doel project No 51512003 5-6 Affected Environment 5.2.5 Good Practices for Construction Noise Reduction Implementation of the following recommended practices prior to project construction would ensure that potential construction noise effects are less-than-significant: + The hours ofconstruction including noisy maintenance activities and all spoils and material transport shall be restricted to the periods and days peIIDitted by the local noise or other applicable ordinance. Noise-producing project activity shall comply with local noise control regulations affecting construction activity or obtain exemptions therefrom. + All noise-producing project equipment and vehicles using internal combustion engines shall be equipped with mufflers, and air-inlet silencers where appropriate, in good operating condition that meet or exceed original factory specification. Mobile or fixed "package" equipment (e.g., arcwelders, air compressors) shall be equipped with shrouds and noise control features that are readily available for that type of equipment. + All mobile or fixed noise-producing equipment used on the project, which is regulated for noise output by a local, state, or federal agency, shall comply with such regulation while conducting project-related activities. + Material stockpiles and mobile equipment staging, parking, and maintenance areas shall be located as far as practicable from noise-sensitive receptors. + The use ofnoise-producing signals, including horns, whistles, alaIIDs, and bells shall be for safety warning purposes only. + No project-related public address loudspeaker, two-way radio, or music system shall be audible at any adjacent noise-sensitive receptor. + The on-site construction supervisor shall have the responsibility and authority to receive and resolve noise complaints. A clear appeal process to the appropriate Town ofAddison staff shall be established prior to construction commencement that will allow for resolution of noise problems that cannot be immediately solved by the site supervisor. 5.2.6 Good Practices for Operational Noise and Vibration Reduction To assure that vibration and noise is not created by vehicles traversing gaps and/or unnecesary breaks in vertical or horizontal alignment, the bridge shall be designed and constructed with particular care to avoid any such unnecessary gaps or breaks, to the extent allowable under the current state of the practice. Expansion joints and changes in grade shall be designed to mlnjmize gaps or sudden vertical "steps" in the roadway surface. URS P;\Afapaho Road Bridge\OocS\Noise & Vibralion\Orafl Noise Report\Oraft Noise Report ,1.docJ project No 5/5/2003 5-7 Affected Environment 6.0 LIMITATIONS The opinions and recommendations presented herein are based in part upon field measurements and observations of what is believed to be typical and representative conditions of normal motor vehicle and community activity and URS's understanding of the project as presented in this report. The noise and vibration measurements and analyses were conducted using the professional standard of care as practiced in the industry and are representative of the activity being measured during the environmental conditions existing during the measurement periods. Because of the variability of factors not within the control of the investigators, no warranty can be made that the exact noise, vibration, traffic, or activity levels would be obtained by subsequent field measurements. However, for similar climatic and seasonal conditions, and intensity of community activity, the noise, vibration, and traffic levels measured would be similar to those reported herein. DRS P;\Arapaho Road Bridge\Oocs\Noise & Vibtation\Orafi Noise Repol1\Oraft Noise Report r1.docl project No 5/5/2003 6-1 Affected Environment 7.0 REFERENCES Barry, T.M. and Reagan, J.A, December, 1978, FHWA Highway Traffic Noise Prediction Model, Report number FHW A-RD-77 -108, by Federal Highway Administration. Washington, D.C. Beranek, Leo L., ed. 1971. Noise and Vibration Control. McGraw-Hill, Inc. New York, NY. Beranek, L.L. and I.L. Ver, cds. 1992. Noise and Vibration Control Engineering. John Wiley & Sons, Inc. New York, NY. Beranek. Leo, (Ed.), 1988, Noise and Vibration Control. Institute of Noise Control Engineering. New York. Bolt, Beranek, and Newman, Inc. 1973. Fundamentals and Abatement of Highway Traffic Noise. U.S. Department of Transportation Contract Number DOT -FH-Il-7976, Office of Environmental Policy, Federal Highway Administration. Diehl, George M. 1973. Machinery Acoustics. Jon Wiley & Sons, Inc. New York, NY. Harris, Cyril M., ed. 1979. Handbook ofNoise Control. Second Edition. McGraw-Hili, Inc., New York, NY. Harris, Cyril, M., ed. 1991. Handbook ofAcoustical Measurements and Noise Control. Third Edition. McGraw-Hili, Inc. New York, NY. Hassall, J.R. and K. Zaveri. 1988. Acoustic Noise Measurements. Fifth Edition. Briiel and Kjrer Instruments, Inc. Copenhagen, Denmark. Peterson, AP.G. and E. Gross, Jr. 1972. Handbook ofNoise Measurement. Seventh Edition. General Radio Company. Concord, MA Texas Department of Transportation, Environmental Affairs Division. 1996 (rev. 1997). Guidelines for Analysis and Abatement ofHighway Traffic Noise. Austin, TX. Town ofAddison. 2002. Code ofOrdinances (Noise, Dust and Debris), Section 70-140. Addison, Texas U.S. Department of Transportation, Federal Transit Administration, April, 1995. DOT-T-95-16. Transit Noise and Vibration Impact Assessment. (Prepared under contract by Harris, Miller, Miller and Hanson). Burlington, MA U.S. Department of Transportation, Federal Highway Administration, Office of Environmental Policy, Noise and Air Analysis Division, June, 1995. Highway Traffic Noise Guidance and Policies. Washington, D.C. U.S. Environmental Protection Agency, 1971. Noise from Construction Equipment and Operations, Building EqUipment and Home Appliances, Prepared under contract by Bolt, Beranek, and Newman, Inc., Boston,MA. tJRS F':'lAmpahO Road Bridge\Oocs\Noise & Vibration\Oraft NOise Report\Draft NOise Report r1.docJ project No 51512003 7-1 9T29911m T-762 P.002/00l F-779A.i-07-02 11:14am 􀁆􀁦􀁯􀁭􀀭􀁕􀁾􀁓􀀠Corpor,tion URS August 7, 2002 Mr. Steven Z. Chutchian, FE Assistant City Engineer J 680 1 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re; Arapaho Road Bridge at Midway Road Phase 11 -Design Development, Contract Documents, and Constructioll Administration Conceptual Construetion Cost EsIIlI1ate -"TxDOT" Bridge Dear Mr. Chutchian: Enclosed please find a COPy ofthe Conceptual Construction Cost Estimate [or a standard "TillOr" bridge for the referenced project for your review as you n:qucsted. This estimate in addition to a stand,rd bridge includes minimal urban design & landscaping. roadway deck and parking lot lighting, lighting along the traffic rails, a rail to separate.pedesTrians from the roadway and some soundwalls. The conceprual cost is -$4.1 million. We trust that this will help in moving the process forward so we may proceed with finalizing our scope and fee proposal. Sincerely, URS Corporation 􀁾􀀻􀀷􀀻􀀺􀀯􀁦􀀠Cliff R. Han, FE Project Managcr Enclosure URS Corporation Pr$$tonwDod 􀁔􀁯􀁷􀁾􀁲􀀠 51S1 BGl'Jtllne Roed, S1.O'It& 700 Oallas, TX 75Z54 Tel! 􀁾􀁩􀀲􀀮􀁧􀁂􀁏􀁟􀀴􀀹􀁓􀀱􀀠 Fa);: 972,991.7665 A'a-D1-02 11 :14am From-URI Corporation 1-162 P.003/003 F-119 Arapaho Road Bridge at Midway Road Phase 2 • Conceptual Estimate of Construction Costs Description Urban Design Elements Trees & shrubs @thrust blocks Trees & shrubs @retaining walls Railing around parking lot Civil Works (subtotal) Traffic Control & Temp works Bridge Structure Steel Arch SOLlndwalls PedestrianiTraffic Rail separation Lighting Bridge Stinger Lights Arch and Hanger Liaghls Marker light -Arch top Marker Light -Hanger side Bridge Railing Lights Approach Bridge Deck Lighting Under-Deck Lighting Electrical Services Subtotal Contigency Overhead Utility Reloeation Total E,.limaled Cost Range TxDOT Bridge Comments wI landscaping, & lighting $50,000 minimallstic $50,000 minimalistic $160,000 1600 ft@$100/lf $10,000 $3,100,000 abulment to abutment ($35181) $260,000 1400 ft cone. wall $80,000 1600 ft @$501lf $0 $0 $0 $0 $107,000400 fl of rail each side $170.000 45 light assemblies $65,000 77 light ftxtures $55,000 $4,127,000 "I?'? Arapaho Road Bridge at Midway Road Phase 2 -Conceptual Estimate of Construction Costs Oe9crlptlon Urban Design Elements Trees 8. shrubs@thrust blocks Trees 8. shrubs@retaining walls Railing around parking lot Civil Works (subtotal) TraffJC Control 8. Temp worts Bridge Structure Lighting aridge Stinger Lights Arch and Hanger UaghlS Marker LIght. Atch top Marker lI9ht • Hangor side Bridge Railing Ughts Appmach 6ridge Deck Lighting Under-Oeclt Lighting Eleclfical Services $ub1otal Contlgency Estimated Cost Range Low End $50,000 $50,000 $180,000 $50,000 steel A,ch ()lVe 51 pe 􀁾􀀬􀀬􀀱􀀠$3,980,000 So1,lndwalls --¢r􀁾􀁹(r-"'--$260.000 PedcstrianITraffic RaJl seperaHon 􀁴􀀮􀀮􀁥􀁴􀁖􀀴􀁙􀁾􀀠$80.000 $128,000 Overhead UtUlty Relocation !-I CiH7> Total I'" 124lL.l>o-f 􀀨􀀻􀀧􀀩􀁾􀁴􀀮􀀭􀁹􀀠4l4e ,.." ( P 4..-.A-! Comments minimallstrc minimalisttc 1600 􀁾􀁀$100111 abutment to abutment 1400 tt cone. wall 1600 ft@$5om $90,{)00 while light $18,000 $18,000 $107,000 400 ft of rail each side $170,000 45 light assemblies $85,000 85,000 77 light fixtures $80,000 $5,306,000 17? Estimated Cost Range Estlmatru1 Cost Rang' Estimated Cost Range No stlngors or landscaping & reduced !ightlng Comments No stingers or landscapIng & arch lights only Comments No stingers or landscapIng & road/park lights only Comments $0 $0 $0 $50,000 $3,800,000 abuUo abut. No stingers $280,000 1400 ft cOJ\C. 􀁗􀁡􀁾􀀧􀀠$80,000 1600 ft @$50m SA-<, 􀁾􀀠fls IS, 􀀶􀁔􀀱􀁾􀀠$0 $SO,OOO white light $IB,OOO $18,000 $107,000 400 It of rail each side $100,000 26 light assemblies $46,000 42 light fixtures $55,000 $4,824,000 F.f '""''''' L r IitiE'-I Iff qrHe ?17 11Ir'r13"I<5IT\( 10 4'eT rFlf'V( <-->'tCe"""" (t.. ':'''''''1I"..-A7701/$0 $0 SO $50,000 $3,800,000 abut,to abut. No stingel'$ $O? Af) ,!iQf/MJ 1#1Ii:-'f $0 '> dt<:' PI! f) '/. I'Vtt '-f""'''' $0 0"-' i""S, Pe: $90,000 white Ughl $IB,OOO $18,000 $0 $0 $0 $25,000 $4,001,000 LI/(tI''i5 "'" .A-/fCA 0"," y?71 ,/WT """. t24(CS OR .􀁴􀀢􀀧􀁾􀁋􀁉􀀧􀁖􀀢􀀬􀀠A/Z(/! tJ;f ALc,-..t; €'/.f' t.-:rl te.J) "e'oA,p "--At $0 $0 $0 $50,000 $3,800,000 abuUo abut. No stingers $0 $0 $0 $0 $0 $0 $0 $100.000 26 light assemblies $48,000 42 light fixtures $25,000 $4,021,000 M ,A;eC(-f 1-( 'fI1J 17.fW.( (.s FV"Cp.......k 17? £.( c􀁉􀀫􀁔􀁉􀀬􀀮􀀮􀀮􀀮􀀮􀁾􀀠o.<-&y _ ,At:. "''''" 4 '-e 􀁾􀀬􀀺􀀻􀀠m Pr 1i!J4?Flf FIRE HYORAIIT ..'ttN WATER vAlVE """ WATER Io£TER 0"" GAS Io£TER N ! FOR INTERIM REVIEW ONLY !Iv .ERR'\' (I, HQ.OER, "', .1'. E. • ann HNT8 CORPORATION ARAPAHO ROAD· PHASE IIIWITHIN }J>.IQ ADJACENT TO THE \TTEt-PT HAS BEEN MALlE TO LOCATE 􀁓􀁕􀁾􀁅􀁲􀁏􀁒􀀠8CXJl£VNl[) TO /ll)[}lSON ffl))I) IS• .ALL EXISTING UTILITIES MAY NOT BE EXISTING UTILITY PUW£ LOCATI()-( Cf' THE UTLITIES SHOWN 􀁾􀀠N ON THE PLANS. PF?lffi TO THE STA 50«! TO 6(H)()XCAVATION. THE CONTRACTOO SHAlL VEO AND MAKE ARRANGEMENTS U.. ITY ON THE GROONO. THE TOWN OF ADDISON. TEXAS THE UTILITY LOCATIOO t-tAAKII'iGS I([CESSARY. -----------------1iiJrJ1W􀁾􀀠􀁾􀀠􀁾􀀠I􀁾􀀠􀁭􀁾􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀁲􀁭􀁭􀀱􀁴􀀱􀁉􀀱􀁬􀀱􀁴􀁭􀀱􀁴􀀱􀀱􀁾􀁭􀁭􀁵􀁾􀁵􀁾II 􀁾􀀠111111111111111I 1111 II i􀁉􀁬􀁬􀁭􀀱􀁉􀀱􀁴􀁬􀁨􀁾􀁬􀁭􀁭􀁬􀁴􀁊􀁪􀁩􀁊􀁾􀁭 􀁬􀁪􀁭􀁬􀁬􀁬􀀱􀁬􀀱􀁬􀁬􀀱􀁬􀁲􀁵􀁴􀀱􀁭-----_.. ........... . ..........-... ..----'K\ J l-Oeo.􀁾􀀠 􀁏􀁦􀁁􀁾􀀠 􀁾.. -7 ......... .. CIS-OO..􀀭􀀮􀁾/-;7 􀀶􀀰􀀢􀀬􀀢􀀬􀁁􀁔􀁅􀁾􀀠SO"WATE:R SQVAT(RISII-W'-' R &0""''' 1'101 􀁾IL. 􀀭􀁆􀁾􀁾􀀽􀀭􀀷􀀠j If-;' ·/·';'1 I /I . f 􀁾􀁴􀀺􀀺􀁦􀀠IF/II􀀭􀁾􀀠􀀻􀀭􀁾..':-:: , , , /. . -/-1 􀁾􀁦􀀮􀀮􀀻􀀠,. /...c.c.-...{.:::s, r=} ;,j."o::ss '/if "'''', I I J '" S , . I􀁾􀀠. .. .. . .. . .. -. . -. . ... . 􀁾... -I I -7)l't • .. . 􀁾􀀭􀀱􀀧􀀠:-yd 􀀭􀁊􀁪􀁾􀁴􀀧􀁬􀁹􀀭􀀭􀀧􀀠ij[; SAHITMY HNfoK1.£' . . _. . '--I _. Fl 4'; S .. 60<1.58.i fl 6" W .. 50t..ge .. -... .... -. -. --. j -: -=.,...OsNi-Hi' .•H j. r􀁾􀁛􀁉􀁃􀁬􀀠. L;; .. ....... _... L :J 􀀭􀁾􀀬􀀠.-. =. -_ .... ..-􀁾􀀬􀀬􀀭􀀭􀀭..1'-· v ----\;u Z STOOr BRICK 1-1_ , • ..􀀬􀀬􀁾􀀠..... 􀁾􀀠I \\ ,,-------------Re. 􀀡􀁯􀁾􀁂􀀠-._. /" ------....--;-.-_._-.. /--........_---_.. ----_.._..-._-.7",. I -:7 tiO"1tlATER 􀀶􀁏􀁾􀁗􀁁􀁔􀂣􀁒􀀠􀁥􀁏􀀢􀁗􀁁􀁾􀀠60......"T£R 􀁾􀀠_..􀀭􀀮􀁾.. -I-------i1-CoG rl if-,-1"-:-􀁾􀀮􀀠.. . ... . -. ... .... . .... ... . -. -.. .. _. ..--l..:' 􀁩􀀧􀁾􀁏􀁃􀀠oStOO􀀵􀀶􀁾􀁃􀀡􀁊􀀠􀀮􀁾􀀠.-.. .. ---.-􀁔􀁾􀁁􀁕􀁌􀀠t c 􀁔􀁴􀁾􀀠TOI'«'.lCf:" ENTRY STf.:PSn c,.CO ENTRY ST£PSI c;[ NOm Ji"" IL 3􀀱􀁒􀁁􀁴􀀮􀁪􀁾􀀠UNOERGROO UT1UTfES IS;WiTHIN Nt) ftC'''' . l: STORY CONCRETE liMns cj:' C11=.􀁾􀀧􀀧􀀧􀀧􀀧􀀽􀀭􀀭􀀭􀀭􀀭.;;",;--= ---".... ---._0'. -... ----􀀮􀀭􀁾􀀮􀀭-.---.. -... 􀀭􀀮􀀭􀀭􀀭􀀭􀁉􀀭􀀫􀀭􀀭􀀭􀂷􀀭􀂷􀀭􀂷􀂷􀂷􀀭􀂷􀀭􀁪􀁦􀀮􀀮􀀮􀀬􀀬􀁾􀀱. ==== ...... --==-􀀮􀀺􀀭􀀽􀀭􀀭􀀭􀁾􀀭􀀺􀀭􀀭􀀭􀀽􀀢􀀧􀁾􀀽...-_w--__. tI . NOm t)1t1Gt tJtJ· I UNDERGROUND UTILITIES EXIST WITHIN AND ADJACENT TO THE j LIMiTS d:' C(NSTRUCTICN, AN ATTEI'-PT HAS BEEN f.W)E TO LOCATE I lHESE UTILITIES ON THE PLHlS. N.l EXISTING UTILITIES MAY NOT BE SHOWN ON THe: PlANS, AND THE LOCATION OF THE UTlITIES SHOWN􀁾􀀭􀀭􀀭􀀭􀀮􀁾􀁾􀀮􀁾􀁾􀀭..-.---..MAY VAAY FROM THE LOCATION 00 THe: PLANS. PRIOO TO THE BEGINNING 􀁾􀀠ANY TYPE OF EXCAVATION. THE CCNTRACTOO SHM..L CONTACT THE UTILITIES lNvctVEO AND MftKE PRRANGE}£NTS feR THE LOCATIOO OF THE UTILITY 00 THE GROOM). THE: ca-lTRACTOR SH/lLl MAINTAIN THE UTILITY LOCATlC« WRKINGSIrlTlllTrrr 􀁉􀁾􀀠umlL THEY PRE NO LONGER NECESSARY. o 20 40 60 80 i : I ' ! : .' I I i I I, : ., ., '" ,. , DRAINAGE AWAY FROM EXISTING BUILDING LEGEND --·61 ,'--EXISTING COOTOUR 􀁾PROPOS£D COOTOUR )(612.42 PRCPOSED SPOT GRADE NOTE: GR.ADING ooT51o£ PARKING LAYOOT ON THESE PlI«S IS FOR RruGH GR.ADING. Ct»iTRACTCR TO REFERENCE LAlIDSC.... E PLPJO£HT IHFOIW.'IllOH. 3J 􀁁􀁕􀀮􀁾􀁾􀁡􀁥􀁓􀁔􀁎􀁃􀁅􀁄􀁉􀁎􀁔􀁬􀁴􀁥􀁆􀁬􀁅􀁬􀁏􀀠ff(1"H! CON'l'RAClOR AHO Al"PRO'.IED ff(1'HE tANOSCAPE ARCHfl'ECT AND ONNER'S RS>.I"RIORTO COHSl'RUC'I'lON OR IHSTAU.ATIOtt ••1 TH£ cotnRACTORSHIU.VERlF'I' AU EASEM£HT UNeS IN THE Fl£U) pRJOA TO I'IEGlNNIHG WORK. $J 􀁾l.IWJ.L VERIfY Al..J. tmurn;;s SHCl'MoI ON TH£Se I'lAHs AS WEU. AS ANY OTHERS IN FIELO PRIOR 10STAAT QF C<>NSTRU"""" ALl C¢NS1RI..ICTlON WIll COHFOfW TO 11£1'(MIN OfAOOISOH STAHtWWS IWD SPEClF!CA.11ONS, AS WEl.l. M. /W'( GOVERNING 1XDOT OR R.A.Il.RCW> STAAOAADS N4D Sf>ECiflCA.TlONS RELATED TO THIS I'ROJECT. 9,) THE CON'T'RACTORWIlLCOORDIHATE InsTAllATION OF AU. SIGNS, PAV'EMEHT IoWOONGS AND OllifR TAAFl'lC COHl'ROl 0E\IlCES ByTtE CfTY O\IAJNG CONSTRUCTlOH LEGEND: ---(il'XI--ElOST1HO co,,,,•••• --tlOO--,. ;5'''' I lATA ING ::i1" W _--'_::::::"'-_ ARAPAHO ROAD EXTENSION SURVEYOR BOULEVARD TO ADDISON ROAD STA 55+00 TO 60+00 LAYOUT & DIMENSIONING PLAN TOWN OF ADDISON , TEXAS __ I 'f T i i ,'1-1-1 􀁊􀁾􀀪􀀽􀀺􀀭􀁾􀁾􀁾􀁾􀁾􀀻􀀻􀁅􀁾􀁈􀀽􀀪􀀭􀀴􀁾􀁩􀀺􀀻􀁙􀀻􀀺􀀮􀁔􀂷􀀠-;-r; _n.. . 􀁾􀀭􀀽........11ct-c. t-_. i i I I 1 LAYOUT COORDINATE TABLE (@H 10063.G4 E 921S,94 􀁬􀀡􀀡􀁊􀀺􀁾􀀠[@􀁾 􀁾􀁵􀀺􀀠􀁬􀁲􀁵􀁾􀁾􀀠[i] N 1008J,04 􀁾N 10112.0& 􀁾H 1Q13M'lI.D E 9309.54 E 9328.52 􀁾􀀠􀀺􀀺􀀬􀁾􀀠1 • """"" [EJ 􀁾􀁾􀀱􀁕􀁾􀀠 (!!] : 􀁾􀀺􀁲􀁮􀀵􀀹􀀠(!!J : 􀀺􀁾􀁾􀀺􀀱􀀠􀁾N 10137.1(1 !!!) N 10150.01 '.􀁾􀀺􀀽􀁾􀀠..,.,... E 93$)4.69 􀁾􀀺􀁾􀀠 (E] 􀁾􀁾􀁾􀀠􀁾􀁾􀀺􀁾􀁦􀀠􀀮􀀭􀁟􀁾􀁟􀁃􀁟􀁏􀁟􀁎􀁔AlNERI MOW CURB CENTERLINE CURVE DATA:....,.-:-::=:-. BEARING CHORD 􀀭􀀭􀀭􀀭􀀭􀀭􀁾..􀁾􀀮􀁾􀀮􀀠ARAPAHO ROAD ---'. !$§IN eRICK PAVERS PAVING ST1\. 1tMG 􀁾􀁐􀁁􀁖􀁉􀁎􀁇􀀠WI1l1 MEQlUM BROOM FlNISH{lYP,j ,/􀁒􀁁􀁍􀁾􀀠'" EXPANSION(TYP,)@JOINTS l,w.t!tWlE TO LOC,TE i . ..ol..1.. EXiSTING UTILITIES MA'f NOT ee: 􀁾􀀠Ltx;;A110l'{ CF THE UTLITIU 5110."".. i ON THE' PLANS. PRIOR 10 THE f>T IllS • THeSE UTJLITIES Ok( THE PI.ANS. ALL ExIST INC SHOWN ON' TI-lE PL.ANS:. AN!) THE: lOCATla'i <:f" .....Y VARY FROM THE LOCATlCfl (JII THE PlJ'I" BEGiNNING OF "NPE OF fV(CAYATION. 1l1E CONT,ICT TliE VT!L1l'IES IriVCt.VED NG IS fCR RruCH GRAI)!NO_ 􀁃􀁏􀁦􀁭􀁴􀁁􀁃􀁔􀁾􀀠TO REFERENCE 􀁴􀀮􀀱􀁊􀁉􀀩􀁾􀀠PLANS FOR FiNPl. !lRiD£S NID ELEVATIONS ftR TRAIL !..AYaJT AND 􀁬􀁁􀁎􀁏􀁓􀁃􀁁􀁐􀁉􀁎􀁾􀀠SCHEt-E. CHARrER FURNIrURE. = GR,6()ING PLAN ---_.-..._--------,---- Apr-2e-D4 03:1 gpm From-URS Corpor.lion 9728982042 H,I P.D07/001 F-DZ3 N • A' ..'" GO I 􀂷􀁾􀀧􀁾􀀱􀂷􀁾􀀬􀀮􀀭􀀭􀀧􀁾􀀺􀀠.;., I H I GENERAL NOTES: I t.} II'YRIf'TtiolOIIolGNt::>JQH$.NJ/;JC(')()ROIN.4llM r.-..SHAlLOOVERN 􀁃􀁙􀁅􀁒􀁉􀁃􀁯􀁜􀁉􀀮􀀮􀂣􀁄􀁉􀁘􀁍􀁾􀀠2.1 􀀸􀁅􀀱􀁩􀁔􀁴􀀴􀁅􀀤􀁾􀁥􀁴􀀺􀁬􀁗􀀢􀁬􀀧􀁊􀁴􀁏􀁬􀁒􀀮􀁁􀁗􀁾􀁉􀁎􀁦􀁦􀁩􀁦􀁉􀁎􀀠nNi &E'T FOR OXIRDlMn: CONm.o. POINT 􀁗􀁾􀁮􀁏􀁎􀀮􀀠l.j A.U..IUPAOII'ehlEHB&1W.t ilESTNIfD!lillE FIEI.O 􀀸􀁙􀀱􀀩􀁦􀁅􀁾􀁁􀁈􀁄􀁎􀀧􀁐􀁒􀁏􀁙􀁴􀀡􀀩􀁴􀁦􀀨􀁗􀁕􀁯􀁎􀁴􀁊􀁂􀁏􀁖􀀢􀁅􀀠􀁾􀁎􀁉􀁬􀀩􀁏􀁗􀁎􀀺􀁅􀁒􀀢􀀺􀁩􀁒􀁡􀀾􀀮􀁐􀁒􀁬􀁾􀁔􀁏􀁾􀁏􀁈􀀠OR1N$TlII...LAtlOH. •.} 􀁮􀁴􀂣􀁾􀀮􀀸􀁋􀀶􀁕􀀮􀀧􀁖􀁓􀁜􀁉􀁎􀀮􀀮􀁵􀁾􀁵􀁊􀁬􀂣􀁓􀁉􀀢􀀧􀁩􀀧􀁈􀂣􀀠'FIEI..O 􀁾􀁁􀁁􀀺􀁁10 BeDIHN!J«l wot\ll B., eOlfffIUCTOR 􀁾VERlI'YJroU. U'fIU'TlEsSl:fO'l'Wf¢ti JHESS f'V.H,$AS: WEl.1.AS AAY 􀁾􀀮􀀮􀀬F1aO PRIOR 10tlfAAT OF t:ON$.1la\l¢TiOW. w,; Al.L 􀁾􀁏􀁾WlU.COHf'IORIITOntllC/'J'MOf'AOOISOH 􀀤􀁔􀁾􀁎􀁃􀁴􀁳􀁐􀂫􀁉􀁦􀀱􀁃􀁊􀁜􀁮􀁏􀁈􀁬􀁬􀀮􀁁􀀮􀀸􀁗􀁅􀁬􀁊􀀮􀀮􀁍􀀮􀁦􀁊􀁬􀀧􀁦􀁾􀁎􀁇􀀠T)l :IOTOR 􀁾􀁳􀁴􀁎􀁬􀁾􀁓NOIPEiCIFlCAfiON1-RE1.AlEiD TO l'fiL9. PFtOJECT. 7.) AU DlIWiI5I1':'lN::> Ml! TO 􀁾OF ct.RII 0" 􀁬􀀼􀁾OF PJI.'tI'EMENT 􀁕􀁎􀁕􀁩􀀺􀁡􀀮􀁕􀁾􀁴􀀮􀀱􀀰􀀱􀀢􀁦􀀳􀁩􀀮􀀠I.) PUiilNFDI'lC:E.MEI'Ir 'HOUID'BE t:CImftUOU$ THA.OOOtI 􀀨􀀻􀁴􀀮􀀱􀁉􀀧􀁦􀀱􀀧􀁬􀁬􀁾􀀠,.."... LEGEND: .. ___ IiilO __ _ ..,.'.,,,.,,""""""" "....,'10.-0 t1)7JO110.17 ,,,""'".. lATA INa CHORD ..... ARAPAHO ROAD EXTENSION SVJM:YlJR BOlJL!YAJiO ro ADf>iSON /ICW) STA 55+00 TO 60+00 LAYOUT &: DIMENSIONING PLAN TOWN OF ADDISON , TEXAS -----------------------------------0) :l9pm Fro.-URS Corpor.tion T-SS! P 009/009 I,:; T 􀁾􀀭􀀮􀁾􀀭􀀭􀁾􀁾􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀮􀀭􀀭..􀀭􀀭􀁾􀀭􀁾􀀮􀀭􀁾􀀮􀁾􀀢..---. , 􀀮􀁾􀀮􀀨􀀧􀀭... ,.. . .,' 􀁾􀀮􀀠' . .----.--..􀁾.., 􀁦􀂷􀀭􀀭􀁾􀀢􀀢􀀧􀀭􀀧􀂷􀀠LAYOVT COORDINATE TAfiLE @J W 1da.5ll(i]:=: 􀀱􀁬􀁦􀁊􀀺􀁾􀀠I!.Y 􀁾􀀺􀀺􀀮􀀬􀁾􀀠E !!SM.':I::I D4 Ii[J 􀁾=r.4􀁾􀀺􀀽􀀻􀀺􀀠[§] : 􀀺􀁾􀁾􀁦􀀠􀀸􀀺􀁾􀁾􀀠[!!) 􀁾􀀺􀀬􀁾􀀠􀁾:=r.J' iii lot 'IDistAl E !)111M Ii) H 􀁾􀀱􀁩􀁉􀁇􀀱􀀱􀁃􀁬􀁑􀀠[!1 H 101:"'.11) 􀁾􀁎􀀱􀁑􀀧􀁉􀁭􀁾􀀱􀀠£" It.Pt.''. eml,W £ &aN.1i1 􀁉􀁩􀁬􀀺􀀽􀁾􀀠ffiJ =􀀺􀁫􀁇􀁩􀁴􀁾􀀠􀁾􀁾􀁾􀁭􀀭􀁲􀀠CONTAINER /MOW CURl! 􀁃􀁅􀁎􀁾􀁌􀁉􀁎􀁅CURVE DATA OEtTA RADIUS TANCIENT ' 97ZBB8Z04Z From-URS Co,por.tion03:19pm ' ...-. ,'" 􀂷􀁾􀂷􀁬􀁾􀂷􀀭􀁾􀁾􀂷􀀠' ... 􀁾􀀮􀀠􀀬􀁾􀀭􀀭",r􀀢􀀧􀁾􀀧􀂭􀀢􀀢􀁾􀀠. -""-, --"-,-􀀮􀁾􀀠-... ) -._---'-􀀮􀀭􀁾􀀭􀁾􀀭􀀭􀁾􀂭,-' -,:",,-,--􀀺􀀣􀁩􀂷􀁾􀁾􀀮􀀠f4 SW>Nir:1RONJ 􀁾H fOzoo.77 􀁅􀀱􀁾􀀡􀁩􀀤􀀠fiiJ 􀁾􀀠;gr,:,: ffi'iJ::: I!!J 􀁾􀁩􀀽􀀠fi!l] 􀁾􀀠::: mt::=: 1m) 􀁾􀀺􀀽􀀠􀁾􀁾􀀺􀀽􀀽􀀠Iffi) ,. 􀀧􀁡􀁬􀀧􀁉􀀧􀁾􀀱􀀧􀀠li2J N tOtClM􀁾􀁾􀀺􀀽􀀺􀀠I f HUIO.n ffiIl =j=: IEi1 􀀺􀁾􀀺􀀮􀀮􀁾􀀠t§J 􀁾􀀺􀀺􀀺􀀠􀁉􀁀􀀽􀁩􀀺􀁾􀀠1:10..1.111 􀁾􀀺􀁾􀀽􀀺􀀠lim 􀁾􀀠􀁾􀀽􀀺􀀮􀀺􀀺􀀠􀁾􀁾􀁾􀀽􀀺􀀠􀁾􀁾􀀺􀀺􀀺􀀮􀀮􀁾􀀠􀁾􀀽􀁾􀀺􀁫􀁾􀀠I§l 􀀺􀀺􀁲􀁾􀀠IiiJ ::=: 􀁕􀁓􀁬􀁾􀀡􀀽􀀠􀁾􀀺􀀺 􀀺􀁩􀀮􀀢􀁾􀀠􀁾􀀺􀀺􀀽􀀮􀀺􀀠f2!J 􀁾􀀽􀀺􀀺􀀠fi3 􀀨􀀺􀀽􀁾􀀠lliJ 􀁾􀀺􀀺􀀡􀀡􀀠􀁾􀀺􀀽􀀡􀁾􀀠BID 􀁾􀀠:::: ff!!) : 􀁾􀀺􀀺􀀮􀀺􀀻􀁾􀁾􀁾􀀽􀀠t'!!il H 􀀱􀁴􀂻􀀱􀀨􀁩􀀮􀁾fiE 􀀺􀁾􀀽􀀺􀀺􀀠1m) 􀁾􀁾􀀺􀀽􀀠(ffil : 􀁾􀀽􀀺􀀺􀀠􀁾:i::.: e 10t.U",1I Iiil 􀁾􀀺􀀽􀀠􀁦􀁩􀁗􀁾􀁾􀀽fi!l 􀁾􀁾􀀽􀀠 m1l 􀀺􀁾􀀽􀁾􀀠 CONTAINER I MOW C\lR!! CENTERLINE CURVE DATA , CURvJ;: CElT A RADIUS 1 ARC TANGENT l:5f.AAING ei. 14·5.2'&0" 150,00' , ,...,' 10$> SQ"OS13"'W <>11 :we U":l4" 1$0,00' 53M ",as s. GQ',2&"38" w en "I0"5S'07" ,_"", 1$9,86' 95,7% NtW31'5re C!3 2nS'2:>' iSO.CO' .,." 3$..,. 􀁎􀀷􀀷􀀧􀁾􀁥􀀻􀀠c1< ""''23'' 1$0.04' 53.£1' Z1.11' N7Sl 2),1.' N7,,'OV411'E' 016 ""I1m' ,....., ....... 11,11" N7'2""1'1" E Cit ,ra:m,.... 4S.!il2' zt14' /II 􀁔􀀱􀁾􀀧􀁴􀀢􀀴􀀡􀀢􀀧􀁅􀀠"" "'."..... '200.00' 71.&6' 35,,,' H71"3S'1S"E. =1 ""50"" 1S,TJlfl' "'.... .U."9' N8r,,'W"E; "'" I tn",i ...... «---"" CHORD ...... 􀁾􀀬􀁥􀁬􀁲􀀠""ST....,. .,... 4$."".",w4.5.14" 􀁾􀁾"',.. 􀁁􀁰􀁲􀀭􀁚􀀷􀁾􀀰􀀴􀀠03:39pm From-URS Corporation 9729992042 T-858 P,OOZ/OOZ F-020 URS LETTER OF TRANSMITTAL Date: 4/23104 TO; HNT6 Corp FROM: Cliff R. Hall 5910 W. Plano Parkway URSCorp Plano, TX 75093 3010 L6J Freeway Attention: Jenny Nicewander Suite 1300 Dallas, TX 75234 JOB No.: 25334401 RE: ARAPAHO ROAD BRIDGE The following items are being sent [gJAttached o Underseparate cover byo Shop Drawings 0 Prints [gJ Plans osamples !8J Specifications oCopy of leiter [gJ Other Item Copies Date Description 1 2 3 4 5 1 1 4123f04 4123/04 100% Bridge Plans Technical Specifications Sections: Be, SSH, IB, BELF Transmittals for reasons checked: o For Your Approval oNo Exceptioll$ Taken o Resubmil copies for approval [gJFor Your Use oMake Corrections Noted o Submit copies for distribution o As Requested DAmend and Resubmit o Retum corrected prints o For ReView and Comment o Remarks: Bid Tab Items and sheet list were sent via electronic mail Copies: Steve Chutchian • Town of Addison (""("'..., ....... ' il,., tJ.4-.. d" ''J ) Ifenclosures are not as noted, kindly notlly us at once. URS Corporation lClla-IIfTI'MJmilUl 􀁾􀀬􀂫􀁉􀀬􀀠6fJ)1\l2 􀁭􀁳􀁭􀁄􀁾􀁚􀀠T-.58 POOI/CCZ F-OIO03:38pm From-URS Corporation URS Facsimile To: Firm: Facsimile: From: Date: Page 10f: Subject: Message: ce: URS Corporation 3010 LBJ Freeway. Su!IC 1300 􀁏􀁡􀀢􀁾􀁳􀀮􀀠TX 75234 Tel: 972A06.G!l$O Fax; 972.406.6951 \4NNI_urscorp,cotn CONFtIlENTIALITY NOnc£ The in(Oml;lIior) in thi' 􀁾􀁩􀁭􀁩􀁬􀁾transmission is intmdtd sotdy fill Ihe 􀁾􀀨􀀶􀁴􀁾􀀠tc;:fph::nt orlhi$ tmUrnluion.. If you 1u1le ft:ctlved 􀁾􀁨􀁪􀁳􀀠Cu in elTOr. pk:a$4 nOtilY Ihe sender 􀁊􀁦􀁴􀁉􀁾􀁩􀀴􀁬􀁣􀁬􀁹by tclephCIilc. tr)")u are flQl tht: 􀁩􀁁􀀡􀁾􀁤􀁦􀁬􀁦􀀬􀁬􀀠􀁾� �􀁰􀁩􀁣􀁮􀁴􀀮􀀠􀁰􀁬􀁥􀁵􀁾􀀠be ;JIjviS¢d fhat dibemil'1ii11Cion. disnibulicn. Of 􀁾􀁮􀁧of,he informalion tonlained in Ibb. 􀁾􀁬􀁉􀀠is 􀁾􀁴􀁔􀁩􀁣􀁤􀁹􀁰􀁲􀁣􀁨􀁩􀁢􀁪􀀡􀁥􀁤􀀮􀀠 DRS April 21, 2004 Mr. Steven Z, Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re: Arapaho Road Bridge at Midway Road Phase II -Design Development & Contract Documents Invoice for Professional Services Dear Mr. Chutchian: Enclosed please find our invoice for Professional Services for the Arapaho Road Bridge at Midway Road for the period between February 28, 2004 and March 26, 2004. Also included is our Progress Report for this period outlining the services provided. Sincerely, DRS Corporation CliffR. Han, PE Project Manager Enclosure URS Corporation Graystone Center 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Tel: 972,406,6950 Fax: 972,406,6951 L Monthly Progress Report Design of the Arapaho Road Bridge Over Midway Road URS Project No. 25334400 Period: February 27,2004 to March 26, 2004 General Accomplishments 1.1 Continued final design and plan preparation 2. Progress This Period 2.1 Continued final design and drawing production 2.2 Met with the Town to discuss progress. 2.3 Meet with Town's consultant to coordinate drainage, parking and other issues. 2.4 Continued finalizing lighting, including incorporating new street lighting standards. 3. Anticipated Next Period 3.1 Submit 95% review plans. 3.2 Incorporate or resolve Town's comments on 95% plans. 3.3 Finish final design and drawing production. 3.4 Perform quality control checks. 4. Schedule Status 4.1 95% submittal will be made on April 2, 2004. 4.2 100% review plans are expected to be submitted April 23, 2004. 5. Issues I Impacts 5.1 The final grading plan was received to fmalize the elevations ofthe drilled shafts for the bridge bents. The elevations ofthe shafts for the thrust blocks are set. Ground elevations at the thrust blocks need to be revised to provided adequate cover on the shafts. 5.2 The Town's roadway consultant has not provided any bridge drainage inlets. The Town was to decide if bridge drainage inlets were needed. If bridge drains are needed, receipt ofthis information will delay the completion of the bridge plans. Arapaho Road Bridge Town ofAddison MEETING NOTES Addison Service Center April 22, 2004 ATTENDEES: Town ofAddison URS Mike Murphy Cliff Hall Jim Pierce Steve Chutchian Luke Jalbert The meeting was held to resolve four issues outlined in an e-mail by URS to the Town of Addison (attached) and the conflicting responses received from Mike Murphy and Steve Chutchian (attached). Issue 1: Should a physical barrier be added to the bridge deck around the stingers to meet ADA requirements as interpreted by URS. The Town ofAddison (Addison) requested URS to detail a warning strip in the deck pavement in lieu ofa physical barrier. Issue 2: Should a retaining wall be added near the thrust blocks to raise the finished grade to cover the top ofdrilled shafts. Addison advised that a two to three foot high retaining wall should be used to raise the grade. URS was asked to advise Addison's landscape consuhant to include the wall in their plans and the elevation offinished grade required. Issue 3: Should the bent and retaining retaining wall plans detail the "Addison" logo or the"A" as a relief pattern in the concrete. Addison requested that URS show the logo on the bents and retaining walls with a note on the plans for the Contractor to coordinate with the Town. URS was also asked to provide a separate bid item for the form liner fur the logo. Issue 4: How should the monument plaque be detailed and where should it be located. Addison requested that URS provide notes and a bid item requiring two 24"x24" brass monument plaques in the plan set. The Contractor will need to coordinate with the Town on wording, location and mounting requirements. TOWN OF ADDISON PUBLIC WORKS To:_---'C::..:L.=-..:....!.,F.-!F_--L!tf.£.ALL=__ Company:,_--..::./'/-.:.::12'-'5::::-.____ FAX#: '!72 -ftJG -6'1Sf No. of pages (including cover): 2TffBE /tEe-/I1(KE fo1 vR-fl-lr'-> W"'1 "'t e'"'V7S . Phone: 972/450-28' f'i'1.-openR-3924 Bridge Drain Frame and Bolted Grate 􀂧􀀮􀀴􀁾􀀮􀀠VJ?}\A'iVV\/iiDA, Heavy Duly , fl ..A • 􀁾􀁾􀀠􀁾􀁾􀀻􀀻􀀻􀀻􀀺􀁾􀀠Considered bicycle safe only when installed with slots perpendicular to the curb (JG..l.¥ \...UAJI V .. A 􀁾􀀠􀀳􀀷􀀠516' rrr=17 1/2" 35 114" 􀀭􀀭􀀭􀀭􀁾􀀬I ,.' --+-j r-2' r-516' t-!:-r12716'! 12' 241 NOTE: When specifying/ordering grates, refer to "CHOOSING THE PROPER INLET GRATE" on pages 108-109. For FREE OPEN AREAS of Neenah Grates, rafer to pages 326-330. R-3948-V Bridge Scupper with 5 1/2" Outlet, Bolted Grate Heavy Duty 􀁾􀀧􀀬􀁒􀀭􀀳􀀹􀀵􀀱􀀠􀂥􀁾􀀠!3ridge Scupper with 8" Outlet, Bolted Grates -> Heavy Duty Sv Sr ?//o, r(" 7· 7.'1. ? ·f" k. =-t6 ==--;-;-;;----::-:-...-....􀀻􀀭􀀭􀀭􀁣􀀻􀀭􀀭􀀭􀀭􀀺􀀺􀀭􀀭􀀭􀀻􀀭􀀭􀀭􀀺􀁣􀀽􀀽􀀽􀁾􀀠􀁾􀀽􀀽􀀽􀀮􀁾􀀺􀀽􀀭􀀻􀀺􀀽􀀽􀀭􀀭􀀭􀀭􀀬NOTE: When specifying/ordering grates, refer to "CHOOSING THE PROPER INLET GRATE" on pages 108-109. For FREE OPEN AREAS of Neenah Grates, referto pages 326-330. R-3922-A Heavy DUly Same as R-3922 except with bolting flaIlge. Downspout fumished by others. Type "V"' ductile iron grate (shown) is considered bicycle safe only when Installed with vanes perpendicular to the curb. 2.3 ff-z.. openR-3924 Bridge Drain Frame and Bolted Grate 􀁾􀀮􀀴􀀠􀁾􀀢􀀠flIJl A"JVY\t\r,; A, Heavy Duty r-􀀭􀁾􀁾􀀻􀀻􀀻􀀻􀀺􀁾􀀠Considered bicycle safe only when installed with slots perpendicular to the curb 􀁾U -12' DRS March 12,2004 Mr. Steven Z. Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re: Arapaho Road Bridge at Midway Road Phase n -Design Development & Contract Documents Invoice for Professional Services Dear Mr. Chutchian: Enclosed please fmd our invoice for Professional Services for the Arapaho Road Bridge at Midway Road for the period between January 30,2004 and February 27, 2004. Also included is our Progress Report for this period outlining the services provided. Pleasebe advised that timely completion ofthe project is dependant on immediate receipt ofinformation relative to the final grading under the bridge and the drainage inlets on the bridge. Your roadway consultant should provide this information. Sincerely, DRS Corporation CliffR. Hall, PE Project Manager Enclosure " I" URS Corporation Graystone Center 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Tel: 972.406,6950 Fax: 972,406,6951 Monthly Progress Report Design of the Arapaho Road Bridge Over Midway Road URS Project No. 25334400 Period: January 30,2004 to February 27,2004 I. General Accomplishments 1.1 Continued final design and plan preparation 1.2 Received Town Council Decision on lighting and arch color. 2. Progress This Period 2.1 Performed lighting mock-up on Addison Circle sculpture. 2.2 Made presentation to Town Council relative to lighting and received a decision to use the blue paint on the arch and white lights. 2.3 Continued fmal design and drawing production 2.4 Met with the Town to discuss progress. 2.5 Began finalizing lighting, including incorporating new street lighting standards. 3. Anticipated Next Period 3.1 Continue final design and drawing production. 3.2 Meet with Town to discuss progress. 3.3 Meet with Town's consultant to coordinate drainage, parking and other issues. 3.4 Review DWU comments on 60% plans and meet with Town to discuss. 3.5 Perform quality control checks. 4. -Schedule Status 4.1 60% submittal was made on schedule. 4.2 100% review plans are expected to be submitted April 2, 2004. 4.3 Delay to the schedule could occur if information from Town's roadway consultant is not received by March 12,2004. 5. Issues /Impacts 5.1 Decision by Town Council made February 24,2004 on lighting could delay project completion. 5.2 URS was provided a new lighting fixture for use on the bridge. This fixture is being evaluated-to see how it can be incorporated. This fixture could have impacts to the design. 5.3 The final grading plan is needed to finalize the elevations of the thrust blocks and the elevations of the drilled shafts for the bridge bents. Receipt of this information from the Town's roadway consultant is needed by March 12,2004 to complete the bent design on schedule. 5.4 The Town's roadway consultant has not yet provided the bridge drainage inlets. Receipt of this information is needed by March 12, 2004 to complete the design on schedule. Arapaho Road Bridge Town ofAddison MEETING NOTES URSOffice March 2, 2004 ATTENDEES: Town ofAddison :!.lR.S Mike Murphy Cliff Hall Jim Pierce Gregg Durham Steve Chutchian Luke Jalbert 1) The Town ofAddison (Addison) requested DRS to prepare a letter to Addison describing DRS' QAlQC policies and procedures for the bridge design and plans. 2) DRS advised that there are clearance issues between the parking lot and the bridge bents. Addison will discuss with Grantham and Associates the possibility ofrevising the culvert at Surveyor to lower the parking lot grades. 3) DRS advised that they still had not received information relative to the bridge inlet drains. Addison to follow up with Grantham. 4) Addison advised that the transformer boxes shown on the new lighting standards would not be used. 5) Addison advised that the contractor is to install the roadway light poles. Some form of specification needs to be in the planlbid set ofdrawings. 6) Addison advised that DRS may use TxDOT specifications for the bridge. The TxDOT specs will need to be referenced with the COG specs. DRSIHNTB will add notes to the bridge plans and notes in the specifications referencing the TxDOT specs. 7) Addison asked DRS to add additional power outlets on the bridge (probably 6 total on each side). Conduit can be run through the concrete portion ofthe T4 (S) rail. These power outlets are to handle 120 volts. 8) DRS proposed a cable-fence type barrier to separate the sidewalk from the stingers, cables, and arch. Addison preferred the use ofa textured warning strip in the sidewalk around the stingers, cables, and arch to conform to ADA requirements and not a physical barrier. 9) DRS advised that the colunms at the ends ofthe bridge would be extremely short (one to two feet). Addison concurred this would not be an issue ofconcem. Arapaho Road Bridge Town ofAddison 10) URS advised that they would likely have the review plans complete by April 2, 2004. Completion ofthe lighting and electrical work is the critical tasks due to changes in the lighting standards and Town Council's recent decision on the lighting. Quick resolution ofthe clearances and bridge drainage are also critical. 11)Addison provided URS with a copy ofDWU's comments on the plans. There were no comments from DWU on URS' plans. Addison had no comments on URS' 60% plan submittal. rDRS February 25,2004 Mr. Steven Z. Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re: Arapaho Road Bridge.at Midway Road Phase IT -Design Deveiopment & Contract Documents Invoice for Professional Services Dear Mr. Chutchian: Enclosed please fmd our invoice for Professional Services for the Arapaho Road Bridge at Midway Road for the period between December 26, 2003 and January 30, 2004. Also included is our Progress Report for this period outlining the services provided. The total contract amount has been updated to include Change Order No.3. Sincerely, DRS Corporation CliffR. Hall, PE Project Manager Enclosure URS Corporation Grayslone Cenler 3010 LBJ Freeway. Suite 1300 Dallas, TX 75234 Tel: 972.406.6950 Fax: 972.406.6951 Monthly Progress Report Design of the Arapaho Road Bridge Over Midway Road URS Project No. 25334400 Period: December 26, 2003 to January 30, 2004 I. General Accomplishments l.l Submitted 60% plans 2. Progress This Period 2.1 Submitted 60% Plans. 2.2 Continued the final design. 2.3 Completed approach span superstructure drawings. 2.4 Met with the Town to discuss progress. 2.5 Set-up lighting mock-up demonstration. 2.6 Met with Town and Town's consultant to discuss bridge drainage. 3. Anticipated Next Period 3.1 Perform lighting mock-up on Addison Circle sculpture. 3.2 Make presentation to Town Council relative to lighting 3.3 Continue final design and drawing production. 4. Schedule Status 4.1 60% submittal was made on schedule. 5. Issues I Impacts 5.1 Decision by Town Council on lighting is needed immediately to provide direction to designer on lighting method. This could delay project completion. 5.2 URS was provided a new lighting fixture for use on the bridge. This fixture is being evaluated to see how it can be incorporated. This fixture could have impacts to the design. 5.3 Need the final grading plan to finalize the elevations of the thrust blocks. Steve Chutchian From: Cliff_Hall@URSCorp.com Sent: Thursday. February 12. 2004 5:37 PM To: Luke Jalbert; Mike Murphy Cc: Steve Chutchian Subject: Arapaho Road Lighting Standards This e-mail is to confirm the discussions we had on Tuesday evening, February 10, 2004 during the lighting mock-up demonstration. During our talks 􀁾􀁥􀀠􀁾􀁥􀁲􀁥􀀠instructed by you to incorporate the Lighting Standards as developed by Gensler onto the bridge structure with the exception of the recommended spacing. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 1 DATE SUBMITTED: February 16, 2004 FOR COUNCIL MEETING: February 24, 2004 Council Agenda Item SUMMARY: This is an informational item regarding the proposed bridge lighting package, as presented by URS Corporation. FINANCIAL IMPACT: N/A BACKGROUND: The firm ofURS Corporation is cnrrently underway on the design ofthe bridge that will span Midway Rd., in conjunction with the Arapaho Road, Phase ill project. The cost for providing a revised lighting package, as a component ofthe overall design, is presented for consideration. RECOMMENDATION: N/A 􀁾􀁾􀀠\ 􀀱􀀬􀀭􀀬􀁾􀀠􀁇􀁾􀀠\ 􀁾MA-J 􀁴􀀺􀀧􀁁􀁾􀀠SJ:Mt::-􀁣􀁾􀁾􀀠A.:pT.Jc.f-􀁾􀁽􀀮􀀼􀁴􀀢􀁆􀀠 , , URS January 30, 2004 Mr. Steven z. Chutchian, PE Assistant Ci1y Engineer 16801 Westgrove Drive P.O. Box 90 I 0 Addiscn, TX 75001-9010 Re: Addendum 1 to the Final Report for the Arapaho Road Bridge Noise and Vibration Analysis Phase II -Design Development & Contract Documents Arapaho Road Bridge over Midway Road Dear Mr. Chutchian: Submitted herein are the results ofthe additional noise analyses that were undertaken after the "Final Report" was submitted. These studies were conducted to evaluate the fully open rail option requested by the Town Council in June 2003 and to confirm the use of the 1.5-foot concrete rail recommended to the Council in August. These results had been discussed previously with the Town of Addison and have been incorporated in URS' bridge design and have been discussed with the Town's consultsnt to be included in their roadway design. The conclusions from these studies are: I. The selected T4 (S) bridge rail adequately reduces the noise to meet the criterion levels. 2. The T4 (S) rail should be extended to the western edge ofthe BullougblLykos Building. 3. A 3-foot high earthen berm should be used along Arapaho Road adjacent to the Heritage Inn property. • Included in this report is a Design Memorandum dated July 29, 2003 relative to the noise analysis for the open rail option. The Predicted Exterior Noise Levels determined in this study would exceed the Criterion Noise Level if open rail was used for two properties, Motel 6 and the Comfort Suites (Heritage Inn property), and approaches the levels considered as Substsntial Increase in noise at two properties at the western edge ofthe project as shown in the excerpt ofTahle 2 below. Table 2 -Predicted Exterior Noise Levels without Concrete Rail Receptor Location Combined Future Noise Level (Ambient plus Projeet) (dBAL,q) Estimated Future Noise Sub,tantialIncreas e Over Criterion Level Exceeds Increase Criterion Existing Noise Noise '-;,;Ie"ion" Noise (Greater than 10 Level (dBA L..l Level? dBA) Exceeded? (dBA L ..) No 71 URS Corporation Graystone Centre 3010 LB) Freeway, Suite 1300 Dallas, TIi 75234 Tel: 972.406.6950 Fax: 972.406.695i # Receptor Location L""el (Ambient plus Project) (dBAL,q) XIS mg OISe eve C 0t . Level (dBA L \ . rI erlOn .., L..,.I?(dBA L,q) (Greater than 10 dBA) Exceeded? Addendum 1 Noise Report January 30, 2004 URS Page 2 • Based on these results, we recommended that some fonn ofconcrete barrier rail be used to reduce the noise to acceptable levels. We choose to modify a TxDOTType T4 (S) bridge rail, which consists ofan IS-inch high solid concrete barrier with a steel rail mounted above. This rail was presented to the Town Council in August and approved. • To verify that the selected rail would adequately reduce the noise levels, a revised analysis was perfonned using a I-foot high solid concrete barrier. The full results are show in the attached table. Although these results were sufficient for the properties adjacent to the bridge, the Heritage Inn property (Comfort Suites) still showed predicted noise levels that exceeded the criterion as highlighted in the excerpt ofthe table shown below. We also recommended that that the limits of the concrete barrier be extended from the beginning of retaining wall at grade to the western edge ofthe BulloughlLykos Building to reduce the increase in noise from 10 dBA, which approaches the Criterion Level, to below 8 dBA. Predicted Exterior Noise Levels with l' Higb Concrete Barrier, Rest Decorative and Pipes Combined Estimated SubstantialIncrease Over Criterion Future Noise Future Noise Increase Criterion E . t· N· L I' Level Exceeds • Because the noise levels at the Heritage Inn property (Comfort Suites) still exceeded the Criterion Noise Levels, we ran a further refined analysis to study this property specifically. The results ofthis analysis are summarized in the attached Design Memorandum dated August 8, 2003. Based on these results we recommended that an approximately 3-foot solid barrier, which could consist ofan earthen berm, be used for the limits shown in this memorandum. Future noise level for the proposed project used in this Addendum to the Final Noise Report as well as as in the Final Noise Report, are derived from the FHWA's TNM® noise model. Criterion noise levels are based upon TxDOT I FHWA exterior "approach or exceed" Noise Abatement Criteria for Activity Category C (which includes commercial land uses) and Activity Category B (which includes hotellmotelland uses). This Addendum to the Final Noise Report should be taken with the Final Noise Report, dated May 13, 2003, forthe complete noise study ofPhase m ofthe Arapaho Road Project. Sincerely, DRS Corporation aII/zdY( CliffR. Hall, PE Project Manager ..; " Enclosures URS Corporation 2020 East First Street, 􀁓􀁵􀁾􀁥400 URS Santa Ana, Caftfomia 92705 Tel: 714 835 6886 Fax:: 714 667 7147 To: Cliff Hall, P.E. From: Mike Greene, INCE Bd. Cert As requested, I have modified the noise model for the project to determine the predicred change in noise levels for a "no concrete rail" design. Under this scenario, the approximately three-foot high concrete "k-rail" or 'Jersey barrier" would not be constructed along the edge of the bridge deck as initially planned. Instead, an open rail design would be used in which two to three horizontal steel pipes (oriented one above the other) would serve as the safety barrier. This open rail design would provide negligible noise "shielding" from passing vehicles at nearby land uses. The Traffic Noise Model 􀁾version 2.1 was used to predict the resultant change in noise levels at adjacent land uses from this design modification. The model (constructed previously) was modified by effilctively removing the low barrier at the edge of the bridge deck. Table I presents a summary of the modeled data for the ''with concrete rail" scenario as originally modeled, while Table 2 presents the data summary fur the ''without concrete rail" case. As Table 2 shows, the ''without concrete rail" case is expected to result in several FHWA and TXDOT noise abatement criterion (NAC) exceedances. Specifically, noise levels would exceed FHWA and TXDOT NAC at two modeled locations. The two locations where noise levels are predicted to be exceeded are at adjacent hotel/motel establishments (Motel 6 and Comfort Suites). The criterion noise level of 66 dBA L,q fur residential uses (including transient residential) would be equaled or exceeded at these January 30, 2004 locations. These exceedances are not predicted to occur in the original "with concrete rail" case. Thanks again for the opportunity to participate in this project. Ifyou have any questions or ifI can be offurther assistance, please call or e-mail me. Best Regards, Mike Greene, lNeE Bd. Cert. Senior Project Scientist DRS Corpomtion 2020 East First Street, Suite 400 Santa Ana, CA 92705 • Page2 Table 1 -Predicted Exterior Noise Levels with Concrete Rail ReuptorN Receptor Location Existing Ambient Level (based upon Noise Measurements) (dBAL",) Estimatedl Future Noise L..el «(rom Arapaho Bridge) (dBA L",) Combined Future Noise Level (Ambient piUS Project) (dBA L,.) Estimated Increase Over Existing Noise L.vel (dBA L,.) Criterion Noise Levee (dBA L",) Future Noise Level Exceeds Criterion Noise Level? Substantial Increase Criterion (Greater than 10 dBA) Ex.eeded ? 1 W ofCrouch Properly. 10' fin bridge 58 57 61 3 71 No No 2 W orCrouch Property -3S' fin brid"" 58 58 61 3 71 No No 3 W of Crouch Property -60' fin brid"" 58 57 61 3 71 No No 4 W of Crouch Property -85' fin bridge 58 56 60 2 71 No No 5 W of Crouch Property -110 ' fin bridge 58 54 S9 1 71 No No 6 E ofCrouch Property -10' fin brid"" 58 SS 60 2 71 No No 7 E or Crouch Property -35' fin brid"" 58 56 60 2 71 No No 8 E of Crouch Property· 60' fin bridge 58 56 60 2 71 No No 9 E ofCrouch Property· 85' fin bridge 58 56 60 2 71 No No 10 E of Crouch Property -110' fin bridJre 58 55 60 2 71 No No 11 Outdoor Break Area· Furniture Store 59 S4 60 I 66 No No 12 Ice Rink in Parking Lot 66 56 66 0 71 No No 13 Adj to Motel 6 63 58 64 1 66 No No 14 Ad; to Homewood Suites 59 57 61 2 66 No No IS Ad; to Comfort Suites 57 65 65 8 66 No No 16 Adj to E side ofFurniture Store 66 54 66 0 71 No No 17 Adj to Intervest 58 60 62 4 71 No No 18 Adi to S.torilThe Harbor GrouD 58 62 63 5 71 No No 19 Adj. to Building near W side ofPro;ect 58 62 63 5 71 No No I -Future noise level from proposed 􀁰􀁲􀁯􀁩􀁥􀁣􀁾􀀠derived from the FHWA's TNM® noise model. 2· Criterion noise levels 􀁾􀁡􀁳􀁥􀁤􀀠upon TxDOT I FHWA exterior "approach or exceed" Noise Abatement Criteria fur Activity Category C (which includes commercial land uses) and Activity Category B (which includes hoteVmotelland uses). . Table 2 -Predicted Exterior Noise Levels without Concrete Rail Re"ptor# Receptor Location Existing Ambient Level (based upon Noise Measurements) (dBA L"Il Estimatedl Future Noise Level (from Arapaho Bridge) (dBAL",) Combined Future Noise Level (Ambient plu. Project) (dBAL..) Estimated Increase Over Existing Noise Level (dBA L,.) Criterion Noise Level' (dBAL..) Future Noise Level Exceeds Criterion Noise Level? Substantial Increase Criterion (Greater tban 10 dBA) Exeeeded ? 1 W ofCrouch Property -10' fm bridge 58 63 64 6 11 Nn No 2 W nfCrouch Property -35' fin bridge 58 63 64 6 11 Nn No 3 W nfCroucn Prnnerty -60' fin bridee 58 63 64 6 71 No No 4 W ofCrooch Property -85' fin bride" 58 61 62 4 71 Nn No 5 W ofCrouch Property -110' fin bridge 58 59 61 3 71 No No 6 E ofCrouch Property -10' fin bridge 58 61 62 4 71 No No 7 E of Crouch Property -35' fin bridge 58 61 63 5 71 No No 8 E ofCrouch Property -60' fin bridge 58 61 62 4 71 No No 9 E of Crouch Pronertv -85' fm brid£e 58 60 62 4 71 No No 10 E ofCrouch Pronerty Pronerty -110' fin bridge 58 59 62 4 71 No No Il Ouldoor Break Area -Furniture Store 59 58 62 3 66 No No 12 Ice Rink in Parking Lot 66 60 67 1 71 No No 13 Ad; to Motel 6 63 62 66 3 66 Yes No 14 Adi to Homewood SuileS 59 60 62 3 66 No No IS A
  • Jsting EsHlllalEd' Combln Arapaho Bridge) pillS ProJed) Level (dBALq) Level? (Grealerlhan 10 (dBAL.'Il (dBALq) (dBAL"l1 (dBAL,q) dBA) Elceelled t I WofCmuch Property -10' fm 􀁢􀁲􀁩􀁤􀁾􀀠58 61 63 $ 71 No N<> 2 \V or Cmuch P",peny· 35' fin 􀁢􀁲􀁩􀁤􀁾􀀠58 61 63 5 71 No No 3 W .fC",,,,,b Pmpmty 60' fin bridliO S8 60 62 4 11 N<> No 4 W of Crouch Property -85' em bridp sg 59 61 3 7J No No S Wo[Crouchl.'ropert)l-110 'fin briru.c 58 57 60 2 71 No No 6 II of C!OUch property -10' fin bridge 58 59 61 3 71 No N<> 7 IE ofCmuch l'rImertv. 35' em brldgo sa 59 62 4 71 N. No 8 BofCrouch P"",crt\' -60' fin bridllO 58 􀁓􀁾􀀠61 3 71 No N<> 9 BofCrouch P"",.,tY -85' fm bddge 58 5& 61 3 71 No No 10 II ofCrouchProperty -110' fin bridge 58 58 61 3 11 N. No II Outdoor Brcek Area -Fumirur. St.", 59 S6 61 2 66 No No 12 roo RInk in PIIlkins J.ol 66 S9 66 0 1J No N<> 13 Adj t. MoIoI 6 63 61 65 2 65 No No 14 Ad; 􀁾Hot1lllW!llld S.i(e. 59 S9 62 3 66 N. No IS Adj to Comfort Sniles S7 65 66 9 66 Yes N<> 16 Ad' 10 Eaid.ofFumilo", Store 66 S6 66 11 11 No No 11 Ad !olntm...t sa 63 64 6 71 N<> No IS Ad 􀁾SalorifI'hclliuOOr Groll!> S8 65 6S 1 71 No No 19 __ f, 10dEAl it is right on the threshold. Therefore we recommend that the traffic rail be carried to the end of this building, approximate station 45+00. As a reminder we need a 3-ft high noise barrier in front of the Heritage Inn property (including along the east side of the driveway). We discussed accomplishing this with an earthen berm. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Jenny Nicewanderlt To: . com> Subject: RE: Bridge barrier 01/24/2004 10:30 AM You mentioned extending the rail on the southwest retaining wall, let me know how far you need that extended and I will include that on the plans. 􀁾􀀠. ; . ; 􀀬􀁾Jenny -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.com] Sent: Tuesday, January 20, 2004 9:12 AM To: Jenny Nicewander Subject: Re: Bridge barrier 1 We are using a "T4 (5) (mod)'f. The modification is to increase the thickness by 1" (1/2" to each side} and use a recessed triangle 􀁰􀁡􀁴􀁴􀁥􀁲􀁮􀁾􀀠Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Jenny Nicewander" To: - Subject: Bridge barrier 01/20/2004 07:50 Cliff, Could you let me know what type of barrier you are uSing on the bridge? I was wanting to be sure I callout the right one on the retaining wall. Thanks, Jenny Nicewander liNTB Corp. 972-628-3164 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail totheintendedrecipient.be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying of this a-mail is 2 strictly prohibited. : ." 3 URS Corporation Arapaho Road Bridge at Midway Road Design Development and Contract Documents Change Order No, 03 to Work Order No, 001 ATTACHMENT M Revised Estimated Schedule TASK 1 1 ..v .. 12 􀁏􀁾􀁬􀁯􀁾􀁥􀁲2 =10' IINTPI ,Issues INTP For Prelim. Design Desion 1 i at Arch 1Ft,:I g 'I!:."" Plansl ,Review 􀁉􀀧􀁾􀁾􀁯􀁥􀁳􀁬􀁧􀁮􀀠Final I ".port Final , Plans Final Desion 􀁾􀀠, Desig n 1(60% Plansl • Review .to 􀁾IBridgel IFinal Design &. IFinal Desion 1195% Plansl • Review 􀁾􀀮􀁮􀁾􀁾􀀠12 0 0 2 ." 2 0 0 2 2 􀁊􀁾􀁮􀁾􀁲􀁹3 2 0 0"3 12 􀁾􀁡􀁲􀁾􀁨􀀠3 • 12 􀁾􀁰􀁲􀁩􀁲􀁩􀀠3 12 :a'b 3 2 􀁾􀁕􀀢􀁾􀀠3 2 􀁾􀀢􀁾􀀠3 2 􀁁􀁾􀁧􀀺􀀠3 12 '0 0 3 2 􀁵􀁾􀀧􀀺􀀧3 •• • • • 12 0 0 3 200 3 2 Jagui 4 1 2 0 0"4 􀀱􀀲􀁾􀁲􀁾􀁨􀀴􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠... 􀁾􀀠-- ·1 :t.-$140.00: t $125.00 TASK·iI 􀁾􀀬􀀠Ai\Cl!iTecnf fW.:'· y "0' .;'0, .0 􀀧􀀭􀀧􀀬􀁾􀀺􀀧􀀠,'. 􀁾􀁟􀀠.. A. Design'o.wloJ;;.g;" 1. ArchItecIir.iI Studies & 􀁏􀁥􀁴􀁡􀁩􀁬􀁾􀀠 De1Ielop milled In!Iflic rail 􀁾and \he AJtMedura! option to realim the :, : :'1 :1-: ,1)i'· 18 12; 4 4 4 :.1!. 6 •o· .. • ..S. h .• 4• J!., ! .!!. 4 o I,24.1· ... B.12 4 ,. $60.00 'J :;,1 $35.oo::k' "36""'" 0 􀀬􀁾􀀧􀀠0: "8 238 12 • 20 22 24 14 " 2. I.• ". '" 66 22 . -124 : 124:' I': 1:1 :1 '" lJoveiop Sl'Idge Mounted "SVngarG"􀀭􀁾􀀭􀀭􀀮􀀠76D 􀁛􀁾􀁝i2\-_C:EJ 36 AltendAd • 4. Ccuncll orolhe(' TQWn MOOIiogs (1) 4 6, Prqoct Mealing$ v.iU'I Addison. F\lbllc WOrks (2) 4 I J I: I I I I I Grand Total 116 ., 54 22 4 ...• '" '" " CHANGE ORDER NO. 03 In accordance with the Agreement between the Town ofAddison ("Clienf'j, and URS Corporation rURS"j, a Nevada _corporation dated November 11, 2002 (for Work Order No. 001 ) this Change Order describes the agreed upon changes to the SelVices, Schedule, and Payment for the SelVices. Project: Arapaho Road Bridge at Midway Road URS Project NO.25334401 Date:___ REFERENCE: Drawing No. NIA Specification No. Other uN!!..IA-'--___________ The Agreement is hereby changed as follows: See Attachment K, "ADDITIONAL SCOPE OF SERVICES" Justification for Change: The need for additional unforeseen coordination with the Addison Town Council and subsequent requested modifications to the bridge renderings, lighting, traffic rail and layout plans. CHANGE TO ESTIMATED CONTRACT PRICE (See Attachment !) Original Estimated Contract Price: Current estimated contract price, including previous change orders: The estimated Contract Price due to this Change Order will be increased by: The new estimated Contract Price due to this Change Order will be: $ 550.965.00 $ 593,090.00 $ 49,470,00 $ 642.560.00 CHANGE TO THE ESTIMATED SCHEDULE (See AttachmentMJ The Contract lime will be increased by .1§.L calendar days. The date for completion of all work under the contract will be: -"J"'u""ne"-3"'0""...=2""OO""4L -______________. EXCEPT AS PROVIDED IN THIS CHANGE ORDER, ALL TERMS AND CONDITIONS OF THE CONTRACT REMAIN UNCHANGED Acceptance of the tenns of this Change Order is acknowledged by the following signatures of the Authorized Representatives, CLIENT .-!, _'S =\" 􀀩􀁾􀀠/$. EmilY Taylor, RE.I Vice President Typed NameITrtle Typed NameITrtle ,.II/e:> 􀁧􀁬􀁯􀁾􀀠Date of Signature Date/of Signature cc: Accounting SIgnature CHANGE'()RD1.DOC 4.J1UG-OO · ,I'f: ••i: « · 􀁾􀀮􀀠;1. I·• f: .1 ••I",'.􀀬􀀭􀁾:fois: I: i: •• •lieS: 􀁪􀁾􀀠" •f: « " •b·'0 N " 􀁾􀀺􀀠• « M f: " 􀁾􀀠M 􀁾􀀺􀀠•• :si 􀁾􀀺􀀠• 􀀡􀀮􀀻􀁾􀀠• 􀁾􀀺w·:el i:􀁾􀁩􀀠i 􀁾􀁉􀀠,: 􀁾􀀢􀀠• 􀁊􀁾􀀠N • " • • • • 􀁾􀀠􀁾􀀠i•0 􀁾􀀠􀁾􀀠􀁾􀀠• i 0 0 􀁾􀀠􀁾􀀠§ J! Ii': « 􀁾•J: •••N URS December 26, 2003 Mr. Steven z. Chutchian, PE Assistant City Engineer 16801 Westgrove Drive P.O. Box 9010 Addison, TX 75001-9010 Re: Arapabo Road Bridge at Midway Road Phase n -Design Development & Contract Documents Invoice for Professional Services Dear Mr. Chutchian: Enclosed please fmd our invoice for Professional Services for the Arapaho Road Bridge at Midway Road for the period between September 20, 2003 and November 28, 2003. Also included is our Progress Report for this period outlining the services provided. The total contract amount included on the invoice does not include Change Order No.3, as we have yet to receive the signed copy from your office. Sincerely, URS Corporation CliffR. Hall, PE Project Manager Enclosure URS Corporation Graysfone Center 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Tel: 972.4tl6.6950 Fax: 972.406.6951 Monthly Progress Report Design of the Arapaho Road Bridge Over Midway Road URS Project No. 25334400 Period: September 20, 2003 to November 28, 2003 I. General Accomplishments 1.1 Progressed the Preliminary Design 2. Progress This Period 2.1 Progressed the preliminary design. 2.2 Began setting the arch geometry. 2.3 Began setting the thrust block geometry. 2.4 Met with the Town Council at the Council Meeting for Change Order No.3. 2.5 Coordinated abutment configuration with storm and sewer pipes. 2.6 Received the Geotechnical Report from Town's consultant. 3. Anticipated Next Period 3.1 Continue the preliminary arch design, arch size and shape. 3.2 Finalize the thrust block shape and location. 3.3 Begin approach span design and details. 3.4 Begin arranging for the lighting mock-up. 4. Schedule Statns 4.1 The Town Council approved Change Order No.3 including a new scheduled completion date oflate March. 5. Issues I Impacts 5.1 Need the final grading plan to finalize the elevations of the thrust blocks. 5.2 Placing sidewalk exterior to the arch is creating a more difficult structure to design, construct and light. This may increase the cost ofthe bridge. 5.3 Town Council has requested changes to the bridge rail type, added the "stingers" back onto the bridge, and requested colored lighting for the bridge. These changes have impacted the schedule and cost ofthe project. , . ',' 􀁃􀀾􀀭􀁾􀀠HANCER ROPE_____ I I I I I I r-1','I SHLOR. -4 LANES S' 􀀱􀀱􀁾􀀠= «14' -0" .. It DlAfR:=,I 50;-0" 1􀁾􀀠-6" SHLOR." .. • • <1 ,r 'i I if' "\ ".--e>< 􀁾􀀵􀀴􀀢􀀠U-BEAM (TYP) TYPICAL SECTION IN.T.S.) SOUTHNORTH ROWROW 14' ,, I 􀁾􀁜􀀠(,\JJ 6 O.D. WATER PIPE •• • $\ • :e • • • =• :8 :8 •• :8 • • ::8 =• • ::8 ., ::8 :tJ • • ., .. • • HANGER ROPE 􀀭􀁾􀀭􀀮􀁊􀀠1'-6" 8'-0" SIDEV/AlJ( .. .. .. , I, S'i -, 58' (js 4 U>HES fJ II' = 44'-0· 􀁉􀀭􀀭􀁾􀀭􀀭􀀡􀀮􀀠-TYPI CAL SECTION " "-6" SHLDR. .. 54" U-BEAM ITYP) ..------.--t--r-7' -o"/b DRillED SHAFT ,􀀸􀀰􀀭􀁾__________________________􀁾􀁾􀀠 AP..ot <.. I,jof.1 \Z-0uJ CJ g.<1> 9. '"a '" ::>􀁟􀁬􀁟􀁾􀀠:L Cl ,";: . 􀁾􀀠􀁾􀀠09\J '"' '" \."\ \i\ C) C) ." 0r-o .9. 􀁾􀀠:I jli'"'" c::Ii '" ;z􀁾􀀠9!.if tT '< ......-: .I I a a I I DALLAS AREA RAPID TRANSIT 60" WATER RAIlROAD I 􀀭􀀭􀀭􀀭􀀭􀁾􀀮􀁾􀀭􀀭---------lifARAPAHOROAD----------r-_= PLAN OVERALL BRIDGE LENGTH = 1600'-0" DIRECTIONIOF STATIONING'i':"=, ,• 62 a ------------r-----.,-,,,..'-: !o, , I io3 SPANS Ii? 105'-6" -316'-6"-f74'-0" 105'-6" q; PIER II MATCH LINE 2􀁾􀀠'7' 􀁾􀁾􀀠III III 􀁾􀁾􀀠􀀱􀁾􀀠I, . .." 􀀶􀀵􀀰􀁾640 630 •• •• *• 􀁾􀀠HANGER 􀁒􀁏􀁐􀁅􀁾􀁟􀁉􀀠=, I, 5'1 -(.=• 58' Q' 1'-6" =SHLOR. 4 LANES @/I' 44'-0'8'-0" SID[WAIJ( •• =... ---... .. ==54' U-BEAt.I (rrp)DlAFRAM ==* =:.t) * :I) 􀁾􀀠7'-()"!b ORILLED SHAFT •:f) • I 0' p. • TYPICAL SECTION I "•., $0-0 -, -,. -" --> 􀁾􀀠---􀁾􀁾􀀠., 􀁬􀁉􀁲􀀾􀀮􀀺􀀮􀁊􀀮􀀢􀁾􀁲􀀢􀀬􀀬􀀭􀀢􀀧􀀺􀀢􀀧􀀬􀁪􀁯􀀮􀀻􀀠, ••• ARAPAHO BRiDGE 􀁾􀀠. . .. . . TOWN OF,ADDISON, TEXAS . ..:.J ;:' 􀁾􀀮􀁾􀀩􀀠=.:-_.' •• • • 􀁾􀀠􀁾􀀠:;e •:t RAllflOAD =:a •••• :a ,. ,. ,. ::t PROPOSED R/w PROPOSED H/W'-WATER .., .. MIt:JNAY ROAO CT11.10-100.00 1; --, ji,,) , ::t PLAN =::to .________________􀀭􀀭􀀭􀀧􀁾􀀬􀀧􀁟􀀧􀁅􀀽􀁒� �􀁁􀁌􀁌BRlfXjE LENGTH =1600'-0' :t J SPANS t!! IOS'-6' 􀁾􀀠􀁾􀀠:a , 650 -If: PieR 6 MATCH LINe 1-, I 3[6'-6' ,, II , I-------------,----II I lei. U. J. 7' " DRILLED SHAFT (TYP) ._.._.--105'-6" If: PIER /I --MATCH LINE 2-􀀭􀁾􀀭􀀭􀁾􀁾􀀠. fP' , 650 640 640 , :t 630 62.0 􀀯􀀡􀁾􀀠􀁟􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀁾􀁾􀀠___ i 630 ' .J ___ I --62.0 , 610 610 600 600--]-U iU . Li U i , ' '.. .' 590 590I 􀁾􀀠I... ...580 580 eXISTING GROIIND .. • ElEVATION -. , ARAPAHO BRIDGE TOWN OF-ADDISON TEXAS ...:' , 􀀧􀁾􀀧􀀮􀀠􀁛􀀽􀁾􀀢􀀢􀁾􀀠 •• •• •• HANCER ROPE_____ n NORTH ROW 14' 3' MJNG' 0.0. WATER PIPE "-6 I. SHLOR. 4 LANES ell' = 􀀴􀁾􀁦􀁟􀁏􀁈􀀠. \ '-6"" n ,1'';;" .. .. l' .....," SHLOR., 􀁾􀁉􀀠SOUTH ROW I••I••I I I ,• I,, :::::>.•, I TYPICAL SECTION tN.r.s.) DRS Page __ of 􀁾􀁾􀁾􀁾􀁾􀀠Project No, _______ Sheet of Description _____________ Computedby ______ Date ________________ Checkedby _______ Date Reference -r .:} d /-;t /..-----... "-----"---.. 􀁾􀁾􀁾􀀠I , I I I \ ! i \ I i \ /,....I =< I '>{, 􀁾 i 􀁾􀁟􀀯􀀩􀀠 Ll\ .... Eachfirm wiD be given two hours to make their presentations and answer questionsfrom the panel, with at least 30 minutes dedicated to question and answer. }> Panel will use evaluation criteria stated in information below, with each item having equal value to assist in ranking each firm. }> Each member willthen individually grade each firm, in a similar manner, giving eacll item a grade from 1-10, wit" 10 being best. » Each member based on the total score given will rank thefirms in order of grade 1s', 2nd, or yd. » Allpanel members will submit their rankings to establish initial order. » Group will have open discussions about individual concerns and opinions. » Allpanel members will review tlteir initial rankings andre-submitforFma/order. » Each firm will be given an overall grade based on rank submitted by eac1, member. 1st place will be awarded one point, 2nd place will be awarded 2 points and Jrd place will be awarded J points. Thefirm with tlte fewest total points will be the competition winner. Please note that I have included a copy of each firm's original Statement of Qualifications submittal. Thank you, and I look forward to seeing all of you on April 11th, Should you have any questions prior to April 11th, feel free to contact my office at 972-450-2871 and speak with me or the Assistant Director ofPublic Works, Jim Pierce. Sincerely, Michael E. MurphylDirector of Public Works Arapaho Road Bridge Pre-Competition Meeting Agenda February 14, 2002 I. Welcome and introductions: Ron Whitehead,. City Manqer II. Directions to Consultant: Milee llllurphy. Director ofPublic WOIIc$ A. Announce tentative day and time ofpresentations 1. First Presentation 8:ooam-10am 2. Second Presentation 10:30am-12: 30pm 3. Third Presentation 1:30'pm-3: 30pm B. No more than two desi.ns III_ Gradin.. will be based on the following criteria A. Aesthetics -appearance day and night, should include IIghtin. desi.n plan B. Landscaping C. Acoustics (how will noise affect adjacent buildings) D. Vibrations (how will motion affect adjacent buildings) E. Estimated cost of construction of the bridge design F. FunctionalityI build ability (parking,pedestrian and bike users.. safety. ADA etc.) G_ How does the bridge minimize obstruction to adjacent buildings from roadway H. Overall quality and creativity of presentation (vision, team plan I effortJ Presentation Schedule: Time (April 11th) Firm 7:30am -"8:00am Committee Members 8:00am-lO:OOam VRS Griener H):30am -12:3Opm Freese & Nichols l2:3Opm-I:30pm Lunch 1:30pm 3:30pm HNTB 3:30pm -5:00pm Panel Discussion/Selection Conference Centre Location BoaraROom Stone Cottage BoardRoom BoardRoom Stone Cottage BoardRoom EXAMPLE SCORE SHEET 1. Aesthetics -appearance day and night, should include lighting design plan (1-10) 􀁾10 POINTS 2. Landscaping (1-10) _-'7L-----!POINTS 3. Acoustics (how will noise affect adjacent buildings) (1-10) 5 POINTS 4. Vibrations (how will motion impact adjacent buildings) (1-10) 8 POINTS 5. Estimated cost of construction of the bridge design (1-10) 6 POINTS 6. FunctionalityI build ability (parking, pedestrian and bike users, safety, ADA etc.) (1-10) 4 POINTS 7. How does the bridge minimize obstruction to adjacent buildings from roadway (1-10) 10 POINTS 8. Overall quality and creativity of presentation (vision, team plan I effort) (1-10) 9 POINTS TOTAL SCORE 59 POINTS COMMITfEE 1 2 3 4 5 6 7 TOTAL SCORE FIRMfll 3 I 3 2 I 3 3 16 #3 FIRMf12 2 2 2 I 2 1 2 12 111 FIRM#3 I 3 1 3 3 2 1 14 #2 F Each firm will be given two hours to make their presentations and answer questionsfromtheJ1anel... with at least. 3fJ minutes dedicated to lJ1lesI.io11 and answer. }> Group will have open discussions about individual concerns and opinions. » P.anel wm lISe evaluation criteria statedin injor.madD11. below, with each item having equal value to assist in ranking each firm. }> Each member wm then individually grDd.e each firm, in a similar mnnner, giving each item a gradefrom 1-10, with 10 being best }> Each member bDSed 011. the JOIalscore given wJllrank thejirms in order 0/grade 1", 2"4, orr. }> AltpanefmemJ;ers wiltsulimit their ranltings to establish i'nitiiltunler. }> Each firm will be given an overall grade bflSed on rank submitted by each member. 1"place will be awarded one poiat, 2"4place will be awOl'ded 2 points mul3'"place will be awarded 3 points. Thefirm with the/_est Mol pomu willbe the competitiiln winner. NAMEOFFJRM'----------------SCORESHEET 1. Aeilflhetics -appearance day and night, should include 11ghtlng design plan tt-t(t} POINTS 2. Landscaping (1-10) ___POINTS 3. Acoustics (how will noise affect adjacent buildings) tt-10) POINTS 4. Vibrations (how will motion impact adjacent buildings) (1-10) POINTS 5. Estimated cost of construction of the bridge design {'t-10) POINTS 6. FunctionalityJbuild ability (parking,pedestrianand bike users, safety, ADA etc.) (1-10) POINTS 7. How does the bridge minimize obstruction to adjacent buildingsfrom roadway' (1-10) POiNTS 8. Overall quality and creativity of presentation (vision, team plan Jeffort) (1-10) POINTS TOTAL SCORE ___nHNTS, .' 0 .;.:/'::I{' .;,-;,'; f:'-,l ," 1'·;'1 ,;(. ...'J !';'. heavier cables to supportthe extra weight offloor framing. With a lightweight box., girder, a'design team th'tt includes OPAC Consulting Engineers, ,San Francisco, held down the Caxquinez 'Bridge's suspension cables to a diameter of512 nun. Ina:first for a U,s. suspension 'bridge; Spow says, the design makes specific allowances for the loss ofanyone ofthe vertical 'ropes that support the superstructure from the main cables, MARYLAND HIGHWAY OFFICIALS ARE scr.unbling to figure a "Plan B" after the sole bid for the main oontract for a new WOodrow WIlson bridge,near Washington, D.C., came in nearly $360 million, or 72%, above their estimate. If they can't find a way to cut 'the bid price, Maryland mces a big shortfull for its part ofthe $2.4-billion overall project , Au:he Dec. 13 opening, a team of KiewitConstruction Co., Tidewater Con,struction Corp. and Clark Construction Group InC. filed the only bid for two, sixlane bascule spans across the Potomac River and demolition ofthe existing 4{). year-old drawbridge. BaSed on prooid 􀁳􀁣􀁵􀁴􀁴􀁬􀁥􀁢􀁵 􀁴􀁾􀀠Slate Highway Adruinistrator Parker F. Williams wasn't surprised that he gotjust one offer. The price was the shocker: $859.95 million, or some $360 million above the state's estimate. "Nobody could have expected...that the . bid was going to be this rngh,' he says. According to Spoth. using largediameter drilled Shaft foundations for the towers instead ofconcrete caissons is also rarely seen in D.,s. bridges. In a quake, massive caissoris'-tend to rock. The 3-m-<:s Tow"-of Addlso.... \:lr::1)450-::1l?j'lS' -----Onginal Message----From: Chris Teny Sent: Tuesday, January 29, 2002 10:06 AM To: Michael Murphy Subject: BRIDGE SELECTION COMMITTEE -DRAFT Mike, Here is the compOSition of the committee as Ron and the Mayor discussed it. This is not absolutely final, but close. I Will keep you posted as this is still in flux. Committee Members: Mayor Wheeler ....-Councilmember Diane Mallory ..... Ron Whitehead .r' Art Lomoneck, developer /' Bill Crepeau, property owner along bridge ROW -Charter Fum. I spoke with Bill Crepeau and he said he is 99% sure he will be the new owner. Mike Murphy .,/Chris Terry tI' 1 TOWN OF ADDIsoN PUBLIC WORKS To: 6;H e.e+re.11i. From: Jim Pierce, P.E. Asst. Public Wks. Dir. Company: f-e..tve \Lt. k ' Phone: 972/450-2879 FAX: 972/450-2837 FAX#: 􀀱􀁾􀀸􀀱􀀷􀀭&33 -1,507 j pierce@ci.addison.tx.us Date: :J -S -0')... 16801 Westgrove P.O.Box 9010 # of pages (including cover):--,-I_ Addison, TX 75001-9010 Re: AY'tlra..ho tet Br'wl,fL o Original in mail pi Per your request 0 FYI o CaUme Comments: 5 Y1t{ 1/sf-s 'Rt:t YY1 :5 ; ---!I!\!!!---...., PUBLIC WORKS DEPARTMENT (972) 45G-2871 16801 W,,'grove ® PoalOffice Bt»: 9010 Addison, TexHs 75001M 9010 23 January 2002 Freese-Nichols 1701 N. Market Street #500, LB 51 Dallas, TX 75202 ATTENTION Mr. Alan D. Greer, P. E. SUBJECT Arapaho Road Bridge Finalist Dear Mr. Greer: Congratulations! This is to advise you that Freese-Nichols, along with URS Corporation and HNTB Architects, has been selected as a Finalist for the design competition for the Arapaho Road Bridge at Midway Road. We will be in contact with you in the near future to schedule a pre-competition meeting to discuss the next steps. Please call me at 972-450-2879, if you have any questions. Sincerely, es C. Pierce, Jr., P.E. 􀀭􀀴􀁌􀀭􀁾􀀠ssistant Director of Public Works JP:sef cc: Chris Terry Mike Murphy PUBLIC WORKS DEPARTMENT (972) 450-2871 Post OfJiI• I • 1/_&_ • .1--1 SECTION ••• •• •• •• 1/2" BAR STEEL RAILS @6" O.C. WIDTH I I 0 1 ft. y," TRIANGULAR 1n X2" CENTER POST STEEL PLATE ELEVATION @PEDESTRIAN ELEVA TlON @TRAFFIC RAIL STEEL RAILSI iRAIL @6" O.C.SECTION o 1 ft. Yon 􀁔􀁒􀁉􀁁􀁎􀁾􀀮􀀠􀁾􀀠STEEL PLATE 1"X2" TUBE STEEL FORM-___ 1 }'2 11 1'-2Y." 7)6" 7" •o " (') SECTlON@PEDESTRIAN I I 0 1 ft. RAIL 3" DIA. STEEL PIPE \ GUARDRAIL 􀁾􀀢􀀭􀀭􀀭........ 1"X2 " TUBE STEEL CENTER POST 1"X2/f TUBE STEEL 3"X1 H -......,.. TUBE STEEL END POST LINER•«), 1/2" BAR (') SECTlON@􀁾􀀺􀀠,TRAFFIC 􀁾􀀠.:RAIL ARAPAHO BRIDGE URS22 MAY 2003 CaRGAN METAL PEDESTRIAN RAIL REVEALS IN RETAINING WALL IN SAME PROPORTION AS RAILING. RETAINING WALL SET IN SLiGHTL Y FROM EDGE OF ROADWA Y I I o 1 ft. 􀁾􀁒􀁅􀁃􀁅􀁓􀁓􀁅􀁄AREA & RAILINGS 􀁾􀀠TERMINA TE TOGETHER I iii I o 4 ft. PRELIMINARY RETAINING WALL STUDIES -NORTH ELEVA TION -FLA T RECESSED OPTION ARAPAHO BRIDGE CORGAN22 MAY 2003 AS ROADWA Y AND GRADE GET CLOSER CONCRETE PEDESTRIAN RAIL METAL PEDESTRIAN RAIL FORMLINER IMPRINTED ON RETAINING WALL :.,..---BRIDGE STRUCTURE I I o 1 ft. --.--FORMLINER PATTERN STEPS DOWN Ii' , I o 4 ft. PRELIMINARY RETAINING WALL STUDIES -NORTH ELEVA TlON -STEPPED OPTION ARAPAHO BRIDGE 22 MAY 2003 -CORGAN