\-) o ::. v, :r '\: 5-j Ci o (' ( J I-. " 􀁾􀀠 Arapaho Rd Conflicts Issues & Problems Bullet 􀁐􀁾􀁳􀀠::J"€-r"""( • Added Temporary 6' chain link fence @DWU plant. • Add Communication cable, re-route and tie existing irrigation to new controller, as well as add 13 new 14 gao Wires for future expansion at D WU pump station. • Add "Pardon Us" signs facing the hotels/motels. e Added TXU conduit profiles & stabilized sand backfill. • Additional Tree Removal e' Changes and holdups on 60" DWU water line. e Added 8" isolation valve @the storage building to allow work on the 8" water line to be performed during the day. • Relocated fence @storage building (sta 39+50) to allow work on the waterline and hydrant relocation. e Delete Railroad crossing from contract. • Relocate 8" water line @Storage building due to conflict with existing 24" Storm Drain. • Add flow fill @steel casing to protect pipe (in place ofadded bituminous coating) • Change Paint Systems for the Arch and Rail. e ModifY openings on stingers & add PVC conduit as well as 1 boxes. • Change all RCP pipe wi standard tounge and groove joints to a confined grooved joint between stations 0+68 to 6+00. • Modification of rebar connections for the U-beams on span #9. • Relocation of 12" waterline which is in conflict with lines A&B @Surveyor. • Furnish one portable Changeable message board. • Relocate irrigation line outside proposed construction limits @courtyard Suites. ; ..' • Relocation of Inlet A-I to the existing Drainage Flume • Delayed moving low profile barrier from phase I to phase II due to TXU not meeting schedule. • Redesign MSE wall #3 due to cross sections on the paving did not match wall drawings. e Redesign Manholes@lineASta 18+70 and line B Sta 19+01 from a Manhole wi a riser to a flat top manhole. • ModifY bottom of 9x5 box culvert to allow for elevation ofexisting gas line. ;-.. • Redesign parking lot Concrete to 6" from 10" • ModifY IOx6 box culvert @Surveyor to avoid existing 24" waterline. • Added Corrugated Metal Pipe and Drainage system to provide drainage to existing properties along along MSE wall. • Added dirt mounds @TXU conduits to existing buildings to get the proper ground cover. • Added two Lateral tie-ins @RCB after RCB was already placed. • .Added 450 LF of6" Curb & Gutter to control storm water. • Added Taps and Irrigation work at Surveyor, Midway, Comfort Suites and Addison Road. • Addition oflocating 8" Valve and replacement ofDriveway Concrete @Comfort Suites. • Wall Mounted Luminare type change on wall 3 &4 • Change in Trough Drains from Maximum I' depth to 4' depth. • Added closure pour @RCB Line "B" @Midway due to existing pipe not being at tie-in location. • Extension ofMSE wall #2 due to substantial grade difference between roadway and existing parking lot. • . Swap Stingers @Bent #9 due to deck blocking access holes on stingers. • Demo existing SBC manhole to allow placement of 12" sanitary sewer • Provide Police escort for beams. • Delay due to TXU work on Iines@Midway holding up Beam Placement .. RFI's • Missing horizontal aligrunent information for PI, PC, PT, ETC Coordinates. • Missing ROW Coordinate or station & offset information in the following areas. o North side from station 60+75 to 62+73.88 (sheet 16) o South side from station 60+75 to 63+50.88 (sheet 16) o North side from station 66+47.29 to 76+17 (sheet 16+17) o South side from station 74+51 to 78+32.69 (sheet 17) including bent point at approx station 77+45. • Missing cross slopes information from Station 66+85 to 85+50 (Sheet 48 to 51). • Missing information on the limits ofthe brick yard excavation. • Incorrect ROW information@stations 74+20.41 to 87+76.65 (sheets 17 to 19). • Discrepancies in offsets ofretaining walls 1 & 2. • Incorrectly detailed diameter ofsteel guide pipe for cylindrical socket on bridge cables. • Request for information on the bronze monument. • Discrepancies in the removal ofexisting concrete at the Rink. (Sheets 24, 59 & 63 • Discrepancies in the DWU line ofmounting a 6" valve onto a 12" flange. • Discrepancy in the plans and specifications as to which version ofthe NTCOG is to be used. • Problem with median curb grades causing large undulations in the roadway profiles. • Need alignment information on longitudinal weld for the Arch. • Addition of drop bowl assemblies at the sanitary sewer drop manholes. • Missing detail for grouted Riprap at inlets and headwalls. • Clarification of bent 9 and 10 dimensions. • Clarification of bent 9 beam seat elevations. • Discrepancies in beam seat elevations on bents 9,10 &13. • Adding "Town ofAddison" logo to the Manhole covers. • CI'lrification of bearing seat thickness. • Clarification on the I" conduit @Columns 8 & II o Is the conduit externally mounted. o If the conduit is poured in the co1= does it need to be RMC or PVC • Unavailable 790 kip strand. • Conflict between SBC phone lines and Retaining wall #2 • Clarification of Tie-In for 4" tree well subdrains. • Realignment of 10" line "B" sanitary sewer from sta II +52.57 to 13+60 • RCP pipe orientation in casing pipe, lines C and lateral A -13. • Change in dimension for bents 9 & 10. • Conflict with 10" all-release manhole and the proposed roadway paving. • Conflict between lateral B-7 and DWU 60" waterline (2nd go around)(RFI 40). • Conflict between 10" Sanitary Sewer line and 16" Water line @Midway Rd. • Changes to Trenched Footings going from 2' thick to 3" thick due to minimum cutting bar width of trencher's capable ofcutting to required depth. • Relocation of electrical and irrigation sleeves to avoid obstructions. • Information on specified voltage for the street and lighting circuits. • Revised grading and change in throat elevation ofthe y-inlet for lateral B-8. • Conflict with the drainage from BulloughlLykos parking lots to inlet A-4A. • Clarification that conduit run A-2 is routed in the south T-4 Rail. (Neg) • Confirm that wall offsets are to face of coping not face of wall. • Addition ofjoint filler between the structural retaining wall and the MSE retaining wall. • Conflict between the abutments and MSE wall panels due to the cantilever portion of the abutment is in the way ofthe panel. • Relocation of Sanitary Sewer Manhole in Midway Blvd. • Conflict between existing railroad crossing grades and the roadway prome grades of 4 inches in some areas. • Confmnation of grout thickness between the arch plate and the bolt template. • Provide information on the location and routing ofpower sources for load distribution centers (LDC) A @bent 11 & (LDC) B @bent 8. • Clarification of anchor bolt location in MOD A T -4 Rail. Rebar appeared to be outside the rebar cage. • Relocation of street lighting from the MSE wall to the T-4 rail resulted in conduit run under the T -4 RaiI. • Proposal to adjust street lighting to coordinate with T-4anchor bolt layout. • Review of pennant to picket tack welds requested by manufacturer. • Confirmation ofdimensions ofslab blister(sheet 285). • Relocation ofInlet A-6A because it was originally on high side of roadway. • Provide information on location of conduit for Luminaries on Wall RW4. • Relocation of 8" water Main and Valve from under wall #4. • Missing approach slab details. . .Aco. po..hq __Bc􀁩􀁣􀁬􀁾􀁟􀁟􀀠,_. . . . 􀁪􀀮􀁰􀀭􀁊􀀷􀀮􀁾􀀠9$".._. ._ 􀁉􀁏􀁜􀀮􀁾􀀮􀁏􀁾􀀠PhOI'\L rYl?! .. , 􀀬􀁎􀁡􀀮􀀬􀁾􀁾􀀠􀀢􀀧􀁾􀀻􀁾􀁟􀁟􀁟􀀮􀀮􀀠8dd.\.scrn ("Ita) 4fi9.:: 2zOj .. ,. 5iffl€: ..C'(,,::fdr'Mth a aass 5 TxOotJolnt Seal. We believe that this will allow fOC' the jill move as f\eeded and minimize water from entering the bIoGk out this acc:eplatlle? Page 1 433.1 RFI 􀁾􀀠433.1 to 433.2 l'l'EM433 JOINT SEALANTS AND FILLERS 433.1. Desaiption. This Item shB\! govero lb. material requi...,. menls for joint sealanls, backing _rials and joint fill.",. 433.2. Materials. The material. for this item shall conform to Ib" following: (1) Joint Sealant Materials. Joint sealant material sball be Ihe •1.... indicated. on Ihe p\aos or in Ihe goveming specifications. The various classes of ....I...t described herein shall be in .coon\.ance with Deparlmental Material Specification 􀁄􀁾􀀭􀀶􀀳􀀱􀀰􀀮􀀠Copies of specification D-9-6310 "'" availoble from Ihe Texas Department of TmnsportatloD, Director of MlIterial• ..,d Tests. 125 B. 1I1lt Street, Austin, TX 18101-2483. (l) Storage. Class I and 2 -'ants shall be stored at temperatures betw_ 40 F and 100 F. Class 4 and 5 -'ants shall be stored in ....led conw-s at a temperature of 100 I' or below and the material must be used within two (2) _nibs of receipt OD the project. (3) ClasseS of Joint SeaI...ts. (al Class 1. Two component, Synthetic Pol;ymer, Non-sq. The CQmpoIloolS shall be proportioned and mixed in 8l:COTdanee wilh tbe /IlIIllu&.cturer'• ....,.,mmendation9. (b) Class 1, Two Component, Synlhelic Polymer, Self·\evelillll· The comporumls sball be proportioned ...d mixed in a<:<:OrdBnce with Ihe lJI8Ilut'acturer'. 􀁾􀁯􀁮􀁳􀀮􀀠(e) Class 3. Hot Poured Rubber. This sealant shall be • tubber asphalt compouod whielt when heated shan melt to lb. propet _.istency for pouring and shall solidify on coolin, to .""'iont temperatures. (d) Class 4. Non-s&g Low Modulus Silicone. The material sball be a single compooent formulation nol requirinB addition of a catalyst. (e) Class S. Selr·\evelillll Low ModulllS SiJiame. The motorial shall be • single componenl formulation Dot requiring addition ofa catalyst. 700 _.,".",.(f) Class 6. Prtrormed lllint SWant (PJS). The preformed joint sealant shall be an extruded e!astomeric material having a Dlulti-oiumneled abape. 00 Class 7. Self·leveling, Rapid Curillll, Low ModulllS Silicone. The mo.teriaI shall be a two component, rapid curing, ""If·leveling, low modulua fonnulatioo. The components shall be proportioned and mi.ed in accordance wilh \he manufacturer's recommendations. The size shown on \he plans shall be the nominal width of \he sealant. The uncompJeSsed depth of lb. seal shall be equal to or greater tIuuJ the widlb • All preformed joint ....Iants ; ..ralled by the Contractor shall bave beeIl ptequalified for compliance with the requirements. Eacb size and cOldii"ralion of seal produced by a manufacturer mllS!. be approved by the Jlngineer prior to use on Department projects. For a sealant manufacturer to ptlIqualify and oblain approval of • sealant, detailed di""",sions and coofiguration of eacb size of seaJant and certified test reswts indicating colllpliance with Departmental Material Specification D·9-6310 and any I\lqtIimneals shown on the plans and specifications shall be submitted to the Engineer. S .. bmission shall be done ""fljci.ntly in advance of woIl< to allow for testing and evaluation of the material. The Engineel' will confiml by visual inspection that the sealant proposed fot instaUation is the ssme size, configuration and manufacture as shown on plans. The Engineer will examine the sealant for any undue clislortioltll, S\Ich as dissymmetry, warping, lhick webs or unevon width which are likely to impair Ihe performance of the joint. If the magnitude of lb. distortions are Nfficient to create doubt as to Ihe perfonnance of the sealant, \he I!ngineer may di""t tlIat the sealant be replaced or that samples representing the worst of tho lot be subjected to further testing to verify their perforlJl8llce. (4) Backer Rods and Badtlllll Materials. These materiols sholl be c.apablo ofholding the fluid sealant in open joints in place. In aU ""'""" Ibeae materials shall be ofsuch. type that will not bond to the sealant. Th. 'backing materials shall meet the requirements of tbe sealant manufacturer. Thoy shall be compressible type materia!s, such as closed-cell, resilient 791 t:: ---o ') Product Information Silicone Sealants FEATURES Easy to use All-temperature gunnability Unprimed adhesion • Seals irreguJar surfaces • High movement capabillty • Low modulus Fullyelastie Resilient • Good weatherability • Fast cure -typically taek-free surface in one hour or less • Long-life reliability COMPOSITION One-part, cold-applied silicooe that cures to • dorable, flexible, lowmodulus silicone rubber joint seal 1>011 􀀨􀁻􀀩􀁮􀁾􀁛􀁜􀀨􀁾􀀠Dow Corning® 888 Silicone Joint Sealant Low-modulus silicone sealant for new and remedial joint sealing applications in Portland cement concrete APPLICATIONS • Sealing transverse contraction and expansion joints, longitudinal, center line and shoulder joints in Pordand cement concrete (peC) TYPICAL PROPERTIES Specification Wri""" Please contact your local Dow Coming sales office or your Global now-Coming Connection before writing specifications on this product Test Unit Result As Supplied Color Gray Flow, Sag or Slump Nil Extrusion Rate grams per minute 90-250 Specific Gravity 1.450-1.515 SJdn..O'Icr Time,.t 25"C (n°F) minutes 10 Tack-Free Time, at 25"C (77"1') minutes 60 Cure Tune, at 2S"C C/1°F) days 7-14 Full Adlle.ion days 14-21 A. CuRd -after 7 days at 25"C (77"1') and 50 pel'Wlt RH Elongation, minimum percent 1200 Modulus, at 150 percent elongation, maximum psi (kPa) 45 (310) Durometer Hardness, Shore A points 15·25 Joint Movement Capabmty, +100/-50 percent" 10 cycles No failure Adhesion to Concrete. minimum elongation percent +500 DESCRIPTION Dew Corning" 888 Silicone loint Sealant can be used as the original sealant in new concrete construction or as a remedial or repair sealant in old construction. In new construction, it provide, lbe extra insurance needed ifall the "shrink" or contraction cracks do oot occur during lbe initial "weak· eningfl step. Thus, two or three conerete lengths act in unison, stressing a sealant two or three times lbe design dimensions or movement. Because of its low-modulus characreristics and good exrension/C(]mpression recovery (+1001·50 50 percent oforiginal joint width), Dow Corning 888 Silicone Joint Sealant gives outstanding performance in highway, airport and bridge joints in which high movement occurs. Highway concrete contraction! expansion joints are generally sealed to preveDt erosion ofpavement sub-base andlor corrosion of metal tie bars embedded in lbe conerete. Such corrosion results from water and deicing chemicals entering lbe joints at the pavement surface. Sealing of highway joints also prevents spalling and breakage of concrere along the slab edge, which occurs when notICompressibles (dirt, stones and/or ice) are forced into or form in lhe joint. For use in repair Or remedial applications where other joint sealing materials have fulled hecause of excessive movement or poor weather.. ability, Dow Coming 888 Silicone Joint Sealant can be used to seal irregularly shaped andlor spalled joints. Thus, the joints do not need reforming before sealing. These joints should be dry and free of all old sealing eompounds. Benefits Easy to use -one-component, cold· applied, ready-to-use as supplied; no mixing required; disponsed directly from bulk container into joint by band or with an airpowered pump. • All-temperature gunnabilityconsistency i. relatively unchanged over normal installation temperature range. Unprimed adhesion -primer 1S not required for bonding to pcc. For optimum adhesion, the surface must be clean, dry and frost-free. • Seals irregular surfaces -can be used to sea!joints where spalls have occurred, provided adequate contact is made between seafant and substrate. • High movement capability -the sealant will perform in a continuous joint movement of +1001-50 parcent. In new construction, it will take the 25 percent movement ofeach oftwo or three slab lengths working in unison before aU the "shrink" Or contraction cracks occur. • Low modulus -the sealant stretches 100 percent in the joint with very little force. This places very little strain on the bond line or joint wall, which maximizes the probability of a successful seal with continuous joint movement. Joint movement caused by temperature, traffic and faulting requires a sealant that does not strongly resist stress andlor shear. Fully elastic -the sealant can be stretched to 100 percent or compressed to 50 percent of the joint bond width and held there. When released, it wiu recover 95 percent or greater of the original dimension, The extension and/or compresslon can be repeated many times and the sealant will resume its original shape without splits or cracks. Thus, when properly installed in a highway contraction joint, it does not 􀀡􀀧􀁰􀁵􀁭􀁰􀁾􀀧􀀠out ofthe joint during compression. Nor does it split, crack or lose adhesion during extension. • Resilient -once cured, the sealant prevents stones and other noncompressibles from entering the joint by "squeezing" them out as SOOn as the force pushing these noncompressibles into the sealant is removed. • Good weatherability -its 100 percent silicone rubber is virtually unaffilcted by sunlight, rain, snow, ozone or temperature extremes, • Fast cure -typically, the sealant win have a tack-free surface in one hour or less. With this fast cure and recesscdjoint design, the road ean be opened soon after sealing in most applications. Figure 1: Good Joint Design • Long-life reliability -under normal conditions, cured sealant stays rubbery from -45 to 149°C (-49 to 300°F) without tearing, cracking or becoming brittle. Applicable Standards Meets andlor exceeds ASTM D 589396 "Standard Specification for Cold Applied, Single Component, Chemically Curing Silicone Joint Sealant for Portland Cement Concrete Pavements," Type NS (Non-Sag). In addition, tha Federal AlIiation Administration has published the "FAA Engineering Brief 36 -Silicone Joint Sealants." This publication approves the use ofthese materials in aitfield situatioos. Meets and exceeds botb Federal SpecificationsTI'-S-00154 3A Class A (one-part silicone sealants) and IT-S00230C Class A (one-d to allow fur 􀁳􀁵􀁲􀁦􀁾􀀠􀁾􀁩􀁯􀁵􀁳on the bottom and to provide :n:x.mt for old $CIlMt to 􀁾􀁰up from hduw duJin3 reMbililation worlt in the 􀁾􀁥􀁴􀁾􀀠specifications that require a iowmodulus sealant with high movement capability. HOW TO USE Please refer to the PocJret Installation Guide for additional infonnation on applications, preparation and installation infonnation. Low-modulus Dow Corning 888 Silicone Joint Sealant easily withstands extreme joint movement when properly applied. The sealant will withstand 100 pernent ""tension and SO percent compression ofthe original joint width_ However, the recommended joint movement design is for ;as percent (SO percent total) and not at the sealant limits_ This difference ensures a successful seal when job site joint widths are different than designed widths. Therefore, the joint design dimensions should be less than the ultimate sealant capability. A thin bead ofsilioone sealant will accommodate more movement than a thick bead. Dow Corning 888 Silicone Joint Sealant should be no thieker than 112 ineh (13 mm) aad no thinner than 114 inch (6 mm)_ mm)_ Within th_Iimits, the sealant width-to-depth ratio should be2:L In all cases, the sealant must be =essed below the pavement surface atleast 318 inch (9 mm) with 1/2 inch (13 mm) recess being acceptable in wider joints (see ThbJe 1)_ Consideration should also be given to other possible road-working operations, such as diamond-grinding of the surface. Activities ofthis type would require the sealant bead to be recessed even deeper. Dow Corning 888 Silicone 10int Sealant is a norn;ag sealant. This allows its use in vertical curb joints as well as horizontal joints-Being a non-leveling 􀁳􀁥􀁡􀁬􀁡􀁮􀁾􀀠Dow Coming 888 Silicone Joint Sealant must be "tooled" to eos\lfe good eontact and adhesion as well as to control sealant depth and provide a recessed surface. Several deviees can be used for tooling. Among the simplest and easiest to obtain is the expanded closed-cell polyethylene foam backer rod, which must be larger than the joint width. In new construction where the joint is • new cut, • shallow cut is recommended where the backer rod is placed on the "shelf" or bottom ofthe joint (..,. Figure 1). Recommended depths are shown in Table 1. This design provides a f!l1l1 support fur sealant tooling, making the sealant easier to install, and further ensures good sealant/concrete contact A shallow cut design also saves saw blades and time. In repair work: where previous sealing materials bave been ofe.joint mling type rather than a joint sealing type, or where the joint is not broadened by sawing, a standard joint design is recommended in whieh the backer rod is slightly above the shelf. Extra spaee (114 to 112 inch [6 to 13 mm]) between the bottom ofthe backer rod and shelf should be provided to allow for possible ''pumping'' ofold joint filling material from the bottom ofthe joint. It is recommended that care be given to selection ofproper oversized backer, so that a finn tooling support is obtained (generally 114 inch [6 mm] larger than the joint works quite well). Dow Coming 888 Silicone 10int Sealant is part ofa system that must include the proper hacker rod and proper installation procedures. The hacker rod must be expanded elosedcell polyethylene foam. Where irregularly shaped joints exist, backer rod that is open-cell with an impervious skin is recommended to ensure a tight fil-Several other back-up materials (paper, fibrous ropes and open cell foam) are available, but have proven to be unacceptable. There are several manufacturen; of closed-cell polyethylene foam and any may be used. Please refer to the Pocket installation Guide for more infonnation on applications, preparation and installation information. HANDLING PRECA1ITIONS PRODUGrSAFE'lYINPORMATION REQUIRED FOR SAFE USE IS NaT INCLUDED IN THlS DOCUMENT. BEFORE HANDlJNG, READ PRODUCT AND MATERIAL SAFETY DATA SHEETS AND CONTAINER LABELS FOR SAFE USE, PHYSICAL AND HEALm HAZARD INFORMATION. mE MATERIAL SAFETY DATA SHEET IS AVAILABLE ON THE DOW CORNING WEBSITE AT WWVWOWCORNING.COM. OR FROMYOUR DOW CORNING REPRESENTATIVE. OR DISTRIBUTOR, OR BY CALLING YOUR GLOBAL DOW CORNING CONNECTION. USABLE LIFE AND STORAGE When slored in original, unopened containers between O·C (32°F) iIlld 32·C (90·1'). Dow Corning 888 Siliconc Joint Sealant has a shelfUf. of 12 months from date ormanufacture. K£ep containers tightly closed. Retl:r to product packaging for "Us. ByDat.:· PACKAGING Dow Corning 888 Silicone Joint Sealant is supplied in 29-fl oz (SS7-mL) disposable cartridges, 4.5-g01 (I7-L) bulk pails. and SO-gal (IS9-L) bulk drums. LIMlTATIONS Dow Coming 888 Silicone loint Sealant is not ",commended for conditions wltere continuous waterl moisture exposure is expected. It should not be applied in to1alJy confmed spaces wbere the sealant is not exposed to atmospheric moisture. The sealant should never he applied to wet or damp concrete or installed during inclement weather. New concrete should be allowed to cure and dry for at least 7 days of good drying weather. For each day ofrain that occurs during that period, an additional day should he added to the 7-day drying time. For "Fastraek" or high early concrete Illi:xes, please contact yeur Dow Corning Technical Service Representative. The sealant head should he recessed below the pavement surface to prevent abrasion from \:n!.ffic and snow removal equipme.nt. The adhesion to substnlles other than PCC should he checked before performing full-&ale sealing. Contact your Dow Corning Technical Service Representative. This product is neither tested nor represented as suitable for medical or pbannaceutical uses, HEALTH AND ENVIRONMENTAL INFORMATION To support customers in their product safety needs, Dow Corning has an extensive Product Stewardship organization and a team ofPro duct Safety and Regulatory Compliance (PS&RC) specialists available in each area. For further information.. please see our 􀁷􀁥􀁢􀁳􀁩􀁴􀁥􀁾􀀠􀁷􀁷􀁷􀀮 􀁤􀁯􀁷􀁣􀁯􀁭􀁩􀁮􀁧􀀮􀁣􀁯􀁾􀀠or consult your local Dow Corning repteSentative. LIMITED WARRANTY INFORMATION -PLEASE READ CAREFULLY The information contained herein is offered in good faith and is believed to be accurate. However, because con.. dirio!lS and methods ofuse ofour producl$ are beyond our control, this information should not he used in substitution for customer's tests to ensure that Dow Corning's products are safe, effe<:tive, and fully sausfuctory for the intended end use. Suggestions of use sball not be taken as inducements to infringe any patent. Dow Coming\; sole warranty is that the product will meet the Dow Coming sales specifications in effect at the time ofshipment. Your exclusive remedy for breoch of such warranty is limited to refund of purebase price or replacement of any product shown to he other than as wartanted. DOW CORNING SPECIFICALLY DlSCLAIMSANYOTHER EXPRESS OR IMPLIED WARRANTY OF FITNESS FORA PARTICULAR PURPOSE OR MERCIlANTABn.ITY. DOW CORNING DISCLAIMS LIABILITY FOR ANY INCIDEN· TAL ORCONSEQUENTIAL DAMAGES. 􀂷􀁾􀁉􀁴􀀭􀀽􀀭􀁾􀀺􀀬􀁳􀀻􀀦􀁾􀁾􀁉􀁉􀀧􀁟􀀭􀀭􀀢􀀢􀀬􀀬􀀡􀁪􀁯􀁪􀁪􀁾􀀬􀀻􀀡􀁉􀂷""....,,,.,,;,,*iI;,􀂷􀁬􀀧􀀭􀀭􀀭􀀯􀀮􀀮􀁩􀁩􀀺􀀬􀁡􀁾􀀢􀀢􀀢􀂷􀀧􀁉􀀭􀀭􀁾􀀭􀀧􀁊􀁯􀀡􀀮􀁉􀁉􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀮􀁊􀀭􀀭􀀭􀀭􀀭􀀭􀁉􀁬􀀡􀁉� �􀁈􀁉􀁎􀀬􀀠􀀭􀀭􀀭􀀭􀀭􀀭􀁌􀀭􀀭􀀭􀀭􀁾􀀭􀁾􀀮􀁉􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀀮􀀭_:;...;----------lII-1 <0 Ul I-4" MIN, --, r-411' MIN. ---.j (<;J I G: HviS ( • 􀁾􀀠c • • IIa TG-3 L ARIIPAHO ROllO (WEST) 7 • >"," ,JPRELIMINARY,' ",RENbfNG CIT'( APPROVAL ," .. :>PRELIMINARY ,PENDING ""RAfLAMEsrCA' A8PROVAL:. ..' . : T' ,;' . : DDT· 􀁾􀁘􀁩􀀧􀀠·.·,l!Clml$: APPROACH CIRCUIT DISTANCE CALCULAliON '. __NGTIHE :III 5E& !'LUll TIME _ a £MAIU OISTIINCIi >3\1' " 8 I.. SEC _$ I'U!If£D V_ TIME Iiii..US tIME FOR _ REII'OHIiE ' 38 "" SEC 4iIU if'Lus TIME __Ie 􀁐􀁒􀂣􀀺􀁾􀁉􀁜􀁉􀁎􀀠/0 .1;lt!'i; EtlIMI.$ CIRCUIT __ "HI!. lt1. IiI43 5E& TIllES MfoXIIU4 PLANNED T!lAIN SPEEQ 11TIMES !lATU! I/f' FEET PER SEClNl TO MIl.! PER IQJII HIlI iEOOAi.& __CIRCUIT DISTANCE WITH Am' FRACTIONAl. VALUE lNCA£ASIiD TO FULL IMT 143IIn (",110 ·. '''' 'If' \ I I 1 'C. (/'8' 4 􀁾􀀠M.P.... ARAPAHO ROAD ("/CST)00'1 "'I2l 'I7eP MERICA, INC ---.-... ---􀁾􀀠\IIIEIDIIIlIID CAlI.! DGNO 􀀧􀀭􀁖􀁟􀀧􀁾􀀢􀀢􀀢􀀢􀀢􀁟􀀬􀁶􀀬􀀭􀀮􀁶•• ,, 10/11/2004 2:20:16 PM •• "PENDING CIlY APPROVAL' ' ." ',' -.. 0,' ...... ., ;'Y*"'--"-,,' . :'-􀀬􀀬􀀭􀀭􀁾􀀭" 􀁾􀀧􀁟􀀢􀁾__􀁾_____􀁾􀀠.,If_IJI,sqllle!<4sr IV)'4" f'"/f!1ft r.1t:) ( I • tiIlIEJJ\. a'l1£=rr.Drllt' _Ill< IS '16 AVB mx UM.\lS6 ' 2. 􀁾􀁾􀀦􀁾IJm1ffiNC=1.B' T"= FDR 3. _ITTER I/llfE TI AMI TI NUST lIE RUN TO TIE 1'!tIICK _OW SIlllI OF CRDS6111D. 􀀼􀁾􀀠SEC 4 IIEC '1'41 SEC 18_ UJlS ElIUAL6 AI'PI1IIACIf CIRCUIT OI$TI\HCE WITH lINt I'IIACTlIlNAL YAI,\I! _ASEO TO FILL UNIT leMFT _IZEA--AIII!E$TER TO _ 􀀮􀁾􀁖􀁾􀀽􀁾􀁆􀁄􀁄􀁔􀀠ME TD BE _0 FROM TIlS APPROACH CIRCUIT DISTANCE CALCULATION P'RE-...lMINARY, 􀁲􀁁􀀧􀀬􀁾􀁾􀁾􀀢􀀧􀀦􀁩􀁾􀁾􀀱􀀠􀁾􀁾􀀻􀁲􀁾􀀽􀀡􀀺􀀺􀀻􀀧􀁈􀁩􀁩􀁣􀁬􀁪􀁕􀀼􀁅􀀮􀀠􀀺􀁁􀁉􀀺􀁾􀁟􀀧TMQI: \ BASE V_IHO TJIiIE 38_ 􀁾􀁾􀀠P\.US TIME FIlII CU;_ OllnN«:£ ) 3!Y ';1 SEC I!llUAI.II PLANNEO _ tIlE {£ ( .H' P\.US TIlE FOR I!IlUlPMI!IIT I!EIlPIIIISE Pl.US TIME FOR TIW'IC PIIE·EMPTION CI EQUjU ClRCIIIT Al'PR(IACH TIME ,":.1S)TIMES __ IUllNED TltAIN 8PIID .......... TIMES RATIO OF mr !'Ell _ TO MILE PER HOOII \ \\ \ \ \ '=,,...,,---------J'V/HIAtllI1 􀀷􀀿􀀩􀁦􀀢􀀮􀁴􀀱􀀬􀀭􀁾􀀭_ 􀁾􀁃􀁌􀁴􀀡􀀧􀁉􀁦􀁴􀀺􀁴􀁁􀁾􀀠􀀧􀀭􀁾􀀠􀀬􀀬􀁟􀁾􀁾􀁐􀀯􀁾􀀢􀀢􀀧􀁉􀁦􀁉􀀱􀀯􀀱􀀱􀁴􀀡􀀧􀁅􀀠IS. '" '75 J' -....􀀧􀀭􀀮􀀮􀀮􀁶􀀭􀀮􀀮􀀬􀀮􀁾􀁟􀁾􀀮 􀀬􀀬􀀢􀁾􀀬􀀮􀀬􀁟􀀠,/GAllJl.CINl UYCIlT 􀀮􀁾􀀠'" 'N' d 1\ fa 􀁾􀀠'C' \ \ \ II31II _N 5OUNO BLVD.''''' BOCA RATON. FLORIIlA ," '(tZ).= " -" 􀀢􀀧􀀭􀁾􀀬􀀠.I "'-.c· ". " :,' . TO ...􀁾􀁾􀀢J' 1>,gf)!.WI . IUIAD !liotUc/, " "---.-" ---------._I>IIU DGNO CABlE & FOUG\nDN PI.A/j ARAPAHO AD. lEAST> ADDISON. TX ''l21 q71!1t MILEPOST .."" ", 􀁾􀀠IIOTIl,iI:, 􀁾􀁪􀁦􀀩􀀧􀀭􀁜􀀠􀁤􀁾􀀠("'.ir r..IYe ) ....􀁾􀁲􀁴􀀮􀁊􀁃􀀮􀀠WI -5t> '1"0· . I -3#11.4 T;«!.AC.":"L '/,,,, AflAPAHo 􀁾􀁁􀁲􀁲􀀠\ HoUSE. . ./1'I1J;r '11/􀀱􀁖􀁲􀁊􀁴􀁦􀀮􀁾􀀢􀀧􀁩􀀹􀀠I "Q .t ,n- fliPIIJII'( 􀁾􀀠... .. ...D.::-» 􀁾􀀠􀁾􀀠c 􀁾􀁾􀀠􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭"L .. WHEEL STG' 267.5' --" I' ,I i 􀁾􀀠, !L ____􀁬􀁟􀁾􀀠......._-! I'" \ \ •, { PROPOSED CONCRETE PAVEf.£NT (NO CURB ANO CUTTER) , .n " 􀁾􀀮􀀮􀀮􀀮􀀻----;;;;;; -------.:::.'.􀁾􀁜􀀠MATCH A 1.; (. .. >􀁔􀁎􀁓􀀷􀁾􀀠.b, 'yrE '1/􀁉􀀽􀁉􀀩􀁬􀁬􀀬􀀬􀁾􀀠,5n. 5:. +-+0-􀁾􀁔􀀠7 I " :-,;1, +-:-1'\. \, ABSOlUTE SYSTEMS,LTD , \ \ ANY VERTICAL OBSTACLE (CURB. BUILDING. STAIRS. 􀁅􀁔􀁃􀀮􀀩􀁾􀀠PLAN SECTION VEHICULAA WHEEL STOP DETAIL NOT TO SC;lLF; REBAR P1N tz PER STOP) NoTE: SEE SHEET C..1 rOO PARKING GRiDlNC PU/'I, LEGEND PRCPOSED SQ.IO .." WHITE STRIPE PRCPOSEO P}RKlNG LoT PIJ'IKING MBNA The HNTE' Ce:n;:::::!1!e: 15150 􀁓􀁵􀁲􀀧􀁊􀁾􀁜􀀧􀀺􀀺􀀺􀀻􀀠􀀺􀀺􀁾􀁶􀁤􀀮􀀠TC;..:-pM!"'.C ("912) 361-['054􀁆􀁮􀁬􀁊􀀡􀁮􀀡􀀧􀀨􀁾􀁲􀀼􀀻􀀠􀀡􀀧􀁬􀀮􀁲􀁲􀁨􀁩􀁴􀁾􀁤􀀩􀀧􀀻􀀠Plt\tln,,;;. ¥="1!t:)';ifl".i!t' (g7?; 1t-:HlOfi=-i wwwJmtb.com HNTB Job F. 2576B" Arap.mo Roud !:'haslO 111 VIA Hand Oeliyeroo july 14.1uilS To:: $leYtt CilUkhianLetter Gf MNTRTo"h"""!'1 ofAddis-onT'iiiismiHai --...􀁾􀀠.P.U.BOA%iG 16001 Westgrove Drive Addison, TX 7,nm We are forwarding to yOU! F:-;!ir!1i;jp,> R2pcrts Chor Blvd. Addison TX. 75001 TelephOne (972) 361-0064Facsimile (972) 361-0065 www.hntb.r::om HHT£I Job # YIA 25768 • Arapaho Road· Ph...ill lJ:.nd De&vemI 0_ Ju1y6,2005 To< Steve ChutdlianLefler of TownofAddison =-tNTBTransmittal P.O. Box 9010 16801 Wettgwve Drive Addloon, TX 75001 ShopDzawingsl Calalog Cub Submittal> w....... lorwanlll'l9 tD you: Estimates Plan. X Prints Reports Shop Drawings Samples __ 􀁃􀁾􀀮􀁮􀁧􀁥Order Disk Copy of lefulr Book other # of Copies Drawing # last Dated Code Description 2 ISubmittalSl.l 6/28/05 -Roadsaver Silicone SL PrimaWCrako ( Silicon_Joint Compound) 2 I SUbmittal821 6/28/05 HBR Backer Rod -PrimatefNomaco (Backer for pavement joint) 1 . Pages 1to ji'" Sll6/0S Prequalified foint Sealers -TxDOT Those ..... t,..nsmitt"'" For approval As requested Copies for distribution 􀁾 For your use Resubmit 􀁾for Review & comment Return Copies for review No exception taken Corrected prints Submit Amend and resubmit Make corrections noted Ple........te: 􀀩􀀺􀁴􀁾􀀹􀁾􀀠􀁾􀁴􀁯􀁉􀀠File ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste.103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28. 2005 Submittal # :,-1___-=82:;..:.,1___-' To: Attn: HNT8 I Town of Addison 16801 Westgrove Addison, Texas 75001-9010 (972) 450·2886 GuyVan-Baulen Project: Arapaho Road Phase III New Submittal: X Re-Submittal : NW# 204059 Engineer: HNTB Submittal Specification Reference: Description of Submitted Item: H8R Backer Rod Manufacturer/Sub/Supplier: Primate I Nomaoo Related Section /Drawings: Additional Comments: Lm ________-'Ad=d"'is o"'n'--__-'____---'Backer ROO: for the eRe? Paving Joints Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as otherwise Engineer's Stamp Indicated." Sign: Title: Asst. Project Manager Reviewed by: Andrew Schneemann Date: June 28, 2005 Copy: -------------------p.s PRIMATE CONSTRUCTION INC P.012B 05 01:53p 􀁕􀀢􀀧􀁌􀁬􀁊􀁾􀁒􀁾􀀠􀁐􀁾􀁏􀁄􀁕􀁃􀁦􀀧􀁓Jun .. _. w_ 􀁾􀀳􀀠􀁾􀁾􀀻􀁾􀁾􀀠􀁾􀁴􀁬􀀠8V. 􀁾􀀮􀀠7136561032 BACKER ROO 􀁉􀁾􀁾􀁾􀁅􀁾􀁾􀁂􀁒􀁑􀁐􀀮� �'Ii.. : J! TYf>I! 1C -Cyfirll:irical. llexible saal",,! bacII!ngs tJOmtlOllI!d preduminantly cd do6ed oen malerial perASTM C 1330, for NOMACO usa wilh cold IIPPfied sealants FORM: ROi.rid Foam Rod TEMPeRATURE LIMITS: 045'1" to 100'F SltVh tt DlLI-t)/P"tl.l","",,,',, "··'·W· " .. \1....,<;.' .. ;'"•.,' 􀀢􀀧􀀧􀀨􀁉􀁾􀂷􀁉􀁙􀀠'11 􀁾II i ! Jl E NOMA SPEC SUBMITIAl SHEET II0000pooslng (No. "'-, IICM',*",,"-""1 ('II; v:r u ;liS' 10 21>00 762 2 SIZE SIllEC'!ION (Tot>Ie 1) 􀁉􀀧􀁾lIIze 􀁾􀁏􀁉􀀧I$ln1jXlll>o I, '" 􀁾􀀠con\i'Ol.lt1a depth o/1he ow!ant boad. ft moot bo OIIeni!:ed lo ft. Ughlfy InIo 'he jo\'1t. and 1\t1c. 000 as a􀁜􀀺􀁬􀁯􀁮􀁤􀁉􀀩􀁯􀁾to p!eVen\ botIom-si:le se m.!arial rom IJ1e jOi1t I!ces. Wfe bru!/'ing. SilIldblaslirl;l. high-ilrestur6 wa1er, or any com· bh!lIlen 􀁯􀁦􀁾􀁯􀁇􀁵􀁥􀁳sholJld be used to lOO1OVe conIaminants Ill· rnalni'lJ ()I1ihG )011'\ 􀁾􀀠 be cIeiIn and dlywten Ihn!leW 􀁾􀁮􀁴􀁩􀁳inslaIi'!O. In 􀁾Old joinlS. aaCl\1 􀁾􀀬􀁾or!ilermust 􀁢􀁯􀁾􀀮Tl1lIcan be!dule l:iu deplh recomo'16I'lWd by !he SI!/lIa.,1 rIl!lI1llfacl,.er will a b01l1 kxl orroller. Rei... to _,""1\vfat;· 􀁾reoorT'IlK:!i1 <00 SS2 36D 7.0 ,« PRECAUTIONS 00 J\ot 􀁰􀁵􀁮􀁣􀁴􀁵􀁲􀁾􀀮􀀠over compress cr strelch H8R+-duflng llitierw lion. 00 ""t uso wlln hOI applied 0.a'81\1$. rests for b.'· gassing of oold applied '''DIDOIS shall be "",de rn a.:oordance with ASTM Tesl Melr.Od C 1253. Genlonl compatibili\y should "" oonfirmed by the sealant manufacturer. CompaUbllily char· acteristlcs 􀁯􀁦􀀮􀁾􀁥􀁡􀁬􀁡􀁮􀁜􀀤􀁬􀁮􀀠contact With sM••n! backings call be determined by ASTM T".t Methort C 1087. ,m -..'n -I ••" ...... ' ... 1 .,..J ..... ! 12 • 33. 259 "18"1,18"1'31" loe llf';dS'x3'" 􀀱􀀲􀁾􀀠IS"lt18")::,!,/N '68 12"x22)( 74flO 1,<22">< 14" 7J 12')c22",.. lit .. To ensure agood sealantllond.]I:illts.l1\I1It 􀁌􀀮􀀮􀀻􀀻􀀮􀀮􀀮􀀮􀁌􀀮􀀮􀀺􀀮􀀺􀀺􀀮􀀮􀀮􀁴􀀮􀀬􀀮􀀻􀀺􀀮􀀮􀀮� �􀁴􀀮􀀮􀀮􀀮􀀺􀀮􀀺􀀺􀀮􀀭􀁊􀁌􀀮􀀮􀀮􀀺􀀺􀁾􀀮􀀮􀀺􀀺􀀮􀀮􀀮􀁌􀀺􀀺􀀺􀀮􀀮􀀺􀀮􀀺􀀻􀀺􀀺􀀮􀀺􀀮􀀮􀀺􀀮􀀻􀀻􀀮􀀮􀁊􀀻􀀮􀀮􀀺􀀺􀀺􀀮􀀮􀀮􀀺􀀮􀀺􀀺􀀮􀁊􀀠􀁾􀀠 ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640·3898 FAX: (817) 640·8734 SUBMITTAL Date: June 28. 2005 Submittal # :LI___-=.82:::,.:..1___-' New Submittal: X To: HNTS I Town of Addison Re-Subrnlttal : 16601 Weslgrove Addison, Texas 75001-9010 Project: Arapaho Road Phase III NW# 204059 (sn) 4S0-28es Eng;neer: HNTB Attn: Guy Van-8al.lIen Submittal Specification Reference: Description of Submitted Item: HBR Backer Rod ManufacturerlSublSupplier: Primate I Nomaco Engineer's Stamp Related Section I Drawings: Additional Comments: BaCker Rod for the eRe? Paving Joints Contractor's Certification "Having Checked this submlss!on, we certify -that it conforms to the requirements of the Contract in all respects, except as otherwise Indicated." Sign: l1ne: Asst. Project Manager REnfiewed by: Andrew $cl1neemaOrl Date: June 28, 2005 Copy: p_B281-441-3414 PRIMATE CONSTRUCTION INC 28 05 01,53p -,Jun .. _. 􀁾􀁾􀀠􀁾􀀷􀀠􀁗􀁾􀀻􀁾􀁾􀀠􀁾􀁴􀁬􀀠713686H332 BACKER ROD 􀁉􀁾􀁾􀁍􀀺􀀠􀁈􀁂􀁒􀁾􀀠l.:, II TYl'I! I C -CyIIndriC$1. 􀁡􀁥􀁾􀁩􀁢􀁉􀁥saal"nl bacIIIl'l\IIl 􀁾predominantly CI e!oeed 􀁣􀁥􀁾􀀠􀁭􀁡􀁴􀁥􀁾􀁡􀁬􀀠per ASTM C 1330, kit' usa \\;Ul COld I!PPfied sea\arlls FORM: ROlI'Id Foam Rod TSl'iPERATUREUMITS: 04S'F 10 16O"F NOMACO NOMA SPEC SUBMITTAL SHEET SIZE SElECTION cr_l) 1'l1»li'5/Ze MIt 11".-:, 􀁾􀁩􀁬􀀧􀀱􀂷􀀠II,,!,} , (U" .... r \J"" .. 􀁉􀁾􀀮􀀢􀀬􀁩􀁬􀁤.. '"I' -r,', 􀁾􀀠I I,e' 􀀢􀀧􀀭􀀧􀁾􀀠" .'rn!'" Iy 'I'), f' ':4' \'" I vJ 3110-1\)lltss 1/4" • 3IS" ! 10 11113 :!f8" 1& ,,'t1116' 13 31"1" i 19 '2 71S" [m l' 1fe-I􀁟􀀮􀁾􀁧􀀠􀀬􀁾􀀢􀁓􀁉􀀸􀀭I 41 2" : fit 2112:-\-" 04 3000 26CXl 1550 1100 e50 5SO 400 5S2 360 740 1... 1091 ?G:! 472 l:l' ,09 199 1122 HiS 110 73 . '.􀁾􀀠. 􀁕􀁉􀀢􀀧􀁉􀁉􀀻􀀱􀀸􀁾􀁸􀀳􀁖􀀠U'·l. 􀁴􀀸􀀢􀀢􀀳􀀱􀁾􀀠le·lIHS'l.01'" Hr.18,,),3i12",22-' H' 12 \ 12 : lZ 'Il. la • 18 I$ 18 ! a ! mn fl!1ea5e agents, OJrlng CO!1lJOUIId 􀁾􀀬􀁬􀁡􀁬􀁬􀁡􀁾􀀮􀀠or arry b"ei;;n!1'\l!\!1ials FmeI1tt wvedi.linlS shwld be washed v.ilh wal!!r inmGaiaelt al!erward to m<11OvC ar>J Ico$e M'l6blriaI tom \he jor1t fac:es, Wre bnJ!i'IitIg. S811:!bIasIirg. 􀁾􀁨􀀭􀁰􀀡􀁥􀁳􀁳􀁵􀁲􀁥water, or rrjlre&llOl1 i usea fOrUlIs JlUrp:lSe must 􀁢􀁥􀁥􀁱􀁾wllh veps kit' ""nova! of\lII and lTXlistulll. Inslan Il19 bQcI(llI" /Q r=1t111r:' uso wltll hot applied sealalllS, lasts 'Of 1Mgas.lng of cold applied ""ttlant ••hell be "'ade In acoon:1ance with ASTM To.! Mett.od C 1253, Sealant 􀁣􀁯􀁭􀁰􀁡􀁕􀁵􀁩􀁬􀁾􀁹􀀠should be """finned by Ihe sealant manufacturer, CompaUblli1y char' acterisUcs of.l"'alanIS In contact Witil sealani baclt ..,_....,. <>I 􀁾􀁾􀀬􀁭􀀮􀀮􀀢.."\II.fIIl,t"'<:l! 1i"t',('lIJiI'&h.UU,1 Hot oftlt' ",1II1i.11)1. ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28, 2005 Submittal # ,1'-___.::.81:..:,1'-__---' New Submittal: X To: HNTB! Town ot Addison 􀁒􀁾􀁓􀁵􀁢􀁭􀁩􀁴􀁴􀁡􀁬􀀠; 16801 Weslgrove Addison, Texas 75001-9010 Project: Arapaho Road Phase III NW# 204059 (972) 450·288. Engineec HNTB Attn: Guy Van,:-i3aulen Submittal Specification Reference: Addison Description of Submitted Item: Roadsavet Silicone SL Manufacturer/Sub/Supplier: Primate I Crafcn Related Section I Drawings: Additional Comments: Silicon Joint Compound for Concrete paving. Roadsaver Silicone SL Is on the TxDot Approved material List for Concrete Paving Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contfact in all respects, except as otherwise indicated." Title: Asst Project Manager Reviewed by: Andrew Schneemann Date: June 28, 2005 Engineer's Stamp Copy: p.2 Jun 28 05 01:51p PRIMATE CONSTRUCTION INC 281-441-3414 PRODUCT DATA SHEETCRAFCO:NC ROADSAVER SILICONE SL AN IEIIQONII' CQMPPNf PART NO. 34903 420 N. Roosevelt Ave •• Chandle-r AZ 8522.6 JANUARY Zoo4 1-600-528-<1242 • (602)27600406' FAX (480) 961·0513 www.crafco.oom READ BEFORE USING THIS PRODUCT GENERAL Cmf<:o RoodSaver Silicone SL is a low modulus silicone which offers the performance and durability characteristics ofconventiorull silicone with 1he ease of installation 􀁯􀁦􀁳􀁥􀁬􀁦􀁾􀁬􀁥􀁶􀁣􀁬􀁩􀁮􀁧􀀠materials. Crafuo Roadsaver Silicone SL is supplied as a ready to use one component moisture curing system which provides a: lasting and flexible seal. C'ra!co Roadsaver Silicone SL offet'S outstonding weathering resistance; remains 􀁦􀁬􀁾􀁩􀁢􀁴􀁥􀀠down to remperatw"ei as low as -500F (..46°q. is jet-blast resistant and will maintain field serviceabitity when exposed to intermittent fuel and oiI spills. It bonds strongly 1.0 concrete joints without the usc of a primer. Ccako Roadsavtr Silicone SL can be used in aU typical concrete joint appJi<;;ations on hlghway and airfield pavemenlS in all climates, RoadSaver Silirooe sealant is oompatible with aspllal( paveme.tlr. RoadSaver Silicone SL is easily applio1lo wncrete joims using bulk dispensing system uuils such as those available from manufacturers including PyIe&'Graco and Johnstone. The leveling chatacteristics insure that the required joint wetting for development of appropriate adhesion occurs during application. no tooting Is required. USAGE GUIDELINES RoadSavet" Silicone SL pav""enl 'empernrure High Tcmpernture Grnde ("C)perfomumce limits at'e 81-46 fur joint w.lliug. Usage rero:mmr.:nd3lions me shown in Onfco pavenu:nt tcmpera1Ure grade charts shown at !he right. Refer ,to Cnlfco Product Selection Procedures to dctcrm.inc sealant or 􀁦􀁩􀁾􀁥􀁲􀀭and pavement 􀁴􀁥􀁭􀁾􀁬􀁷􀁥grdlles. .. !iii••"',,,,,.",,, """"""'" • 􀁲􀁭􀀻􀁾􀁬􀁪􀁭􀁩􀁬􀁬􀀠o 􀀢􀀢􀀬􀁒􀁾􀀢􀀢􀀢􀀠SPECIFICATION CONFORMANCE Crafuo RoadSa... Silirone SL _ 10 􀁾􀁴􀁩􀁯􀁮􀁳􀀠fur low _ siJj""" fur many many bigl_ departUlcnts and federal ag:t'ICies. The product also 􀁭􀁾􀀻􀁭􀁤􀀠exceeds al1 requiremenlS of ASTM D5893. "Standard Specification for Cojd-Applied Siogle Component, Chemically D.uing Silicone Sea!ant fur Portland Cement Concrete PavemenlS" for type SL sealants. In the lbllowing specifications several ofIlle D5S93 parameters are more restrictive to better reflect properties ofRoadSaver Silicone SL. ASTM DS893 Physical RegulrwlImts ABTM 00893 SL Requirements RoadSaver Silicone SL Requirements Cure Evaluation Pass at 21 days Pass at 21 day max. Rlleological Properties (ASTM C639) Typt I. smooth level surfilce Type 1, ,;mooth level surface Extrusion-Rate (ASTM C1183) Type $, 50 mV min. minimum Type S, 200 mllmln. minimum Tack Free TIme (ASTM C 679) 5 hr. max. 3 hr. mnx. Effects oiHeal Aging (ASTM C 792) 10% rna•. Loss 10% max. Los, Soud, -2'PC 􀀨􀁾􀀲􀀰􀀢􀁐􀀩􀀮􀀠100% Extension Nou-.lmmersed Pass 5 Cycles Pass 5 Cycles Water immersed Pass 5 Cycles !'ass 5 eyeles Oven-Ag,," Pass 5 Cycles Pass 5 Cycles Hardness (Al>"TM C 661) • 29'C (.20'C). Type A2 2Smax. lOmax:. 23'C(7J'P1 Type 00 JOmin. 40-80 min. Flow No flow No flow Rubber Properties in Tension Ultimate Elongation 600% min. 800%mm. Stress ilt 150%· Elongalion 3t 0 K pa (45 psi) max. 207 K P' (30 psi) max. Effects of Accelerated Weathering PQSS 500 hours P-dSS a!. SOoo hours Resilience 75% min. 75% nltn. AddltklnRI properties ofRoadSaver SiUcoheSL Sealant Ilrc: Specifie Om.i!)' (ASTM D792·A) (I) L 10·l.40 Adhesion to Conere'" (MIL 8802) (2) 20pli (35 kg/em)lnu.. Bond and MovemcntCapability +/. 50% (ASTM C719)(2) Pass 10 oycles Bond 10 Morrar(AASHTO Tl32) (2) 50 psi (34.4 Nlom') min. Tensile Adb",ion. 'V.,(ASTM D5329) (3) 600% min. Notes: (1) Specimens shall be obtajned from 1/8 inch (3nun) thickness sheets of material which has been cured for 7 days at 77+1-3':'F (25+/2<>C) and 5041-5% relative humidity. (2) Specimens cured for23 days nt 17 􀀫􀀯􀁾􀀠3"F 􀀨􀀲􀀵􀀫􀀯􀁾􀀲􀂰􀁃􀀩􀀠and 50+1-5% humidity prior to testing, (3) Specirrn:m: shall be Ill" x 1/2" X2" ((1.2cru 􀁾􀀠J.2(:nl x 5.Ocm), cured 1 days Al 77 􀀫􀀯􀁾􀀠􀀳􀁾􀁆􀀠􀀨􀀲􀀵􀀫􀀱􀁾􀀲􀁣􀁱􀀠and 50% +1-5% reluuyc hUioidity. p.3 281-4 4 1-3414PRIMATE CONSTRUCTION INCJun 28 05 01:52p APPUCATION The uni, weigh, is 10.7 pound, per gallon (1.28 kgIL). One gallon will ,eal150 feet (45.7m) of III iooh (l.2cm) wide by 1/4 inch (O.6cm) deep joInt. Exact yield wl11 vary depeOOing on thickness of sealant, waste, applicallon techniques. etc. Prior to use, the user must read and Collow Apphcation instructions for RaadSaver Silicone Sealants (January 2002) to verifY proper product selections, applicator pumps, pavement preparation procedures, application geometry, usage precautions and safety procedures, These instructions are provided with each drum ofsealant ' PACKAGING Roadsaver Silicone SL Sealant is packaged in plastic lined open head 55 gallQl\ (208 L) drums which contain 50 gallons (189 t) of materbL Additionally, tor small appHlriltlon:s the setl!;mt is 􀁡􀁜􀀧􀁡􀁩􀁬􀁡􀁢􀁾􀀠in plnstic 5 gallon (/9 l) pails nnd quart (.95 L) caulking tuOOs=.____. WARRANTY CRAFCO, Inc. warrants that CRAfCO sealan19 rn.tef 􀁡􀁰􀁰􀁬􀁾􀁢􀁬􀁥􀀠ASlM. AASHTO. 􀁆􀁾􀁣􀁲􀁡􀁬􀀠OT Srate $pa;ifJCauOAS at time o( shipment.. Te1::hniques used for the prepar.!tion of 􀁉􀁨􀁾􀀠cracks and joints prior tG sealing are beynnd our control as are the use and application of lhe sealants; thererore, Cmf(O $hall not be responsible for improperly applied or misused sealants. Remedies ngairu.:( Cr.Ifco, 􀁉􀁮􀁾􀀱􀀠1i3 IIgreed to by Cm(eo, lire limited 10 revlac1l1g. nonconlOmtmg product or refund (full or partial) or pun;base price from Ctafco, Inc. All claims fot breach of this wamuny must be made within lhrte 0) monlfn cflbe dale of use ot 􀁬􀁷􀁤􀁜􀁬􀁾􀀠(12) month!! from the date of delivery by Ctaico. Ine. whichever is earlier. There sho.!! he no 0'00 WltrnmlJes 􀁾􀁥􀁤or implied. For ol'dmum pe:rformanu. foUow Cra{to milmmendntloos for seaJant In5taUation. Jun 28 05 01:52p PRIMATE CONSTRUCTION INC 281-441-3414 p.4 420 N, R........lf Ave, • Chandler AZ 85226 1-800..528.11242. (6Q2) 27s.o406 • FAX (480)961.0513 www.crafco.com APPLICATION INSTRUCTIONS ROAOSAVER SILICONE SEALANTS JANUARY '004 READ BEFORE USING THIS PRODUCT GENERAl: Crafco Road8aver Siltcone sealants are uniquely formulated low modulus sealants produted fOf usc in sealing joints in porttand corl\ell! COOCJete pavemc:ub, TIle senlanl are supplied as single component moisture curing materin1s wbich provide lasting weather resistant flexible seals. The sealants are supplied in both 􀁯􀁯􀁮􀁾􀁧􀀠and self-leveling (SL) app!iculion consistencies, SEALANT PREPARATIQN: CrafOo RoadSaver Silicone sea1aHI.5 are supplied in a ready to use tbnn, With no mixing or any other preparation required to prepare the sealant for use. JOINT PfSIGN AND PREPARATION FOR SEALING: After apptopriate curing of the concrete (a ntinimum of 7 days is recommended) joint reservoirs for the sealant can be eut into the concrete using appropriate concrete sawing procedures and equipment in "filst track" or high early strength concrete mixes, it may be possible to saw and seal the joints sooner than r:he recommended 1 day minimum for standard concrete mixes. Contact Crafco or yoor representative fOT further details. Resemird"P'" lOrv.u:ioosjoint widlbs is sbown in Table I. !ointwidlh should besclecred 10 Umil movemen! due to ex:par$on am COm:raaiOll '" no more !ban 25% of the joint width. After sawing, immediao:ly flush dle joillls with water IiJ remove amajority of1hc saw slurry. After thejoIms htive dried.jusrprior IiJ applying sealant the remaining residue .-be remol'OO by sandblasting. Both joint !ilces must be ad«jual!:!y sa.ttdbIasfI:d 10 remove 􀁾􀁧tmcesofsawiog teSid1J(';. Foreffi::ctive 5alldblasting, !he ilO'a!e ,hould be positionOO witbin 2 inches (5cm)of !he surliice bcing 􀁣􀁉􀁾􀀠AlIct sandblasting lhe joint should be ilioroogbIy cleatl\!rl using dean compressed air wilh a minimum p"""",, of90 psi, Moi'.... and oil traps are requiro:! on lite_pressor unit. Th<: object oflhe above cleaning 01'.""'"'' is iD p""ride _. inlai't, and c",," bonding _ which are 1m: firun all oontaminants and "" dry, JoinlS should be carellllly inspected 10 """'" illa! an appropriale level of clealWnrss has been achieved. This WlIIer absoIpOve backerrod ofttle stre S]'X".ii6cd in Table 1 shall be placed tn the joint 10 the depth listed in Table I. Do ooIpureturebacl beca"",damage can crea!c bubbling ill sealant SEALANT APPUCATION; RoodSaver &1ioone sealant is npplied 10 pavement joilllS using "" powmd built lbspemi:ng systems or _ =lking guns, The applicator unit must be tree ofall residue left m)ln other brands oriypes of materials to elinlio:ite cootamination and assure proper ""Iant perfortnallCe. During application, !he SCfl!nnl is dispcostd directly from its cootainer through the npplicator hose, wand Iliid nozzle and inlO !he prepared joint The jointshould be tilted from the bottom up. RoadSaver Silicone SL sealants ale selfleveling und 00 oorttXtUire tooling. RoadSaver Silicone NS S¢alanls are not seltteveling, and must be t001t:d to the proper goomc!Iy, Tooling must be 􀁾􀁯􀁥􀁤belbre !he _ forms a _ sliin of cured material (prelCiably wi1Illn 5 min1J1ll< aJlcr applicaJion), Tooling may be 'coompli!lled using , varicJy oflools including Snned ., that !he . These mois.... "'potS will migr.>1e through partiallycuml_􀁾air pockets, When the sculant h.. obtained a fuJI cure no bubbles will devclilJ' A test S1)]op, Using a 1'\Ol'I-S8g silicone sealant wiU 􀁾􀁴􀁬􀁹􀀠reduce the ri.o;k of air poektt fQl.'IJlation. Con!a.ct Ctatbo for further information. RESEALING JOINT DESIGN AND PREPARATION FOR SEALING: Old sealant ShoUld be rem(lved by any appropriate methoo:. After removal of old sealant, the jQint l!O (0 be saw eut to an appropriate width to provide clean vertical bonding surraces whi'Cb are free frolll culllami0311UJ1 by old sealant. As a general rule:, the joint should be sawn to a width which 15 between 118 inch and 114 incb (3·6mm) wider than the onginal joint. The recess, sealant bead thickness, backer size. and sawed joint depth sbalt meet requirements shOWI) in Table I for the joint width used. Thc snodblo.sting. oleDning and sealing operations above shan Jhen be followed. CLEAN UP: Uncured seaJant can be removed fi"om equipment and tools with solvents such as naphtha or mineral spirits. All p.5 Jun 28 05 01:52p PRIMATE CONSTRUCTION INC 281-441-3414 hoses and lines in lhe appliCt many I;ghway 􀁤􀁾and federd! 􀁾The product al:ro llleets and exceeds all requ1remerus of ASTh1 05893, "Standard Specification for COld·ApplieeJ Single Component, Oiemically Curing Silicone Sealant for Portland Cc:n.'lI;nt Concrete Pavements" for type SL sealants. In the following specifications several ofille D'893 parameters are more restrictive to better reflect properties ofRoadSaver Silicone SL. ASTM D58.93 Phmcal Requirements ASTM DS893 SL Re(Jwrements; RoadSaver Silicone SL Requirements Cure Bvaluatioll Pass at 21 days Pass at 2 I day max. Rheological Properties {ASTM C639} Type 1, smooth Jevel surfaee Type t. nmooth level surface 􀁅􀁘􀀨􀁲􀁵􀁳􀁩􀁯􀁮􀁾􀁡􀁴􀁣􀀠(ASTM ell83) Type S, 50 mil min. minimum Type S,200 mVmin, minimum Tack Free Time (ASTM C 679) 5 Itr. max. 3 hr. m:Ut, eITeclS of He" Aging (AS1M C 792) 10% mJIX. Loss 10% mill(. Loss Bood, -29"C 􀀨􀁾􀀲􀀰􀀢􀁆􀀩􀀮􀀠100% Elttcmion Nou-immersed Pass 5 Cycles Pass 5 Cycles Water Immersed Pass 5 Cycles Pass 5 C)-cles 􀁏􀁶􀁥􀁴􀀱􀁾􀁁􀁧􀁥􀁤􀀠Pass 5 Cycles Pass 5 Cyeles Iiardness (AS1M C C 661) ·29'C (·lO'C), Tl'1'e A2 2;'C (73'F), Type 00 25 max. 30 min. 10 max. 40.80 min. Plow NoHow No flow Rubber Properties in Tension Ullimatc Elongation 600% min. 800% min, Stress at 150"10 Elongalion 310 K pa (45 psi) max. 207 K pa (30 psi) max. Bffccts ofAccelerlltcd Wealheriog 􀁐􀁡􀁾􀀠500 hOUfS P\1.$ at 5000 hours Resilience 75% miu. 75% min. Addidonal properttts-of RoadSftve-r SiUtone,SL Sealant are: Specifie Gr,vil)" (ASTM D792·A)(1) LI o.l.4() Adhesion to Concrete (MIL 8802) (2) 20 pli (3.5 kg/cm) mul. Bond and Movemctrt Capability +1-50% (ASTM C719) (2) Pass lO cycles Bond to Morr., (AASHTO T132) (1) 50 psi (34.4 Nlcm') min. Tensile 􀁁􀁤􀁨􀁾􀁬􀁯􀁮􀀮􀀠%(AST.M D5329) (3) 600% min, Notes; (1) Specimens shall b0 obtained from 118 inch (3mm) Ihickness sheets ofmaleriai which has been cured for 7 days at 77+1-􀀳􀁾(25+12°C) :and 50 +/-5% relative humidity. (2) Specimens cured Cor28 days at 77 􀀫􀀯􀁾􀀠3'Of1 􀀨􀀲􀀵􀀫􀀯􀁾􀀲􀂰􀁃􀀩􀀠and 50+1-5% humidity prior to testing. (3) Sp«:imcns shall be 112" x 1/2" x 2" (1.2cm x. 1.2c01 x 5.Ocm), cured 7 days at 71 +1-3Q F (25+1_21)q lind 50% +f-5% telativ<: humidity. 281-4 4 1-3414 1'.3PRIMATE CONSTRUCTION INCJun 28 05 01:521' APPLICATION The umt weight is 10.7 pOWld'per gallon (l.2a kgtL). One gallon will seal UO feet (45.7,") ofll2 ineh (1.20m) wide by 1/4 inch (O.&:lO) deep joint. Exact yield wIll vary depending on thickness of sealant, waste, application lechniqucs, etc. Prior to use, the user must 􀁲􀁾􀀠and follow Application Instructions for RoadSaver Silicone Sealants (January 2002) 10 verify proper product selections, applicator pumps, pavement preparation ptoceduresj application geometry, usage precautions and safety procedures. These inslrUcLions are provided with each drum of􀁳􀁣􀁾􀁬􀁡􀁮􀁴􀀮􀀠PACKAGING Roadsaver Silicone SL Sealant is packaged in plastic lined open head 55 gallQn (208 L) drums which con:ain 50 gal!OD!i: (18.9 L) of rruntlnal. Addilklll.ldly, for !l'I\llli appltcilli!,ins the sculant is available in plnstic 5 gallon (191.) pails nnd 􀁱􀁾(.95 t) taulking 􀁬􀀮􀁕􀁾􀀬􀀬􀀬􀀬􀀬􀀮___􀁾_____ WARRANTY CRAFCO. Inc. WlUTtlflts that CRAFCQ sealanl3 meel appIit"!.lble ASTM, AASJITO. Feder.al (If Stale spccifiWitkms at lime of shIpment, Tef!lmlques used for tbe preparation of lhe cracks and joints priDT 10 sealing are '!:Ieyoo:! our control as are the lJSe and application of the sealants; therefore. Crafco sha!lnot be responsible for improperly applied or rnisw.e:d sealants, Remedieo:: Ilpins( Crafeo, Ine., aa agreed to by l."ntfco. m limiled {o replacing norv.:oolomUng produ;;t or rerUM (full or partial) of purchMe price from Crafco, Inc. AlI claims fur 􀁢􀁲􀁥􀁡􀁤􀁾􀀠of Lhii W':lmUll)' must 􀁾made within three (3) months ;:;fthc date;:;f use (If twtlve (12) months from Lhe date of delivery by Crafco. fru:, whichever is earlier, There 9hoJi br; no Olher wntran(ies !Ji\pm;sed or implied. ror optimum performance, foDDW Ct-afct) rect)Jnwendatioos (or sealant lnstallation. Jun 28 05 01:521' PRIMATE CONSTRUCTION INC 281-441-3414 APPLICATION INSTRUCTIONS ROADSAVER SILICONE SEALANTS JANUARY 1004 420 N, Roosevelt AVe•• Chandler AZ 85226 1-800-528-8242· (602) 276.Q406. FAX (480) 961-0513 \WIW.cmfco.com READ BEFORE USING THIS PROOUCT GENERAL: Crafuo RoadSaver Silicone sealants are uniquely formulated low modulus sealants produced for use in sealing joints itt portland cement concrete pavements. 􀁮􀁬􀁴􀁾􀀠:;ealant are supplied as single component moisture curing materials which provide lasting wenther res1stant flexible seals, 'file sealants are Sl1ppl1ed in bolli t'JODwSag and self-leveling' (St) application consistencies. SEALANT PREPARATION: Crafco RoadSaver Silicone sealant3 are supplied in a ready to use form, with no mixing or any other preparation required to prepare the sealant for use, JOINT DESIGN AND PREPARATION FOR SEALINCy. Mer appropriate curing of the concrete (a minimum of 7 days is reconuncndcd) joint re:servoirs for tile sealant cao be cut into the conc:rete using appropriate concrete sawing procedl.ll'eS aDd equipment. In "fast track" or high early strength concItle urix.es, it may be possible to saw and seal the joints soouer than the recotnmeooerl 1 day minimum for standard concrete mixes. Contact 􀁃􀁲􀁡􀁲􀁾􀁯􀀠or your representative for further details. Reo:rvoirdepth fon.rioosjoi!ll 􀀢􀁩􀁤􀁬􀁨􀁳􀁾􀀠shown in Table L Jointwidth sltould be 􀁾􀁥􀀺􀁣􀁴􀁥􀁤􀀠to !imiL moven1Qll due (0 expansion and COliil'aClioo 10 00 more than 25% of Ihe joint width. After sawing, im.mediately fiush thejoints with WIll« "'remove a n'1iority ofthe saw sluti)'. Aller the joinls have dried. justprior to applying sealant the remaining 􀁾􀁤􀁵􀁥􀀠must be """",0:1 by sandblastinjj. _joint faoes must be adequalely sandblasWd to n:ttlove ranaining traces ofsawing residue. For cffix:tive sandblasting, Ihe 11OZ7.le should be posiciOOre tn, sealant funns a _ sldn of cured ll1Il!eriaI (prerClllbly wilhin S minu"" all" applicolion). Tooling may be acoomplislJ1 l"J.1 l1g•• 1 1/4H 13/S" : I 112" I 11411 1/4" 5/16" 5/16" I 3/8" 3/8" 3/8" I 112" 1/2" 1/2" ll2'· I Sacker Rod Dituncter 3/8" 1/21> 5/8" 3/4" I 7/8" I" I 114" 􀁾􀀠I 1/2" I liZ" 13/4" 2" I I Sealant Bead Thickness 1.1 I 1/4" 1/4" [14" 5/16" I 3/8" , 7116)1 112" In,j 1/2" l!2H 1/2" I , Minimum Joint , I liS" I 114" I 112" , 1314" : I 1/8" 2" 23/8" 2 211'l:' 3118" 3 318" iI SawfReservoir 􀁄􀁾􀁴􀀡􀁴􀀭􀀭􀀺􀀻􀀭I . Minimum Backer Ror!l5ePil1 112'1 112" 5/81 ' 11/16" I 314" 13116" 7/81\ I" I" I J" I" I I Estimated Usage Non-Sag . 245 149 112 70 I 51 35 26 23 18 16 15 J I Estimated Usage I 273 1112 130 82 I 58 41 31 17 22 20 19 JSeJf-leveling(ftlgal) --,.I Backer rod dilUllCter should not be vaned from spectfied dimenSIOns. ItIarger SIZes are used, mereased saw depth IS needed. 2 Sealant bead thickness can vary by ±25% ofdesign value. 3 Never install Roods,ve, Silicone to • deplh gre_than the joint width (I to I). *Please contact Crafeo for additional joint size ddign recommendations. TYPICAL JOINT DESIGNS: NotToStale '-"···"··CUI Texas Department o/Transportation Prequalified Joint Sealers The following producers arc prequalified to supply joint sealants by class. Materials with lab numbers represented by dates of •••_ .....u ...........􀁾􀀠... .... u .... u .• " .. 'V .......... " .... .........yu.·b .................."' ........_. "1 .......... 􀁾􀀠.........""'..................... , .......... 􀁾􀁾􀁈􀀠............. I ---------______ _ _p,.equalified Joint Sealers 􀁾􀀱􀀮􀁬􀁉􀁓􀀠2 !'roducts Sof-Seal Low Producer Address/Phone No. Contact Lab No. Tested ExjJires W.R. Meadows of P.O. Box 7752 Andrew W. Tam C03370028 01101/03 06/30/03 Modulus Horizontal Texas, Inc. 2555 NE 33" C02372057 07/01102 12/31102 Sealant 99867 Fort Worth, TX 76111 C02370025 01/01102 06130102 804 (817) 834-1969 CO 1372028 07/01101 12131/01 C01370015 01101101 06/30/01 C00372091 07/01100 12131100 C00370015 01101100 06130100 3 Road Saver 221 Sealant Part No. 34221 809 Ceafeo, Inc. 99579 -------6975 W Crafeo Way Chandler, AZ 85266 (602) 276-0406 --------Vern Thompson C05370040 C04372227 C04370072 C03371953 C03370007 C02372036 C02370007 C01372010 CO 1370007 C00372083 C00370OO7 01101105 06130105 0710 1104 12131/04 01101104 06/30/04 07101103 12131103 01101103 06130/03 07101102 12131102 01101102 06/30/02 07101101 1213110 I 01/01101 06130/01 07101100 12131100 OliO lIOO 06130100 3 Road Saver 222 Sealant Part No. 34222 809 Crafcot Inc. 99579 . --------6975 W Crafeo Way Chandler, AZ 85266 (602) 276-0406 Vern Thompson C05370039 C04370073 C0337195I C03370005 C02372034 C02370005 C01372008 C01370005 C00372081 C00370005 OliOl/05 06/30105 01101104 06/30/04 07101103 12/31/03 01/01103 06130103 07/01102 12131102 01101/02 06130102 07/01/01 12131101 01101101 06130/01 07/01100 12/31100 01101100 06/30100 01101105 061301053 Hi-Spec Hot Pour W.R. Meadows of P.O. Box 7752 Andrew W. Tam C04374868 Material/Producer List 1 '. . 5116105 Texas Department a/Transportation Prequ.Jified Joint Sealers Class Products Joint Sealing Compound 809 Producer Texas, IIlC, 99867 Address/Phone No. 2555 NE 33'" Fort Worth, TX 76111 (817) 834-1969 Contact Lab No. C04372 I 14 C0337 1973 C03370027 Tested 07101104 07101103 01101103 E!(1jres 12131/04 12131103 06130/03 C02372056 07101102 12131102 C02370024 01/01/02 06/30102 CO 1372027 07/01/01 12131101 CO 1370014 01101101 06130101 C00372090 07/01100 12131100 3 CMC 102 809 Crackfiller Manufacturing Corporation 99064 P,O, Box 6738 Cheyenne, WY 82003 (307) 778-86lO Mark Langer C00370014 C03370011 C02372040 C02370011 CO 13720 14 OI/OliOO 01/01/03 07/01102 01101102 07101/01 06/30100 06130103 12131102 06/30/02 I213 1I01 C01370019 01101101 06130101 C00372095 07/01100 12131100 C00370019 01101100 06130100 3 Sea/Master Ind" Inc, 3405 809 S.alMaster Ind" Inc, 99219 ISO I Lancasterl Hutchins Rd, P. O. Box 1008 Lee Malone C03370024 C02372053 C02370021 OliOl103 07101/02 01101102 06/30103 12131102 06130102 Lancaster, TX 75146 75146 CO 1372024 07101/01 12131101 (972) 227-9093 CO 1370024 0110110 I 0613010 I C00372099 07101100 I2I31100 4 Dow Coming 888 810 Dow Coming Corporation 99875 390 I S Saginaw Rd Midland. Ml 48686 (517) 496·5799 Rich Palmer C05370140 C04373972 C03375509 01/01105 09/16104 o1/0 I/()4 06130105 12131104 06130/04 C03371958 07101103 12131103 C03370012 01101103 06130103 C02372041 07101102 12131102 C02370012 01101102 06130102 C01372015 07101101 12131101 CO 13700 I I 01101101 06130101 C00372087 07/01/00 12131100 C0037001 I 01/01100 06/30/00 Material/Producer List 2 5/16/05 Texas Department o/Transportation CI.ss 4 Products Non-Sag Producer CrafeD, Inc. Prcqualified Joint Sealers AddresslPhone No. 6975 W Crafco Way Contact Vern Thompson L.b No. C05370034 Tested 01/01/05 Expires 06/30/05 810 99579 Chandler, AZ 85266 C04373023 07/01/04 12/31104 (602) 276·0406 C03371954 07/01/03 12/31103 C03370008 01/01/03 06/30/03 C02372037 07/01/02 12/31102 C02370008 01/01102 06/30/02 C01372011 07/01/01 12/31101 CO 1370008 01/01101 06/30/01 C00372084 07/01/00 12/31/00 \I 􀁾􀁄􀀮􀀹􀀱􀁬􀀠Jlrim!ffiWii;"l'ilii iWQ;1!.\W[IiJi¥tml 􀁾􀁊􀁪􀁊􀀠C00370008 􀁩􀁭􀁍􀁾􀀱􀁲􀁪􀁊􀁍􀁾􀀠01/01/00 M!.Q1ZQ)l 06/30/00 􀁲􀁵􀁩􀁬􀁾􀀮􀁬􀁩􀀷􀀮􀀡􀁴􀁾􀀠􀁾􀀠􀁾􀁾􀁬􀁩􀁬􀁾􀀠􀀡􀀧􀁦􀁂􀁀􀁪􀀩􀁾􀁡􀁪􀁩􀁩􀁭􀁢􀁭􀀧􀀵􀁂􀀠45872 4 301 Non-Sag Pecora (l;5Wti!8,gl[4 165 Wambold Rd. Roy Cannon C05370309 01101/05 06/30/05 810 99981 Harleysville, PA 19438 C04370184 01/01/04 06/30/04 (215) 723-6051 C03371966 07/01103 12/31103 C03370020 01101/03 06/30/03 C02372049 07/01102 12/31102 4 Tremco Tremco, Inc. 3777 Green Rd. Ta-Min Feng C02370030 C04374746 C04374746 01101/02 01101/05 06/30/02 06/30/05 810 99083 Beachwood, OH 44122 C04371979 07/01/04 12/31/04 Spectrem 800 (216) 766·5680 C03375499 01/01/04 06/30/04 Fax (216) 765-6737 C03371971 07/01/03 12/31/03 C03370025 01/01/03 06/30/03 C02372054 07/01/02 12/31102 C02370022 01/01/02 06/30/02 5 Dow Corning 890SL Dow Corning 390 I S Saginaw Rd Rich Palmer C01372025 C05370139 07/01/01 01101105 12/31/01 06/30/05 810 Corporation Midland, MI 48686 C04373971 09/16/04 12/31/04 99875 (517) 496·5799 C03375510 01/01/04 06/30/04 C03371960 07/01/03 12/31103 C03370014 01/01/03 06/30/03 Material/Producer List 3 5/16/05 Texas Department a/Transportation Prequ.lified Joint Se.lers CI.ss I'roducts Producer AddresslPhone No. Conlact Lab No. Tesled Expires C02372043 C02370014 C01372017 COl370013 C003720S9 C00370013 07102102 01/01/02 07/01101 01/01101 07/01100 01101/00 12131/02 06130102 12131101 06130101 12131/00 06/30/00 5 Pecora 300 SL 810 Pecora Corp. 99981 165 Wambold Rd. Harleysville, PA 19438 (215) 723·6051 Roy Cannon C03371964 C03370018 C02372047 C02370028 C01372031 07/01/03 01/01/03 07/01/02 01/01/02 06/21101 12131103 06130103 12131102 06/30/02 [2/31101 5 Sika 810 Sika Corp. 99572 6122 Rachel', Court Kaly, TX 77494 (281) 693·2121 Greg Reisz C03370021 C02372050 C02370018 CO 1372021 CO 1370020 C00372096 COO370021 01/01103 07/01/02 01/01102 07/0 1I0 I 01101101 07/01100 OliO 1100 06130/03 12/31/02 06130/02 12131/01 0613010 I 1213 [100 06130/00 5 Sika 15LM SL 810 SikaCorp. 99572 6 [22 Rachel', Court Kaly, TX 77494 (281) 693·2121 Greg Reisz C04374648 C03370022 C023720S1 C023700[9 COl3n022 CO 137002 I 0[/01105 01/01103 07/01102 0[/01/02 07/01/01 0[101101 06/30/05 06130/03 12131/02 06/30/02 12121/01 06/30/01 5 Tremco 810 Spectrem 900 SL T􀁲􀁥􀁭􀁣􀁯􀁾􀀠Inc. 99083 3777 Green Rd. Beachwood, OH 44122 (216) 766·5680 Fax (21 G) 765·6737 To·Min Feng C04374745 C04371980 C03375498 C03371972 C03370026 C02372055 C02370023 CO I 372026 0[101105 07101/04 01101104 07101/03 01101103 07/01102 01101102 07/01/01 06/30105 12131104 06130/04 12131103 06130/03 12131102 06130/02 1213110 [ 7 Dow Coming 902RCS Dow Corning 390 I S Saginaw Rd Rich Palmer C05370141 01101105 06130105 Material/Producer List 4 5//6/05 Texas Department 0LTransportation Joint Producer Address/PllOnl 810 I Corporation Midland, MI 48686 99875 (517) 496-5799 7 I WatsonlBowman 􀁉􀀺􀁾􀁴􀀺􀀻􀁮aowman I􀀢􀀧􀀧􀀧􀀧􀁾C,.,,; l810 Dnve Spring, TX 77388 (281) 651-8394 􀀱􀁩􀁴􀀧􀀱􀁴􀁾􀁬􀀱􀁩􀁣􀀮􀀠.. '---j6975wcrafcoway 99S79i Chandler, AZ 85266 (602)P6-0406 􀀮􀀭􀀭􀀭􀀭􀁴􀂷􀁉􀀡􀁩􀁓􀁗􀁩􀁬􀁩􀁬􀁂􀀭􀀭􀁩􀁩􀀱􀁴􀁡􀁴􀁾􀁍􀁩􀀱􀀩􀁀􀁊􀀠􀁬􀀡􀁭􀁾 􀁯􀁯􀁾􀀠II'iI 􀁾􀁾􀁴􀁾􀁦􀀠'" 􀁗􀁾􀀢􀀢􀀮􀀠 􀀱􀂷􀁜􀁻􀁾􀁩􀀮􀁁􀁾􀁰􀁷􀁮􀀠 I. I􀁾􀀡􀁉􀁬􀁾􀀮􀁩􀀻􀀴􀁨􀀶􀀱􀀠 IC04373973 C03375511 C03371959 C03370013 C02372042 C02370013 C01372016 CO!370012 C003720SS C00370012 C0437 1668 C03375541 C03370030 C02372059 C02370027 COI372030 COl370023 COO372098 COO370023 C05370035 C04373022 C04370452 C03371952 C03370006 C02372035 C02370006 CO I 372009 CO 1370006 C00372082 I􀁾􀁾􀀬􀁾􀀻􀀻􀀠 09/16/04 01101104 07/01103 01101103 07101102 01101102 07101101 0110 [10 I 07/01100 01/01100 07101/04 . 01101104 01101103 07101102 01101102 07/01101 01101101 07101100 01101100 01101105 07/01104 01101104 07101103 01101103 07101/02 OliOl102 07/01/01 01/01101 07101100 01101100 􀁾􀁾􀀠12131104 06130104 12131/03 06130/03 12131102 06130102 12131101 06f3010 12131100 12131104 06130104 06130103 12131102 06130102 1213110 06f30/0 12131100 06/30100 ! 06130105 12131104 06130/04 12131103 06130/03 12131102 06/30102 12I3110 06130/01 12/31100 I􀁪􀀩􀁊􀁪􀁀􀀡􀀱􀁬􀀡􀀱􀁾􀀠 Material/Producer List 5 5116105 -----------------Texas Department o/Transportation Fr.qualified Joint Se.lers ExpiresCia.. Products Producer Lab No. TestedAddress/Phone No. Cont9ct (Gm':fiis':-SI14 Pecora SL Low Pecora Corp. 165 Wambold Rd.8 Roy Cannon 􀁐􀀱􀀱􀀬􀀨􀀩􀁬􀁬􀁬􀁽􀁾􀀠􀁐􀁩􀁩􀁬􀀳􀀱􀀱􀁩􀁬􀀩􀁾􀁩􀀲􀁩􀁩􀀧􀁦􀁩􀁬􀀺􀀷􀀬􀁬􀁩􀁾􀀬􀁏􀀺􀁾􀀠Modulus Harleysville, PA 19438 , C04370185 01101104 0613010499981 810 01/01103 06130/03(215) 723·6051 C03370019 12131/02C02372048 07101102 01101102 06130102C02370029 12/31101COl3n032 􀁾􀁉􀀯􀁏􀁉..... r'···--··01101105 061301058 Sika 15LM SL Sika Corp. 6122 Rachel's Court Greg Reisz C04374649 1213110407101104810 99572 Kaly, TX 77494 C04372182 01101104 06130104(281) 693·2121 C04370458 07101103 12131103C03371968 01101103 , 06130103C03370022 C02372051 07101102 12/31102 01101102 06130/02C02370019 07101101 12121101CO 1372022 o[{O 110 I 06130101CO 137002 1 MateriallProducer List 6 5116105 HIITB Cotpa; u". 15150 surveyor SIvd. Telephone (972:) 361-0064 The: HNT8 􀁾􀁡􀁮􀁲􀁥􀁳􀀠AddIson. TX 75001 Faeslmi1e {'!11'Z} 361-0065 Engineers Architects Planners www.hntb.com Archer Western Contractors. Ltd. 2121 Avenue"f HNTB Suite 103 Arlington. TX 76006 Request for Information Response JulyS. 2005 Originator: Andrew Scheermann RFI Number: R-AWOIOI Subject: Light Pole Template conflict with pennant Reqoest:: Please Reference Plan Sheets 306 & 303 and attached sketch Archer Western has discovered that the bottom template for the light pole anchor bolts is in conflict with the pennant The Template extends approximately Y.i" past the face of the pennant Please provide a solution for this conflict as soon as possible as not to delay the project ResponselAction Twn: As discussed on July 1". Archer Western is directed to install the anchor bolt pattern for the South traffic rail with the offset towards the traffic lace -Y.i" off center of the T -4 rail. (Opposite ofsketch provide by Archer Western) It's requested that the area of the embedded anchor bolt template near the pennant be cold spray galvanized to prevent rusting due to minimum concrete coverage. The Light pole for the North traffic rail should be centered on the T -4 rail concrete. By: Guy V Baulen, BIT HNTB Corporation Date: July 5,2005 Cc: Fne Steve Chutchian, Town ofAddison Jerry D. Holder. HNTB Corporation IM1'B Coi/poIlllla. 15150 Surveyor Blvd. Telephone (97Z>J61-0064 The HNT8 Companies MdIs"" TX 75001 F._Itt (91Z) 361-0065 EngIneers Arc:hitects ?1ilnners VfWW.hntb.com Ardler Western Contractors. Ltd. 2121 Avenue T HNTB Suite 103 Arlington, TX 76006 Request for Information Response July 5. 2005 Originator. Andrew SclIeennann RFINumber: R-AW073 Subject: Power Source for load distribution centers A Be B Request Please Reference the Revised Plan Sheets 335 Please provide details on the locations and routing of the power sources for load distributing centers (LDC) A at Bent 11 and LDC Bat Bent 8. Please provide information at your earliest convenience. Response/Action Taken: In response to the location of the power sources for the Bridge lighting, please reference contract plan sheets BL-6 &:7, pages 327 & 328. The electrical service drop will be located near Station 58+50. The power sources for LDC A at Bent 11 will be provided by the conduit run from GB3 at Bent 8 underground and under Midway Rd. to GB 7 at Bent 11 as shown on sheetBL-22 &23, page 343 &344. 􀀴􀁊􀁾􀁌􀀭 By: Guy Van Baulen. EIT Date: July 5, 2005 HNTB Corporation 0;; File Steve Chutcllian. Town ofAddison Jerry D. Holder. HNTB Corporation ,!..... Ccc,... ..... Ccc,... 15150 Surveyor Blvd. Tnfi,rm these revised conduit focatlon. Page 1 Conduit Layout per Plans 􀁾􀀲􀁆􀁉􀀺􀀺􀁤􀁵􀁲􀁾􀀧􀀠􀀺􀁾􀀡􀁾􀀺􀀬􀀺􀁾􀁾􀀱􀁾􀁩􀁾􀁾􀀧􀁾􀀬􀁨􀁾􀀱􀀴􀁪􀁾􀁴􀁾􀀻􀁩􀁪􀁾􀀬􀀠􀀧􀁾􀁯􀀧􀀠" 􀀳􀁾􀀻􀀺􀀺􀀠􀀺􀀻􀁉􀁾􀁾􀁩􀀸􀀺􀁴􀀻􀀱􀀮􀁇􀀺􀀺􀀼􀀠􀁾􀁾􀁾􀀠􀁾􀀯􀀢􀁾􀀧􀁾􀀬􀀬􀀬􀀺􀀠 ,C·2 􀁆􀁩􀁾􀁾􀀬􀁾􀀺􀀺􀁴􀀠􀀻􀀧􀀺􀁤􀁾􀁾􀁾􀁾􀁣􀀺􀀠'B 􀂢􀁑􀁾􀁩􀁾􀁊􀀮􀀬􀀠'0ulpUl 339. C-2 Fin: 􀁏􀁵􀁴􀁰􀁾􀁾􀀧􀀠. .. :":: " Ii:··/.; , . 􀁩􀁾􀁴􀁾􀁢􀁾􀁤􀁊􀁛􀁴􀁳􀀺􀀠.5' , 􀀧􀀺􀀧􀁴􀁾􀁴􀁡􀁬􀀠􀁃􀁾􀁵􀁊􀁴􀁓􀀺􀀮􀀧 􀀭􀀧􀀺􀁾''"':,:, , Proposed Conduit layout '. :"':T: 􀀧􀀻􀁾􀀧􀀺􀀮􀀮􀀠.', ': ' '" \ 􀁾􀁔􀀮􀁯􀁩􀁡􀁦􀁃􀂷􀁏􀁾􀁤􀁴􀁬􀁬􀀢􀀢􀀻􀂷􀀠0.' SpecifiC section of the T·4 Rell, where more than five Specificsectlon orlhe T-4 Rail, YAlere more than five coi1duits will be present at one ttme the two col'lduils for conduits wllJ be present at one lime the two conduIts the type B fixture& will be run In \he bridge dock (span 9) for the type B f'IxtImls will be run in the Pridge deck (span 9) Find /Replace dialog box Page 2 of2 lie IItum off special meanlnQof character c I IA llbeginning 01 line I 1$ !lend of line I I· Ilany single chaiacter I I:a Ilany alphabetical character [a-z,A-Z] I I:d Ilany digit [0-9] I I:n lra;1valphanumeriC character [a-zIA-ZI0-9] I I: IIA colon followed byaspace also'matches any punctuation characterl 1[···] lIany one 01 the characters in ... ; ranges such as a-z are 􀁉􀁾􀁡􀁬􀀠I I[A... ] lIany single character not in ... ; ranges are legal I Is' Ilzera or more occurrences of string s I Is+ Ilona or mor".occurrences of slling s I 1st IIstring s followed by string t I In Cells If on, specifies a search for text in cells. Fractions If on, specifies a search for fractions. Fino Clicking the Find button locates the specified text. Change Clicking Change replaces the text element in the Find field with the text element from the With field. Change All Clicking Change All replaces all the specified text elements in the design file. Change Fence Clicking Change Fence replaces the text elements that match the current Fence search criteria. Change Single Clicking Single replaces a single text element in the design file, as identified by the user. mk:@MSITStore:D:\Program%20Files\Bentley\Documentation\MicroStation.cbm::/ustnhel.. , 7/5/2005 Archer Western Contractors, Ltd. Arapaho Road Phase III Job No. 204059 IREQUEST FOR INFORMATION RFI # __""10,,,9,--_ PROJECT No. Arapaho Phase III Date: ___",Ju",I:LY"'S:z..!2",0:=0",S:.......__ review of the attached Sketch '1', you wIll notice that the reflector as specified in the contract p'ans is in conflict with 'he approved Type C Lights i and Bracket Sketch '2' shows modifications as discussed in the owners meeting. The modificatIons shown in Sketch '2' will minimize light ! maintenance issues.. ! iPlease direct Archer Western and S&J on how to proceed with lighting issue, i Please respond as soon as possible as not to further delay the project. Page 1 '" ·Ii 0!f:) 􀁾􀀠a \.L. 􀁾􀀠 --. _. .',.􀀭􀀭􀁾􀀠Cl 􀁾􀀠a b.;l: -Cl "" 􀁾􀀠-l.a .g 􀀬􀁾􀀠-4 L􀁾􀀠1.\2 1 􀁾􀀠 '-' .§ ] J 􀁾􀀠'-D " 􀁾􀀠• • 􀁾􀀠::t:: .l;!' -l 0..... 􀁾G Cs b 􀁾􀀠a 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠Cl .2c:: "'"'􀁾􀀠 Ii: 􀁾'-0 􀁾􀀠 C) I{\ lJ c5 􀁾􀀠ii, 2"\ lJ ":!:: 􀁾􀀠\:: :::..::. '4\-􀁾􀀠Ii: 1\1) R.􀁾􀀠0 i:: j:;': @@@@ --1) t':l 􀁾􀀠-E =t • -\ 􀁾􀀠e t 􀁾􀀠• t () 􀁾􀀠'(\ 􀁾􀀠t:"\ 6 􀁾IlL • '(\ () 0-. 􀁾Itt 􀁾􀀠@@@@􀁾􀀠t '(\ d 􀁾􀀠􀀮􀁾􀀠w "'"'􀁾􀀠􀁾􀀠0 􀁾􀀠􀁾􀁾􀀠􀁾􀀠1:: 􀁾􀀠􀁾􀀠ij,--•::c--l V)-C) 􀁾􀀠 􀁾􀀠 '" ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 8, 2005 Submittal # : 1....___-'6;;.;0-'.1'--__...... Now Submiltlll : X To: HNTBITownofAddlson Ro-Submlttal : 16801 Westgrove Addison, Texas 75001-9010 Project: Arapaho Road Phase III A1W# 204059 (912) 450-2886 Engineer: HNTB Attn: Guy Van-Baulen Submittal Specification Reference: Town of Addison /Plan Sheet DT-03 Description of Submitteilltem: Decomposed Granite -Product Summary Report &. Samples Manufacturer/Sub/Supplier: Martin M arietla Related Section I Drawings: Town of Addison I Plan Sheet DT-03 Additional Comments: Contractor's Certification "Having Checked this SUbmission, we certify that it conforms to the requirements of the Contract in all respects, except as otherwise indicated." The Decomposed Granite will mixed with Type Ill! Cement lnclude 2 Sags of Material Engineer's Stamp Slg.: Print Name: Tide: Asst. Project Manager Reviewed by: Andrew Schneernann Date; June 8. 2005 􀁶􀁾􀀺􀀠Andrew Schneemann Copy: File Product Quality Summary Report Arapaho Road Phase III Submittal for Decomposed Granite Plant: 32 Mill Creek Decomposed Granite DGOl 5/8"(16) 316"(9,5) #4(4,75) #8(2,36) #40(Q.425) #200(0.075) PAN(O) PlasUcily Index 100,0 89,9 58,4 46.1 30,7 9.10 0,00 7 aggQC Martin Marietta Materials, Inc. Page: 1 of 2 Product Quality Summary Report Arapaho Road Phase III Submittal for Decomposed Granite Plant: 32 Mill Creek Comments: This gradation is for information only. This material Is said exclusively for landscaping purposes. Samples.are available prior 10 shipment. Query: OYary Seldons: Report Create} 1"1( 􀁾􀀠 *􀀡􀀱􀀱􀀱􀁁􀁾􀁲􀀠&:-􀀻􀀱􀀱􀁾􀀠&c:::..V67S I%x.-. "'$(ez1. 􀁾􀁩􀀼􀀺􀀮􀁁􀀢􀁦􀁬􀁯􀁾􀀠, Buckner: One Piece Quick Coupling Valve Spec Page 1 of4 $'/1 '7$,'I" Click Here to Print Page Quick Coupling Valve 11 /One Piece Models fYliJiU' Description 6( B 3 sB1..,.0 7 Quick Coupling Valves are available in %" , 1" and 1y,;" inlet sizes. They are used where a water outlet is required for possible irrigation or wash-down. Application Quick Coupler Valves offer economical irrigation of large turf areas and provide for future conversion to pop-up rotors. They are also used where supplemental watering or washdown is required. Features • Available in %" , 1" and 1y,;" Female NPT inlet· • Lid stays closed by strong positive-action spring. • High visibility TuffTop'" or brass lids available. • Constructed of solid red brass for durability, economy and recycla bility. • Corrosion resistant stainless steel spring and self.. flushing brass plunger. • Wrench flats at base for easy installation. , • Drain hole in body to minimiZe debris collection. • Chevron-shaped wiper seal to reduce leakage around key while inserted. • Self cleaning seal design. • Brass plunger and stainless stael spring to eliminate corrosion. • Availabie locking lid for vandal resistance and non-potable application. • Flow ranges from 5 to 100 gpm. '. Handles pressures up to 150 psi. • Locking rubber lid (use with TLK lock top key). • Lavender TuffTop'" locking lid for non-potable water (NP). • Optional British Standard Threaded version available (BS). • Five-year warranty. QB5NP10 1" One-piece Quick Coupling Valve with Non-potable Lavender TuffTop"" Locking Lid Specifications The quick coupflng valve shall be a one piece type using a [single, double] slot keyway. The valve body and coupler key shall be made of cast red brass. The lid shall be made of brass or polypropylene. The seat disc plunger shall be spring-loaded to maintain the valve in a closed position at zero inlet pressure. Coupler seal shall be removable from the top while valve is under pressure. The lid shall be spring loaded for positive closing and made of 302 stainless steel spring temper cres wire. The TuffTopTM shall be capable of locking (and unlocking with the use of a (TLK) key, which prevents unwanted use of the Quick Coupling valve. The valve shall have a inch inlet and be capable of gpm flow at psi maximum pressure loss. The -va-;Iv-e-s-:-h-a:;-II;:'be opened and closed by a [single, double) lug coupler key having a;;_-:-__ inch Male NPT outlet thread, and/or a ____ inch Female NPT outlet thread. Note: All inrigation systems should be properly filtered to eliminate contaminants. Chemical pollutants may also be hazardous to valve life and operation. Be sure to determine the fitness of any product for ils application. To Specify: QBS NP 10 BS Model Lid Size Option Option Quick Coupling Valves· One Piece Model Cecriptions 8117/2004http://www.ewing1.com/ewing/htmjpgsi02005314.htm Buckner: One Piece Quick Coupling Valve Spec Page 2 of4 1 􀁾􀀠􀁷􀁧􀀮􀁾􀁮􀀠5 "-_-IHeight 4 3/8' Widlh 2 318' Height S 3/8' Width 3 3/8' HeightS 718' Width 3 7/8" .;.;;.",.------1 􀀡􀀢􀀧􀁾􀁟􀀮􀀢􀀢􀀢􀀧� �􀀧􀀧􀀧􀀧􀁢􀁾􀀠',' ',' 􀁾􀀠>iuofor' lO7 􀁾􀁦􀁾􀀧Female, doubl& lug , I􀁾􀀠:!I'ale.􀁾l' Female, doubl& lug for' , WDgC' ",e, ..􀁾􀀧􀀢􀀠D, ' "D,' ''', TlK ) kev for Qulek QB -O"e-'"'i.. , .... Body Design ,In PSI GPM 􀀭􀀺􀁾􀀺􀀳􀀠. . --􀁾􀀠:::j • In Bar Metric! rr.-nkPa 􀁾􀀭􀀺􀁾􀀵􀀠􀀭􀀺􀁾􀀡􀀿􀀠AIIQII3 AlIQ'" AJIQB7 lim 􀀻􀀻􀀡􀀮􀁾􀁾􀀮􀀳􀀠􀀭􀀺􀁾􀀡􀀶􀀠m3Jhr -$0... $0110 $0_ 12:41 -1." 0.05 · · 28.21 --49,51 · 225 0,12 ]. · · -· . 3.38 0.28 · -· 4.51) 0,49 0.07 · R75 · 0,20 -; -. -9.00 -0." · 11.25 · 0.6l 0," 13,51) -O.S/􀁾􀀲􀀧􀀠15.75 · -0,., 1•.00 · -045 22.50 --0,75 Installation 8/17/2004http://www.ewingl.comiewing/htmjpgs/02005314.htm Buckner: One Piece Quick Coupling Valve Spec Page 3 of4 Install all avc's on swing joint assemblies and hand tighten. Use only Teflon tape as sealant. Position and level as required 10 grade. http://www.ewingl.comiewing/htmjpgs/02005314.htm Quick Coupler Valve (One-Piece) In$ta1latiort Detail L Buckner series quick ooupler valve Model# _____ 2. finish grade 3. ____ PVC schedule 80 nipple (\..____ min. length) 4. PVC Tx T 90· ell 5. PVC street ell 6. ____PVC schedule 80 nipple \..(____ min. length) 7. Lateral line piping 8. Lateral line pipe fitting NOTE: Teflon tape all threaded joints. Quick Coupler Vatv. (One-Piec:e) Inatallallan Detail 1. Buckner series quick ooupler valve Model# ____ 2. Finish grade 3. ____PVC schedule ao nipple (L..____ min. length) 4. PVC Tx T90· ell 5. PVC street ell 6. ____PVC schedule aD nipple (L..____ min. length) 7. Laleralline piping 8. Lateral line pipe fitting 9. Rebar, length as required for support 10. SS Pipe clamps, size as required 8/17/2004 ARCHER WESTERN CONTRACTORS, L TO. 2121 Ave J, Ste.103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28, 2005 Submittal # :LI___.-!7::.6:.:.1___--' New Submittal: X To: HNTB i Town of Addison Re..Submittal : 16801 Westgrove Addison, Texas 􀀷􀀵􀀰􀀰􀀱􀁾􀀹􀀰􀀱􀀰􀀠Project: Arapaho Road Phase III ANV# 204059 (972) 450·2886 Engineer: HNTB Attn: GIlY Van·Baulen Submittal Specification Reference: Description of Submitted Item: Manufacturer/Sub/Supplier: Related Section /Drawings: 02810 􀂷􀁬􀁲􀁲􀁩􀁧􀁡􀀡􀁩􀁯􀁑􀁾􀁓􀀢􀁹􀀢􀀧􀁳􀀡􀀢􀀧􀁥􀀢 􀀧􀁭􀀧􀀭________1 Jumbo Box American landscape Systems 2810 Additional Comments: Contractor's Certification "Having Checked (his submission, we certify lhat it conforms to the requirements of the Contract in all respects, except as othel\v;se indicated." TItle: Asst. Project Manager Reviewed by: Andre'N Schneemann Date: June 26. 2005 Copy: ____-'-'''-____ SHOP DRAWING REVIEW Review is only for general conformance with the deSign concept of the contract documents. Markings or comments shall not be c.onstrued as relieving the contractor from compliance with the project plans and specifications, nor departures therefrom. The contractor remains solely responsible for details and accuracy, for confirming and correlating all quantities and dimensions, for selecting-fabrication processes, for techniques of assembly, for safety ilnd for satisfactory performance of his work. 􀁾􀁯Exception Taken 􀁉􀁾Corporation [J Make Corrections Noted [J Amend and Resubmit [J 􀁒􀁾􀁥􀀨􀀻􀁴􀁥􀁤􀀠-See Remarb Page 1of 1 Click Here to Print Page \METEK"ACCESS BOXES Jumbo Box Today, AMETEK, Inco Access Boxes are considered to be the best -within significant irrigation industries. An independent crush test at the University of Wisconsin Engineering Test Lab showed the AMETEK, Inc. Product to be much stronger than all of its competitors. Meter Boxes are manufactured in five major sizes. They have extensions, a variety of names and colors, and various applications in the turf Irrigation, waterworks and electrical Industries. Boxes are available in green, black, gray. tan, red brick and mulch brown. Uds come labeled with 'Control Valve; "Water Meter," "CATV," "Sewe(' and 'Telephone." 8117/2004http://www.ewingl.com/ewing/htmjpgs/38008510.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28, 2005 SUbmittal # : I 75.1 􀀧􀀭􀀭􀀭􀀭􀀭􀀧􀁾􀀭􀀭..... New Submittal: X To: HNTB I Town of Addison Re-.$ubmittal : 16801 WestgfOYe Addison, Texas 75001·9010 Project: Arapaho Road Phase III AIW# 204059 (972) 450-288£ Engineer. HNTB Attn: Guy Van-8aulen Submittal Specification Reference: [ 02810-Irrigation System Description of Submitted Item: Master I Slalion Valves i Manufacturer/SUD/Supplier: -C" American 􀁌􀁡􀁮􀁤􀁾􀁰􀁥􀀠Systems ; Related Section /Drawings: 02810-12 A & B Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it confonns to the requirements of the Contract in all respects, except as otherwise Indicated." Sign: Print Name: Andrew Schneemann ritle: Asst. Project Manager Reviewed by: Andrew Schneemann Date: June 28, 2005 Copy: File Engineer's Stamp SHOP DRAWING REVIEW Review is only for general conformance with the design concept of [he contract documents. Markings or comments shall not be construed as relieving the contractor from compliance with the project plans and speCifications, nor departures therefrom. The contractor remains solely responsible for details and accuracy, for confirming and correlating aU quantities and dimensions, for selecting' fabrication processes, for tecbnlques of assembly, for safety and for satisfactory performance of llis work. 􀁾􀁯Exception Taken llNI'B Corporation CI Make Corrections Noted CI Amend and Resubmit 􀁾􀀠CI Rejected -See Remarks By 􀀮􀁪􀁾􀀠DatA! 1/rl/6!"" Page 1 of3 􀀷􀀭􀁾􀀩􀀠\ CliCk Here to Print Page 11000CR SERIES CONTAMINATION RESISTANT VALVE The 11 OOOCR Series is a normally closed type valve; in the event of power failure, valve closes. The 11000CR has excellent low flow characteristics which make it an ideal choice for microirrigation. Features: • 5 Year Limited Warranty on valve, 7-Year Limited Warranty on the S24B solenoid. • Unique Dual Ported Diaphragm to greatly minimize clogging and malfunctions. In operation, the diaphragm ports constantly flex, inhibiting sand, silt and debris from blocking the valve action. • The unique porting design also permits equal pressure on both sides ofthe diaphragm wall, regardless of line pressure, when valve is not operating. This feature prevents diaphragm "stratching", a common cause of valve failure in valves which are ported through the seat. • The 11 OOOCR Series diaphragm is made of nylon fabric reinforced Buna-N rubber; a grooved rib interlocks with cover and body to prevent leakage. • Exhaust Orifice is non-corrosive and has an opening sized larger than the diaphragm ports so that any pieces of sand or silt passing through the diaphragm will not be trapped beneath the solenoid actuator. • S24B Solenoid manufactured by Weather-matico Construction is molded resin having no carbon stael components exposed thereby efiminating possible external corrosion and deterioration. Solenoid is completely waterproof, With an O-Ring Seal, and complies with NEC Class II circuit requirements for 24V a.c. operation (also operates on 12 volts d.c. up to 75 psi). • The S248 Pro-CaplM actuator is slain-less steel enclosed in a watertight protection capsule with a molded-in-place rubber exhaust port seal; a stainless steel spring assures pOSitive seating. • High Strength Glass-Filled Plastic Body and Cover designed to operate in heavy duty commercial applications. Stainless steel 1/4 inch cover bolts and mating brass body inserts make reassembly easy. • Shock Cone on diaphragm sealto eliminate water hammer in all except extreme cases. • Flow Control. A brass, non-rising type flow control stem for throttling the valve from full open to full close positions. 8/17/2004http://www.ewingl.com/ewingihtmjpgs/52002660.htm Page2of3 • Manual Bleed Lever. An easy-to-use, hand operated control bleeds valve to downstream; has stops for open and closed positions. Options: (Factory Installed) • XPR Pressure Regulator. The Weather-matic XPR pressure regulating module senses inlet pressure and maintains constant outlet pressure. See PRK-24 in valve accessory section for specifications. • Non-potable Alert Solenoid. May be substituted for standard model. Specify XS24NP. Operating Data: • Cold water working pressure: 150 psi Electrical: • Wiring requires a single lead from the controller to each solenoid, plus a common newalto all solenoids. Type UF wire, U.L. listed, is recommended for all hookups. 24VACI60 Hz. Inrush: 9.86 VA Holding: 5.69 VA 24VACI50 Hz. Inrush: 10.7 VA Holding: 7.5 VA • Do not use nominal voltage ratings listed above for sizing of valve wire. See wire sizing tables. Installation: • Teflon tape is recommended. • 1 inch FIP can be bushed to 3/4 inch. • 1 -1/2 inch FIP can be bushed to /-114 inch. • Intemational Threads. (Specify ISO) 8/17/2004bttp:llwww.ewingl.com/ewing/htmjpgs/52002660.htm Page 3 of3 .'" ""'ltallQWSi,....llJOl 􀁬􀁜􀁴􀁾􀀠􀁾􀀠1M 􀀮􀁾􀁾, U--, U " "'.1 " ... > , -" ••• J •• aD > ,. 1l.' T "" .., 1 "''1 u I __􀁾􀀠.. 1Ll! .. .a D..7 I ... __􀁾􀀺􀁾􀁾􀀧____􀁾􀁾􀀱􀁾􀀱􀁾􀁏􀀭􀁾􀁾 􀀭􀀡􀀺􀀠__,,'.."---I-___ 􀁾􀁾􀀮􀁟􀂷􀁾􀀽􀁉􀀠',2 __􀁴􀀢􀁴􀁾􀀬􀀺__+ 􀀫􀁾􀁾1, ____ [ __. 1M I lUI-r" 8/17/2004http://www.ewingl.com/ewinglhtmjpgsl52002660.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640·3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28, 2005 Submittal # :LI____􀀷􀀺􀀮􀀮􀀺􀀴􀁾􀀮􀀱􀁾____..J New Submittal: X To: HNTB/TownofAddison Re·Suhmittal : 16801 Westgrove Addison. Texas 75001·9010 Project: Arapaho Road Phase III ANV# 204059 (972) 450-2BB6 Engineer: HNTB Attn: Ow Van-BauJen Submittal Specification Reference: 02810 -Irrigation System Description of Submitted Item: Ball Valves 􀁍􀁡􀁮􀁵􀁦􀁡􀁣􀁴􀁵􀁲􀁥􀁲􀁉􀁓􀁵􀁢􀁩􀁓􀁵􀁰􀁰􀁬􀁩􀁥􀁲􀀺􀀭􀁾. American 􀁌􀁡􀁏􀀡􀀻􀀻􀁾􀁰􀁥􀀠Systems Related Section I Drawings: Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Centrad in all respects, except as otherwise indicated." An:her W !em Contm "'. Sign: Print Name: Andrew Schneemann Title: Asat. Project Manager Reviewed by: Andrew Schneemann Oat.: June 28. 2005 Copy: ____-'-''''-____ 02810-12C"-_______-' Engineer's Stamp SHOP DRAWING REVIEW REVIEW Review Is only for general conformance with the design concept of the contract documents. Markings or comments shall not be construed as relieving the contractor from compliance with the project plans and specifications, nor departures therefrom. The -l---,,,,,,,,,,actor remains solely responsible for details and accuracy, for 􀁾􀀠confirming and correlating all quantities and dimensions, for selectlnglfabrlcatlon processes, for techniques of assembly, for safety and for satisfactory performance of his work. I , Il!f No Exception Taken [J Make Corrections Noted [J Amend and Resubmit [J Rejected -See Remarks INrB COl'IIOration '1 􀁊􀀱􀁬􀁾􀀠By. Jft?.Date'__ ..."""􀁟􀁾􀁟􀁾􀁩􀀮􀁉􀁬􀀠 Page 1 of 1 ( Click Here to Print Page 2" Utility SS Ball Valve A high quality, economical, quarterturn shut off valve designed for home, irrigation, and pool and spa applications. Available in IPS sizes 1/2" through 2" with choice of either socket or threaded end connectors. Features: • One piece sealed unit never requires adjustment. • Heavy bodied PVC construction. • Standard EPDM o-rings. • High Impact Polypropylene handle with double stop engagement. • Equipped with Spears high strength Safe-T-Shear stem. • All Utility Ball Valves are NSF Listed for potable water use. • Full Schedule 80 bore in full open position, full bore virtually eliminates pressure drop, providing optimum flow. • 150 psi Pressure rating maximum internal pressure at 73"F for a variety of applications. :' Itlt. ,,,..11-' til' i':" 11" lid.'«\...um t 􀁾􀁭􀁬􀁾􀀠,f,/"'f'I"'In4!Utt"'} ("t"t fl.\) rUtj i-t\:. 􀀭􀀮􀀺􀀮􀀮􀁾􀀧􀀮􀀢􀁌􀀠..!±!.. 􀀧􀁾􀁾􀀮􀀧􀀬􀀻􀀠-􀁾􀀭. 􀀭􀀭􀀺􀀮􀀮􀁾􀁾.. 􀁾􀀧􀀡􀀺􀀮"', --rf'·􀁴􀂷􀁾􀀬􀀠" *' d 8117/2004http://www.ewingl.com/ewing/htmjpgsl20001860.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 26, 2005 Submittal # To: HNTB I Town of AddisOll New Submittal: Re-Submittal : X Attn: 16601 WestgroYe Addison, Texas 75001-9010 (972) 450·2886 Guy Van-Baulen Project: Arapaho Road Phase III AfW# 204059 Engineer: H NTB Submittal Specification Reference: Description of Submitted Item: SOlvent Weld PVC Manufacturer/Sub/Supplier: American Landscape Systems Related Section I Drawings; Additional Comments: Contractor'S Certification "Having Checked this submission, we certify 􀁴􀁨􀁾􀁴􀀠it confonns to the requirements of the Contract in all respects, except as otherwise indicated." Archer Westem c?;ft",rac.:' Sign: 􀁾􀀠.,./'" /" POnl Name: Andrew 􀁓􀁣􀁨􀁮􀁥􀁥􀁾􀁡􀁮􀁮􀀠Title: Asst. Project Ma.nager Reviewed by: Andrew Schneemann Date: June 2B, 2005 Copy: _____􀁆􀁾􀁉􀁉􀀺􀀺􀀺􀁥____ Engineer's Stamp SHOP DRAWING REVIEW ReView Is only for general conformance With the design concept of the contract documents. Markings or comments shall not be 􀁉􀁾􀁯􀁮􀁳􀁴􀁲􀁵􀁥􀁤􀀠as relieving the contractor from compliance with the r----project plans and specificatiOns, nor departures therefrom. The contractor remains solely responsible for detalls and accuracy, for confirming and correlating all quantities and dimensions, for 􀁳􀁥􀁬􀁥􀁣􀁴􀁪􀁮􀁧􀀧􀁦􀁡􀁾􀁬􀁣􀁡􀁴􀁩􀁯􀁮processes, for 􀁴􀁥􀁣􀁾􀁮􀁬􀁱􀁵􀁥􀁳􀀠of assembly, for safety and for satisfactory performance of his work. 􀁾􀁯Exception Taken IWTB Corporation [J Make Corrections Noted [J Amend and Resubmlt [J Rejected -See Remarks . Ewing Irrigation Products Catalog: PVC, Fittings page:.: ot 1. C' 1 ,.J<.-hI11Imi 73/(12Slt;l'if) 5 6 a 10 SOil, Out:&fde Jnside J Weill ' , Diameter , ,Thldme-ss it i (inc....) (lI>eM,)! (I"ohesl 6;lIPS ! 64 5.563 i 6.37. O.O!S1 160 IPS 2Ii' _200 􀁾_J 􀁾􀀱􀀠J SGH 4011"1; ISO Nil 6311'5 64 -;<;oIPs f 41 12511"5 : 32,5 .. -160 IPS 􀁾􀀠􀁾􀁉􀀾􀀠200 IPS 21 .SCH 40iPA 11101 NA SCH eO/PIl2BO' NA 5.563 .." "'ts..sea i 􀀵􀀮􀁾􀀠􀁓􀁾􀀵􀀶􀀳􀀠I .... -...􀁾􀀮􀀠􀁾􀀮􀀻􀀶􀀳􀀠52:i6a , J 6.0>5 -' I6.625 6.62;' : . _·····t··· 􀀶􀁾􀀠! &.625 6.625 , 􀁾􀀮􀀻􀀻􀀲􀁓􀀠, 5.27 0,138.. ,------5.19 0.171 􀁾􀁾􀁩􀁏􀀠, 0.214 􀀴􀀺􀀹􀀹􀁾􀀱􀂷􀀠Q.2GS 􀀬􀀬􀁾..,;J,(J1 􀁏􀀮􀁚􀁾􀀠4.76 0.375 'I.btH /fft/7/. I 02.$ i 0 .-1'-1 [ Click Here to Print Page PVC Sch 80 Nipples 8/17/2004http://www.ewingl.comlewinl¥htmjpgsl04005390.htm ARCHER WESTERN CONTRACTORS, L TO. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640.3898 FAX: (817) 640·8734 SUBMITTAL Date: June 28, 2005 To: Attn: HNTBfTownofAddison 16801 Westgrove Addison, Texas 75001-9010 (972) 450-2886 GuyVan-Baulen Submittal Spec1ficatron Reference: Description of Submitted Item: Manufacturer/Sub/Supplier: Submittal # :L.I___.....:7.;.O:..:.1___.. ....J Project: Arapaho Road Phase III L _____􀀭􀀧􀀰􀁾􀀲􀁾􀀸􀀱􀀧􀁟􀀢􀁏􀀮􀁾􀀠Irrigation System Rain Bird 1aoo Series Sprinkler Head American Landscape Systems New Submittal: X Re-Submittat : ANV# 204059 Engineer: HNTB Related Section I Drawings; 02810·13 A & C Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as otherwise indicated." Archer Western Co 􀀺􀁾􀁾􀀺􀁴􀁎􀀮􀁭􀁾􀀠 Title: Asst. Project Manager Reviewed by: Andrew Scttneemann Date: June 28, 2005 Copy: ____-'-""-____ 4" Tan Heads in the Grass. Areas 12" iall Heads Heads in landscape Beds Head Pattems will be selected to best fit the situation Engineer's Stamp SHOP DRAWING REVIEW Review Is only for general conformance with the design concept of the contract documents. Markings or comments shall not be construed as relieving the contractor from compliance with the project plans and Specifications, nor departures therefrom. The contractor remains solely responsible for details lind acculaCY, for confirming and correlating all quantities and dimenSions, for selecting·fabrlcationprocesses, for tec:linlques ofassembly. for safety and for satisfactorv perfol'llWlCe of his work. 􀁄􀁾􀁯Exception Taken Ilm'J Corporation Ii)lake Corrections Noted fi(Amend and Resubmit D Rejected 􀁾􀀠See Remarks By., Jg.K Date 7/Z1<,t: * dF 􀁉􀁗􀁾􀀠PCN. 70./. r-, ? ufO -1"L!t-t) .._}[ CliCk Here to Print Page) RAfN:l-BIRD 1800 Series, 1800-SAM 1800-PRS,1800-SAM-PRS Primary Application Industries leading series of spray sprinklers for turf and shrub applications. FeaturesI • Precipitation rates matched across sets and across patterns. • Ratcheting on all models. • Exclusive pressure-activated wiper seal. • Plastic and stainless steel materials, • Seamless, mOlded construction. • Strong, stainless steel retract spring, • Side or bottom Inlet on 1806 and 1812 only. Industries leading series of spray sprinklers for turf and shrub applications. Operating Range • Precipitation Rate .42 to 11.7 Inches per hour. • Spacing: 3 to 20 feet, • Pressure: 15 to 70 psi. • Specifications • Flow-by 0 at 8 psi or greater: 0.05 GPM otherwise. Dimensions • 1/2" female threaded inlet. 1800-SAM Series 8/17/2004http://www.ewingl.com/ewinglhtmjpgs/35003496.httn rage '-OJ ';I Ideal for use in areas with changing elevations. Features: • Suilt-in Seal-A-Matic (SAM) check valve. • Reduces low head drainage, puddling and erosion. • Eliminates the need for under-the-head check valves. 1800w pRS Series Designed for areas with high and/or widely fluctuating water pressures. Features: • Unique built-in stem pressure regulator. , • Delivers uniform water distribution at an 􀁡􀁶􀁥􀁲􀁡􀁧􀁾􀀠30 psi. • Ends misting and fogging caused by high pressure. 1800-SAM-PRS series Meets the needs of all spray areas, regardless of changing elevation or water pressu res. Features: • Built-in Seal-A-Matic (SAM) check valve. • Reduces low head drainage, puddling and erosion. • Ends misting and fogging caused by high pressure. Performance Charts 5 series MPR 5 Trajectory I • ... ! Nozzle Pressure psi Radius ft. Flow GPM Precip In/h PreciIn/h p SF 15 2 0.09 2.07 2.39 I 8/17/2004http://www.ewing1.com/ewing/htm jpgs/35003496.htm 20 3 0.19 2.01 2.32• 25 4 0.27 1.62 1.87 30 5 0,41 1.58 1.83 5H 15 2 0.04 2.07 2.39 20 3 0.09 2.01 2.32 , A 25 4 0.13 1.62 1.87 , 30 5 0.20 1.58 1.83 I 5T 15 2 0.03 2.07 2.39 I 20 3 0.06 2.01 2.32, 25 4 0.09 1.62 1.87 30 5 0.13 1.58 1.83 5Q 15 2 Oi02 2.07 2.39 20 3 0.05 2.01 2.32 .. 25 4 0.07 1.62 1.87 30 5 0.10 1.58 1.83 Series MPR 10 Trajectory • .. I Nozzle Pressure Radius Flow Precip Precip I psi ft. GPM In/h In/h ' 8F 15 5 0.54 2.07 2.39, 20 6 0.75 2.01 2.32 ! , • 25, 7 0.82 1.62 1.87 30 8 1.05 1.58 1.83 8H 15 5 0.27 2.07 2.39 20 6 0.38 2.01 2.32 A 25 7 0,41 1.62 1.87 , 30 8 0.52 1.58 1.83 i I I pageJ or':) 8/1712004http://www.ewingl.comlewing/htmjpgsI35003496.htm Page 4 of9 15 5 0.18 2.07 2.391sT , 0.25 2.01 2.3220 6! 7 0.27 1.62 1.8725 ! 0.35 1.58 1.83830 0.13 2.07 2.39515SQ 2.01 2.320.19620 • , 1.62 1.870.2125 7 8 0.26 1.58 1.8330 10 Series MPR 15 Trajectory Nozzle 10F ! •! 10H .. lOT , 10Q • , Pressure psi 15 20 25 30 15 20 25 30 15 20 25 30 15 20 25 30 Radius ft. 7 8 9 10 7 8 9 10 7 8 9 10 7 8 9 10 Flow GPM 1.16 1.30 1.44 1.58 0.58 0.65 0.72 0.79 0.39 0.43 0.48 0.53 0.29 0.33 0.36 0.39 • Prec:ip In/h 2.28 1.96 1.71 1.52 2.28 1.96 1.71 1.52 2.28 1.96 1.71 1.52 2.28 1.96 1.71 1.52 .. Prec:ip In/h 2.63 2.26 1.98 1.75 , 2.63 2.26 1.98 1.75 2.63 2.26 1.98i 1.75 2.63 2.26 1.98 1.75 12 Series M PR 8117/2004http://www.ewingl.com/ewing/htmjpgs/35003496.htm 30 Trajectory • • ,Nozzle,Pressure Radius Flow Precip Precip! 'i ! psi ft. GPM In/h In/h 12F 15 9 1.80 2.14 2.47 20 25 10 2.10 11 2.40 2.02 1.91 2.34 2.21• 30 12 2.60 1.74 2.01 15 9 1.35 2.14 2.47 20 10 1.58 2.02 2.34 25 11 1.80 1.91 2.21 30 12 1.95 1.74 2.01 12TQ 15 9 1.20 2.14 2.47 20 10 1.40 2.02 2.34 12TT 25 11 1.60 1.91 2.21 30 12 1.74 1.74 2.01 12H 15 9 0.90 2.14 2.47 20 10 1.05 2.02 2.34 25 11 1.20 1.91 2.21 30 12 1.30 1.74 2.01 , 15 9 0.60 2.14 2.47 20 10 0.07 2.02 2.34 12T 25 11 0.80 1.91 2.21j 30 12 0.87 1.74 2.01 15 9 0.45 2.14 2.4712Q i 20 10 0.53 2.02 2.341 .. i 25 11 0.60 1.91 2.21 􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀁾30 12 0.65 1.74 2.01l 15 Series MPR 30 Trajectory • I • rage;) or "? 8/17/2004http://www.ewin g1.com/ewing/htmjpgs/35003496.htm I ! INozzle Pressure Radius Flow PrecipIPrecip psi ft. IGPM In/h i In/h I ! 15F 15 11 2.60 2.07 2.39 20 12 3.00 2.01 2.32i• 25 14 3.30 1.62: 1.87 30 15 3.70 1.58 1.831 , 15TQ 15 11 1.95 2.07 2.39 20 12 2.25 2.01 2.32 I· 25 14 2.48 1.62 1.87 30 15 2.78 1.58 1.83 I 15Tr 15 11 1.74 2.07 2.39 I 20 12 2.01 2.01 2.32 1 25 14 2.21 1.62 1.87 30 15 2.48 1.58 1.83 15H 15 11 1.30 2.07 2.39 1 I 20 12 1.50 2.01 2.32 I .. 25 14 1.65 1.62 1.87 30 15 1.85 1.58 1.83 1 15T 15 11 0.87 2.07 2.39 20 12 1.00 2.01 2.32, 25 14 1.10 1.62 1.87 30 15 1.23 1.58 1.83 15Q 15 11 0.65 2.07 2.39 20 12 0.75 2.01 2.32 tit. 25 14 0.82 1.62 1.87 30 15 0.92 1.58 1.831 15 Strip Series 30 Trajectory • • 1 I Ii Nozzle Pressure WxL Flow I 8117/2004http://www.ewingl.comiewing/htmjpgsI35 003496.htm ragt; I VI ;7 , psi , ft. GPM 1 ! l5SQ 15 18 X 18 2.68l 20 19 X 19 3.06 1• 25 21 X 21· 3.42l 30 23 X 231 3.73! , 1 , l5EST 15 4 X 13 I 0.45: , 20 4 X 14· 0.50 I 􀁾􀀠25 4 X 14 0.56 , I 30 4 X 15 0.61 l5CST 15 4 X 26 0.89 20 4 x28 1.00 -25 4x 28 1.11 30 4 X 30 1.21 15SST 15 4 X 26 0.89 20 4 X 28 1.00 , 25 4 X 28 1.111 I -30' 4 X 30 1.211 i j 9SST 15 9 X 15 1.34 1 i 20 9 X 16 1.47 : I • 25 9 X 18 1.60 30 9 X 18 , 1.73 ! 16 Series MPR 15 Trajectory • .. I i i Nozzle Pressure Radius Flow I psi ft. i GPM I 1 ! 8/17/2004http://www.ewing1.com/ewing/htmjpgsI35003496 .htm 16 f-SLA 15 13 2.371 20 14 2.66 *'... 25 15 2.96 1 i 30 16 3.22 16H-5LA 15 13 1.18 I i 20 14 1.33 i :iJk 25 151 1.48/30 16 1 1.61 i i 16Q-5LA 15 13 0.59 i 20 14 0.67 .'i::. 25 15 0.74 30 16 0.81 ,'" -...􀁾􀀭􀀮􀀭􀀭􀀭..􀀭􀀭􀀭􀀭􀁾􀀮􀀭...,. , ..􀁾􀀮􀁾􀀠􀁾..... .. 􀁾􀀭􀀭.. 22 Series M PR 35 Trajectory ..I • i Flow'Pressure IRadiusNozzle GPMpsi . It. 22F-55 15 17 2.37 20 18 2.66 25 2.9619 􀁾􀀠3.2230 20 I 15 17l 1.1822H-55 18 1 20 1.33 : 􀁾􀀠25 19 1.48 : 30 20 1.61 17 0.5915 22Q-55 8/17/2004http://www.ewingl.com/ewing/htmjpgsl35003496.htm • • \2:. 20 18 0.67 25 19 0.74 30 20 0.81 Series Stream Bubbler Nozzles oTrajectory Pressure Radius Flow Nozzle psi ft. GPM * SF-B 15 5 1.50 20 5 1.50 25 5 1.50 30 5 1.50 SH-B 15 5 1.00 20 5 1.00 25 5 1.00 30 5 1.00 SQ-B 15 5 0.50 20 5 0.50 .{. 25 5 0.50 30 5 0.50 SCST-B 15 5 0.50 20 5 0.50 25 5 0.50 30 5 0.50 􀁾􀀧􀀮􀀺􀀠Note: Indicates adjusted radius @psi shown. Note: Flow @adjusted radius of 5 feet. 􀁾􀀠 8/17/2004http://www.ewingl.comiewing/htmjpgsi35003496.htm .Page 1 ot 1 Click Here to Print Page j TORO Toro Compensating Flood Bubbler Nozzles Features: • Built-in pressure regulation • 2 GPM adjustable flow • 0.25, 0.50 and 1.0 GPM fixed flow • All pressure compensating, nil-intalning constant 30 PS( performance at pressures exceeding 30 PSI • Use on shrub adapter, 570Z Series sprinkler, 570 risers :and riser extenders Specifications: • Recommended operating range: 20-50 PSI • Maximum operating pressure: 75 PSI 􀁾􀀧􀁜􀀠&'1!JrtJ.PVE'<2, 􀁾􀀠8117/2004http://www.ewingl.comiewing/htmjpgs/30009202.htm J:;wmg rrngsnon t'roauc,s "Stalog: .DUU.D':;U ( Click Here to Print Page 􀁒􀁁􀁉􀁎􀁾􀁂􀁉􀁒􀁄􀀠Plastic MPR Nozzles Primary Application Matched Precipitation Rate (MPR) nozzles simplify the design process by allowing sprinklers with various arcs and ready 10 be mixed on Ihe same circuil. Models available for spacing from 3 to 20 feel. Fil all Rain Bird spray heads and shrub adapters. Features -Matched precipitation rates across sets and across patterns in new 5 Series, 8 Series, 10 Series, 12 Series, and 15 Nm-OTV LIlfl..i>JEfa Series for even water . -I ' 􀁜􀁌􀁾􀀠distribution and design 􀁾__--_..c---""--flexibility . -New 5 Series nozzles meel smell-area shrub or turf requirements. -New and Improved 8 Series nozzles now have a lower water flow which allows more spray heads per zone. -1800 Series white niter (.035" x .045") screens (shipped with nozzles) maintain precise radius adjustment and prevent clogging. (New and improved 5 and 8 Series nozzles are shipped with blue nne·mesh (.02" x .02,,) filter screens.) -Stainless steel adjustment screw to adjust flow and radius. Operating Range: -Spacing: 5 10 15 feet (1,5 to 4,5 m) -Pressure: 15 to 30 psi (1 to 2,1 bar) -Optimum pressure: 30 psi (2,1 ber) Models -5 Series -5 Series: bubbler nozzles -a Series -10 Series -12 Series -15 Series -15 Strip Series -18 Series: stream spray -22 Series; standard stream spray 8/17/2004htlp:llwww.ewing1.com/ewinglhtmjpgs/35003820.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28, 2005 Submittal II :LI___􀀭􀀽􀀶􀀹􀁾􀀮􀀱􀀮􀀺􀀮􀀮􀀮􀀮􀀮__.... .J New Submittal: X To: HNTB JTown of Addi$on Re.submittal : 16801 Westgrove Addison, Texas 75001·9010 Project: Arapaho Road Phase III A1W II 204059 (972) 450-2886 Engineer: HNT8 Attn: Guy Van-Bal..llen Submittal Specification Reference: L _____􀁾􀁏􀀬􀀲􀀸􀀱􀀰􀀠-Irrigation System Description 01 Submitted Item: Mini Clik: tI Rain Sensor Manufacturer/Sub/Supplier: Related Section /Drawings: 02810-20C Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the tequitements ofthe Contract in all respects, except as otherwise Indfcated. " TItle: Asst. Project Manager Reviewed by: Andrew Schneeman" Oate: June 26, 200$ Copy: ____-'-Fl=do'--___ Engineer's Stamp SHOP DRAWING REVIEW Review Is only for general conformancewlth the design concept of the con\ract documents, Markings or comments shall not be construed as relieving the contractor from compliance with the project plans and specifications. nor departures therefrom. The contractor remains solely responsible for derails and accuracy. for confirming and correlating all quantities and dimensions, for selectln!l'fabrlcation processes, for teclm!ques of 8I)sembly. for safety and for satisfactory performance of Ills work. Cfto Exception Taken Sflake Corrections Noted I!fAmend and Resubmit C Rejected -See Remarb .. '* 􀀤􀀬􀀭􀀬􀁾􀁾􀀮􀁊􀀺􀀮􀀮􀀮􀀭􀁾1J-l ..........QC 􀀨􀁬􀀮􀁁􀀱􀁾􀀠..... 􀁾􀀬􀀠􀁾::stl-f 􀁲􀁾􀀧􀁓􀀠/l-Jro---IS 􀀬􀁾􀀬􀀠""" , ","" 􀂷􀁾􀁒􀁊􀀮􀁪􀁉􀁎INiSriR® '.' 􀀮􀀾􀁾􀀧􀀬􀀠 .-.; .-, ' .', ' ,', 1 825,103 Surveyor Avenue, Simi Valley, CA 93063 Ph: 805 527·4498 Fax: 805527·2813 UN.'''' ,.,.,i .... mnd...r r("tr'f'\ o EVOLUTION DX2 SPECIFICATIONS The Evolution DX2TM irrigation controller shall be manufactured by Rain Master Irrigation Systems, Inc. The controller shall have the following features and functions: 􀁾􀀮􀁊􀀬􀀮􀁽􀀠",p-ArJo I􀁾􀁾􀀧􀀻􀀻􀀩􀀠 Part 1.0 -Hardware Features f'£1!-􀀮􀀮􀀮􀀬􀀧􀀢􀁾 ..-_-1.__ 'Sr",(..:l'i u", I 1.1 all mount cabinet or pedestal enclosure. 1.2 Station configuration options 6, 12, 18, 24, 30, 36, 42 or 48 stations. Dedicated outputs for 2 normally closed master valves, 1 normally open master valve, and 1 pump. ,! 1.3 Connectivity for 4 input sensing devices. Fbur pulse input type devices e.g. flow sensors, flow meters, ET device, rain gauge, anemometer, etc. 1.4 80 character LCD display \vith 24-key membrane keypad. -'. 1.5 Built-in remote control jack. Permanent internal remote mount available.) 1.6 Built-in transient protection. 1.7 Optional lightning protection available. 1.8 Audible tone(s) for valid or invalid operator entry. 1.9 Lifetime retention of the user's program and :date/rime, without the use of batteries. 1.10 All outputs are protected from field wiring short circuits. 1.11 Built in amperage meter to accurately measure and diagnose valve solenoid electrical problems. 1.12 Modular architecture. Modular output boards (6 or 12 station) facilitate maintenance and elitninates total controller down time. RMIS PART No. 500675 Rev. A Page I EVOLUTION OX2 SPECIFICATIONS 2.0 -Scheduling Capabilities 2.1 Operation of12 conventional programs with 8 start times, 48 ISC (individual station control) or a combination ofeach. 2.2 Watering based upon 14-day schedules, skip day schedules, or 31-day schedules. 2.3 Continuous cycling of programs based upon user established start and end times, with a programmable delay/soak time. 2.4 Water budget per program from 0 to 999% in 1 % increments for adjustrnemof program run times 2.5 Program by time. 2.6 Programmable monthly water total terminates over budget irrigation. 2.7 Quick station programming allows groups of stations to be programmed with the Same runtime. 2.8 Programmable water window. 3.0 Program Setup Options 3.1 Programs overlap protection or concurrent operation. 3.2 Irrigation programs, lighting programs, security, etc. (Non-irrigation programs are independent of rain shutdown mode.) 3.3 Inter station delay from 0 to 255 seconds. 3.4 Runtimes from 1 second to 24 hours programmable in hours/minutes Or minutes/seconds. 3.5 Master valve selections: 2 Normally Gosed Valves or Normally Open Valves with programmable delay from 0 to 600 seconds. Page 2 RMIS Part No. 500675 Rev. A EVOLUTION DX2 SPECIFICATIONS 4. 0 Maintenance and Alarm Diagnostic Capabilities 4.1 Flow monitoring. Automatic alann processing (which provides station and/or master valve shut down and program advance as required) diagnosing and reporting station underflow and overflow, mainline breaks, and unscheduled flows. Maximum upper flow limit is 2000 GPM. 4.2 Electrical field wire monitoring. Automatic alarm processing (which provides station shutdown and program advance) for station over current, short circuits, broken field wiring or faulty solenoids. _ ; \ 4.3 Power monitoring. Automatic alarm prqcessing/reporting for power outages and power restoration. Intelligent program resumption for all outages or power glitches, no lost cycles or water window violations. 4.4 Communication monitoring. Automatic alarm generation/reporting for lost communications or restoration when using hard wire communications. Automatic fault isolation of communication wiring problems to wire path between controllers. ) 4.5 Diagnostic lights (LEDs) for all station outputs as well as the dedicated outputs: :MV1, MV2, N.O. MV, and PUMP. Lights indicate when 24 VAC is at output temlinal. 4.6 Built-in test (BI1) functions allow selected controller circuitry to be field-tested. 4.7 Manual test mode. Allows user to automatically advance from station to station using manual run time while displaying valve solenoid electrical current for each station as well as station flow in GPM. 4.8 Manual station and manual multi-station modes. -Turns on any station for user entered runtime and automatically selects usage of the proper master valve and/or pump for this station. Multistation mode allows any single station or output to be turned on individually or in combination with any other station(s). Valve solenoid electrical current is displayed. 4.9 Manually entered program. Allows user to enter a one-time program to be run immediately or scheduled for la ter in the day. The manual program is independent of automatic programs and shaU start onl)' one time. time. 4.10 Manual starr ofautomatic programs (1-12). Start any program independent of the scheduled start time and water day. RMIS PART No. 500675 Rev. A Page 3 EVOLUTION DX2 SPECIFICATIONS 5.0 Miscellaneous Features 5.1 English/Spanish language selection. 5.2 Automatic limit setup (learn mode) for flow lllld current. Global percentage adjust for limit establishment. . 5.3 Omit by date allows the user to enter up to 15 dates to exclude irrigation. 5,4 Operates as a standalone or central. 5.5 Fertilizer injector station with programmable delay from 0 to 255 seconds. 5.6 Flow Max -This exclusive feature allows controllers with a single point of connection to share a pump, master valves, and flow meters without the need for peripheral wiring/relays. All flow limits are dynamically managed as stations across controllers trllllsition off and on. Features include: A. Automatic protection and reporr for main line breaks, unscheduled flow, station high and low flow. . B. Read flow at any controller C. Dynamic monitor shows system status at all times D. Pump protection during exception conditions 6.0 Electrical Specifications .6.1 Input Power Required: 117 VAC +/-15%, 60 HZ, 20 VA, plus load current. 6.2 Maximum load current per station or master valve output: 1 AMP 6.3 Maximum combined load current: 2 AMPS 6.4 No batteries required. Page 4 RM1S Part No. 500675 Rev. A Evolution DX2 Stainless Steel Pedestal Cabinet Installation 15.5" 15.5" 􀁍􀁯􀁵􀁮􀁴􀁩􀁮􀁾􀀠Pad28"x 28 x 8" minimum concrete P!Id with beveled edges --r----' Pedestal Mounting Mounting Templateprovided for easy installation 1.75" Iyp. 6.5"-1 Bolt Holes-stainless steel hardware standard with enclosure CD .. to. 0® I 3.5" 13.5" @I ®--I CL.I 8·.·.L􀁔􀁃􀂩􀁾􀁾􀀰􀁟􀁂-,-,-_®,-'-1 0 J /ffont/1-/'---15"------..; Bolt and Conduit Template .RMIS Part No. 5005G1 Rev. B Item Description A,B 2" conduit· station wiring C 1" conduit· communication D AC power conduit E 1" conduit· sensor wiring I F External antenna G Grounding rod Rain Master is a technology-based, innovative, environmentally sensitive company dedicated to providing water management solutions to the irrigation industry. 􀁾􀁈􀁁􀀧􀀧􀀧􀀧􀀧􀀧􀀧􀀧􀀧􀀡􀁊􀀮􀀧􀂧􀀮􀁬􀁳􀀺􀁭 3910-B Royal Avenue, Simi Valiey, CA 93063 ph: 805 527-4498" Fox: 805527-2813 Evolution DX2 Stainless Steel Pedestal Cabinet AC on/off swikh with built-in GFI ulility outlet Stainless steel Two P.!lint lakhingulility door o o Louvered vents top and bottom with splash guard filter RMIS Part No. 500502 Rev. B Locking Lid Natural brushed stainless steel finish reAects surrounding colors Angled stalion terminal boards provide easy accessibility Rain Master is a technology-based, innovative, environmentally sensitive company dedicated to providing water management solutions to the irrigation industry. 􀁾􀀢􀁁􀀮􀁎􀁉􀁄􀀮􀀡􀀡􀀮􀀮􀀮􀁾􀀻􀀮􀁀􀀡􀀠 391O-B Royal Avenue, Simi Valley, CA 93063 ph: 805 527-4498 Fax: 805 527-2813 document basket , •• c .. Versatile 􀁐􀁾􀁧􀀧􀀠􀁏􀁰􀁾􀁡􀁬􀁊􀁾􀁦12 􀁃􀁾􀁾􀁶􀁭􀁪􀁩􀁯􀁮􀁡􀁊Programl andiar ;ndillitirudJt4&ial1 amrrol Up (0"8 rtart:tim'es dtJ; or rontinuous 'lck wi.h progrnmmabt: soak limt 14 day ,chrduk, ,kip by Joy, .,31 day "",uring feh""j" Multiple MasUr 􀁾􀁉􀁶􀁲􀁾􀀠􀁳􀁾􀁫􀁣􀁴􀁯􀁮􀁾􀀠offWC?fIdJttr 􀀱􀀡􀁦􀁉􀀱􀀱􀁉􀁾􀁳􀀬􀀠nndil PUll1P, on aprr pr(}gmm bllJiJ. !111m nonnoliy opmtd or nurmally c/oml. " • 􀁍􀁵􀁬􀁴􀁩􀀭􀁌􀁩􀁮􀀦􀁵􀁡􀁬􀁬􀁮􀁵􀁲􀁦􀁩􀁵􀁾􀀠-d4signtd to opmzu in !tvmtllanguagtJ Programmabk stntlon nmlirnn/fI.>m 1 !aona to 24 Duun f InuNtation Jdayfom 0 to 2551tConds Warer rationing tools: 􀁾􀁴􀀨􀀱􀀧􀀠Imdgn from 0 to 999% in 1% incrtmtnn ltugrammahlt waUr window Programmilhk fJHJllthly wnur total tmninotu 􀁏􀁬􀁬􀁴􀁲􀀮􀀮􀁊􀀩􀁦􀁉􀁊􀁧􀁾􀁴􀀠ir rigation Omit by daft exclusion foaturt Pntgmmmable rain􀁦􀁩􀁡􀁴􀁵􀁾􀀠 Reliable Modular D";gn Modular 1hort circuitproqfOUtpUll IlI!ailabk/mm 648!tImom in 6sffttiOJl incrtmrnts Upgratkfor untral communitnrhm1 atany rimt 􀁉􀁮􀁤􀁲􀁦􀁩􀁮􀁩􀁾􀀠􀁾􀁴􀀨􀁭􀁩􀁯􀁮􀀠a/pegramt MUltlt tlJ 􀁲􀁩􀁭􀁾and dale dun'ng aU􀁰􀁮􀁷􀁾􀁲flitrm; Oplional 􀀢􀁾􀁡􀁬􀁬􀁊􀀠duty lightning tIltd Jltrg( for lightningpront /mat .Integrated Flow Monitoring 􀁐􀁲􀂣􀁲􀁯􀁾􀀠highIJow tlatio1'/, mainlin£. tmJ uflJ£htdukd limits 􀁄􀁾􀁩􀁣limit adjustmtnlfor 􀁭􀁴􀁬􀀡􀁴􀁩􀁾􀁲􀁴􀁡􀁴􀁩􀁯􀁮􀀠nptrDtion • Attto lmrn jUnai(m with dimt GPM readout in dirpkty • lntelhgmta!mm 1WtijicatWn, nation coMmmmion. andprogram advmumtmr -'. , \ Integna",d E1eruical Cumnt Monitoring 􀀧􀁾􀀩􀀠Built#in tkrmcal currrnt 􀁭􀂣􀁦􀁾􀁲􀀠with amp(rag( lIinmd in diJplay Q;ntinuollJ (kmical mUJUrt:mmt o{ttitrion Si1ItlUJidi, masttr valvti. pumps Auto kam fimrtiOIl with adjusf.4bk high ondlow Jimiu Dynamic limit adjuttmmrfor 􀁭􀁵􀁬􀁴􀁩􀁾􀁪􀁦􀀴􀁴􀁕􀁭􀀠op('fation lnuUigmtalann rwtijiCfltWn. !tatum amtiemltl1tion. andprogtam adllOnwnmt Intelligent Single Point of Connection Operation f Shot( asingle flow fnttlr and maJur llIllwlpump I1crtm multipk conrrti1lm. • Fit;w limiu 11" inulligmfly and dYllnmicil/ly updatl!d i1! lwionJ Imltfi/ion prollidingfililprouttionfor moiu/int, nation. and 􀁬􀁩􀁮􀀮􀁳􀁣􀁨􀁾􀁤􀁵􀁫􀁤flow • lUodflow at any conl1'oIler Manual Diagnostic Features Multi-italian opmrtion with im/an/Ol1m" jlotvlcumnt 􀁶􀁩􀀨􀁦􀁦􀀩􀁾􀀧in disploy SJl!pn station d,«k ConlToikr built-in J(lfu>t Diagmmic LEDs for a/10UtplltJ Rain Mtlltfr Rnnalt muly 􀁍􀁵􀀱􀁴􀁩􀁾􀁭􀁯􀁤􀁥􀀠reliable communications • biMdimtiortl1/(two"rwy) communications cruuu irJttgriry • Hardwin, UHFpoint to poim radio, tnmk mdio, .(tl{ular, UHF stort ilJlti forward radio, phon!, rtpMur opmuion Field or Cenrral Programming Full $iPpOr! for contro""progrommbrg in thtfidd or ar mltml utilizing comparison manogtmtnl tlJQls on the PC Trvo·/trd.Pt1J!I(}Qrd tufmatlit,tlltd by tlx: USN prouro ag!lintllln(lJIlhorfud madijifario!H to controlltr progri11l1!i 1825-103 Surveyor Avenue' Simi Vall,y, Califomia 93063' 805.527.4498 • Fax 805.527.2813' www."innt.lM 1 til WHITE FOR FLOW -SENSOR IPRO\1DEDjiNPUT I.. VALVE SOX 1NM1MI1IVIlIT SLACK 􀁾􀀠" ' I " /, '" _,,' 1_,,' 􀁾􀀬􀀠. ';c" 1,,::'1' • t.;;,;.,;.J .,.. BLK /'" DIRECTION OF FLOW . 0 .. 􀁍􀁓􀁾􀁴􀁁􀁃􀁋􀀠, 1 􀁾􀀠"'-,, I' "" -􀁾􀀠,"-, \-, .. '" ",,'-/\-, i -.-..,--. -1 '-, . " -"'-,1, \ I' v, .f \ 1 1-\ '), 1'/-\,....... \ OJ I " " "... ,,-I ''',... -J f ,,}.:-.,:.... /,;!... I -t;"'*\. 􀁾􀀠" /;,_-I 􀀺􀁜􀀬􀀬􀁾􀀠.. ",,I' /)-I " "',MS1FN'Hr '\ !" '" "," -" .. I '\ I' -" .. I I1, f t ' /" 'I ,,\ I 􀁾􀀠\,! I \ I \ 􀁉􀁉􀁾􀀯􀀧􀀠􀁾􀀠r,l 􀁾􀀠􀀺􀁬􀁬􀀧􀁾􀀱􀀠;'" 􀁲􀁩􀀬􀀭􀀢􀀡􀀧􀁾􀀠􀁴􀁜􀀺􀁾􀀯􀀬􀀻􀀠,1) 􀁾􀁜􀀻􀀻􀁜􀁉􀀢􀁘􀀻􀀾􀀠I .. _ I " " .. .--". ... _ ! _ 1" " ", ... .--_ '" _ ! _ 􀁾􀀠'" ", '" ........... _ j _" ..... ')"': .... j-/\,.:' y.: ....... I\h..... ",\: /: -(1/'SENSOR \\-􀁉􀀧􀀯􀀢􀀧􀁉􀁾􀀭" ...... '1'-1,/",\,,",,-\􀀭􀁪􀀢􀀧􀁜􀁩􀀢􀀧􀀢􀀢􀀬􀀭􀀭􀁾􀀭􀁜􀁾􀀺􀀢􀀠'f"!;' ".::\-)-􀁾􀀧􀁻􀁜􀀬􀀧􀀭􀀧􀀠,-:.,"",,,_",' ... 1", _,,' .-1/..... ' ".1/TERMINAL SOARD 1 I, 1";: "I ... _ .. '. .. '-'", :t,.. "\/",(11"'" 1-... "--1-,,1"-,.., 􀀬􀁾􀀠... I'" '" -,,, I 1 ... I -" Ie -'''' t I -... , , 􀁾􀀠,,,> I"PC·[)X2ST" ·1" -..... ... " , .... .., ",,"" ".. 􀁾􀀠.... ," '" ,-"-'" 􀀢􀁾􀀯􀀠I'''"" ,"\ .... ", ,"", ,-," 􀀧􀀢􀁾􀀢􀀢􀀢􀀭􀀧􀀧􀀧􀀧􀀧􀀧􀀧􀁉􀀠,,-,"\'" /.... r\· .. 'r .. r. '; "1\ ...·1\INSIDE CONTROLLER I' " .. , _ -/' .... 􀁜􀀭􀁾􀁜􀀠.. 􀀧􀀭􀁾􀀧􀀠",--\ I' \-_-:-/--\-_.; 􀁾􀀠􀁾􀁜..: 􀁾􀀭􀁾􀀠.' 􀀨􀁜􀀬􀁾􀀧􀀢􀁾􀁾􀀭􀀮􀁃􀀬􀀬􀀢, ," -" 1 , -' "EV-{:Aa:SEN 􀁾􀁁􀁂􀁴􀁅􀀧􀀠-I,'-'" \-, \ j I , '\, \ \ ! -I " "... . , ,,'" .. 􀁾􀀠2:" -I.. --J" 􀁾􀀠.... 􀁟􀁾􀀠I'll.., , I< 8 7.·lO\4&" W HILQI' CO .......,. ,0>", ""$ ,.... SI1·4$'$7"W 3&88' ,...., ......,CO ......... 211.1$ S !1'2Z'V" 'II ...... C,. ,....",. ,-,..... NIW31?E ""'J)"...'" Hm:=: 􀁾􀀢􀁟􀁕􀁉......, lEGENO: _....... o --""'" 61 § N o 40 lSCAI..E IN FEET 1l 'l'IfIITTt:ft 􀁾HfDCOCIRllIMl'a CM;TA l!IiHH.L 00\U\ft-""""2.) e&: 􀁔􀀱􀁃􀁳􀁵􀁴􀀮􀀧􀁅􀁙􀁾􀁐􀁜􀁁􀁈􀀹􀂣􀁅􀁔􀁉􀀧􀁍􀀧􀁐􀀴􀁦􀁾􀀤􀁕􀀠􀀱􀀧􀁏􀁦􀁜􀁾􀁾􀁊􀁉􀀼􀂻􀁉􀁔􀁾􀀠l) 􀁉􀀨􀁊􀀮􀁾􀀤􀁈􀀮􀁉􀁉􀁕􀀮􀀮STAKE{) tlnttNU) 􀀱􀁗􀁜􀀢􀀧􀁉􀀧􀁈􀁦􀁾􀁉􀁦􀁴􀁬􀁾􀁬􀁨􀀧􀁮􀁥􀀺􀁾􀀠JrfOm:.C'f􀁊� �􀁉􀁏􀁏􀁈􀁃􀁁􀀢􀁓􀁐􀀺􀁅􀁐􀀮􀁾􀁔􀁏􀁾""...,""""" '4 lHI! 􀁾􀀤􀁈􀀮􀁉􀁉􀁕􀀮VE:f'I:tf't ,lIU.1!:ASBI!Jd' ....u1'llWt! 􀀢􀁉􀁗􀀩􀁉􀀧􀁦􀁴􀁉􀀨􀁬􀁒􀁔􀁏􀁾􀀧􀁉􀀡􀁕􀁏􀁴􀀠eo ". 􀁾􀀤􀁊􀁗􀀮􀀱􀀱􀁯􀀧􀁅􀁒􀀷􀀧􀁬􀀧I(J. unt.JT1eS1If4QI\Il oti n£Se PUIiIiAS 􀀧􀁬􀁩􀁮􀁌􀁍􀁉􀁉􀁦􀀨􀀻􀀧􀁴􀁾􀁉􀁬􀁦􀁐􀁭􀁊􀀩􀁐􀁉􀁕􀁏􀁁􀁔􀁴􀁬􀀤􀁔􀁬􀁁􀁔􀁯􀁴􀁾􀀮􀀠III 􀁊􀁬􀁬􀁾􀁗􀁌􀁉􀀮􀁾􀁔􀁏􀁬􀁈􀁉􀀡􀁔􀁏􀁗􀁦􀁩􀁦􀁯􀁴NXliSOfI 􀀤􀁔􀁉􀁬􀀧􀁃􀁉􀁎􀁉􀁏􀁓􀁎� �􀁓􀁉􀀢􀁅􀁃􀁉􀁉􀀧􀁬􀁃􀁁􀁬􀀱􀁏􀁴􀁴􀀤􀀮􀁁􀀡􀁯􀁗􀀡􀁬􀁬􀀬􀁁􀁓􀀬􀁒􀁬􀀧􀁦􀁯􀁡􀁾􀀠􀁔􀁊􀁉􀁄􀁏􀁔􀁾􀁾􀁾􀁈􀁬􀁏􀁉􀀮􀀱􀀢􀁊􀁭􀁉􀁁􀁉􀀧􀁏􀁾􀁃􀁁􀁬􀁑􀁑􀁉􀁕􀀡􀁬􀀮􀁁􀁔􀀧􀁅􀁏􀀠TOtHIIlMOJEC'T. 1.l ,tjJ. 􀁾􀁁􀁒􀁦􀀺􀀧􀁉􀀱􀀩 􀁬􀀺􀁜􀁉􀁉􀁑􀁃􀁯􀁴􀁃􀁬􀁬􀁍􀁏􀁒􀁂􀁘􀁬􀁉􀀡􀁃􀁦􀀧􀁾􀀠.......Q1"\ER\\1SIi HOTEO. III 􀁾􀁬􀁩􀁋􀁍􀀮􀁄􀁡􀁲􀀻􀁾􀀧􀁬􀁊􀀻􀁒􀁏􀁴􀀮􀁏􀀧􀁉􀁣􀁴􀀻􀁍􀀢􀁉􀁉􀁉􀁄􀁉􀀮....... "1 􀁔􀁬􀀧􀁉􀀡􀁾􀁍􀀮􀁬􀀮􀁾􀁴􀀱􀀡􀀢􀀧􀁬􀁕􀀮􀁁� �􀁯􀁈􀁏􀁆􀁉􀁩􀁕􀀺􀁳􀀮􀁴􀁇􀁉􀀧􀁉􀁴􀁦􀀮􀀠PAVEJ.IEIQ 􀁾Nl)C'll£R. 􀁔􀁾􀁾DEVICES 8'('fl4E em.......""""""'" 1Q.J 􀁊􀁬􀁬􀁦􀀢􀁦􀁏􀀧􀁏􀁋􀁏􀁉􀁬􀁉􀁦􀁗􀀮􀀧􀀸􀁉􀀧􀁃􀀱􀀡􀁴􀁁􀁔􀁭􀁎􀁦􀁬􀁩􀀻􀁾􀁜􀁬􀁩􀁉􀁖􀁃􀁉􀁅􀁉􀀱􀀠 11,) JllUtJlO FCRH8, $'MIUJI, NtOGIVDD SWIU. • 􀁾􀁅􀁄105A SMXmI. 􀁮􀁾􀁁􀁉􀁘􀁴􀁈􀀧􀁏􀁅􀀧􀁏􀁬􀁍􀁖􀁬􀁉􀁃􀁦􀀺􀁐􀁒􀁏􀀧􀁗􀀱􀁉􀁈􀁉􀁬􀁾􀁾􀀠􀁁􀁋􀁏􀁾􀁾􀁾􀁜􀁊􀁦􀁔􀀧􀁉􀀧􀀮􀀠􀁾􀀮􀀩􀀠􀁾􀁦􀁏􀁉􀁴􀀧􀁬􀀧􀁈􀁦􀁾􀁳􀀮􀁷􀀮 􀂣􀀮􀀰􀁃􀁃􀁕􀀧􀁴􀀴􀁾􀀱􀁉􀀧􀀢􀀠\,JH'l$CN'E NICHI1"ECT MI'N'I"HI! RlU,a.a 􀁾􀀠􀀮􀁾􀁾􀀤􀁗􀁕􀀮􀀢􀀬􀀬􀁾􀁁􀁃􀁦􀁴􀁏􀀺􀀤􀀤􀁾􀁏􀁆􀀲􀀧􀀥􀀡􀁎l1C 􀁾􀀠ClF'f'HEl'lOYftotlJ.SDE. . tte 􀁬􀁾􀁾􀁡􀁲􀀧􀁦􀀧􀁈􀁅Wl\I)I$:!t W.L "lOT ucunw. 11. NQ u.RTI'WI SUA>S SitWJ.1E.FR!AT1!R nwt :\(1• =.... 65+00 TO 70+00 LAYOUT & DIMENSIONING PLAN ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: April 26, 2005 Submittal # :L.1____6=-1:.;..1.:..-__--I New Submittal: X To: HNTB /Town of Addison Re-Submlttal : 16801 Westgrove Addison, Texas 75001-9010 Project: Arapaho Road Phase III AIW# 204059 (972) 450-2886 Engineer: HNTB Attn: Guy Van-Baulen Submittal Specification Reference: 2x2 Plaque Description of Submitted Item: Manufacturer/Sub/Supplier: Related Section /Drawings: Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as otherwise indicated," Title: Asst. Project Manager Revjewed by: Andrew Schneemann Date: April 26, 2005 2 x2 Plaque Soulhwell Company Copy: File SATIN FINISH f e sf,ufhwell co. p. o. box 299 salt antonio, tx 78291 . ph. {210] 223..1831 fax {210} 223·8517 o 􀁡􀁰􀁰􀁲􀁯􀁖􀁾􀁤􀀠(no corrections}o 􀁡􀁰􀁰􀁲􀁯􀁶􀁾􀀠as noted o revise and resubmit signed by: date: CUSTOMER: ARCHER WESTERN CONTRACTORS, LTD, 2121 AVENUE J, SUITE 103 ARLINGTON, TX76006 SHIP TO: ARCHER WESTERN CONTRACTORS. LTD. 1510 SURVEYOR ADDISON, TX 75001 CAST BRONZE PLAQUE RAI SED BORDER AND ,OTT"." SPECIFY MOUNTING ATTACHME WOOD SCREWS W/ROSETTES EXPANSION BOLTS W/ROSETTES TOGGLE BOLTS W/ROSETTES ATTN: ANDREW SCHNEEMANN 􀁐􀁌􀁾􀁁􀁓􀁅􀀠SIGN & • ..-.... "" ... i:7 •• , RETURN/r ONE COpy 24" 24" W X24" H ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Wh itehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager HNTB Corp. Designer Roadway-H NTB Corp, Bridge-U RS Corp. General Contractor Archer Western Contractors, LTD. \) 7ilORDER WILL Bf PRODUCED fROM THE ARTWORK YOU SEf HERE, IF APPROVE THIS ARTWORK AND IT CONTAINS ERRORS, YOU WILL BE HELD RESPONSIBLE FOR THE WORK WE DO, PLEASE CAREFULLY THAT ALL IS CORRECT REGARDING SPELLING, DESIGN, COLOR AND 􀁾􀁢􀀠􀁌􀁅􀁔􀁾􀀠􀁾􀀠##"&fr CD \YOll AilE UE (IINU PIlOOF·IlEADEIt e 􀁾􀀠m"' \)" -\,. -r;; 0 QUOTE # leJ547 FILE NAME: 04-4689,CDR JOB # 04-4689 DATE P.O. # 1 SUBMITTED:"'12=,2"'7..:.:,O'-4=--__ RE: ARAPAHO ROAD PHASE III! DRAWN BY: MARl HERNANDEZ 􀁑􀁕􀁁􀁎􀁔􀁉􀁔􀁙􀀺 􀁾􀀺􀀭􀀬􀀺􀀭􀁔􀁗􀀮􀀺􀀽􀀮􀁏􀁾􀀨􀀲􀀧􀀺􀁌􀀩􀁣􀀭􀀺􀀭􀀭􀀽􀀭􀀭__________ MATERIAL: CAST BRONZE FINISH: ' OXIDIZED BACKGROUND SIZE: 24" WIDE X 24" HIGH BORDER: DOUBLE LINE t::'TTI: PLEASE o CONCEALED o o o THE DESIGN OF THIS PLAQUE COMPUTERIZED GRAPHICS. THE CASTING WILL BE MADE BASED ON SUBMITTAL DRAWING, THE FORMAT, SIZE, SPACING AND MOUNTING ARE STANDARDS AND OUR CAPACITIES QUALITY CASTING. 􀁾􀁾􀁁􀁌􀁅􀀺􀀠1/4" '" 1" OXIDIZED TEXTURE CONCEALED FASTENER HAS BEEN MADE USING ACTUAL PATTERN USED IN FINAL APPROVAL OF THIS LETTER STYLE, LETTER BASED ON INDUSTRY TO PRODUCE A HIGH 􀁾􀀠I ARAPAHO ROAD PHASE III " October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager' HNTB Corp. Designer Roadway-H NTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. I IIMT8 Cot"'___ 1S150 SurveyOf Blvd. Telephone (972) 36J 􀁾􀀠0064 The HNTS Companies AddIscn. TX 75001 F,cslmll. (97<) 361-0065 Engineers Architects PI;,nners www.hntb.eom Archer Western Contractors, Ltd. 2121 Avenue"J" HNTBSuite 103 Arlington, TX 76006 Request for Information Response July 6,2005 Originator. Andrew Scheermann RFI Number: R-AW092 Subject: Watson/Taylor Driveway Grades According to Sheet 53 of the Plans, the elevation at South end ofthe WatsonJTaylor Drive to "Match Existing Pavement". The elevation of the Driveway at STA 0+96 is 600.849' (See attached Sheet for calculations). but the existing driveway/pavement varies in elevation from 599.72' to 600.34' (See attached Drawing). Please advise. Response/Action Taken: In response to the elevation and alignment issue at the WatsonJTayior Drive. Archer Western in directed to move the Drive centerline forward/up station along the Arapaho Rd PGL to align the 24ft wide driveway entrance with the existing pavement Archer Western Contractors. Ltd. is then directed to change the driveway slope to .8% from .9%; this new slope is to be utilized up to 10fi before the proposed end of the Drive. The remaining 10fi to end of Drive shall be install almost flat holding the grade to the gate location, were Archer Western is directed to remove an additional25fi back along the existing pavement and replace the existing pavement with new ({' thick pavement matching the new elevation at the gate and transitioning the pavement to match the existing pavement 25fi from the gate. Note additional information will follow. ifthere are any question and conflicts please forward all information under this existing RFI nnmberas an addendnm. (Example 92.1.92.2. etc. .. ) -br.:!;;)-------Br. Date: July 6. 2005 HNTB Corporation Cc: FUe IIM1'B Cwpoaulkc 15150 Surveyor Blvd. Telepbone (97ZJ 361 • 0064 The HNTB Companies Addson.TX7500l r._.(97Z) 361 ·0065 EnQineers: Architects pfanners 1fWW.hntb.com Mr. Ben Withered Project Manager HNTB Archer Western Contractors, Ltd. 2121 Avenue j" Suite 103 Arlington, TX 76006 Re: Arch Splice Connection July 7, 2005 Dear Ben: On July 2"", I discussed with Archer Western Superintendent that the backer ring for the Structural steel arch was not fabricated correctly and doesn't meet the AWS standard for a full penetration field weld with a backer plate/ring. Every day I have question the status ofwhat Archer Western is doing to correct this condition. At this time, I'm requesting Archer Westerns to provide their correction procedure to rectify this issue ofthe splice connection to conform to the A WS standard as required by the TXDOT Standard prior to the erection of the arch. Note this correct must also meet the standard to allow for the test byUltrasonic Testing ofthe full penetration field weld. Thankyou, Thankyou, /() 􀁾􀁾􀀰􀁌___ Guy Van Baulen HNTB Corporation Cc: File Steve Chutchian, Town of Addison Jerry o. Holder, HNTB Corporation Michael Ebeling, HNTB Corporation CliffHalI, URS Corporation Addison TX. 75001 fa(!'$irnlle (912} 3611)065 wwwllntb.cQm HHT8.J<>b # 25168-Anpaho Road -Phase ill VIA Hand Delivered 10:00 "'" Dot", July 5. 2005 To: BenWithmdLetter of Archer W_m Contractors, Ltd. c-INTBTransmittal 2121 Avenue T Suite 103 Adlngt<>o. TX16006 Shop I>rn.wi11g Submittal w. are forwerdln9 to you: Estimates -L PI.ns Prints Reports Shop Drawings Samples Change Order Disk Copy of leUe.Book Other # of Copies Drawing # last Dated Code Description 2ftX 2ft Bronze Plaque 􀁾􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀁾􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭Submittal.6l.L2 4126/05 Thn. aro t....nsmltted: For approval As requested Copies for distribution 􀁾 foryouruse Resubmit for Review & comment Return Copies for review 􀁾No exception taken Corrected prints Submit Amend and resubmit Make corrections noted Pleaenote: AX; (817) 640·8734 SUBMITTAL Date: April 26, 2005 Submittal # :1L-__......;6::,;1::.,.1:..-__---I New Submittal: X To: HNTB/Town of Addison Re..submittaJ : 16801 Wesfgfove Addison, Texas 75001·9010 Project: Arapaho Road Phase III A/W# 204059 (972)450·2886 Engineer: HNTB Attn: Guy Van-Baul.n Submittal Specification Reference: 2x2 Plaque Description of Submitted Item: 2.x 2 Plaque Manufacturer/Sub/Supplier: Southwell Company Related Section I Drawings: Plans Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to tlie requirements af the Contract tn all respects, except as otherwise indicated." Sign: . Print Name: Andrew Schneemam Title: Ass!. Project Manager RevIewed by: Andrew Schneemann Data: April 26, 2005 Engineer's Stamp 􀁾􀁷􀁾􀁾lDUlVLdF 􀁫􀁍􀀮􀁾􀀠􀁻􀁙􀁜􀁾􀀠􀀷􀁾􀁪􀁡􀀺􀁯􀁳􀀭Copy: _____R:...:':;:le____ "IIZ )UOTE # 16547 ___ FILE NAME: 04-4689,CDR DI I: JI.C:lC' 􀀬􀁾􀀬􀀮􀀬􀀠" ; e sou we co. CUSTOMER: p. o. box 299 san antonio, Ix 78291 ph. (2101223·1831 fax {210, 223·8517 ARCHER WESTERN CONTRACTORS, LTD. T 2121 AVENUE J, SUITE 103o 􀁡􀁰􀁰􀁲􀁯􀁶􀁾􀀠(no corrections} ARliNGTON, TX76006o approvful as noted 􀀬􀁾􀀭􀀮􀀮􀀠... . .. -_...._-...... . o rev'se and resubmit signed by: date: SHIP TO: ARCHER WESTERN CONTRACTORS. LTD. 1510 SURVEYOR TX75001 ATTN: ANDREW SCHNEEMANN • -.""".'.:7 .. • PLEASE SIGN & CAST BRONZE PLAQUERETURN . • ONE COPY 24" 24" W X 24" H SFALE: 1/4"" I" 􀁾􀀠/ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager HNTB Corp. Designer Roadway-HNTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. OXIDIZED TEXTURE YOUR ORDER WILL BE PRODUCED FROM THE ARlWORK YOU SEE HERE. IF YOU APPROVE THIS ARTWORK AND IT CONTAINS ERRORS. YOU WILL BE HELD FINANCIALLY RESPONSIBLE FOR THE WORK WE DO. PLEASE CAREFULLY CHECK THAT All IS CORRECT REGARDING SPELLING, DESIGN, COLOR AND I)iYOll Anll TlIllIIINAl.lln00l1·ImAIH!R CD QUOTE #16547 JOB # 04-4689 P.O. # RE: ARAPAHO ROAD PHASE III 􀁾􀀢􀀢􀀢􀁔􀁲􀀺􀀭􀀭FILE NAME: 􀁑􀀱􀀺􀂱􀂧􀁃􀁾􀁾􀀠 DATE S UBMITTED: ..,,12""'.2"-.7.""04"'--__ DRAWN BY: MARl HERNANDEZ QUANTITY:􀁍􀁁􀁔􀁅􀁒􀁉􀁁􀁌􀀺􀁾􀁃􀁾􀁁􀁓􀀽􀁔􀁾􀁂􀁾􀁒􀁾􀁏􀁎􀁾􀁚􀁾􀁅􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭FINISH: OXIDIZED BACKGROUND SIZE: 24" WIDE X 24" HIGH 􀁂􀁏􀁒􀁄􀁅􀁒􀀺􀁟􀁾􀁾􀁾􀁾􀁾􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭(J 7\l o\j)CJ) IJ) 􀁾􀀠rn 􀁾􀀠􀁾􀀠" 􀁾􀀠0 m RAISED BORDER AND I C'N'CP"" • SATIN FINISH 􀁾􀀭􀁲I7/) "") '-'7􀁾􀀠0-WI ,..17/n 77 B-CONCEALED FASTENER PLEASE SPECIFY MOUNTING ATTACHMEN D CONCEALED WOOD SCREWS W/ROSETTES D EXPANSION BOLTS W/ROSETTES D TOGGLE BOlTS W/ROSETTES THE DESIGN OF THIS PLAQUE HAS BEEN MADE USING COMPUTERIZED GRAPHICS. THE ACTUAL PAnERN USED IN CASTING WILL SE MADE SASED ON FINAL APPROVAL OF THIS SUSMlnAL DRAWING. THE FORMAT, LETTER STYLE, LEnER SIZE, SPACING AND MOUNTING ARE BASED ON INDUSTRY STANDARDS AND OUR CAPACITIES TO PRODUCE A HIGI·I QUALITY CASTING. 􀀧􀁾􀁍􀀠􀁾􀀠􀁾• __••• __'._'_""" ••__.. __•• ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager H NTB Corp. Designer Roadway-H NTB Corp. B ri d ge-U RS Corp. General Contractor Archer Western Contractors, LTD. 9128892042 T-524 p,OOZ/OO! F-040,.-14-05 10:1,.. From-URS Corporation Arapaho Road Bridee, Town cifAddison, Dallas Counry; Texas Page 1/2 Altek Engineering & construction Co. Structural, Foundation and Civil Engineer p. O. Box 172004 Arlington, TX 16003--2004 Phone: (817) 572-1989 Fax: (817) 563-1465 June 06, 2005 Archer Western Contractor, LTD. 2121 Avenue], Suite I03,Arlington, TX 76006Tel: (817) 64D-3898 Attention: Don Goodl Ben 1. Withered, Project Manger Tel: (817) 4D1-54-56, (817) 4D1-7202 Subject: Construction sequence for Arch & Beam Erection Plan, Temporary support system (ShoringTowers); Crane capacity analysis for the Span # 9, Cable installation; Load influence on permanent structure for the Main arch and beam span of the Arapaho Road Bridge.Town ofAddison, and Dallas County.Texas Attached please find the following documentations for the above mentioned subject: Section #1 shows the construction sequence for all work required at span # 9 including "Arapaho Construction Sequence". Section #2 details the erection of arch sections and concrete beams with the required false-work which includes "Arapaho Span # 9 Erection Plan, Arch & concrete U-Beam Erection Drawings, Arch Erection UftTable & Loading, Arch shore tower & Support Beam Analysis, Concrete U -Beam Shore Tower & Support Beam AnalysiS, Plan Sheet # 273 -276 Arch/Main Span Erection Sequence, King Fabrication Dwg # Ol-072-El Arch, Pafco 50 Kip/Leg Sho:reTower, Pafco lOO Kipl1eg Shore tower, IOO-Ton Crane Chart, I 20.Ton Crane Chart, 360-Ton Crane Chart" . Section # 3 details the hanger cable'installation and stressing procedures "CBSI Structural Strand Installation Procedures". ' 9728882042 T-S!4 P 0011003 F-D40Jun-14-0S 10:11.. Fro.-URS Corpor.tion Arapaho Road Bridal:, Town rifAddison, Dallas Couno/, Texas Pane 212 Section # 4 details the influence of loads on the permanent and temporary structures throughout the erection sequence which includes "Sequence Loading and Calculations". These recommendations are for the above referenced. project only. All the other locations must be reviewed, sealed and signed individually. These recommendations are based upon the information and details provided to this engineer by the Archer Western Contractors, LTD. Supporting engineering calculations and Accessories charts for these recommendations are attached. ffyou have any questions, or ifI may be offurther service in this matter, please call me at (817) 572-1989 or write to me at the above address. I 􀀺􀁉􀁾􀁩􀀠i-I 􀁲􀁢􀁾􀀠JlNTB CQmplflll.. 􀁾􀀠For Made by Date Job Number Checked by Backchecked by Date Date Sheet Number tI,j I ' i 􀁾􀀠OJ Jf\l-􀁾􀀠g[j:) GI 􀁾􀀠.p-C{., 􀁾􀀬I" A , 􀁾􀀠􀁾􀀠"""\:: 􀁾􀀠􀁾􀀠) 􀁾􀀠􀁾􀀠l. 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠j , 00 􀁾􀀠􀁾􀀠􀁾􀀠I I Martinez, David (DGNO) From: Duffy. Bob E (GE Trans) [Bob.Duffy@Trans.ge.comj Sent: Thursday, June 23, 2005 9:32 AM To: Martinez, David (DGNO) Subject: FW: DGNO addisionWye Addison.pdf David, Here is information I sent David Eyermann on Tuesday June 21 2005 so your have a copy. I corrected navels E-mail address in later transmission. Bob Duffy GE Transportation > -----Original Message----> From: Duffy, Bob E (GE Trans) > Sent: Tuesday, June 21, 2005 4:58 PM > To: 'david.evermann@railamerica.com' > Cc: Kleinhenz, Paul (GE Trans), Venneman, Pat J (GE Trans), tjleimbacher@qualitysignal.com1i lbbunney@qualitysignal.com'; 􀀧􀁷􀁡􀁬􀁴􀁥􀁲􀁾􀁦􀁩􀁴􀁨􀁩􀁡􀁮􀁀􀁲􀁡􀁩􀁬􀁡􀁭􀁥􀁲􀁩􀁣􀁡􀀮􀁣􀁯􀁭􀀧􀀠> Subject: PGNO addisionwye > > > «Addison.pdf» David, > > Here are the measurements I made last Wednesday June l5, 2005 on the Addison Wye. If the maximum train speed is lO MPH and there is no addition warning time for traffic light preemPtion time required the only wye switch which will be overlapped is the northeast switch of the wye. There will be need for cables between the East Arapaho crossing house and a new Addison crossing house and a switch circuit controller on the northeast wye switch to convey switch position information and crossing approach via HXP circuits at Addison to East Arapaho. The signal locations on the RCL PRELIMINARY plans are reasonable (per MUTeD guidelines) but I have not compared with the city plans for any conflicts. > > I have not received a fax with pre-emption time information. > > If more warning time for traffic pre-emption is required, cables maybe required to the Northwest and South wye switches. If the West Arapaho crossing needs addition warning time for traffic pre-emption cables may be needed from West Arapaho crossing house to both the Northwest (if more than 43 seconds WT at lO MPH versus 39 seconds in PRELIMINARY PLAN ) and South wye (if more than 44 seconds WT at lO MPH versus 39 seconds in PRELIMINARY PLAN ) switches. If the only East Arapaho crossing needs additional time warning time time ( if more than 41 seconds WT at lQ MPH versus 33 seconds in PRELIMINARY PLAN ) for traffic light pre-emption and all the northbound moves from south wye use the east wye track, cables from the East Arapaho house to switch on south wye may be unnecessary. If both wyes are used from south, switch positions information will be needed for Arapaho East requiring additional cable from south wye switch to prevent activation at East Arapaho when northbound move is made to West wye track. A separate house at south switch would be an option to reduce track cable runs on other equipment, if traffic pre-emption time causes both East and West Arapaho crossing approaches to extent through south switch. 􀁾􀁯􀁵􀁲􀀠inch condui!junder track, roadways, 􀁳􀁩􀁤􀁥􀁷􀁡􀁬􀁫􀁳􀁾􀀠parking lots or in any area that .' 􀁾􀁵􀁬􀁤􀀠not be dug up again, would be useful in installing direct buriable signal cable , with armor tape to signals# track connectionI switches, adjacent crossing houses, power, traffic controllers, and remote housings as required. > > Bob Duffy GE TRANSPORTATION Global Signaling > 502-266-8545 extension 2358 > > 1 '", ..$ a " " " '-', 0 v ':t "" To: Eyermann, David (DGNO) ; Martinez, David (DGNO) CC: Venneman, Pat J (GE Trans) ; Kleinhenz, Paul (GE Trans) ; jleimbacher@qualitysignal.com ; bbunney@qualitysignal.com ; Fithian, Walter (Horne-Office User) Sent: Thu Jun 23 10:26:17 2005 Subject: DGNOaddisonwye David, I received the pre-emption timing requirements for the Arapaho Road and Addison Road intersection from HNTB via facsimile. Since Arapaho Road is named as the parallel to track and the clearance green is being applied to Addison Road which has 200 between its warning signal holding traffic back from the Arapaho Road intersection and Arapaho Road, and since Addison Road's southbound lane gate is much closer to the intersection than the Arapaho Road East eastbound gate, 200 feet versus about 365 feet, I like to assume their will be no preempt required for Arapaho Road East. If green clearance time was provided for both Addison Road and Arapaho Road at same time they would be in conflict, unless two preemptions "treated sequentially based on direction of train approach. I am not a aware of any traffic controllers using multiple railroad crossing preemptions in sequence. Please verify with city or HNTB, there is no plans for green clearance time on Arapaho East. If only 33 seconds warning time is required for Arapaho East, its northbound approach start will remain north of the south wye switch frog for 10 MPH trains. Since Arapaho West's eastbound signal is about 985 feet from the Addison Road intersection it is outside the bounds for consideration a traffic preemption. 􀁾􀁨􀁥􀀠Arapaho West approaches will remain within the Northwest and South wye frogs for 39 seconds warning time. Bob Duffy GE Transportation Systems Global Signaling 502-266-8545 extension 2358 1 June 21, 2005 Letter: HNT8 -47 HNT8 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-8aulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Carboline Paint System Pricing Dear GUy: Please find the revised paint pricing for the T -4 and Pedestrian railing utilizing the Caboline paint system. T -4 Rail-5103 LF -$ 18,351.45 Pedestrian Rail -2294 LF -$ 11,113.89 Total Carboline Paint Pricing: $ 29, 465.34 Please process this change order so that the rail manufactures can proceed with the production of the railing and not delay the project If you require additional information, please contact Andrew at our field office. 􀀧􀀭􀁾􀁭Withered r Project Manager fv XC: Andrew Schneemann Don Good File . \ 􀁾􀁾􀁣􀁨􀀢􀀬􀀮􀀨􀁊􀀮􀀢􀀮􀀮􀀬􀀮􀀮􀀮􀀮,-􀁾􀀠\)...r,,}L.k/HtJ13 Tho HHTB Com,..... 15150 Surveyor Blvd. Telephone (972) 361-0064 Engineers Architects Planners Addfson TX. 75001 Facsimile (972) 361-0065 www.hntb.com HNTS.Job 11= 25768 -Ampaho Road Ph... m VIA Hand Dem,cd· Date:: June 15, 2005 Ben WitheredLetter of To: Archer Western Contractors. Ltd. =-tNTBTransmittal 15150 Su"""", Blvn. TX 76006 ShopDrawingo We are forwardl"" to yCH.t: Estimates 􀁾Plans Prints Reports Shop Drawings Samples Change Order Disk Copy of Letter Book other #: of CopIes Drawing #: Last Dated Code Description 􀁾___3_---1r-PK_-2_, Page 5_1_-1-____t-___'!-p-ar-ki-.n-g-La-l"'-u-tMBN--A---C-h-an-ge-du-.-t-o-earth--",-o-un-d-o,""TXueond_"'_"___ 1 'r􀀭􀀭􀀭􀁲􀀭􀀭􀀭􀁾􀀭􀁲􀀭􀀭􀁾􀀭􀀭􀀭􀁉􀀠I '-___--'-____--''-___􀁾___ __L. These are transmItted: For approval As reques ted 􀁾Copies for distribution 􀁾foryouruse Resubmit For Review & comment Return Copies for review No exception taken Corrected prints SUbmit Amend and resubmit Make corredions noted Plus. note: Due to TXU eover ....uirem.uirem.rtt., pleue move the thr.. parki", $pIlCH to the shown foe.ion Oft the 􀀭􀀭􀀭􀀮􀀭􀀢􀀭􀁍􀀭􀀱􀁾􀁛􀁴􀁓􀁾􀀠 8y: Guy Van Baulen. Err COpy to: File JerryD. Holder, HNTB Corporalion 􀁪􀁾ehv.kl., •..:..., Ib",,,.f 􀁾􀀠 ,k !' 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁴􀀽􀀽􀀽􀀭􀁾􀁴􀁟􀀭􀀭􀀭>001--------.----ANY VERTI {CURB. 55+00---+-----I I i---!I i I I ----;1 I m ( o 20 <0 6' 􀁓􀁃􀁁􀁌􀁾􀀠iN F£H N NOTE: SEE SHEET G-1 roo PARKING GRIOINC PLAN. LEGEND PRQ'OSEl) SCLIO £NT INO CURe PM} GUTTER> 550{)0 _,1---------.-------􀀭􀀭􀀭􀀭􀀭􀀭􀀫􀀭􀀭􀀭􀁾􀀭􀀺-\ \ '. ANY VERTICAL OBSTACLE \ '. , \ ICURB. 9UILOINO. STAIRS. ETC.)=-" ABSOLUTE SYSTEMS,LTD REBAR PIN PER STOP) __􀁾􀀧􀀠'I \. _I____ D a 􀁾􀀠r l ' 􀁾􀁩I 6'-0-: PLAN SECTION 􀁾􀀠r-I o 20 40 60 80---.SCALt IN 􀁆􀁅􀁾􀁔􀀠N NOTE, SEE SHEET G-t FOR PARKlNG GRADJNG PLAN. LEGEND 110.. DATE 51 .,.....,.. ARAPAHO ROAD • PHASE III SUlfleYOR EDJl£YNiD TO NJOlSQN f1(J.ID PftRKING LArOlJT MBNAllt= I 􀁾􀀶􀁌___________________________________________ 􀁾􀁖􀀺􀁅􀁈􀀺􀁉􀀺􀁃􀀺􀁕􀀺􀁌􀁁􀁒􀁾􀀺􀁗􀁾􀁈􀀺􀁅􀁾􀁅􀀺􀁌􀀺􀁓􀀺􀁔􀁾􀁏􀁐􀁾􀀺􀁄􀁅􀀺􀁔􀀺􀁁􀀺􀁉􀁌􀀽􀁟_____________________________________________􀁾􀁉􀀬􀀽􀀽􀀽􀀽􀁾____􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁔􀀰􀀸􀁷􀁾􀁎􀁾􀁏􀁾􀁆􀁾􀁁􀁾 􀁄􀁾􀁄􀁾􀁉􀁾􀁓􀁏􀁾􀁎􀁾􀂷􀀵􀁔􀁾􀁅􀁾􀁘􀁾􀁁􀁾􀁓􀁾􀁾NOT TO SC.M..E ( .-r0tr0q,.,I$M 0.--en !)An; sc.t(.£ PIfO.C:C1 tfO. SH£t1 t4 2 CF 5 o.c\ -1)H 􀁯􀀭􀁾􀀮􀁉􀁓􀁈􀀠L o. 􀁾r_ lB' :".. PK-Z 􀁾􀀠j 􀁾􀀠'P"" _oil 􀀬􀀬􀁾7; June 28, 2005 Letter: HNTB -53a HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No, 04-22 Traffic Control Plan for Addison Road Dear Guy: Archer Western will utilize the Traffic Control Plan on Sheet TC-4 (30) for the Addison I Arapaho Road Tie in, We will begin this work Wednesday, June 29, 2005 If you require additional information, please contact Andrew at our field office, XC: Don Good File • • .,. -7N 3 _.􀁾􀀠􀁾􀀠C. 􀁾􀁾􀀨􀀲􀀮􀁲􀁅􀀠􀁾􀀠.0 /'ItSSMt 8JP􀁾􀀠II( :s 􀁾􀀠tol....t4 ..; 􀁬􀀻􀁾􀀠;.. f .. j!. 1ld11/t1lll!Ii e ":t ,\J'" ",.. ......... 􀁾􀀠• .. •• • 􀀮􀁾. • 􀁾􀀠􀁾􀀠.. 􀁾􀁇􀀧􀁜􀀼􀀭􀁾􀁻􀁊􀁾􀀠􀁾􀀢􀀬􀀮􀀬􀀠[ 􀁾􀀠.. 4 ,..) ...1f..,. q:\II 􀁾􀀠~ 1\1 􀀧􀀡􀁉􀀮􀁾􀁾􀁾􀀠d:I" -􀁾􀀠􀁾􀀠-l -+iii "I:I 􀁾􀀠􀁾􀀠" .. ! ..-:> • 0 ... 􀁾􀀠• • .f::"'•• 􀁾+( -,)p -4 -Y .... . -'" .. . .. .... .. .. 􀁾􀀠... .. ... • .. 􀁾.. 􀁾􀀠® 'f... ['f.. 􀁾􀀠--l ±: Jij􀁾􀀠'" ....,. 􀀢􀀭􀀭􀀭􀀭􀁾.::";i!o. •-• • ... .. -EJ //fJ·13 'f-. 'E-. r 􀁾􀀠-􀁾􀀠􀁾􀀮-l±:: lU "foo. 􀁾􀀠• 􀁾􀀠f1i2)lo)Rf 􀁾􀀠􀁾􀀠􀁾􀀠• • -+ ... .. .. .. • .. 􀁾􂂬􀁊􀁴􀁜􀀼􀀭􀁾􀁰􀀧􀀠-4 -••... . . ... • .. .. c .. ........ -"" • • • • Archer Western Contractors July 20, 2005 HNTB 5910 W Plano Parkway Plano, Texas 75093 Attn: Guy Van-Baulen , .; RE: Lane Closures Dear Guy: -..,.. • • ". 􀁾􀀠•.. • 􀁾􀀠Archer Western requests that the Town ofAddison considers the utilization of daytime one (972) 361 -0064 Thl HNTa Companfes Addison. TX 15001 F./( COpy ljf L(>th"( r,! h.·:·, C::de 1 i SubmiHai" ofLi lrrigd.tion Controller -Make Corr«tions Noted i I 2 I Submittal' 69.1 6/28105 Mini CUk II Rain Sensor -Amend.and Resubmit !$ll:liHittiil;; 1ft1 !6/2f!;/O;' R4.ih nird ;:11.0 Series 􀁾􀁬􀀧􀁲􀁩􀀠Ilkltl H",-,w AiUC!I..! alill R,;"ul;;;-,,-'--..------1 '-----I ;-c-fll-:c;c =---c--􀀭􀀭􀀭􀁾􀀢􀀠 ,.,---------2 ··-2----Submlnai ;,'i,Ll 6/28/05 PVC 􀁒􀁩􀂣􀁴􀁬􀁬􀁾􀀠(SCH lID) -Make Cout%tion 􀁎􀁾􀁴􀁣􀀡􀀮􀁬􀀠Co::.tr d Wf::cs -No 􀁅􀀮􀀬􀀢􀀻􀀺􀁃􀁃􀁰􀁴􀁩􀁏􀁬􀁾􀀠TtJtcnIGi2S105 2 "--j submittal 􀁆􀀷􀀩􀁾􀁾􀀠'6ii8/U5 ---,.,.---􀀢􀀭􀀭􀁬􀁾Solvent Weld l"v'C ::: No.cxcepuoo 􀁔􀁾.._...---... ! 2--1 􀀡􀁜􀁵􀁨􀁾􀀧􀁪􀁴􀁴􀁡􀁴􀀠 # 8U 6f2Rfog; L.__􀁾􀁾... -.L___._"""';L.....___-.L Tbese are tramifnitted: A'S 􀁮􀁾􀁴􀀮􀀡􀁴􀁬􀁴􀀺􀀺􀁩􀀠ted For your use 􀁾􀀠Rest.;bm:t For Review & comment fielUl'n Copies for l'pview No exceplion taken Corr0cte<:1 prini:s " 􀀢􀀧􀁲􀀺􀀻􀁾􀁇􀂷􀀺􀀡􀀠one! 􀁲􀁣􀁾􀁌􀁊􀁢􀁲􀁮􀁩􀁴􀀠By: GI!yVnn Bnokn, EIT Copy to: File 􀁔􀁨􀁯􀁈􀁎􀁔􀁂􀁾􀀱􀁵􀀠15150 Surveyor Blvd. Telephone (972} 361-0064 Engineers Architects PhlOoers Addison Tx.. 75001 facsimile (972) 361-1)065 www.hntb.com HNTB Job • 25768 -Alapaho Road -Ph...ill VIA Hlmd De6",red Date '.1y6.2005 To: Stew' ChutcllianLetterot Town ofAddisonTransmittal =--NTB P.O. Box 9010 16801 W",tgrowDrlVll AiIdi>on. TX 15001 Shop Drawings! CaIaIog Cub Suhmiltals We are forward/ncJ to you: Estimates Plans X Prints Reports Shop Drawings Samples Change Order Disk Copy of leHer Book Other # of Copies DrawLng # Last Dated Code Description 2 Submittal8l.l 6/28/05 Ro.dsaver Silicone SL Prim.te/Crafl;o ( Silicone Joint Compound) 2 Submittal 82.1 6128/05 HBR Backer Rod -PrimalelNomaco (Bac","r fur pavement joint) 1 Pageslto 6 5/16105 Prequalified loint Sealers -TxDOT These ... transmitted; For approval As requested Copies for distribution X for your use Resubmit 􀁾forReview&comment Return Copies for review No exception taken Corrected prints Submit Amend and resubmit Make corrections noted p...,...not", 􀁁􀁩􀁬􀁄􀁾􀀠By: :::;;..,. Battle., Err C_to: File ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640·3898 FAX: (817) 640·8734 SUBMITTAL Date: June 28, 2005 Submittal It :LI___...:8:!2;!.!.1___-l New Submittal: X To: HNTB J Town of Addison Re·$ubmittal : 166G1 Westgrove Addison, Texas 750(l1 9010 Project: Arapaho Road Phase III ANII It 204059M (972) 450·2886 Engineer: HNTB Attn: GUY Van-Saulen Submittal Specification Reference: Addison Description of Submitted Item: HeR Backer Rod Manufacturer/Sub/Supplier: Primate /Nomaco Related Section I Drawings: Addison Additional Comments: Backer Rod for the eRe? Paving Joints Engineer's StampContractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as othelWise indicated." Sign: Title: Asst. Project Manager Reviewed by: Andrew Schnee mann Date; June 28, 2005 Copy: p.6281_441-3414 PRIMATE CONSTRUCTION INC Jun 28 05 01:53p p.e1._, 􀁟􀁾􀀠77 􀁾􀁾􀀻􀁾􀁾􀀠􀁾􀀢􀀠􀁾􀁕􀀱􀁌􀁬􀁩􀁾􀁒􀀤􀀠PRODUCTS 71369610!'.i2 BACKER ROD 􀁉􀁾􀀺􀁍􀁅􀀻HBR:,1:iLstJ J II 'I"I'I'e; C -CylindriC(lI. 􀁾􀁅􀁉􀁾􀁩􀁢􀁉􀁴􀁴􀀠"""Iant 􀁾􀁏􀁏􀁉􀁉􀀧􀁾􀁾􀁬􀁬􀁩􀁮􀁡􀁬􀀱􀁬􀁬􀁶or emed cessiYu sealant use. MOurne opUm\lfl1 61_ facttlrlQ proIor\Q $ I$ln1jlOlY', "'" rt controls !he dep\h "'!he """,""Iboad. an'Mlt\xl """"'ittd to til ughlly 100 'he 􀁾andMeJion as a􀁴􀁬􀁏􀁩􀀱􀁤􀁢􀁾􀁬􀁏p!eVllllllxlllcm.sOo I'" 􀀷􀀯􀀦􀀮􀁾􀀠314" 7/S" I SI8' !'i or"'.. G fn 2;.00 13 1550 16 1100.'16 850 ; 19 SSO 􀁾􀀭.. m 4Qi) 29 !ill2 41 360 􀁾􀀱􀀠140 ,.... 412 J3. 2&9 108 168 110 13 .. C12!3 0$249 lR'·xH;'''xJl" ia"d8b .,31" 􀀱􀀸􀀧􀁾113",'1.;;):1· IS-'U,,):3r ,n22-,H' 12M x22"JC 7&" 􀀱􀀲􀀢􀁘􀀲􀀲􀁾􀁊􀀠14" 􀀱􀀲􀀧􀁸􀀲􀁬􀀡􀀧􀁾􀀠1." 12"x22"Y 14' bm Ieie;r.;(l agents. ClJllng OOfl'llOUnd 􀁾􀀮􀁬􀁡􀁉􀁬􀁡􀁮􀁣􀁥􀀮or any for􀁾mal!irieI$ FI'al!I1/y sawed joints ihMIlll!!waslle:l >Mtil vStlr im'ooial9l,t iII!clward to roll'lOl<> ""1ioose malarial 􀁾􀁭lIle jOi1t faI::as. Wre i:l!Usf'ing. sa'dblaslirlg. hlgh-pressul'l1l"'. or any tQI1l. binatcn 􀁯􀁦􀁾SI"OVId be uf!ed to rerrove ron\aminw re· .naini'lj OIl !hepiln fQ\Xl T(l Eifl$\jre 1I good sea!anl bond. janllS must be dean end dIy wi'erllhc l'1eW w.alant is installed. In repaimg ad ..........;;;;..L...;.....,J.....;.:;....L....::.-l...::.:..L.;;..;;;;;;.:..:;;..Ii,.;;;..I...;..1 jail1&. aI cId SIIa\;lnl orfiler I11U$I. be removed. 1M<;811 becbleby PRECAUTIONS􀁣􀁵􀁉􀁉􀀡􀁴􀁾􀁾 􀀧􀀢􀀠iilWi'lJ 0.( Ul!! oij mablIl:!l back", rod. cleen ••jolnls j:e' 􀁕􀁬􀁾ocaIirt with ASTM Tost Mstr.od C 1253. 5ealant 􀁣􀁯􀁭􀁰􀁡􀁾􀀱􀁊􀁩􀁬􀁩􀁴􀁹􀀠should􀁾􀁲􀁥􀁲􀀧􀀤J1lOOIl1!nendalions Ar 􀁾􀁳􀁳􀁡􀁲􀁇uswlorl;/l1S be confirmed by Ihe sealant 􀁭􀁡􀁾􀁵􀁦􀁡􀁣􀁬􀁕􀁲􀁥􀁲􀀮􀀠Compatlbllity cher􀁊􀁬􀁕􀁾rtl\I61 be 􀁥􀁱􀁵􀁾wllh 􀁉􀁲􀁜􀁜􀁾􀀠fQI' "",millof 011 end ITXllsture. Ins!:!U !he becker rod allhe depll> reoommel1Ugh!y, ",movi!Ig MV c: et>J icooe mahlrial from the)oi1t faces, Wre bnl!I'ing, sardblasting, hlgr..prllSSlJre water, 01' any com· Ilin!Ito'l 􀁯􀁴􀁾sl1Oll0l be used to remJ\tl! COIlIaminarlSl9' 1&.-22 .. "ff!.... ly 'j, <:' >"}' '/)'1' ",1 IloIoIV 􀁉􀁉􀀼􀁉􀁖􀁜􀀡􀁉􀁾􀀠􀁏􀁵􀁬􀁧􀁬􀁗􀁬􀁧􀁾􀁾􀀺􀀠􀁾...'""""'Y r"l 􀁾􀁉􀁟􀀨􀁉􀀼􀁐􀁡􀁬􀀠31l1r rr or !,)tle6$ "'..",,-6 3/!' 10 !tiS" I"· 13 􀁾􀀯􀀴􀂷􀀠􀁾􀀸􀀢􀀠􀀱􀀱􀀱􀀱􀀶􀁾􀀠.-, iZS 3M" 19 '1-'"116" i_22Z 51 1'1/8-1 􀁾􀀮􀁾􀁾􀀠151.'1 41 2" 61 􀀲􀀱􀀱􀁾􀂷􀀠􀁾􀀴􀀠..... 􀁾􀀱􀀠C tal ,lit. 0 $l4ll 􀀾􀀲􀀰􀀮􀁾􀀠0e:/49 3600 2£00 UJ91 1650 1100 .12 illiG 6SO 25Q dQQ 552 lza 360 740 ,.. 1\0 76Z 􀀳􀀳􀁾􀀠'oa 168 I' .,"" . tl"x11l'x31" 1a")I,18"1'31-IS-x1S"1.:n'" lfrK13"'X31" 12"):22'"" 14· l\12lni"l,l 00 !he,Pif111OOi) To 􀁥􀁮􀁾􀁵􀁲􀁥aIJOOd sealantbood. J!;lnls must L..;.. ..... :;.:;..I-:...J.....::.::...J.....::.::...J...:;;...A.;=;;.;:.:;..A..:;;.J.,;;.,1 manufl;:ll,erwllh ablrt,t I::dorm\\eI, ReIer 10 _lmanufQo, 􀁤􀁥􀁬􀁥􀁬􀁭􀁬􀁮􀁾􀀠by ASTM Test Method C 1087. mrs reco!I1Ile1d8lio!1s, ........,...... ht? d,.. , 1>.... 1'ofo.... ",1Id'" '" .......... 􀁾"""""""I'M"\>1 ;,'1"',,, ....... "'1\1 tlIIlI4I1;;1Y.'I"III1!Il.'iII\' III 􀁮􀀮􀁾􀀠fY\\INGU. 􀁎􀁑􀁮􀀺􀁙􀀧􀁾􀀠iVI 􀀡􀁩􀁴􀀾􀀮􀀮􀀢􀀧􀁾􀁾􀀠t\'O 􀁴􀀴􀀧􀁐􀀾􀁾􀁕􀀢􀀧􀀧􀀧􀀧􀀧􀀧􀀠'Pi' 􀀬􀁾.."'" 􀀯􀁜􀁉􀀨􀀢􀀮􀁾􀀠􀁖􀀨􀁉􀁾-.wt1WI...􀁾􀀱􀀠1)11"",, ....􀀢􀀮􀀬􀀮􀀬􀁬􀀱􀁦􀁾􀁴􀀠, .. 􀁉􀁾􀀢􀀠􀁾1ICfQh ..III 􀁍􀁾􀁕􀀧􀁬􀁬􀁦􀁬n.. 􀁕􀀢􀀡􀁃􀁉􀁕􀁾􀁴􀀮􀁬􀀡􀁲􀁴􀁜􀁤􀀧􀀠IIl'mO /JI 􀁦􀁬􀁾􀀧􀁍􀀢􀀢􀀧􀁬􀁤� �􀁷,.,.,.....;4.. Uu.... _ 􀁾􀁾􀁬􀁦􀁯􀁪􀀠Wl'llalif' 11.-01'>111111, \0 (t$hlll"nl\:l(1I \ ••􀁴􀁾􀀮􀀮􀁷􀀠􀁍􀁬􀁉􀁉􀀢􀁍􀀨􀁾􀀠eI eN\1UI.:I1 Il'JI/t<.l« Voef tl\4 􀀢􀀧􀁾􀁉􀀧􀁾􀀧􀀾􀁬􀀡...' .'fJr:t,;{,'J(;h,..... 􀁾􀀧􀁾..-..M..... 􀁾􀁉􀀠"frlo..r 􀀢􀀧􀁜􀁯􀁑􀁵􀁬􀁬􀁬􀁾􀀠..11 􀁾􀁴􀁾􀁍...􀁬􀀡􀁾􀀠.... jlllQut»OlTt!TIIMndiI'_. ""' 􀁾􀁬􀀬􀁬􀁓􀀨􀀩􀁤􀀡􀁯􀁦􀀡􀀯􀁬􀀱􀁳􀀠 􀁰􀁵􀁾fl1\I9t be equipped wIIh I!epI for nm'IJval of oIIlBl !TI:lSluIll. Inslat the backlll'fW al \he 􀁤􀁥􀁾reoommelluw by ih& sealan! ! PRECAUTIONS Do nOl punctlJre. O\l0r COF\lPl'eSS c.;r s\mlch HOR:""dunog 􀁬􀁮􀁴􀀻􀁾􀁲􀂷􀀠lion, 00 I'Ialt be "","e In ,",oordance wIlIlA$TM Test Ma!t;od C 1253, Sealant 􀁃􀁑􀁭􀁰􀁡􀁴􀁩􀁾􀁍􀁹.hould be ""nfirmed by the sealant manufacturer. CompaUbllily char· acteristlcs of􀀬􀁾􀀢􀀮􀀡􀁡􀁮􀀡􀀮� �In contact wtlh soar.nt bacillngs cal' be ARCHER WESTERN CONTRACTORS, L TO. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28. 2005 Submittal # :1...1___-=.81.:.;.c.;.1___-' New Submittal: X To: HNTB I Town of Addison Re.$ubmitta! : 16601 Westgrove Addis-on, Texas 75001·9010 Project: Arapaho Road Phase III AIW# 204Q59 1972) 45s !O spll:fing swfa<:es which are lite from all_i""", and "'" dty. Joints _ be carefully inspectl:>,lllJ assure fl1aI. an 'flIllOPriaie levcl of ele."I..,., IIJlS b= achievplim '" joints in green _ during bot and humid condiliom. Wann ambiem temperatures accel.ern!e pavement l1y Backer Rod Din.nteter 3/8" 1 Sealant Bead Thickness . I.1/4" Minimum Joint !I 118"SawlReservoir Dept11 ib Joints: in FCC Pavements 3/8;-t 1/2" 5/S" J 3/4" 718" ·1/4"5i16" 5116" 3/8" "3ig'" 112" 5/8" 3/4" 718" I" 1/4" i14" 5116" 􀀳􀁦􀀸􀀧􀁾􀀠7116" 1 114" I liZ" . 1314" I 17/8"J 2" I" J I I/S"J 1 1/4"J 1 3/8" 1 J/2" 318" 1 112" 112" 1/2" tl2" t 1/4" , 1 l12'J I 112" I 1 3/4" 2" 1!2" 112" 112'1 , 112" , 112u 2 318" 2 2 718,,13 1/8" I 3 3/8" . Minif!1lmlBackfrRodD1h 1 112" 􀁾􀀱􀁔􀀲􀀢􀀠5/8" 11116" 1 314" , 13/16" 7/8); I" J" I" I !" Estimated U..􀁾􀁥􀁎􀁯􀁮􀀭􀁓􀁾􀁟L 245 149 112 70 1 51 1 35 26 23 18 16 1 !5 Estimated Usage I 273 In : 130 82 I 58 J 41 31 21 22 20 I 19Self-Ieve!ing(IVgal) , I 1 Backer rod iliarneler should no' be vaned from specified dimenSIons. Iflarger SIZes are used, mcreased saw deplh lSneeded. 2 SeaI""t bead thickness can vary by ±25% ofdesign value. 3 Neverinstall Roadsaver Silicone to a depth greate, tl.." the joint width (l to I). "Please contact Crafco for additional joint size design recormT1endations. 􀁾􀁁􀁌JOINT pESlGNS' RoadSaler NotToscale InltlalCut Not To Scale ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste.103 Arlington, Texas 76006 PH: (817) 640·3898 FAX: (817) 640·8734 SUBMITTAL Date: June 28. 2005 Submittal # :t.1___...::.81.:.:.;..1___....l To: Attn: HNTBJ Town of Addison 16801 Westgrove Addison, Texas 75001·9010 (912) ,",0·2.8. Guy VaJ'l;Bau!en Project Arapaho Road Phas" III New SubmittaL: X Re·Submittal : AIW# 204059 Engineer. HNTB Submittal Specification Reference: Description of Submitted Item: Roadsaver Silicore SL ManufacturerlSub/Suppller: Primate I Crafco Related Section I Drawings: Addison Additional Comments: Silicon Joint Compound for Concrete Paving. Roadsaver Silicone SL is on the TxDot Approved material List for Concrete Paving Contractor's Certification 􀁾􀁈􀁡􀁶􀁩􀁮􀁧􀀠Checked this submission, we certify that it conforms to the requirements of the Contract in all respects. except as otherwise indicated," Title: Assl Project Manager Reviewed by: Andrew Schneemann Date: June 26, 2005 Engineer's Stamp Copy: p.2 'Jun 28 05 01:51p PRIMATE CONSTRUCTION INC 281-441-3414 PRODUCT DATA SHEET􀁃􀁒􀁁􀁆􀁃􀁄􀁾􀁎􀁃􀀠ROADSAVER SILICONE SL AN ERCION!lCOMPAN'( PART NO. 34903 420 N. Roosevelt Ave ... Chandler A2. 85226 JANUARY 1004 1-800-528-8242' (602) 276-<>406 • FAX (480) 961-0513 WVNI.c:rafua,com READ BEFORE USING THIS PRODUCT GENERAL CmCco RoodSaver Silicone SL is a low modulus silicone which offerS lhe petfom1allC:e and durability characteristics of􀁾􀁮􀁴􀁩􀁯􀁮􀁡􀁬􀀠silicone with lhe ease ofiustallation of􀁳􀁥􀁬􀁦􀁾􀁬􀁥􀁶􀁥􀁴􀁬􀁮􀁧􀀠materittls. Crafco Roaihaver Silicone SL is supplied as a read)! !o use one component moisture curing 5)'Stem which provides: it lasting and flexible seal. Crafuo Roadsavet Silicone SL offers ouismnding wCIltrn:ring resistance, rtmalns IlC)Oble down to temperatures as low as -Soop (46°C), is 􀁪􀁣􀁴􀁾􀁢􀁬􀁡􀁳􀁴􀀠resistant and will maintain field serviceability when exposed 10 intt:nnittem fuel and 01'1 spills, It bonds strongly to concrete joints willlOUl the use of It printer. Crafuo ROlId$aver Silicone SL can be used in all typical concrete joint applications on highway and airfield pavements in: aU climates. RoadSavcr Silicone sealant is compatible with asphah pavement RoadSaver Silicone SL is easily applio;U to (,;oncrete joints using bnlk dispensirlg system urnts such as those available from manufacturers including PyIc&'Gr.lO) and Johnstone. The leveling characteristics insure Utal the required joint wetting fur development of appropriate adhesion OCCUJS during applicatiOll, 00 tooling is required, USAGE GUIDELINES RoadSaver Silicone SL pavement temperature High Temperature Grode ("0pertbrrmmc:e IimilS arc 82A6 fur jOint sealing. 􀁕􀁓􀀳􀁾􀀠recormnmdatiOIlS are sOO\VTI in Crnfco pavetnent temperJ1Ure grade chill1S shown at !he rigbt. Refer to Crafco Product SeIection Procedures to determine sealant or filler' and pavement remper4ture gr«les. .. -. I EIIIIIII."';,'" 􀁲􀁾􀀢􀀢􀀠• Pm'Im\IUlCe 1 imill o 􀁎􀁯􀁴􀁒􀁣􀁲􀁯􀁍􀁭􀁾􀀠SPECIFICATION CONFORMANCE Cmtoo RoodSaveI Sill""" SL conI'oons to speci!ica1ions lbr low modulus siIicoo: fur rrlIUlY IVllhway dcpartItnllS and 􀁾ageoci;:s. The product also meets and exceeds aU reqwremerus: of ASTM D5893, "Standard Specification for Cold-ApplIed Single Compooent, 􀁏􀁬􀁥􀁬􀁴􀀧􀁴􀁩􀁾􀁬􀁹􀀠Curing Silieone Sealant for Portland Cement Concrele Paveme.o.iS" fur type 8L sealants. In the following specifications several oftlte 05893 parameters arc 0l<.Jre restrictive to better reflect properties ofRoadSavtrSilicone SL. ASI'M D5893 Phys:ietd Requirements ASTM 00893 SL ReauiUments RoodSaver Silicone SL Requirements CutcEvaluat10ll Passat21 days Passat21 day max. Rheological Propme5 (ASTM C639) Type 1, smooth level surface Type 1. smoolh level surface Extrusion-Rare (ASTM e11S3} Type S, S{) mV min, minimum Type S, 200 Illi/min. minimum Tack Free Time (ASTM C (79) 5 hr. max. 3 br. max. ElTeclS of Heat Aging (ASTMC 792) 10% max, Loss 10% max, Loss Bond, 􀀭􀀲􀁾􀁃(-20°f), 100% Exteruion Noo-Immerm:d Pass S Cyeles Pass 5 Cycles Wat"r 1mmersed Pass 5 Cycles Pass 5 Cyeles Oven-Aged Pass 5 Cycles Pass 5 Cycles Hardness 􀀨􀁁􀁾􀁔􀁍C 661) -29'C (-20'C). Type A2 2SmaK, I(} max. H·C (73·F), TyPe 00 30 min. 40..s0 min. Flow No flow No flow Rubber Properties in Tension Ullimate Elongation 600% min. 80()\'/D min. Stress at 15()1'A! Eiongation 310 K pa (45 psi) max. 207 K p. (30 psi) max, Effects oJAccelerated W 􀁾􀁡􀁴􀁨􀁥􀁲􀁩􀁮􀁧􀀠Puss 500 hmm. Pass at 5000 hours Resilience 15% mi.n. 75% min. AddltlODftl properties of RoatlSaver Sflicone,SL Sealant nrc;t Specific Gravity (ASTM D792-A)(I) 1.10-1.40 Ad...ion '" ConcrolC (MIl.. 8802) (2) 20 pli (3.5 kg/em) mil. Bond and MovemeotCapabilily +/. 50% (ASTM C7191 (2) Pass 10 cycles Bond '" Mortat(AASHTO TI32)(2) 50 psi (:14.4 NI='l min. 􀁔􀁥􀁮􀁾􀁬􀁥􀀠Adhesion, %(ASTM D5329) (3) 600% min. Notes: (I) Specimens shall be obtained from 118 inch (3nun) Ihickness sheets ofmateriai which has been cured for 7 days at n+/-JOJ: 􀀨􀀲􀀵􀀫􀁦􀁾􀀠24C) nnd SO 􀀫􀀯􀁾􀀠5% relative humidity, (2) Specimetl'i cured furlS days at 77 +/. 3t1F (25+1-2<)C) and 50 +/.5% humidity prior to testing, (3) 􀁓􀁰􀁥􀁣􀁩􀁭􀁾􀁮􀁳􀀠slmll be 112" x 1/2" x 2" (t.2cm)'(, !.2cm x. 5.0an). cured 7 days at 71 +1-SOF (25+!·2"C) find 50% 􀀫􀁦􀁾􀀠5% relative humidity. p.3 281-441-3414PRIMATE CONSTRUCTION INCJun 28 05 01:52p APPLICATION The unit weight is 10.7 pound, per gallon (1.28 kgtL). One gallon will seal ,50 r;;;' (45.7m) of III ioch (1.2<0» wide by 114 inch (O.6cm} deep joint. Exact yield will vary depending on thickness of sealant, waste. application techniques, etc. Prior to use, the llSer must read and follow Application Instructions for RoarlSaver Silicone Sealants-(January 2002) to verifY proper product 3elections, applicalor pumps. pavement preparation procedures, application geometry. usage precautions and safety procedures. These lnstructions are provided with each drom ofsctllant. PACKAGING Raadliavet Silicone SL Sealant is packaged in plllJi'tk Ulled open head 55 ganon (208 l) drums which .comain 50 gallons (189 L) uf nt:Iterbt Additionelly. for small applicatiuns !hesea!anr is available in 􀁰􀁬􀁬􀁬􀁓􀁴􀁩􀁾􀀠S ea110n (19 L) pails nod qllDJt (,95 L) caulking n.bes.. WARRANTY CRAFCC, inc, wnmmts that CRAFCO sealanl3 meet appliCllble ASTM. AASlfI'O, Federal Federal or State llptcifiC'oltlons at time of shipment. Techniques used for the preparation Iif the «I!JNQ: Aller appropriate curing of the ¢Ona'ele (a minimum of 7 days is reeornrncnded) joint reservoirs for the sealant t;an be cut 1nla the concrete using appropriate concrete sawing procedures and eqllipment In "ralS( track" or high early strength cotID1'ete mixes. il tnay be possible to saw and seal the joints sooner than the recommended 7 day mininltun for standard concrete mixes. Contact Crafeo OJ" your representative for further details. Rescrvoirdepth for ..GriOlJSjointwidlhsisshown in Tnble L Jointwidth should be scleCted to limit movement due to expansion aoo. con:trac1iou to 00 more than 25% of lhe joint width. After sawing. immediately flush 􀁴􀁨􀁥􀁪􀁯􀁩􀁮􀁾􀁷􀁩􀁴􀁨􀁟􀀧􀀢􀀠remove a ruajority ofthe saw 'Iuny. After thejoin1S lulve drl..r.]1&prior In applying scalantthe remaining_ must be removed by saOOblastins-Both joint llIces must be arlequalcly !W'kib1a&td to remove remaining traces ofsawing residue. Por dlbca:ive ""dblasling. !he .mzj. should be posilioncd within 2 irn:bes (5crnlof the stUf"", bang ci",",,". After sandb1....ms the joint should be lhorou.ghIy cll.".tU'M!d using clean oompressed air with a minimum pn:t.;ure of90 psi. MoiSillreandoil tr.Ips are required OIl the comp"""" uni< The objec' of lie above cleaning opmlions is In """'"'" ""'""'l. inmct, and clem bonding _ which are fu:e ftum all conbminanls m! "" dry. loinlS should be carefully insp bac,...rod during insF (32OC), or be exposed to excessive humidity. Dam 􀁓􀁨􀁥􀁥􀁾􀀬􀀠2) Material Safety Dal. Sheets, 3) Safely Manual, Storage life is approximately six montbs from date ofshipment. 4) Sealant Selection Guide. JolDt Design Recqmmeudadons for Crafco RoadSaver SilIronc Sealants n mehi Jol Is in pee Pave .Is , -Joint Width 1/4" 3/8" 112" 518" 314" I 718" I" I !IS" I 1 114" , I 318" \*1IMinimum Sealant Recess U4" 1/4" 5116" 5116" 318" I 318" 318" I 112" 112" I 112" 112" i Backer Rbd Diameter 3181• 112" 518" 3/4" 718" I" 1 ]/4" 1 [l2u I 112" , i 3/4" 2" , , Sealant Bead ThicknC3S ,. 114" 114" lI4" 5/16" 3/8" J 7116" 112" I Inn 112" Ill" i 112" , Minimum Joint , 1718" I 3 318" iI SawlReservoir Depth I 1/8" I 114" 1 112" , 1 3/4" i 2" I 2318" i 2 27/8" 3 118" , I MinimumBacker RodIlellth 112" 112" 518" 11116" 314" i 13fl6" 7/8" I I" 1" I" I" I i Estimated Usage Non-Sag 245 149 112 70 51 J 35 26 23 , 18 16 15 J i Estima!od Usage 273 172 130 82 58 ! 41 I 31 i 27 22 20 19 , ! Self-leveling(!l/gaJ) i 1 Backer rod diometer should not be vaned from spec1fied dimensIOns, lllllrger .lIes are used, mcreascd saw depth IS needed, 2 Sealant bead thickness can vary by ±25% of design value. 3 Never install Roadsaver Silicon. to a depth greater than the joint widlh (I to J). *Please contact Crafco for additional Joint size design recommendations. TYPICAL JOINT DESIGNS: "",""0.'"" Cut .Not To Scale Bond Brtlker InItial Cut 􀁎􀁯􀁴􀁔􀁏􀁓􀁃􀁂􀁾􀀠 Texas Department o/Transportation Prequalified Joint Sealers The following producers are prequalified to supply joint sealants by class. Materials with lab numbers represented by dates of ..._..-facture shown below need no iob site samoling unless material aualitv is auestioned Prcqualified Joint Sealers Class Products Producer Address/Phone No. Contact Lab No. Tested Expires 2 Sof-Seal Low Modulus Horizontal Sealant 804 W.R. Meadows of Texas, Inc. 99867 P.O. Box 7752 2555 NE 33" Fort Worth, TX 76111 (817) 834-1969 Andrew W. Tam C03370028 C02372057 C02370025 CO 1372028 01/01103 07/01/02 01/01/02 07/01101 06/30/03 12/31/02 06/30/02 12/3110 I C01370015 C00372091 01101101 07/01/00 06/30/01 12/31100 C00370015 01/01100 06/30/00 3 Road Saver 221 Sealant Part No. 34221 809 Crafco, Inc. 99579 6975 W Crafeo Way Chandler, AZ 85266 (602) 276-0406 Vern Thompson C05370040 C04372227 C04370072 C03371953 01101105 07/01/04 01101/04 07/01/03 06/30/05 12131104 06/30/04 12/31/03 C03370007 C02372036 C02370007 01/01/03 07/01/02 01/01102 06/30/03 12/31102 06/30/02 C01372010 CO 1370007 C00372083 07/01101 01101/01 07/01100 12/31/01 06/30/01 12131100 C00370007 01/01/00 06/30/00 3 Road Saver 222 Sealant Part No. 34222 809 Crafco,Ine. 99579 6975 W Crafco Way Chandler, AZ 85266 (602) 276-0406 Vern Thompson C05370039 C04370073 C03371951 C03370005 C02372034 01/01/05 01/01104 07101103 01/01/03 07/01/02 06/30105 06/30104 12/31103 06/30/03 12/31/02 C02370005 01101/02 06/30/02 CO 1372008 CO 1370005 C00372081 C00370005 07/01/01 01101101 07/01/00 01/01100 12131101 06/30/01 12/31100 06/30/00 3 Hi-Spec Hot Pour W.R. Meadows of P.O. Box 7752 Andrew W. Tam C04374868 01/01/05 06/30/05 Material/Producer List 1 5/16/05 Texas Department o/Transportation Preaualilied Joint Se.lers Cia" Products Joint Sealing Compound 809 Producer Texas. Inc. 99867 AddresS/Phone No. 2555 NE 33'" Fort Worth, TX 76111 (817) 834-1969 Contact Lab No. C04372114 C03371973 C03370027 Tested 07/01104 07/01103 01/01103 Expires 12131104 12/31103 06130103 C0237205G 07/01102 12/31102 C02370024 01/01/02 06130102 CO 1372027 07/01101 12/31101 CO 1370014 01/0110 I 06130/01 C00372090 07/01100 12131100 C00370014 01101100 06/30100 3 CMC 102 809 Crackfiller Manufacturing Corporation 99064 P.O. Box 6738 Cheyenne, WY 82003 (307) 778-8610 Mark Langer C03370011 C02372040 C02370011 C01372014 01/01103 07/01/02 01/01102 07/01101 06/30103 12131/02 06130102 12/31/01 COl370019 01/01101 06/30/01 C00372095 07101/00 12131100 C003700 19 01101100 06130100 3 SealM..ter Ind., Inc. 3405 809 SealMaster Ind., Inc. 99219 180 I Lancasterl Hutchins Rd. P. O. Box 1008 Lee Malone C03370024 C02372053 C02370021 01101103 07/01102 01/01102 06130103 12131102 06130102 Lancaster, TX 75146 CO 1372024 07/01/01 12131101 (972) 227-9093 CO 1370024 01/01/01 06130101 COO372099 07/01100 12131100 4 Dow Coming 8S8 810 Dow Corning Corporation 99875 390 I S Saginaw Rd Midlalld, MI 48686 (517) 496-5799 Rich Palmer C05370140 C04373972 C03375509 01/01105 09116104 01101/04 06/30/05 12/31/04 06/30/04 C03371958 07101103 12131/03 C03370012 01/01/03 06/30/03 C02372041 0710 1102 12131102 C02370012 0J/OI/02 06130/02 C01372015 07101101 12131/01 C01370011 o110 J/O I 06130101 C00372087 07/01/00 12131100 II 01101/00 06130100 Material/Producer List 2 , ".,'; 5/16/05 Texas Department o/Transportation Pl"Cqualificd Joint Sealers Class Products Producer AddresslPhone No. Contact Lab No. Tested Expires 4 Non·Sag Crafco, Inc. 6975 W Crafco Way Vern Thompson C05370034 01101/05 06/30/05 810 99579 Chandler, AZ 85266 C04373023 07/01/04 12131104 (602) 276-0406 C03371954 07/01103 12131103 C03370008 01/01103 06/30/03 C02372037 07/01102 12/31/02 C02370008 01101102 06/30/02 CO 13720 I 1 07/01/0 I 12131/01 CO 1370008 01/01101 06130101 COO372084 07101/00 12/31100 C00370008 01101/00 06130/00 S !i!!W!Illl m 􀁐􀁉􀁾􀁾􀁊􀀠􀁾􀁾􀀵􀁈􀁩􀀠􀁾􀁬􀀡􀁏􀁊􀁃􀀻� �􀀡􀁜􀀱􀀡􀁗􀀺􀁾􀀠/j!p.i!lftBii!ilhi9l-e; pf!15874 lleij'(J!if9bJll 􀁾􀁭􀀠nttQJ'iliJi 􀀡􀁬􀁦􀁩􀁬􀁾􀁍􀀠('6Sj)'!148'Sll14 4 301 Non-Sag Pecora 165 Wambold Rd, Roy Cannon C05370309 01101/05 06130105 8lO 99981 Harleysville, PA 19438 C04370184 01/01104 06130104 (215) 723·6051 C03371966 07/01/03 12131103 C03370020 01101103 06/30/03 C02372049 07/01102 1213 1102 C02370030 01101102 06130102 4 Tremco Tremco, Jne. 3777 Green Rd. Tn-Min Fong C04374746 01101105 06130/05 810 99083 Beaehwood, OH 44122 C04371979 07/01104 12131104 Spcctrem 800 (216) 766-5680 C03375499 01/01104 06130104 Fax (216) 765·6737 C03371971 07/0ll0J I2I3l/03 COJ370025 01101/03 06130/03 C02372054 07101/02 12131102 C02370022 o110 l/02 06/30/02 CO 1372025 071Ol/0 1 12131101 5 Dow Coming 890SL 810 Dow Corning Corporation 99875 3901 S Saginaw Rd Midland, MI 48686 (5 t7) 496-5799 Rich Palmer C05370139 C0437397I C03375510 01/01105 09/16/04 01/01104 06130105 12/3 lI04 06/30/04 C03371960 07/01/03 [2/31/03 C033700t4 01/01/03 06/30/03 MateriallProducer List 3 .. 5116105 ------------Texas Department a/Transportation P,'cqualified Joint Scalers CI.s. Products Producer AddresslPhone No. Contact Lab No. Tested Exulres C02372043 07102102 12131102 i C02370014 01101102 06130102 C01372017 07101101 12131/01 C013700t3 01101101 06130101 COO372089 07101100 12131100 C00370013 01101100 06130100 5 Pecora Pecora Corp. 165 Wambold Rd. Roy Cannon C03371964 07101103 12/31103 300 SL 99981 Harleysville, PA 19438 C03370018 01101103 06130/03 810 (215) 723-6051 C02372047 07101102 12131102 C0237OO28 01101102 06130102 C01372031 06121/01 12/31101--------------- --5 Sika 810 Sixo Corp. 6122 Rachel's Court Greg Reisz C03370021 01/01103 06130103 99572 Katy, TX 77494 C02372050 07/01102 12131102 (281)693-2121 C0237OO18 01/01102 06/30/02 C01372021 07101101 12131/01 COl370020 01101101 06/30101 C00372096 07101100 12/31100 C00370021 01/01/00 06130100 -----------------------------------5 Six. 15LM SL Sik. Corp. 6122 Rachel's Court Greg Reisz C04374648 01/01105 06130/05 810 99572 K.ty, TX 77494 C0337OO22 01101/03 06130/03 (281) 693-2121 C023n051 07101102 12131/02 C02370019 01101102 06/30/02 CO 1372022 07101101 12121/01 C0I370021 0110110 I 06/30101------------------5 Tremco Tremco, Inc. 3777 Green Rd. T.-Min Fong C04374745 01101/05 06130105 810 99083 Beachwood, OH 44122 C04371980 07/01104 12131104 Spectrem 900 SL (216) 766·5680 C03375498 01101104 06130/04 Fax (216) 765-6737 C03371972 07101103 12131/03 C03370026 01101103 06130103 C02372055 07101102 12/31102 C02370023 01101102 06/30/02 17··· C01372026 07101/01 12131101 Dow CorninK9.02RCS Dow Corning. __ 390 I S SaQ;naw Rd Rich Palmer C05370141 01101105 06130105 5116105Material/Producer List 4 7 Texas Department o/Transportation 12/3110409116104810 I Corporation IMidland, MI 48686 I C04373973 99875 C033755 [[ 01/01104 06130104(517) 496·5799 I 07101103C03371959 12131103 06130103C03370013 01101103 07/01102 12131102C02372042 0[/01102 06130102C02370013 07/01101C01372016 1213110 I C01370012 01/01101 06130101 07101100 12131100C00372088 06130100COO370012 01/01100 Watson Bowman 07/01104 12/31104I WaisonlBowman 3414 Blue Candle Jay Waddock C04371668 Drive 0613010499968 C0337554I 01101104810 Spring, TX 77388 C03370030 01/01103 06130103 (281) 65 1·8394 07/01102C02372059 12131102 C02370027 0613010201101102 12131101CO!372030 07/01101 01101101 06130101CO 1370023 COO372098 07101100 12131100 01101100 06130100C00370023 C0537OO35 01101105 06130105􀁃􀁲􀁡􀁦􀁣􀀶􀁾􀁉􀁲􀁬􀁣􀀮􀀠 I 6975W.Crafco':\vay 􀀧􀁖􀀡􀀱􀀮􀀼􀁉􀁜􀁛􀁥􀁒􀁷􀁬􀀡􀁾􀁰􀁮􀀧􀁾􀁲􀀾􀀧􀀮􀁾􀀬􀀬􀀢􀀬􀀠" C04373022 07/01104 12131/0499579, Chandler, AZ 85266 C04370452 01/01104 06130/04(602) .276·0406 07/01103C03371952 12131/03 01/01103 06130103C03370006 12131102C02372035 07101102 C02370006 01/01102 06130102 12/31101COI372009 07/01101 01/01101 06/30101CO 1370006 07/01100 12131100IC00372082 􀁾􀁥􀁊􀁲􀀮􀁬􀁁􀁁􀁑􀁉􀀱􀁾� �C00370006 01/0 5/16/05Material/Producer List 5 Texas Department ojTransportation Prequaliried Joint Sealers Class Products Producer AddresslPhone No. Contact L.bN•. Tested Exnires I (651)r748·S}J4 8 Pecora SL Low Pecora Corp. 165 Wambold Rd. Roy Call1lon 􀁃􀁏􀁾􀁀􀁪􀀸􀀠pi(olZQ5, 􀀡􀀡􀀶􀁀􀁐􀀷􀀰􀁾􀀠Modulus 99981 Harleysville, PA 19438 C04370185 01101104 06/30/04 810 (215) 723-6051 C03370019 OliO 1103 06/30/03 C02372048 07/01/02 12/31/02 C02370029 01101/02 06/30102 CO 1372032 08/0110 I 12131/01 8 Sib 15LM SL 810 SikaCorp. 99572 6122 Rachel's Courl Kaly, TX 77494 (281) 69)·2121 Greg Reisz C04374649 01101/05 06/30/05 C04372182 07/01/04 12/31/04 C04370458 01/01104 06130/04 C03371968 07/01/03 12J31103 C03370022 i 01/01/03 06/30/03 C02372051 07101102 i 12131/02 C02370019 01101/02 06130/02 CO 1372022 07101/01 12121/01 COl370021 01101/01 06130101 Material/Producer List 6 5/16/05 HIf1'8 Cca,. 1•• 15150 SUrveyor Blvd. 􀁔􀀮􀁾􀀨􀀹􀀷􀀲􀀩􀀳􀀶􀁉􀀭􀀰􀀰􀀶􀀴􀀠The HHTB Companies Addison. TX 75001 F.csimlle (972) 361-0065 tngineers Architects Planner'S www.hnth.eom Archer Western Contractors, Ltd. 2121 Avenue"r HNTB Suite 103 Arlington, TX 76006 Request for Information Response JulyS, 2005 Originator. Andrew Scheennann RPINumber: R-AWOIOI Subject: Light Pole Template conflict with pennant Request: Please Reference Plan Sheets 306 & 303 and attached sketch Archer Western has discovered that the bottom template for the light pole anchor bolts is in conflict with the pennant The Template extends approximately 􀁾􀁮past the face of the pennant Please provide a solution for this conflict as soon as possible as not to delay the project Response!ActioD. Twa.: As discossed on July 1􀁾􀀬􀀠Archer Western is directed to install the anchor bolt pattern fur the South traffic rail with the offset towards the traffic fuce -􀁾􀂻off center of the T-4 rail. (Opposite of sketch provide by Archer Western) It's requested that the area of the embedded anchor bolt template near the pennant be cold spray galvanized to prevent msting due to minimum concrete coverage. The Light pole for the North traffic rail should be centered on the T-4 rail concrete. By: Guy V Baulen, EIT HNTB Corporation Date: July 5, 2005 Cc File Steve Chutchian, Town ofAddison Jerry D. Holder, HNTB Corporation HM"IBeo.... It 15150 SUf'leyor Blvd. Telephone f!11Z) 361 .. 0064 The HNTB 􀁃􀁯􀁭􀁰􀁾􀁮􀁬􀁥􀁳􀀠Addison. TX 75001 Foesl_ (972) 361-1 Ii:: '-' .2 l 􀁾􀀠.:::tJ 0 't ...... (3 !J 􀁾􀀠􀁾􀀠'" 􀁾􀀠\.9 !J § 6 ..::: Il... """ 􀁾􀀠8 l) •'" © © © © .2c::: \s :s,\:J">-..;:::it a 8 J 􀁾􀀠'% \,) 􀁾2"" 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠\-.. :lie .<.,it lV)'0.\ 6 􀁾􀀠􀁾􀀠 ----11 􀁾􀀠􀁾􀀠0 =t -1􀁾􀀠􀁾• t 􀁾􀀠() 􀁾• t ('I c:5 􀁾􀁾IlL ('I • () ] 0 at ---I @@@@' 􀁾􀀠t ('I d 1(\,? 􀁾􀀠a. ] i;:0 􀁾􀀠\\.....-\. 􀁾􀀠.1: 􀁾􀀠􀁾􀀠􀁾􀀠Vi :::.::--l 'V)-0 􀁾􀀠 􀁾􀀠 i';.. 􀁾...: Archer Western Contractors, Ltd. Arapaho Road Phase III Job No. 204059 IREQUEST FOR INFORMA rlON RFI # ____􀁾􀀱􀁾􀀰􀀵􀁾___ PROJECT No. Phase III Date: July 5, 2005 Western and S&J Electric have compiled the attached sheets, showing the revised bridge conduit locations as discussed with the Town of I􀁁􀁾􀀬􀁾􀁾􀁾􀀧􀁾􀁾􀀠and HNTB. The conduit material changes in many instances. We understand that the material wi!! be paid under the appropriate pipe In i bid items. confirm these revised conduit location. Page 1 Conduit Layout per Plans 335 . 33l> < 􀁾􀀢􀀠OiJlPul m C-2 Fixt Oulpllt 􀀼􀁾􀀨􀀩􀁾􀁾􀂷􀁱􀁾􀂷􀁾􀁾􀀬􀁕􀁬􀁾􀀺􀀻􀀻􀀮􀀠􀁾􀀠"Tara! 􀁃􀀮􀁯􀀧􀁾􀁤􀀧􀁵􀁬􀁴􀁳􀀺􀀬􀀠5 . , 􀀬􀀺􀁾􀁾􀁃􀀮􀁾􀁨􀀺􀁾􀀧􀁾􀁬􀁾􀀺􀀠;...2 􀁆􀁉􀁾􀁲􀁥􀀤􀀢􀀠􀁂􀁆􀁾􀀠􀁡􀀬􀁆􀀡􀀩􀁤􀁵􀁴􀁥􀀺􀁾􀁬􀁲􀁉􀀮􀀠,.'."...,.-,.. Proposed Conduit Layout South T-4 Rail Specific section of the T·4 Reil. where more than five conduits will be present et one lime the two conduits for the type B fixtures will be run In the bridge deck (spen 9) 􀀧􀀺􀀺􀀺􀀻􀁾􀁩􀁡􀁬􀀧􀁃􀁾􀁾􀁤􀁕􀀮􀁬􀁴􀁓􀀺􀀠0 . 􀁆􀀺􀀺􀀱􀀢􀀺􀁾􀁆􀀮􀁾􀀮􀀢􀀨􀀳􀁾􀀱􀀮􀀬􀀬􀁅􀀡􀀧􀂷􀀠􀀧􀁾􀁾􀀾􀀠􀀺􀀮􀁂􀀺􀀬􀁆􀁉􀀱􀀴􀁵􀀺􀁾􀀬􀁾􀁟􀀺􀀺􀀺􀀾􀀢􀀠􀀮􀁾􀀬􀀺􀀮􀁦􀁾􀁩􀁵􀁸􀁾􀀮� �􀀹􀀮􀁲􀁉􀀻􀁫􀁾􀀻􀀺􀁛􀁾􀁴􀀺􀀺􀀺􀀭􀀼􀀠. .339''''' 􀀺􀀺􀁾􀁾􀀺􀀺􀀶􀁾􀁾􀁾􀀯􀀡􀀺􀀺􀀠..... . .. 􀁔􀁾􀀺􀁴􀁾􀀧􀁉􀀺􀁟􀁣􀁯􀁩􀁬􀁤􀁾􀁬􀁴􀁳􀀧􀁩􀀠' Specific section of the T·4 Rail, where more then five conduits will be present at one time the two conduits for the type B fixtures will be run in the bridge deck (spen 9) Find /Replace dialog box Page 2 of2 􀀱􀀱􀁾􀀱􀁣􀁾􀀽􀀽Iiturn off special meaning of character c I' Ilbeginning 01 line 1$ ilend of line I 1 ilany single character I , la. lIany alphabetical character [a-zlA-Z] Id Ila!]l 􀁤􀁩􀁾􀁩􀁴􀀠[0-9] I I:n lIany alphanumeric character [a-zIA-ZIO-g] I I, IIA colon loIlowed by a space also matches 􀁡􀁮􀁾􀀠punctuation characterl I[.. ·J Ilany one of the characters in ... ; ranges such as a-z are legal I IIA...J Ilany single character not in ... ; ranges are legal I Ilzero or more occurrences of string 5115' I !!s+ Iione or more occurrences of string s I 151 IIslring s followed by string t I In Cells If on. specifies a search for text in cells. Fractions If on, specifies a search for fractions. Find Clicking the Find button locates the specified text. Change Clicking Change replaces the text element in the Find field with the text element from the With field. Change All Clicking Change All replaces all the specified text elements in the design file. Change Fence Clicking Change Fence replaces the text elements that match the current Fence search criteria. Change Single Clicking Single replaces a single text element in the design file, as identified by the user. mk:@MSITStore:D:\Program%20Files\Bentley\Documentation\MicroStation.chm::/ustnhel... 7/5/2005 Archer Western Contractors, Ltd. Arapaho Road Phase III Job No. 204059 IREQUEST FOR INFORMATION RFI # __--=1"'0"-9__ PROJECT No. Arapaho Phase III Oate: July 5,2005 ow. Plano Parkway, Ste 200 , Texas 75093 Saulsn review of the attached Sketch ;1', you will notice that the reflector as specified in the contract pJans Is in conflict with the approved Type C lights Bracket Sketch '2' shows modifications as discussed in the owners meeting. The modifications shown in Sketch '2' will minimize light !m••int"nalnce issues. Please direct Archer Western and S&J on how to proceed with lighting issue. Please respond as soon as possible as not to further delay the project. Page 1 •• • ".s; 0 IS:). e. !;; Ci-􀀮􀁾􀀠&;; -. "%.0---\0 e. ...f:,) a..... 􀁾􀀠 J-\.L.. L􀁾􀀠-'. --,. 􀀺􀁾.... '" 􀁾􀀠􀁾􀀠1} 􀁾􀀠'-' 􀀭􀁾􀀠::;:: J 􀀮􀁾􀁾􀀠--\ 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠25 >< 􀁾􀀠d §􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠" " a \.) !oJ @@@@􀁾􀀠􀁾􀀠" 5 􀀮􀁾-...:;::t () § \C\ \..) c5 \(\ :t:: 􀀭􀁾􀀠::"\ \..) 􀁾􀀠􀁾􀀠􀁾􀀠>-... 􀁾􀀠\-.. :lie t lV) 􀁾􀀠'\\c5 􀁾􀀠\\: , 􀁾􀀠" l 􀁾􀀠Q-.r e 􀁾􀀠􀁾􀀠.::t 􀀮􀁾􀀠.. 􀁾􀀠a t 􀁾􀀠􀁾􀀠t () 􀁾􀀠''(\ "1:::8 􀁾􀀠0IL • d 􀁾􀀠\J Q j 􀁾􀁾􀀠1\\ 􀁾􀀠-t 􀁾􀀠ij, 􀁾-l 􀁾􀀠􀁾􀀠-􀁾􀀠VI 􀁾􀀠t '(\ v 􀁾􀀠() 􀁾􀀠\-. @@@@ Andrew Schneemann /ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 8, 2005 􀁓􀁕􀁢􀁭􀁮􀁭􀁬􀀣􀀺􀁉􀁾____􀁾􀀶􀁾􀀵� �􀀮􀀱􀁾____􀁾􀀠New Submittal: X To: HNTB /Town of Addison R:e..submittai ; 16801 Westgrove Addison, Texas 7500H010 Project: Arapaho Road Phase iii Af\N # 204059 (972) 450-2886 Engineer: HNTB Attn: Guy Van-Baulen Submittal Specification Reference: Town of Addison I Plan Sheet DT-03 Description of Submittea Item: Decomposed Granite -Product Summary Report & Samples ManufacturerlSub/Su ppJier: Martin Marietta Related Section I Drawings: Town of Addison I Plan Sheet DT-03 Additional Comments: The Decomposed Granite will mixed with Type III! Cement Include 2 Bags of Material Contractor's Certification Engineer's Stamp "Having Checked this submission, we certify that IT conforms to the requirements of the Contract in all respects, except as otherwise indicated. 􀁃􀁦􀁾􀀧􀀠Pe.tibr,,)l 􀀬􀀺􀀭􀀧􀁾􀀱􀀠,PI4.w::., hi" ,('];10 fh;4.ct!:,., 1·10 & 1·20 Ultra Rotors Upgrade to heavy duty. commercial grade features in a sprinkler !hafs ideal for residential and commercial projects. • Models: Shrub and 4" (10 em) and 12" (30cm) Pop-ups (optional stainless steel riser on 4" popup modeO • Radius: 25' to 51' (7,6 to 15,5 m) • Discharge rate: .9 to 1-10 1-20 1-208.2 GPM (0,20 to 1-20-HP 1,86 m3lhr; 3,4 to I31,0 Vmin) • Arc: Adjustable or Full-Circle versions • Inlet: 3/4" • Nozzles: 12 interchangeable nozzles (8 standal:d and 4 low angle) • FloStop(TM) Control allows stoppage of flow at ian individual head The Industrial-Strength Rotor for Residential and Commercial Use If you're looking to upgrade over a typical residential grade rotor, tihis is where tihe search ends. No other rotor in its class gives you more, Uke easy arc adjustment right at the top ofthe sprinkler, a heavy duty sprtng with reliable retraction, and a standard walersaving drain check valve that handles up to 10 feet of elevation change, Plus, we now include a rack of nozzles tihat Includes both standard and low angle nozzles (tihe ideal solution for virtually any landscape situation), as well as the new FloStop(TM) feature that provides tihe added convenience of easily slopping water flow through a single head without turning off the entire system. With its ultra-sturdy construction, rest assured you've got a product thafs sure to endure -irs even protected by a full five-year warranty! But, for tihose who still want more, be sure to consider our stainless steel option. 8/17/2004http://www.ew ingl.comIewing/htmjpgs/44002400.htm Page2of3 FEATURES AND BENEFITS Integral rubber cover Stays put to keep play areas safe Full rack of 8 standard and 4 low angle nozzles Continuously improved, honest performance, superior c1ose-in coverage (now with key-lock installation) NEWI FloStop(TM) Control , Allows stoppage of !low through an Individual head while remainder of system is running Easy arc adjustment (40 -3601 Right at.the top of the sprinkler Contlnl:l0usly improved gear drive Backed:by over a decade of proven reliability Commercial grade spring Reliable retraction every time Drain check valve for up to 10' elevation change Saves water, reduces liability 8117/2004http://www.ewingl.com/ewing/htmjpgsl44002400.htm 'Nt"i';.' .,' R"iJ!$; .3Ptk.PSI . h Page 3 on 30 30' \1 1.6 40 '31 1() 2.t 40 1.&1.0 50 31' 1.2 LA 50 28' 2.1 (iQ 32 1:3.. SP 􀁾􀁑􀀧􀀠.. 2,3 30' 32''', 1:Z": :,1'\ 􀀻􀀺􀁜􀁾􀀻􀀻􀀧􀁦􀁾􀀻􀀲􀁦􀁲􀀺􀀹􀀻􀁾� �􀀧􀂷40': 33"",. 14,15. .􀁾􀁪􀀮􀀢􀀺>􀁾􀀺􀀻􀀺􀀢􀀺􀁜􀁕􀁾􀁦􀁦􀀬􀀧􀁩􀁩􀀺50".. 􀀳􀀴􀁾􀀢􀀠t.· .'. '60',':'" 3'4:. 18' ;􀁾:ooi;·i:$ti:;S;(l 30 34 1S 30 29 2,8 40 36 1a 3.6 40 32 3.12.0 50 38' 2,8 lill 35' ULA(iQ 38 22 60 '37' 3.a 30 36' 2.0 30 31' 3,4 40 􀀳􀀸􀁾􀀠24 4:5 4(}. ..34:3,9U 50 41' 2.7 :511' . .fI' ".'4AIA(iQ 40' 29 eo . . '38'47 30 36' 26 40 40' 303.5 50 42' 3.4 60 42' 37 30. 31.' 32 40 40',. 3.7. U Ij8: 􀀴􀀳􀁾􀀠42 6f) 4l'. 46· 30 38' 42 43' 4,9 6,0 40 50 46' 5.5 60 47' S.O 4(}'"" , 45',. 6.0. 50', .Jar 6.8, U. .tilt 7Jf:110'70 51' 8.2 8/17/2004http://www.ew ingl.com/ewingihtmjpgs/44002400.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (8i7) 640·3898 FAX: (817) 640·8734 SUBMITTAL Date: June 28. 2005 Submittal # : ...1 ____7:..:7.;.,1'--__---' To; Attn: HNTB I Town ofAddIson 16801 Westgrove Addison, Texas 􀀷􀀵􀀰􀀰􀀱􀁾􀀹􀀰􀀱􀀰􀀠(972) 450-2886 Guy Van·Baulen Project: Arapaho Road Phase III New Submittal: X Re...submittal : AIW# 204059 Engineer: HNTB Submittal 􀁓􀁰􀁥􀁣􀁩􀁦􀁬􀁾􀀮􀁴􀁩􀁯􀁮􀀠Reference: 02810 -Irrigation .§y'-'s"'te"'m"-_____:=J_--" 􀁄􀁥􀁳􀁾􀁲􀁩􀁰􀁴􀁩􀁯􀁮􀀠of Submitted Item: Round Box ManufaclurerlSublSupplier: American LandsCape Systems Related Section I Drawings: Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements -of the Contract in all respects. except as othelWise indicated ," Sign: Print Name: 􀁔􀁩􀁾􀀡􀁥􀀺􀀠Asst. Project Manager Reviewed by: Andrew Schneemann Date: June 28, 2005 Engineer's Stamp SHOP DRAWING REVIEW Review Is only for general conformance ·with the design design concept of the contract documents. Markings or comments shall not be construed as relieving the contractor from compliance with the projeCt plans and specifications. nor departures therefrom. The contractor remains solely responsible for details and accuracy, for confirming and correlating all quantities and dimensions, for selectlngfabrlcatlon processes, for techniques of assembly. for safety and fur satisfactory performance of his work. riNo Exception Taken IDi'l'B Corporation [J Make 􀁃􀁯􀁲􀁲􀁥􀁣􀁴􀁬􀁯􀁮􀁾􀀠Noted [J Amend and Resubmit [J ReJected -See Remarks Copy: ____-'-'''-____ Page 1 of! Sub 77. r [ Click Here to Print Page \METEK1/f/'''/7/. I D2.6 i 0-1'-/GliCkHere to Print Page J PVC Sch 80 Nipples 8/17/2004http://www.ewingl.com/ewing/htmjpgs/04005390.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 16006 PH: (811) 640-3898 FAX: (811) 640-8134 SUBMITTAL Date: June 28, 2005 Submittal # 􀀺􀁾􀀱___---,7.::.0.;,;.1____ New Submittal: X To: HNTBI Town Of AddIson Re-Submlttal : 16801 Westgrove Addison, Texas 75001-9010 Project: Arapaho Road Phase 111 AIW# 204059 (972) 450-28se Engineer: HNTB Attn: Guy Val'l-Bauleo Submittal Specification Reference: Description of Submitted Item: Manufacturer/Sub/Supplier: Related Section /Drawings: Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as otherwise indicated." Archer Western Co S,gn: 􀁾􀀠Print 􀁬􀁜􀁉􀁡􀁭􀁾􀁫􀁷􀀠Title: Asst. Project Manager Reviewed by: Andrew Sctmeemann Date: June 28, 2005 02810 -􀁉􀁲􀁲􀁩􀁧􀀮􀁴􀁩􀁯􀁮􀀧􀀮􀀺􀁓􀀢􀀬􀁹􀀢􀀬􀁳􀀢􀀧􀁴􀁥􀀢􀁭􀁾______-, Rain Bil'd 1BOO Series Sprinkler Head American Lai1dscape Systems 02810-13A&C 4" Tall Heads in the Grass Areas 12" Tall Heads in Landscape Beds Head Patterns will be selected 10 best fit the siluatkm Engineer's Stamp SHOP DRAWING REVIEW Review Is only for general conformance with the design concept of the contract documents. Markings or comments shall not be construed as relieving the contractor from compliance with the project plans and specifications, nor departures therefrom. The contractor remains solely responsible for details and accuracy, for confirming and correlating all quantities and dimensions, for selecttng·fabrlcation processes, for tedinlques ofassembly, for safety and for ntlsfll(tory perfollIlllllCe of his work. Dflo Exception Taken 1ii(,.lake Corrections Noted 1StAmend and Resubmit D Rejected -See Remarks 􀁾􀀮􀀠JS< Date '7(Z/c;r*' rJ...Nrtf-.-. PGN. ,0 /5<..j,b'fiiL '1ti1Al..J dP 􀁁􀁏􀁾􀀻􀀭􀁤􀀬􀁊􀀠 , 70, I .. t-. 'i v,t!) -'" 1.:./"-'0 ".I[ Click Here to Print Page J 􀁒􀁁􀀻􀁎􀁾􀁂􀁉􀁎􀁄􀀠1800 Series, 1800-SAM 1800-PRS, 1800-SAM-PRS Primary Application Industries leading series of spray sprinklers for turf and shrub applications. Featuresl • Precipitation rates matched across sets and across patterns. • Ratcheting on all models. • Exclusive pressure-activated wiper seal. • Plastic and stainless steel materials, • Seamless, molded construction. • Strong, stainless s.teel retract spring. • Side or bottom inlet on 1806 and 1812 only. Industries leading series of spray sprinklers for turf and shrub applications. ff or 􀁾􀀠30 Trajectory I • • 1 Nozzle Pressure Radius Flow Precip Precip I ; psi ft. GPM In/h In/h 1 112F • 15 20 25 30 9 10 11 12 1.80 2.10 2.40 2.60 2.14 2.02 1.91 1.74 2.47 2.341 2.21 2.01 12TQ I· 15 20 25 30 9 10 11 12 1.35 1.58 1.80 1.95 2.14 2.02 1.91 1.74 2.47 2.34 2.01' 2.21 12TT 15 20 25 30 9 10 11 12 1.20 1.40 1.60 1.74 2.14 2.02 1.91 1.74 2.47 2.21 2.01 12H 15 20 25 30 9 10 11 12 0.90 1.05 1.20 1.30 2.14 2.02 1.91 1.74 2.47 2.34 2.21 2.01 12T I , i 15 20 25 30 9 10 11 12 0.60 0.07 0.80 0.87 2.14 2.02 1.91 1.74 2.47 2.34 2.21 2.01 12Q l • 15 20 25 30 9 10 11 12 0.45 0.53 0.60 0.65 2.14 2.02 1.91 1.74 2.47 2.34 2.21 2.01. 15 Series MPR 30 Trajectory I • I • 8/17/2004http://www.ewingl.com/ewing/htmjpgs/35003496.htm INozzle 15F • lSTQ • 15TT .. 􀁾􀀠I ISH ... , 1ST , lSQ •, Pressure psi 15 20 25 30 15 20 25 30 15 20 25 30 15 20 25 30 15 20 25 30 15 20 25 30 Radius ft. 11 12 14 15 11 12 14 15 11 12 14 15 11 12 14 15 11 12 14 15 11 12 14 15 Flow1precip Precip GPM 􀁾􀀠In/h , In/h , 2.60 2.07: 2.39 3.00 2.01 2.32 3.30 1.62 1.87 3.70 1.58 1.83 1.95 2.07 2.39, 2.25 2.01 2.32 2.48 1.62 1.87: 2.78 1.58 1.83 1.74 2.07 2.39. 2.01 2.01 2.32 2.21 1.62 1.87 2.48 1.58 1.83 1.30 2.07 2.39' 1.50, 2.01 2.32 1.65 1.62 1.87, 1.85 1.58 1.83 , 0.87 2.07 2.39 1.00 2.01 2.32 1.101 1.62 1.87 1.23 1.58 1.83 , 0.65 2.07 2.39: 0.75 2.01 2.32 0.82 1.62 1.87i 0.92 1.58 1.83 15 Strip Series 30 Trajectory • .. Nozzle Pressure WxL Flow I I , I : 8117/2004http://www.ewingl.com/ewing/htm jpgsl35003496.htm Page 7 01'9 1 psi ft. GPM 15SQ 15 18 x 18 2.68 20 19 x 19 3.06 i • 21 x 21 ; 25 3.42 i 30 23 x 23 3.73 15EST 15 4 X 13 0.45 20 4 X 14 0.50 ; ! 25 4x 14 0.56 I -30 4 X 15 0.61 ! 15CST 15 4 x 26 0.89 20 4 x28 1.00 I -25 4x 28 1.11i 30 4 x 30 1.21 . I i15SST 15 4 X 26 0.89 ; 20 4 X 28 1.00 ! I -:25 4x 28 1.11 30 4 x 30 1.21 I !9SST 15 9 x 15 1.34 20 9 x 16 1.47• 25 9 x 18 1.60 30 9 x 18 1.731 16 Series M PR 15 Trajectory . • • Nozzle .Pressure Radius Flow. psi ft. GPM ' I 8/1712004http://l.vww.ewingl.com/ewing/htmjpgs/35003496.htm 13 2.37 116 F-SLA I 15 1 20 14 2.66 * 15 2.9625>1\ 30 16 3.221 I I I 1 I16H-SLA 15 13 1.181 20 14 1.33 :l;Ik 25 15 1.48 1.6130 16 15 13 0.5916Q-SLA I 20 14 0,67 \10 I 25 15 0,74 30 16 0,81 i 22 Series MPR 3S Trajectory • A ! Nozzle: pre;:rre Radius. Flow ft. :GPM i , 22F-SS 15 171 2.37l . 20 18 2.66 i 􀁾􀀠, 25 19 2.96 I 30 20 3.22 :22H-SS 15' 17 1.18 I 20 18 1.33 :l;Ik 25 19 1.48 I I 30 20: 1.61 22Q-SS 15 17 0.59 8/1712004http://www.ewing1.com/ewing/htmjpgs/35003496.htm • • , 0.67120 18 If: 25 19 0.74 30 20 0.81 l'age':l 01 . . .. ... -_.. ..-.􀁾􀀠5 Series Stream Bubbler Nozzles o Trajectory Nozzle Press.ure Radius Flow PSI ft. GPM * 5F-B 15 5 1.50 20 5 1.50 25 5 1.50 30 5 1.50 5H-B 15 5 1.00 20 5 1.00 25 5 1.00 30 5 1.00 5Q-B 15 5 0.50 20 5 0.50 􀁾􀀠25 5 0.50 30 5 0.50 SCST-B 15 5 0.50 20 5 0.50 25 5 0.50 30 5 0.50 Note: Indicates adjusted radius @psi shown. Note: Flow @adjusted radius of 5 feet. 8/17/2004http://www.ewingl.com/ewing/htmjpgsl35003496.htm ragtl 1 Ul 1 Click Here to Print Page TORO Toro Compensating Flood Bubbler Nozzles Features: • Built-in pressure regulation • 2 GPM adjustable flow • 0.25, 0.50 and 1.0 GPMflxedJlow • All pressure compensating, maintaining constant 30 PSli performance at pressures exceeding 30 PSI • Use on shrub adapter, 570Z Series sprinkler, 570 risers :and riser extenders Specifications: • Recommended operating range: 20·50 PSI • Maximum operating pressure: 75 PSI 8/17/2004http://www.ewingl.com/ewing/htmjpgs!30009202.htm Ewing Inigation Products Catalog: 35003,:lU ( Click Here to Print Page J Plastic MPR Nozzles Primary Application Matched Precipitallon Rate (MPR) nozzles simplify the design process by allowing sprinklers with various arcs and ready to be mixed on the same ci rcuit Models available for spacing from 3 to 20 feet. Fit all Rain Bird spray heads and shrub adapters. Features ·Matched precipitallon rates across sets and across patterns in new 5 Series, 8 Series, 10 Series, 12 Series, and 15 Series for even water N()l' OTl1 A...1Jff..pJ1tia __--...!,,_'􀀧􀁴􀀮􀀮􀁬􀀡􀁌􀁉􀁉􀀮􀀭􀁟􀁾􀁟􀀠distribution and design 􀁾􀀠flexibility. -New 5 Series nozzles meet small-area shrub or turf requirements. 􀁎􀀬􀀴􀁊􀁎􀁾􀁂􀁉􀁎􀁄􀀠 -New and improved 8 Series nozzles now have a lower water flow which allows more spray heads per zone. -1800 Series white filter (.035" x .045") screens (shipped with nozzles) maintain precise radius adjustment and prevent clogging. (New and Improved 5 and 8 Series nozzles are shipped with blue fine-mesh (,02" x .02,,) filter screens.} -Stainless steel adjustment screw to adjust flow and radius. Operating Range: -Spacing: 5 to 15 feet (1,5 to 4,5 m) -Pressure: 15 to 30 psi (1 to 2,1 bar) -Optimum pressure: 30 psi (2,1 bar) Models -5 Series ·5 Series: bubbler nozzles -8 Series ·10 Series -12 Series -15 Series ·15 Strip Series '16 Series: stream spray -22 Series: standard stream spray 8/17/2004http://www .ewing1.com/ewing/htmjpgs/35003820.htm ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste.103 Arlington, Texas 76006 PH: (817) 640-3898 FAX: (817) 640-8734 SUBMITTAL Date: June 28. 2005 Submittal # :LI___.....:6:::9'-.!.1___--..J New Submittal: X To: HNT8 f Town of Addison Re-Submittal : 16801 Westgrove Addison, Texas 75001·9010 Project: Arapaho Road Phase III ANJ # 204059 (972) 450-2886 Engineer: HNTB Attn: Guy Van-Baulen Submittal Specification Reference: 02810 -Irrigation System Description of Submitted Item: Mint Clik II Rain Sensor Manufacturer/Sub/Supplier: American Landscape syistems Related Section I Drawings: 02810-20C Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of (he Contract in all respects, except as othelWise indicated." Titre: Asst. Project Manager Reviewed by: Andrew Schneemann Date: June 26, 2005 Copy: ____􀀭􀀧􀁆􀁾􀁩􀁉􀀡􀀺􀀮􀁥____ Engineer's Stamp SHOP DRAWING REVIEW Review Is only for general conformance 'with the design concept of the contract documents. Markings or comments shall not be 􀁣􀁯􀁮􀁳􀁴􀁲􀁵􀁾􀁤􀀠as relieving the contractor from compliance with the project plans and specifications, nor departUres therefrom. The contractor remains solely responsible for details and accuracy, for confirming and correlating all quantities and dimensions, for selectlng·fabricatlon processes, for techniques of assembly, for safety and for satisfactory performance of his work. 0)10 Exception Taken 􀁉􀀡􀀡􀁦􀁾􀁡􀁫􀁥􀀠Correct ions Noted I!I Amend and Resubmit C Rejected -See Remarks "* 􀀤􀀢􀀢􀀬􀁾􀀪􀀮􀁊􀀮􀀮􀀮􀀮􀀭􀁉􀀧􀁁􀀮􀁾􀀠1/001. c:.<......Q-C 􀁲􀁺􀀮􀀬􀀮􀀮􀀬􀁾􀀢􀀢􀀠fir.a:tE . 􀁾:s-.r,c...!' ft-Lo.! fIr--,J-ro--ISfabrlcat lon processes, for techniques of assembly, for safety and for satisfactory performance of his work. [J 􀁾􀁯􀀠Exception Taken I!il'Make Corrections Noted C Amend and Resubmit o-aejected -See RelnaI'ks 􀁾􀀠U,..i-r Mu.-:;;( lb...,&, &AL<:1 -.r Oy.-fI,JOf"rt'l.N,"* ';fa-AOQi-r-,d,JAL A/dr 6 S I", 􀀧􀀻􀀺􀀺􀀧􀁾􀁍􀀮􀀮􀀠 Evolution DX2 Stainless Steel " -.-..... Pedestal Cabinet 􀀬􀁾􀀠.' , --... AC on/off switch with built-in GFI -, utility outlet " . '<.r-',Louiiered vents top ,"ahd bottom with spiash 'guard filter CONTROL SYSTEMS Locking Lid ,-, r· • ,"" ..,-,' 􀀾􀀺􀁾􀀻􀁜􀁻􀀮􀀭􀀬􀀮􀀠I' ,-􀀮􀁾􀀠... , " ,'; -\' , , , 􀁾􀁬􀀠, " j. ," .., '" , .. ,' 􀀧􀁩􀀻􀁅􀁾􀀭􀀭􀀭􀁴􀀭􀀭􀀺􀀭􀀺􀀬􀀭􀀭􀀢' 􀁾􀁨􀁧􀁬􀁥􀁤'station' , ',termiriilfilo:ards , ":, provide easy' ',accessibility , .' . \: ':,:\i: 􀀬􀁾􀀠"'., , ,':,"., : -, ;', ,: .t1. ': . ',. _ " t 􀀧􀀬􀀧􀀮􀁾􀀺􀀠1,. 􀁾􀀧􀀠.. " , ;". 1.'.: :. ,', ...,:,,': 􀁒􀁡􀁩􀁮􀀮􀁍􀁾􀁳􀁴􀁥􀁲is atethnolofJY-based, innovative/e;lVirorlmentally sensitive company ••􀀬􀁣􀁦􀀺􀁦􀀡􀁣􀀡􀁩􀀨􀀻􀁾􀁴􀁥􀁤􀀠to providinfJ waJe,r􀁭􀁡􀁮􀁡􀁧􀁥􀁦􀀡􀀱􀁥􀁮􀁴􀀺 􀀺􀀤􀀮􀁾􀁬􀁬􀀡􀁾􀁬􀁯􀀡􀀬􀀡􀁳􀀠to the "irrigafion inau5t1! 􀀼􀀢􀁾􀁾􀁪􀁉􀁬􀁍􀁩􀁓􀁩􀁩􀁒􀂮􀀢􀀭, 1825-1 03 Surveyor A;'-nue, Simi Valley, CA 93063 ph: 805527-4498 Fox: 805 527-2813 ....I'Vo/UI rninmnct""l"'rrtm o EVOLUTION DX2 SPECIFICATIONS The Evolution DX2TM irrigation controller shall be manufactured by Rain Master Irrigation Systems, Inc. The controller shall have the following features and functions: 􀁾􀀮􀀮􀀮􀁬􀀬􀀮􀀮􀀩􀀠􀁾􀁰􀀭􀁁􀁯􀁲􀀩􀁉􀁾􀀶􀁾􀀠Part 1.0 -Hardware Features f'£1l-...,.•;::>..-_-L.__ 'Sr􀁡􀀼􀀺􀀨􀀮􀀧􀁾􀀧􀀠LA1 , 1.1 all mount cabinet or pedestal enclosure. 1.2 Station configuration options 6, 12, 18, 24, 30, 36, 42 or 48 stations. Dedicated outputs for 2 normally closed master valves, 1 normally open master valve, and 1 pump. i, 1.3 Connectivity for 4 input sensing devices. F6ur pulse input type devices e.g. flow sensors, flow meters, ET device, rain gauge, anemometer, etc. 1.4 80 character LCD display \vith 24-key membrane keypad. 1.5 Built-in remote control jack. Permanent internal remote mount available. 1.6 Built-in transient protection. 1.7 Optional lightning protection available. 1.8 Audible tone(s) for valid or invalid operator entry. 1.9 Lifetime retention of the user's program and 'date/time, without the use of batteries. 1.10 All outputs are protected from field wiring short circuits. 1.11 Built in amperage meter to accurately measure and diagnose valve solenoid electrical problems. 1.12 Modular architecture. Modular output boards (6 or 12 station) facilitate maintenance and elitninates total controller down time. RMIS PART No. 500675 Rev. A Page 1 EVOLUTION DX2 SPECIFICA TIONS 2.0 -Scheduling Capabilities 2.1 Operation of 12 conventional programs with 8 start times, 48 ISC (individual station control) or a combination of each. 2.2 Watering based upon 14-day schedules, skip day schedules, or 31-day schedules. 2.3 Continuous cycling of programs based upon user estahlished start and end times, with a programmable delay/soak time. 2.4 Water budget per program from 0 to 999% itll% increments for adjustment ofprogram run times 2.5 Program by time. 2.6 Programmable monthly water total teIll'linates over budget irrigation. 2.7 Quick station programming allows groups of stations to be programmed with the same runtime. 2.8 Programmable water window. 3.0 Program Serup Options 3.1 Programs overlap protection or concurrent operation. 3.2 Irrigation programs, lighting programs, security, etc. (Non-irrigation programs are independent of rain shutdown mode.) 3.3 Inter station delay from 0 to 255 seconds. 3.4 Runtimes from 1 second to 24 hours programmable in hours/minutes or minutes/seconds. 3.5 Master valve selections: 2 Normally Closed Valves or Normally Open Valves with programmable delay from 0 to 600 seconds. Page 2 RM1S Part No. 500675 Rev. A EVOLUTION DX2 SPECIFICATIONS 4.0 Maintenance and Alarm Diagnostic Capabilities 4.1 Flow monitoring. Automatic alarm processing (which provides station and/or master valve shut down and program advance as required) diagnosing and reporting station underflow and overflow, mainline breaks, and unscheduled flows. Maximum upper flow limit is 2000 GPM. 4.2 Electrical field wire monitoring. Automatic alarm processing (which provides station shutdown and program advance) for station over current, short circuits, broken field wiring or faulty solenoids. _ 4.3 Power monitoring. Automatic alarm prdcessing/reporting for power outages and power restoration. Intelligent program resumption for all outages or power glitches, no lost cycles Or water window violations. 4.4 Communication monitoring. Automatic alarm generation/reporting for lost communications or restoration when using hard wire communications. Automatic fault isolation of communication wiring problems to wire path between controllers. ) 4.5 Diagnostic lights ((LEDs) for all station outputs as well as the dedicated outputs: MV1, MV2, N.O. MV, and PUMP. Lights indicate when 24 VAC is at output terminal. 4.6 Built-in test (BIT) functions allow selected controller circuitry to be field-tested. 4.7 Manual test mode. Allows user to automatically advance from station to station using manual run time while displaying valve solenoid electrical current for each station as well as station flow in GPM. 4.8 Manual station and manual multi-station modes. -Turns on any station for user entered runtime and automatically selects usage of the proper master valve and/or pump for this station. Multistation mode allows an)' single station or output to be turned on individually orin combination with an)' other station(s). Valve solenoid electrical current is displayed. 4.9 Manually entered program . .Allows user to enter a one-time program to be run immediately or scheduled for later in the da\". The manual program is independent of automatic programs and shaU start only one time. 4.10 Manual start ofautomatic programs (1-12). Start any program independent of tbe scheduled start time and water day. RMIS PART No. 500675 Rev. A Page 3 􀁾􀁒􀁁􀁉􀁎􀁉􀁖􀁉􀁾􀀠 EVOLUTION DX2 SPECIFICA TIONS 5.0 Miscellaneous Features 5.1 English/Spanish language selection. 5.2 Automatic limit setup Oearn mode) for flow and current. Global percentage adjust for limit establishment. . 5.3 Omit by date allows the user to enter up to 15 dates to exclude irrigation. 5.4 Operates as a standalone or central. 5.5 Fertilizer injector station with programmable delay from 0 to 255 seconds. 5.6 Flow Max -This exclusive feature allows controllers with a single point of connection to share a pump, master valves, and flow meters without the need for peripheral wiring/relays. All flow limits are dynamically managed as stations across controllers transition off and on. Features include: A. Automatic protection and report for main line breaks, unscheduled flow, station high and low flow. . B. Read flow at any controller C. Dynamic monitor shows system starus at all times D. Pump protection during exception conditions 6.0 Electrical Specifications . 6.1 Input Power Required: 117 117 VAC + /-15%, 60 HZ, 20 VA, plus load current. 6.2 Maximum load current per station or master valve output: 1 AMP 6.3 Maximum combined load current: 2 AMPS 6.4 No batteries required. Page 4 RMIS Part No. 500675 Rev. A Evolution DX2 Stainless Steel Pedestal Cabinet Installation 15.5" 1 33.5" Mountinlj Pad28"x 28 x 8" minimum concrere Plld with beveled edges ---.,..--' Pedestal Mounting Mounting Templateprovided for easy installation 1.75" typ. Cl 􀀭􀀶􀀮􀁓􀀢􀀭􀁾􀀠:0 @I o ® 􀀳􀀮􀁾􀀢􀀠-+1--®,-1-+--"'-.o.13.5" @CD􀁊􀁟􀁉􀀢􀀧􀂷􀀺􀁏􀀢􀀬􀀮􀁾􀀬􀀮􀀢􀀬􀂩,>Front ",", If-'--􀁬􀁓􀀢􀀭􀀭􀀭􀀭􀀭􀁾􀀠Bolt Holes-stainless steel hardware standard with enclosure lrem Description A,B , 2" conduit -station wiring , C 1II conduit· communication D AC power conduit E 1" conduit· sensor wiring F External anrenna G Grounding rod , , Bolt and Conduit Template ' RMIS Part No. 5005G1 Rev. B Rain Master is a technology-based, innovative, environmentally sensitive company dedicated to providing water management solutions to the irrigation industry. 􀁾􀀢􀁁􀀧􀁎􀁉􀁗􀀮􀀡􀀡􀀢􀀧􀁾􀁊􀀬􀀮􀁾􀀠 3910-B Royal Avenue, Simi Valley, CA 93063 ph: 805527-4498 Fax: 805 527·2813 Evolution DX2 Stainless Steel Pedestal Cabinet AC on/off switch with l:iuill'-in Gfl utility outlet Stainless steel document basket Two j)!)int latchingutility door RMlS Port No. 500502 Rev. B Louvered vents tap and bottom with splash guard filler Locking lid Natural brushed stainless steel Sriish reflects surrounding colors Angled station lerminal boards provide easy accessibility Rain Master is a technology-based, innovative, environmentally sensitive company dedicated to providing water management solutions to the irrigation industry. 􀁾􀀢􀁁􀀮􀁎􀀢􀀢􀀡􀀺􀀡􀀢􀁾􀀢 􀀬􀁾 3910·B Royal Avenue, Simi Valley, CA 93063 ph: 805527-4498 Fox: 805 527-2813 of ,001, and capabilities. packaged in a simple, i'.almos, thinks for irself. notifYing and even Vers.tile ProgrannDiiig Oprratiim tif12 􀁃􀀻􀀻􀁦􀀧􀁉􀀮􀁴􀁬􀁭􀁾􀁯􀁦􀁵􀁺􀁬Programs i1/ld!Of individtlal s/(Jtion control Up to "8 rtart:.!ti"w 􀁾􀁾􀁣􀁨􀀠or ronrinuoUJ cycle with progmmmabk 􀀡􀁾􀁫time 14 d4y "h,du/t. ,kip by d4} od/day waNting "h,du/" Multiple Mtl.ifer \&lve -ul«t one 0/two ;nmttr woo. andif pump. on aperprogram basis. 􀁤􀁴􀁨􀁾normaU] Dpmtd or 1Wrmtllly cu;sd. Multi-Lingu,allntu{ac( 􀁾􀀠t1nigntd tv cptrau in sromtllA11fUdf!s ProUwnm.tbk ltalion T1lJrtim(J from 1 5tcoTUi to 24 houn i!lttr-JUltion dtfa) /rum 0 l() 255 !«fJntiJ Water rationing tools Wftto budgetfrom 0 to 999% in 1%i1lf:remm(J fugrammabk WIltu window Programmable mQnthfy water torol tmnimttfs ovu-budgtt irrigation Omit by datt adu.rioRfillf'Un Programmahk rain ftaturL ReGabie Modular Design Modular swrt circuit proofOUtpllt! iJlJllilabft[rum 648 Jlttlions in 6JIluiOIl inmmtnts Upgradt for untrttl communications at nn] time Indtjiniu mmrion ofpTOgt'llnlJ d1 lIitl! (lJ timt and d4u during nl/pawufoilurtf Optional JMall} duty itghtning and 􀁊􀀯􀁬􀁲􀁧􀁾􀀠for lightning pront amJJ .lntegrat«! Flow Monitoring 􀁐􀁲􀁴􀁣􀁩􀁉􀁾􀀠high/low station, mninline, and tlmdudukd limiu • 􀁄􀀩􀀷􀀱􀁡􀁾􀁩􀀨􀀠limit adjust11unt for mu/fiwstation ojJlration Auto kantfonction with diri!ct GPM r(atiout in display Inttl1igmt almm notijiult1im. ifOmltJ mtdtmn.:ttiOIl, 1Indprogmm adtMm:tmmt \ lntegxa,ed Electrical Cunent Monitoring -) Builtwin tkrtricdl curnmt m(t(r with Ampeml( V;(Wa/in dfiplay ContinU()W' dtmTca{ mttmlrnnmt ()fstlttion solt1loitU. mamr va/Uti, pumps Autfl kant fimction with adjwrahk high and low limits • Dynam;c limit 􀁡􀁤􀁪􀁷􀁴􀁭􀁾􀁮􀁴􀁦􀁯􀁲􀀠􀁭􀁾􀀯􀁴􀁩􀀭􀁭􀁴􀁴􀁩􀁯􀁮􀀠opuation lntdligmt alarm ne:ifiart!o1l, wtion (ondntmtuion, Imtiprogmm tidlHJJlCfflIt'IIt Intelligent Single Point of Connection Operati(Jh • Shau a singleflow mttl!r and mttJtzr tJIllvtlpump amu 􀁭􀁵􀁬􀁴􀁩􀁰􀁻􀁾􀀠rontroll.trl. • Fww limits 11ft intdligffltly and dynamically updaud fJ.J J st4tioru ITttmition providingfi,)lprot«rion for mainlini!, station. and IImchdukdfow • &adflnv at flny CQnrrol1er Manual Diagnostic Features Multi-station opemtion with irutanta;uollJ jlowlatrrmt viewed in diJpfay Systtm swion duck QmtroUtr 􀁢􀁦􀁬􀁪􀁬􀁴􀁾􀁩􀁮􀀠ulftrst Diagnostic LED!for all outputs Rain A[a;ttr Rtmou rurd, Multi-mode reliable communications • hi-dir«tional(l1.tJIrwllJ) rommunicl1t;om ertSll" inugriey 0' Hardwirt, UHFpoint to point radio, trunk mdio. cellular; UHFmire and flf/yard radio, phone, rtptttt« optnJtion Field or Central Programming Full Jifppartfor (ontroUrr programming itl the fidd or (It mmr:l ((tilizing comparisf)!l fflanagcmtnt l(w/s on thr PC Tiw-/tydptrnwordaeUJs IlCtitwud by tIM mer prouds against Imatttlmriud lfIodificatio}'JJ to controller programs 1825-103 Surveyor Avenue' Simi V,liey. Cali forni, 93063 • 805.527.4498 • Fax 305.527.2813 • '",,,,.rninm.,,er.com 􀁾􀀠 EVOLUTION DX2 • FLO. . 􀀮􀁾􀁓􀁏􀁒􀀠INSTAUATION /􀁲􀁙􀁾􀀺􀀧􀁾􀀺􀀻􀀻􀁾􀁾􀀠INMJTYPICAL SPUCE WIRES WITH INftIT 2+ CONNECTIONS WATERPROOF TYPE FOR FLOW CONNEOORS !NM 2 -􀁾WHITE \,"'; .. 􀁾􀀠.. I 1 { , I , ! "" ,.. ... _1,,-' " I, '" \""'1\-I ..-( .... \ 􀁉􀁟􀁬􀀢􀁟􀁾􀀧􀁦􀁾􀀬􀀠"1""1 -"\' >' "I , , I \ . .. ,"-I 􀁜􀁾􀀠\.-/.:" ... ,I" -" SENSOR IPROVIDEDI lNftIT I + VALVE BOX u£5 5HH.L IE m:lA11lR 'TtWt :);l, I.AYOUTCOORDlNATETHItE 1m .'" 􀁴􀁯􀀧􀁬􀁾􀁏􀁃􀁊_.. [@:::: 1l!l!I_.... lffi1:=: ffi!I: i= 6!!J :=: {!I " il1l:5Uil Ii!( /IIlTIAIO._... fii!l""' ..... ffi!} 􀁾􀀺􀀽􀀠Iliil"tl§l: =:: ....." I!ii .-... Ilil /IiOTURO,...... 􀁾􀀺􀀺􀀺􀀺􀀠􀁉􀀡􀁭􀀺􀁾􀀽􀀠ffi!I:=: ffiID N 1111n..-r ,-..I!iJ " 101.D.OCI I!iJ :::.:' It to'lQ!Z.CI:I ff!!l 􀁾􀀠􀁾􀀺􀀺􀀮􀁾􀀠fiE::': LEGEN[}:I!E fI: 11)1:)11O.ff􀁛􀁗􀁝􀀺􀁾􀀠fiiJ 􀁉􀁉􀁉􀁏􀁔􀁾􀀠6E 􀁾􀁾􀀰􀀧􀁉􀀺􀀧􀀺􀁾􀀠Im}: 􀁾􀀽􀀻􀀠Ii 101tUt D E2J 􀁾W/oI.KCENTEALINE CURVE OATI' CURVE OB..TA RAOIUS T...,.,.,. §""" ,...,. "'""""" ...􀀬􀁾S'll"a1'VWC< ,..-....... ...... C1 ,........ ...... ,,􀀤􀀷􀀮􀂷􀁾􀁗􀀢􀀧􀀱􀁾􀀠 ".... ......". '..... ...,r ,... s.r4t?W ....."" ,......o 21·42'10" ...... 􀀢􀀧􀀱􀁾􀀠Se1"an7"W ....... RETAINING WAlL LAYOUT· ENLARGEMENT toi ....􀁾􀁴􀀧􀀳􀀱􀀢􀁅e,."" f""'" f...... ...'" ""...'00Cl.0Q'""",,110M - ARCHER WESTERN CONTRACTORS, LTD. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 640·3898 FAX: (817) 640-8734 SUBMITTAL Date: April 26. 2005 Submittal # :LI___......;6;,,;1,;,,;.1:......__..... .J New Submittal: X To: HNTB ITown of Addison RewSubmittal: 16801 Westgrove Addison, Texas 􀀷􀀵􀀰􀀰􀀱􀁾􀀹􀀰􀀱􀀰􀀠Project: Arapaho Road Phase III A1W# 204059 (972) 450-2886 Engineer: HNTB Attn: Guy Van·Baulen Submittal Specification Reference: 2x2 Plaque Description of Submitted Item: Manufacturer/Sub/Supplier: Related Section /Drawings: Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in all respects, except as otheMise indicated," Title: Asst. Project Manager Reviewed by; Andrew Schneemann Date: Aprtl 26, 2005 2x 2 Plaque Southwell Company Copy: t e sf)uthwell co. p. o. box 299 san antonio, tx 78291 ph. (210} 223.. 1831 fax (210} 223.8517 o 􀁡􀁰􀁰􀁲􀁯􀁶􀁾􀁤􀀠(no corrections)o approv,d as noted o revise and resubmit signed by: date: CUSTOMER: ARCHER WESTERN CONTRACTORS. LTD, 2121 AVENUE J. SUITE 103 ARLINGTON. TX 76006 SHIP TO: ARCHER WESTERN CONTRACTORS, LTD, 1510 SURVEYOR ADDISON. TX 75001 ATTN: ANDREW SCHNEEMANN 􀁐􀁌􀁾􀁁􀁓􀁅􀀠SIGN & CAST BRONZE PLAQUE. .-..."" .. 􀁾.• •RETURN . ONECOPY 24" 24"WX24"H iCALE:1/4" = 1" 􀁾􀀠,//ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager HNTB Corp. Designer Roadway-HNTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. () 􀁾􀀠OXIDIZED TEXTURE YOUR ORDER WILL BE PRODUCED FROM THE ARTWORK YOU SEE HERE. IF yoli APPROVE THIS ARTWORK AND IT CONTAINS ERRORS, YOU WILL BE HELD FINANCIALLY FINANCIALLY RESPONSIBLE FOR THE WORK WE 00. PLEASE CAREFULLY CHECK THAT ALL IS CORRECT REGARDING SPELLING. DESIGN. COLOR AND I "!l7 N ;;(j)(j) //)7 /1 IlOll AlUl 'rlllll11NAL PUOOII·lUlUEil CD (j) !1! rn ... ()'" -\(') -i!: 0 m QUOTE # 16547 FILE NAME: 􀁑􀂱􀀺􀀱􀁀􀀲􀀮􀁩􀀲􀁊􀁾􀀠PLEASE JOB # DATE P.O. # SUBMITTED:-"12"".2",-7",,.0..:..4___ RE: ARAPAHO ROAD PHASE III DRAWN BY: MARl HERNANDEZ QUANTITY: L.􀀭􀀺􀀧􀀺􀀬􀀻􀁖􀁙􀀭􀀽􀁖􀁾􀁜􀀼􀀽􀀮􀀡􀀺􀀺􀁉􀀽� �􀀭___________ 􀁓􀁉􀁚􀁅􀀺􀀺􀀻􀀺􀀺􀀺􀀺􀀭􀀭􀀭􀀽􀀽􀀽􀁾􀀽􀀭􀁾􀀲􀀮􀀭_______ SPECIFY MOUNTING ATTACHMENo CONCEALED WOOD SCREWS W/ROSETTES EXPANSION BOLTS W/ROSETTES o TOGGLE BOLTS WfROSETTES THE DESIGN OF THIS PLAQUE HAS BEEN MADE USING COMPUTERIZED GRAPHICS. THE ACTUAL PATIERN USED IN CASTING WILL BE MADE BASED ON FINAL APPROVAL OF THIS SUBMITIAL DRAWING. THE FORMAT, LEITER STYLE, LEITER SIZE. SPACING AND MOUNTING ARE BASED ON INDUSTRY STANDARDS AND OUR CAPACITIES TO PRODUCE A HIGH QUALITY CASTING. MATERIAL: CAST BRONZE FINISH: BORDER: DOUBLE LINE r"',Tr:nc I ARAPAHO ROAD PHASE III , October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction ManagerHNTB Corp. Designer Roadway-H NTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. I ....CoI ..... 1111 15150 Surveyor Slvd. Telephone (972) 361 􀁾􀀠0064 The tiNTS Companies AddI_ TX 75001 Facs!mlfe ('iT12.) 361-0065 Engineers Architects Pl!mners www.hntb.com Archer Wesrern Contractors. Ltd. 2121 Avenue"r HNTBSuite 103 Arlington, TX 76006 Request for Information Response July6,2005 Originator: Andrew Scheermann RFI Number: R-AW092 Subject: WatsonfFaytor Driveway Grades Request: According to Sheet 53 ofthe Plans. the elevation at South end of the WatsonfTaylor Drive to "Match Existing Pavement". The elevation of the Driveway at STA 0+96 is 600.849' (See attached Sheet for calculations). but the existing driveway/pavement varies in elevation from 599.72' to 600.34' (See attached Drawing). Please advise. Response/Action Taken: In response to the elevation and alignment issue at the WatsonfTaylor Drive, Archer Western in directed to move the Drive centerline forward/up station along the Arapaho Rd PGL to align the 24ft wide driveway entrance with the existing pavement Archer Western Contractors, Ltd. is then directed to change the driveway slope to .8% from .9%; this new slope is to be utilized up to 10ft before the proposed end of the Drive. The remaining 10ft to end of Drive shall be install almost flat holding the grade to the gate location. were Archer Wesrern is directed to remove an additional 25ft back along the existing pavement and replace the existing pavement with new 􀀶􀁾thick pavement matching the new elevation at the gate and transitioning the pavement to match the existing pavement 25ft from the gate. Note additional information will follow, ifthere are any question and conflicts please forward all information under this existing RFI number as an addendum. (Example 92.1, 92.2. etc ... ) Dr. 􀁢􀁾􀀻􀀻􀀬􀁾􀀩􀀭􀀭􀀭􀀭Date: July 6, 2005 HNTB Corporation Cc: File 15150 Surveyor 81vd. Telepho... (972) 361 • 0064NII'I1I Cot'"" 11 The HNTS Companies A. 25763-AIapoho Road· P_m VIA Hand Delivered -10:00 am T", Ben WilhettdLetter of AKh..W-.n Con_Ltd.Transmittal =--NTB 2121 Avenue 'T Suite: 103 Arlington, TX76006 Shop Drawtag Submillal w ...... forward/nq to you: Estimates Reports Change Order Book 􀁾Plans Shop Drawings Disk Other Prints Samples Copy of letter # of Copies Drawing # Last Dated Code Description 2 ; Submittal, 61.1 4126/05 ; I I i 2ft X 2ft BronzePlaque I ! i I Thos..... transmitted: for approval 􀁾For your use Return Corrected prints As requested Resubmit Copies for review Submit X Copies for distribution ror Review & comment No exception taken Amend and resubmit Make corrections noted P....note: ARCHER 􀁗􀁅􀁓􀁩􀁑􀀻􀀬􀀡􀀺􀁩􀁤􀁬􀁢􀀮􀁉􀁾􀀠􀁾􀁾􀀬􀁧􀁧􀀺􀁾􀀠LTD. 2121 Ave J, St.tlI.N\\IS\ Arlington, Tex s 76006 PH: (817) 640-898 APR 2 7 Z005 AX: (817) 640-8734 SUBMITTAL Date, April 26, 2005 Submittal # :11..-___6::,;1:.:..1:.......__......1 New Submittal: X To: HNTB I Town of Addison Re-Submittal; 16801 Westgrove Addison. Texas 75001.9010 Project: Arapaho Road Phase III AJW# 204059 (972) 450·2886 Engineer: HNTB Attn: Guy Van·8aulen Submittal Specification Reference: 2x2 Plaque Description of Submitted Item: 2 x 2 Plaque ManufacturerfSublSupplier: Southwell Company Related Section I Drawings: Plans Additional Comments: Contractor's Certification "Having Checked this submission, we certify that it conforms to the requirements of the Contract in ali respects, except as otheiWise indicated," Sign: . Print Name: TiUe: Asst Project Manager Reviewed by: Andrew Schneemann Dat.: April 26, 2005 Engineer's Stamp Copy: _____􀁒􀁾􀀧􀁾􀁬􀁥____ "'IIZ :lUOTE # 16fuU'---___ FILE NAME: 􀀰􀀴􀂷􀀴􀀶􀀸􀀹􀀺􀁃􀀧􀀽􀀧􀀮􀁥􀁄􀁾􀁒􀁟􀀠D I I/:' JI en:: I""n" , 􀁣􀁾􀀼􀁣􀀬􀀬􀀢􀀠}} 􀀩􀁾􀀠sou we co. CUSTOMER: p. o. box 299 san anfonio, fx 78291 ph. (210) 223..1831 fax (210) 223·8517 ARCHER WESTERN CONTRACTORS, LTD, 2121 AVENUE J, SUITE 103o approv,d (no corrections) ARLINGTON, TX7G006o approv,d as noted o revise and resubmit signed by: date: SHIP TO: ARCHER WESTERN CONTRACTORS, LTD, 1510 SURVEYOR ADDISON. TX 75001 ATTN: ANDREW SCHNEEMANN •-•• 􀁾􀀧􀁾􀀧􀀮􀀧􀀮􀀺􀀷􀀢􀀠• PLEASE SIGN 8. CAST BRONZE PLAQUERETURN• ONE COPY 24" 24" W X 24" H lALE: 114" = 1"f ) /ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh OXIDIZED TEXTURE 24" Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager HNTB Corp. Designer Roaclway-HNTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. RAISED BORDER AND()glYOUR ORDER WILL BE PRODUCED FROM THE ARTWORK YOU SEE HERE, IF SATIN FINISH7\lYOU APPROVE THIS ARTWORK AND IT CONTAINS ERRORS, YOU WILL BE HELD 􀁌􀁅􀁔􀁾FINANCIALLY RESPONSIBLE FOR THE WORK WE 00, PLEASE CAREFULLY \n /) 7) 􀀩􀀩􀁾􀀩CHECK THAT ALL IS CORRECT REGARDING SPELLING, DESIGN. COLOR AND 􀁾􀀠 Texas Page J/2 Altek Engineering & construction Co. Structural, Foundation and Civil Engineer p. O. Box 172004 Arlington, TX 76003·2004 Phone: (811) 672-1989 Fax: (817) 563-1465 June 06, 2005 ArcherWestern Contractor, LTD. 2121 Avenue J. Suite 103,Arlington, TX 76006Td: (817) 640-3898 Attention: Don Good/Ben J, Withered, Project Manger Tel: (817) 401-5456. (817) 401-7202 Subject: Construction sequence for Arch &: Beam Erection Plan, Temporary support system (ShoringTowers); Crane capacity analysis for the Span # 9, Cable installation; Load influence on permanent structure for the Main arch and beam span ofthe Arapaho Road Bridge.Town ofAddison. and Dallas County.Texas Attached please find the follOwing documentations for the above mentioned subject; Section #1 shows the construction sequence for all work required at span # 9 including "Arapaho Construction Sequence", Section #2 details the erection ofarch sections and concrete beams with the reqUired f.Use-work which includes "Arapaho Span # 9 Erection Plan, Arch &: concrete U-Beam Erection Drawings, Arch Erection LiftTable & Loading. Arch shore tower &: Support Beam Analysis, Concrete U -Beam Shore Tower &: Support Beam Analysis, Plan Sheet # 273 -276 Arch/Main Span Erection Sequence, King Fabrication Dwg # 01-072-El Arch, Pafco 50 Kip/Leg Shore Tower, Pafco 100 Kip/leg Shore tower, 100-Ton Crane Chart, 120-Ton Crane Chart, 360-Ton Crane Chart"_ Section # 3 details the hanger cable-installation and stressing procedures aCBS} Structural Strand Installation Procedures"_ ' T-524 P.003/0D3 F-040J.n-14-05 10,lla. F,o.-URS Corporation Arapaho Road Bridge, Town l'Addisol/, Dallas Caullo/> Texas Pane 212 Section # 4-details the influence ofloads on the permanent and temporary structures throughout the erection sequence which includes "Sequence Loading and Calculations". These recommendations are for the above referenced project only. All the other locations must be reviewed, sealed and signed individually. These recommendations are based upon the information and detalls provided to this engineer by the Archer Western Contractors, LTD. Supporting engineering calculations and Accessories charts for these recommendations are attached. Ifyou have any questions, or ifI may be offurther service in this matter, please call me at (817) 572-198!i or write to me at the above address. Sincerely, Attachments: Plans Engineering calculations Drawings . Charts and SpeCifications 􀀱􀀺􀁉􀁾􀁩􀁩􀀭􀁊􀀠The IINTlJ Compallies Made by Date Job Number Checked by Date Sheet Number For Backchecked by Oat. 􀁾􀀠􀁾􀀠OJ l'('\J-􀁾􀀠􀁾􀀠R cr, 􀁾􀀠I ' "" -/4 0 -.:S:>\ .... 􀁊􀀬􀀮􀁾􀀠t "" , 􀁾􀀠&0 􀁾􀀠􀁾􀀠) 􀁾􀀠􀁾􀀠􀁾􀀠l 􀁾􀀠en 􀁾􀁾􀀠,' CO, 􀁾􀀠􀁾􀀠"" .. . } ! \ Martinez, David (DGNO) From: Duffy, Bob E (GE Trans) [Bob.Duffy@Trans.ge.com] Sent: Thursday, June 23, 2005 9:32 AM To: Martinez, David (DGNO) Subject: FW: DGNO addisionWye Addison.pdf David, Here is information I sent David Eyermann on Tuesday June 21, 2005 so you have a copy. I corrected Davels E-mail address in later transmission. Bob Duffy GE Transportation 􀁾􀀠-----Original Message----> From, Duffy, Bob E (GE Trans) > Sent: Tuesday, June 21, 2005 4:58 PM > To: 'david.8vermann@railamerica.com! > Cc: Kleinhenz, Paul (GE Trans); Venneman, Pat J (GE Trans); 'jleimbacher@qualitysignal.com'; 'bbunney@qualitysignal.com'j 'walter.fithian@railamerica.com' > Subject: DGNO addisionWye > > > 􀀼􀁾􀁁􀁤􀁤􀁩􀁳􀁯􀁮􀀮􀁰􀁤􀁦􀂻􀀠David, > > Here are the measurements I made last Wednesday June 15, 2005 On the Addison Wye. If the maximum train speed is 10 MPH and there is no addition warning time for traffic light preemption time required the only wye switch which will be overlapped is the northeast switch of the wye. There will be need for cables between the East Arapaho crossing house and a new Addison crossing house and a switch circuit controller On the northeast wye switch to convey switch position information and crossing approach via HXP circuits at Addison to East Arapaho. The signal locations on the RCL PRELIMINARY plans are reasonable (per MUTCD guidelines) but I have not compared with the city plans for any conflicts. > > I have not received a fax with pre-emption time information. > > If more warning time for traffic pre-emption is required, cables maybe required to the Northwest and South wye switches. If the West Arapaho crossing needs addition warning time for traffic pre-emption cables may be needed from West Arapaho crossing house to both the Northwest (if more than 43 seconds WT at 10 MPH versus 39 seconds in PRELIMINARY PLAN ) and South wye (if more than 44 seconds WT at lO MPH versus 39 seconds in PRELIMINARY PLAN ) switches. If the only East Arapaho crossing needs additional time warning time ( if more than than 4l seconds WT at 10 MPH versus 33 seconds in PRELIMINARY PLAN ) for traffic light pre-emption and all the northbound moves from south wye USe the east wye track, cables from the East Arapaho house to switch on south wye may be unnecessary. If both wyes are used from south, switch positions information will be needed for Arapaho East requiring additional cable from south wye switch to prevent activation at East Arapaho when northbound move is made to west wye track. A separate house at south switch would be an option to reduce track cable runs on other equipment, if traffic pre-emption time causes both East and west Arapaho crossing approaches to extent through south switch. J-Four inch conduiE1under track, roadways, sidewalks, parking lots or in any area that 􀁾􀁵􀁬􀁤􀀠not be dug up again, would be useful in installing direct buriable signal cable with armor tape to signals l track connection, switches, adjacent crossing houses powerIr traffic controllers, and remote housings as required. > > Bob Duffy Duffy GE TRANSPORTATION Global Signaling > 502-266-8545 extension 2358 > > 1 Kuntz. Jim (DGNO) From: Sent: To: Subject: Eyermann, David (DGNO) Thursday, June 23, 2005 10:17 AM Kuntz, Jim (DGNO) Fw: DGNOaddisonwye -----Original Message----From: Duffy, Bob E (GE Trans) To: Eyermann, David (DGNO) ; Martinez, David (DGNO) CC: Venneman, Pat J (GE Trans) ; Kleinhenz, Paul (GE Trans) ; jleimbacher@qualitysignal.com ; bbunney@qualitysignal.com ; •Fithian, Walter (Home-Office User) Sent: Thu Jun 23 10:26:17 2005 Subject: DGNOaddisonwye David, I received the pre-emption timing requirements for the Arapaho Road and Addison Road intersection from HNTB via facsimile. Since Arapaho Road is named as the parallel to track and the clearance green is being applied to Addison Road which has 200 between its warning signal holding traffic back from the Arapaho Road intersection and Arapaho Road, and since Addison Road's southbound lane gate is much closer to the intersection than the Arapaho Road East eastbound gate, 200 feet versus about 365 feet, I like to assume their will be no preempt required for Arapaho Road East. If green clearance time was provided for both Addison Road and Arapaho Road at same time they would be in conflict, unless two preemptions" treated sequentially based on direction of train approach. I am not a aware of any traffic controllers using multiple railroad crossing preemptions in sequence. Please verify with city or HNTB, there is no plans for green clearance time on Arapaho East. If only 33 seconds warning time is required for Arapaho East, its northbound approach start will remain north of the south wye switch frog for 10 MPH trains. Since Arapaho West's eastbound signal is about 985 feet from the Addison Road intersection it is outside the bounds for consideration a traffic preemption. The Arapaho West approaches will remain within the Northwest and South wye frogs for 39 seconds warning time. Bob Duffy GE Transportation Systems Global Signaling 502-266-8545 extension 2358 1 June 21,2005 Letter: HNTB -47 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Carboline Paint System Pricing Dear Guy: Please find the revised paint pricing for the T -4 and Pedestrian railing utilizing the Caboline paint system. T-4 Rail-5103 LF -$18,351.45 Pedestrian Rail -2294 LF -$ 11,113.89 Total Carboline Paint Pricing: $ 29, 465.34 Please process this change order so that the rail manufactures can proceed with the production of the railing and not delay the project. If you require additional information, please contact Andrew at our field office. (vI Project Manager XC: Andrew Schneemann Don Good File . ,􀁾􀁫􀀮􀁶􀀼􀀮􀀭􀀮􀀠o."..J.J.","",-" ,-􀁾􀀠\)""'r JJ1,ltl---IfftJ13 TIM HNTB COM,.., •• 15150 Surveyor Blvd. Telephone (972) 361-(}064 Enqineers Ardl!tecls Planners: Addison TX. 75001 Facsimile (972) 36l-0065 www.hntb.com HHTB.lob# 25768-ArapahoRoadPha.eUl VIA Hand Delivered 􀁾􀀠OM': June 15, 2005 To: Ben WitheredLatter of Ardter Western Contl'actQrs:. Ltd. =-tNTBTransmittal 1515<) Surveyor Blvd. Addi", •• TX 75001 Pavement Joints as per the Town ofAddison We are forw«rdinc;t to you: Estimates Plans X Prints Reports Shop Drawings Samples Change Order Dfsk Copy of Leiter Sook Other # of Copies Drawlnq # Las! Oated Code Description I I Surveyor Blvd Joint 6/14105 Expansion Joints. at Surveyor Blvd 1 I Layout . 􀁔􀁨􀁾􀁳􀁥􀀠art! transmitted: For approval As requested Copies for distribution X ror your use Resubmit ror Review & comment Return Copies for review No exception taken Corrected prints Submit Amend and resubmit Make corrections noted Please note: Please follow the existing pavement details as shown in the contract plans for the $peciti<: 􀁾ofjoint construction. The Town .....·.......􀀧􀀭􀁾􀀭􀀧􀀭􀂷􀀱􀁢􀁾􀁾...· 􀁾􀀴􀀭􀀭HNTB Corporation Copy to: JennyNicewander. Towu orAddison J"'Y D. Iloldtt File (.'\\1l!i l3 􀁾􀀠• , • , I w!ii I ), \ I, • \ I I \\, t \ , Z II • ., ".'". 􀂷􀂷􀁾􀁦..-" .... "--_. ._._-,to 􀁾􀀠""3: ""'􀁾􀁉􀀠I -oo.+ni--+--l %ij:I \ l \• 􀁾􀀠􀁾􀀧􀀠is !/2 􀀮􀁾􀀠 Guy Van·Baulen From: Jenny Nicewander Unicewander@ci.addison.tx.us] Sent: Tuesday. June 14. 20051:23 PM To: Guy Van-Baulen Cc: Andrew Schneemann (c-mall); Steve Chutchian; David Wilde Subject; Expansion Joint IiiI-.-.' redwood j(lIntpdf (214 KB) Fls reference the attached expansion joint locations. The towns preference is for the redwood expansion joint shown in the plans. Jenny «redwood joint.pdf» ****************************************************************************************** ************************* This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the indlvidual(s) and entity (ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regUlations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. **************************************************************** ************************** ************************* 1 Tho flHTll 􀁾􀁉􀁵􀀠15150 Surveyor Blvd. Telephone (972) 361"'l.􀀭􀀭􀁉􀀧􀁾􀁩􀀠Zo' LEGEND􀀢􀀧􀁒􀀺􀀧􀁬􀀺􀁩􀀮􀁾I ?;W ., PRO'OSEO SOLIO .' ----=:L_____ WHlTt STRIPE , \ \ \ " \, \.,, ABSOLUTE SYSTEMS, LTD \ \ REBAR PIN '2 PER STOP) -DELETE. 57 AR.eA June 28, 2005 Letter: HNTB -53a HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control Plan for Addison Road Dear Guy: Archer Western will utilize the Traffic Control Plan on Sheet TC-4 (30) for the Addison I Arapaho Road Tie in. We will begin this work Wednesday, June 29, 2005 If you require additional information, please contact Andrew at our field office. XC: Don Good File ----------------------------------------------------I I 0 I I /; '0I I f I I 􀁾􀀠" 􀁾," /f f 􀁾􀀠􀁾􀀠--------􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭I I I I I I I I I I • I I I I . I r---_.J I I I I I i 􀁾􀀭􀀫􀁾􀁾􀁅􀁾􀀢􀁾􀁾􀀮􀀬􀁌􀀭􀁟􀀬􀁾􀀠I I I I I I I I I I ! I , Ii I .. .. -I I I-I -I I I -• I • • -• I I • I ---• I I I I I I 􀁾􀀠I II I IIII I • DETAIL "8" ----------• • • .. ---20 •--.•..• SHT. TC--4 .. ;I 􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀠 · June 24, 2005 Letter: HNTB -52 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control Plan for Surveyor Blvd Dear Guy: Archer Western is providing the attached Traffic Control Plan for the Arapaho Road Concrete paving tie in to Surveyor Blvd. We will start implementing this traffic control plan on Tuesday, June 281h• If you require additional information, please contact Andrew at our field office. , Andrew Schnee mann XC: Don Good File " " , ". W,i /1 􀁜􀀨􀁾􀁜􀀮􀁊􀀮􀀧􀀻􀀢􀁊􀀠Tc .,." 1';,,-1-4:"" #.e, i<"J/:.c.Lp,.,.,,,,, .j..., 􀀧􀀬􀀺􀀾􀁾􀀠II::;'+",,) "", G-,",,,,,,.).u " " I ••• //t HC/, I I. I 􀀯􀁾􀀧􀁾􀁾􀀭􀀺-'---J-.' l .A'''\􀀧􀁦􀀾􀀧􀁾􀀯􀀠IfO,I,j) -o.tJC I G2D-:t.Q ! :··.I....􀁾􀀠G£NERAL TRAF'FIC CONTROL NOT;;; 1, rx:: TAAfFlC CO,.TIIOI. St40WW 011 THesc IlUHS c rolt n.l£: 􀁐􀁊􀁬􀁅􀁐􀁾􀁁􀁔􀁉􀁏􀀯􀀧􀁩􀀠MO 􀁣􀁯􀁷􀁦􀁬􀁁􀁒􀁪􀁾􀀠or BtO! OWLY. PAlOR TO nu START or 􀁃􀁏􀁾􀁓􀁔􀀮􀁕􀁃􀀧􀁔􀁩􀁏􀁈􀀬􀀠THt 􀁃􀁏􀁈􀁔􀁊􀁉􀁩􀀮􀁣􀁲􀁯􀁾􀀠$)tAU. OEll'OJJP 1.foI0 SUQurr rolt TOWH or ..oIDSOH .'PRO'f'AL 1M ocrAtl... ... COHSJRUCTIOH SOlEDutL. S£OU1i;Hct Of CONS1'ItIJC1IOIf AliO TRM7lC CQHTf(OI.. fl""," TH.;.T SHAou. CAUSE WIIIIWULI lHTtRFUWlet wmt 'T'IUn'TC AlONG• .,CRO£$: AfOO 40JM:EIIT TO 'nit 9JtO.JEc:" OU!UHG COwSfRucnOIf. Ir TH£: SOfEOut..t Oft SEOU,EMCt' lJECOW(!: 􀁕􀁉􀁩􀁗􀁏􀁉􀁕􀀨􀁾􀀠OR UHSATlSr.CTOR'l' to::. 'NOR': 􀁐􀁬􀁬􀀡􀁏􀁃􀂣􀂣􀀮􀁉􀀩􀁾􀀮􀀠AOJU$1W£I'I1'S SKAtJ.. SE UAllE. 6...T EXO or AU. PHo\SCS or COMSTA'UC1fOH. 􀁃􀁏􀁈􀁦􀁬􀁦􀁁􀁃􀁴􀁯􀁾􀀠SHAU. cowPl.El't t:lNM. P,\IJDlOO WAAKINC$, JU:)lcwt 'tnIPOIWtt PA"'OoIEH'T w.AAKIHGS ANti ACtlV4yt TRAmC SlGHALS {IIO S£I".I,U'tC PAY) iLy)tAIf.o.l.. 4:. 􀁾􀀠􀁾􀀠1h"{l: 􀁜􀁾􀁣􀀠􀁉􀁒􀁆􀀺􀁖􀁬􀁦􀀺􀁗􀀨􀁏􀁾􀀠ARAPAHO ROAD PHA,SE !II " ,• ", ; , " 1/".,///Ii' /, /w,' /1 /I /I •• o /, \\1 CONTRACTOR 􀁓􀁾􀀠}./AfNYA1H 4CC(.S!: TO E'Ii1V4TI: OJUVCWAY;;' Ai .AU ilu(!:. "" I, I ( I I , I I , /i .;, .• ///a /I \\ \ . ' , (',􀁾􀀧􀁾􀀬􀀧􀀬􀀭􀀬/----:."-------///􀀬􀀯􀁾:1RO!'!oU! I 􀁃􀀮􀁾􀁾􀀢􀀧􀀠; I ----------)-'".----.:..􀀬􀀮􀁾􀀮􀀠."..:'" ---.----------------------------------------------i ------!!W2O-1J) 􀁾􀁟􀁾􀀮􀁾􀀮􀀭􀀭􀀭􀀢􀀬􀀭􀀱􀁬􀁩􀀭􀀮􀀠DETAil "8" i." ----------I ,.r ; //--, i I ----!􀁏􀁾􀁁􀁗􀁈􀀺􀀠.>kAltltSIGtt: \IO;C IR(VI(W(O; 911G! owc! Z20nUra! owe; I , ____􀀲􀁁􀁾􀁒􀁾􀀮􀁁􀁍􀁐􀁾􀁁􀁾􀁈􀁏􀁾􀁒􀁾􀁏 􀁾􀁁􀁾􀁄􀁾􀁐􀁬􀁬􀁩􀁾􀁾􀁾􀁓􀁾􀁅􀁾􀁛􀁾􀁉􀁉􀁾􀀭􀀭􀀱􀁩􀀠-􀀧􀁾􀀠, 􀀧􀀺􀀧􀁾􀁩􀁬􀁉􀁬􀀢􀁉􀁩􀀧􀁬􀁃􀀻􀁾􀁊􀁲􀁯􀀡􀁾􀁩􀁩􀁬􀁩􀀮􀀠􀀢􀀧􀁾􀁍􀀠I􀁟􀁾􀀬􀀬􀀬􀀬􀀬􀀬􀁩􀁩􀀡􀀧􀀠􀀡􀁩􀀮􀁬􀁬􀁾􀀧􀀩􀁪􀁬􀀠􀀬􀁾􀁾􀀢􀀬􀁀􀀬􀀠,;! ",I\liOO1!Il!:, 􀁾􀀱􀁊􀁬􀁩􀁬􀀠􀁾􀁉􀀡􀀮􀀺􀀢􀁴􀁬􀀮􀀠! TOWN OF ADDISON 􀁾􀁾􀁡􀀺􀀺􀀮􀀮􀀧􀁾􀀭􀀭􀁾􀀧􀀻􀁾􀀽􀁬􀀡􀀧􀁣􀁬􀁾􀁡􀁭􀀡􀀡􀁾􀀬􀁾􀀧􀁾􀀧􀁾􀁜􀁾􀀧􀁾􀀢􀀡􀀤􀀡􀀾􀀬􀁪􀀮􀁾􀀬􀁾􀀬􀁾􀀬􀁾􀀬􀁾􀁩􀁮􀁾􀁣􀀬􀀭􀀬􀀠Si.-:T. ....... CoIpot 􀁮􀁾􀀱􀀠15150 SUrveyor BIYd. TOI.ph.". ('nZl 361· 0064 The HNTB Companies Addison. TX 75001 raC$lml!e (972) 361-0065 Erlqfneers Architects Planners www.hntb.com Mr. Ben Withered HNTBProject Manager Archer Western Contractors, Ltd. 2121 Avenue"r Suite 103 Arlington. TX 76006 Re: Addison Road Traffic Control PIan June 27.2005 Dear Ben: The submitted traffic control plan for Addison Road was review and is rejected. Please revise and resubmit a traffic control plan equal or of greater protection for the moving traffic and Archer Western Contractors personal working adjacent to the active traffic as shown on contract plan sheet TC·4. page 30 and as requirement in the General Traffic Control Notes found on the Contract Drawing. sheet TC-l, page 27. Thank ro:p dl(.(2.. 􀁴􀁉􀀰􀁾___ G.;y Van ';;;len HNTB Corporation Cc: Steve Chutchian. Town ofAddison Jerry D. Holder, HNTB Corporation Fae 􀁀􀁾􀁀􀁀􀁵􀁾􀁀􀂮􀀠June 24, 2005 Letter: HNTB -53 JUN 24 'l005 HNTB 5910 W Plano Parkway CORPORATION Suite 200 􀁈􀁎􀀶􀁾􀁌􀁌􀁁􀀵􀀬􀀠􀁔􀁅􀁘􀁾􀀮􀁓􀀠Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control P Ian for Addison Road Dear Guy: Archer Western is providing the attached Traffic Control Plan for the Arapaho Road Concrete paving tie in to Addison Road. We will start implementing this traffic control plan on Tuesday, June2S'h. If you require additional information, please contact Andrew at our field office. XC: Don Good File 80 0 20 40.,.}:/I L 14 SO,,;yi-//-f Ik/􀁶􀁡􀀧􀁉􀀧􀁲􀁾􀀱􀀠􀁰􀀮􀁾I" j SCALi! IN FEET􀁷􀁬􀀬􀁾􀀢􀀬􀀠",.r .;..,J,,," cd 􀁾􀀠I N I I ! TSIOt: ?AAKING LAYOOT J:: .bt.ANS IS POR RCtlGH CONTRACTOR TO l.ANOSCA?E PLANS F'OO £$ ,A.'ljD .sLEVATIONS FCR .. 􀁾􀀮􀀠􀀭􀁾􀀮􀀭􀀮􀀠􀀬􀁾􀀮􀁾􀀠.. _-" /i iN: 11 )"... f'l. (i /i ?RCPOS£D 42 t Ii 􀁾􀀠CONTooR CONrCUR ARA?AflO ROAD -􀁩􀁐􀁈􀀮􀁾􀁓􀁅􀀠IIIouT »to LANDSCNI !NG SUfYEYOR aoiJl.£VARO TO t>{)DIS(JH ROt>{) GRADING PUW "," I PAAKING LOT AT ADDISON ROAD • "",---I􀁟􀁾_____ ,OWN OF ADDiSON. T2XAS " ....ft 􀁾􀀺􀀾.. I 􀀨􀀮􀀮􀁲􀀭􀁾􀁟􀀢􀀠􀁩􀀬􀀬􀁾􀀠i ·;:,,:r ';'COt£ 􀁾􀁾􀁃􀀬􀀻􀀮􀀺􀀮􀀺􀁾􀀮􀀭􀀬􀀮􀂷􀀬􀀮􀁉􀁓􀁈􀁾􀁾􀀧􀀠.""./! iF 􀁾􀀮􀀠􀀬􀀬􀁾􀁈􀀠O:h'e" -,n ,.pQr. ,,'"1"'1;-' <.;"' 􀀺􀁾􀀡􀀻􀁾􀀠! -;-.: ; i ..,. Cot'" ''". 15150 Surveyor B!vd. Telephone (972) 361-0064 The HNTS Companies AddIson. TX 15001 FaCllfmllel:312) 361-0065 Engineers Architects: Planners www.hntb.com Archer Western Contractors. Ltd. 2121 Avenue'T HNTB Suite 103 Arlington. TX 76006 Request for Information Response June 27. 2005 Originatnr. Andrew Scheermann RFI Number: R-AW097 Subject MBGF Post Detail over Curb lDlet Request Please reference Sheet PP-3 and revised MSE wall #2 drainage plans_ Please provide a detail for attaching guardrail posts to the top of inlet A-5. Please respond to this RFI as early as possible as not to delay the project. Response/Action Taken: In response to the required detail for the MBGF steel post. please supply the steel post connection to the inlet top as per the detail MBGF-03A of TxDot standards. See attached sheet By. 􀀱􀀬􀁾􀁾􀁾􀀩􀀭􀀭--HNTB Corporation Date: June 27. 2005 Cc: File Steve Chutch.ian. Town of Addison Jerry D. Holder. HNTB Corporation 0IIl 􀁴􀁾􀂷􀀠1011 ...Ith 􀁉􀀻􀀧􀁾􀀧􀀠(h '" 􀁾􀀮􀁉􀁴􀁉􀀮􀁉􀁴􀀬􀀠7..... -. (,,'r\t4l"led In ..,.,..,... t2' 'h er 2'5 'teat ncmlnol It:ngH.. 'IIltn Q .. II i. 7 􀀮􀁾􀁲:: 􀀮􀁾􀀭􀀮􀀺􀀺􀀠􀁉􀀢􀀧􀀨􀁬􀁨􀁴􀀮􀁾e,. ••wlfl' ....flIT It____ 􀁾􀀢􀂭rr -SPl.Ja: 1!i!I..'T 0 1 '1•• _1'11 ...., 􀁟􀁾􀀢􀀮􀁾􀀠I»U. 2" raU '" _tt.tt...... IOtO two uaed «> ,.,.. IoEilifrTI.21 tr'Olf'lf.1tI(lt'l ($H WGftTL21 ,ta'W:k:r(\ 􀁾􀀧􀁴•• or on 'the oo.n&tr_ end 'Of (I ccrocre.e 1"'011 locot.d .out.'de ,"'-tlor'l:ronrol OltlGJ"O'IOI Q('.'" of OPQOt.tno tr(lfffc. (See _ Stondor'd $MI'H 'JE:RUlHAl COftNEC'JOR 4. TNt '1W'mIno' 􀁾t)Crt flhQll be Uf Tn CIQf' ••-􀁾􀁟1" 1\1'11... Ctf'*'wiM _ on OlllMl In 􀂫􀁃􀁏􀀢􀀧􀁾􀀠wi#! IfolA. -f'Qrll;:r'O\l 􀁾􀀠􀀽􀁾􀁾􀁩􀁾􀀺􀀽􀁾􀁾􀁬􀁾􀀠􀁾􀀧􀀺􀀡􀀺􀀻􀀱􀁾􀀰􀁾􀀺􀀧􀀺􀀺􀀻􀀺􀁾􀁾􀀢􀀧􀁏􀀠1. ",";:ne/'I(3I" MIWo' "hoi'> to 6 1......11\D! 􀁾tlDfIT B1OI1 _I.t 01 a 􀁾􀂭Hon ,II"II(JI" 1.. 1N ..all tClltc. (7' ,,11..11(7' 1C,.. ........INI 􀁾􀁦􀁑􀀨􀀧􀀮􀀠4. 􀁾􀀡􀀺􀁲􀁾􀁈􀁦􀁯􀁲􀁷􀁯􀁾􀁲􀁮􀁯􀁾􀁾􀀡􀀬􀀮􀀢􀀺􀀠􀁾􀀧􀁉􀁜􀁾􀁩􀀬􀀡􀀻􀁾􀁾􀀽􀁦􀁾􀁾􀁾􀁴􀀠o ra 􀁲􀁾􀁾􀁾􀁃􀀮􀁉􀁾􀁴􀁾􀁾􀀢􀀬􀀮􀀧􀀭I,e. -2· e.d, .II 0.11"tMlSt Sn.ll I'lOO"ro. t. SoIN;;:IOI febrlW'llon '.III ce raQltl..--o at Ina10'IOlI_ "".. InQ''' C\Il"\i(lu.... or I", l.non 􀀱􀁾􀀧􀀠"OCIhJ4. Hl, &.I1"on IWCI/:! POSt bait. (..:500'11 V>all oe I).f 􀁾􀁴􀁉􀀼􀀺􀀺􀁬􀁴􀀺􀁍􀀠􀁉􀁾􀀧􀀢􀀠to 􀁡􀁾􀁦􀁦􀁲􀁾􀀠U" t\tll tl'!.lckrwn. af t,... !'IU'I end 1'1(> ....v••.Mn J'4' IM)'QI"Id If, &I.i,to"> N04 tpUG6 baIt.. (1.301, fT' %..,. l 􀀧􀀯􀁾􀀮􀀠IIIUt\ 0 %. 􀁃􀁉􀁏􀁵􀁉􀁬􀁉􀁾􀀠.--tC<# M. rlf.lngt. (bCI1'.. /\Uta. end ...r-.l V>all 􀁾􀀠tn 􀀬􀀬􀀢􀁯􀁲􀁾􀀠wit'" It..... IIatl;I"" MBGF-03A '----------------------_............._... _----------------------- HIITB Coapo; ._ 15150 SUrveyor Blvd. Telephone (912) 361" 0064 The HN'fB Companies Addison, TX 75001 Facsfmlle (972) 361 • 0065 Engineer! Architects Planners www.hntb.eorn Archer Western Contractors, Ltd. 2121 Avenue"r HNTBSuite 103 Arlington, TX 76006 Request for Information Response June 27, 2005 Originator: Andrew Scheermann RFI N11IIlber. R-AW098 Subject: Ground Rod at T-4 Mounted Ught Poles Request: Please Reference sheet BR-68, attached Ground rod Detail, Ground Rod and Ground Clamp Specifications S & J Proposes to attach the ground rods for the T-4 Mounted Light Poles as shown in attached detail. Is this acceptable? Please respond to this RFI as early as possible as not to delay the project Response/Action Taken: In response to S& J submittal ofdetails and material for the above subject. it was found that the submitted information would be acceptable as long as the electrical contractor uses the compression connector that he has submitted, make sure the insulation is remove from the #6 ground wire at at point ofconnection and that the connector is properly torque to the --]3,/'-By: an Baulen, EIT ----Date: June 27, 2005 HNTB Corporation Cc: File Steve Chutchian, Town of Addison Jerry D. Holder, HNTB Corporation HNTII eoc ..... '11. 15150 Surveyor Blvd. Telephone ('!11'2) 361 -0064 The HNTB Companies Addison. TX 75Q0! F.064 Engineers Architects PllJnnMs Addison TX. 15001 Facsimile (912) 36'HlO6S www.hntb..com HHTB.lcb# 25768 -Arapaho Road -Pb... ill VIA Hand DeliVllred Dat", June 24, 2005 To: Steve CbutdrumLetterot Town ofAddison MNTBTransmitta1 P.O. Jlox 9010 16801 Westgrow Drive Addison, TJ( 75001 ReQenlI"" Midway Trallic Control w..... """"""'1\9 to you: Estimates _X_ Plans Prints Reports Shop Orawlnqs Samples Change Order Disk Copy of letter Book Other #: of Copies Drawing # l.st Oated Code Description 1 6/7.4/05 Addendum to the Traffic Control on MidwayRd. -Prop<» 􀁾􀁫.....l-l1Q ... 􀁾􀀢􀀮􀀫􀀭􀀼􀀮􀀮􀀠NOTE: 1. ALL TRAFFIC CONTROL ELEMENTS INCLUDING THE RETURN OF MIDWAY ROAD MEDIAN TO IT'S ORIGINAL CONDITION IS THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE INCLUDED IN THE UNIT BID PRICE FOR TRAFFIC CONTROL. TRAFFIC CONT'ROL PLAN Ir l 􀁾􀀠__ SINGlE LANE: CLOSURE: ICRASS: _,J=:::::-165' rAPER '20' 120' , H1f1'II Cae,," 11M 15150 Surveyor alvei. Tolephone (97Zl 361· 0064 The HNiS Companies AddIson. TX 7500J Focsfmjfe (912) 361 -0065 Engineers Archlteas Planners www.hntb.com Mr. Ben Withered Project Manager Archer Western Contractors, Ltd. 2121 Avenue"r Suite 103 HNTB Arlington. TX 76006 January 10. 2005 Dear Ben: We are in receipt of your letter date May 2. 2004. in which you are requesting changes to be made to the Change Order #2. After review of your submitted PCO-26. dated December 13,2004 on the unit prices of items 1210. 1211. 1212 & 1213; it was observed that the spreadsheet was missing the compensation for bonds and insurance. The requested in increase of the unit prices respectively will be address in the next Change Order. In reference to your letter for the extension of time. HNTB concurs that the dates indicated due match the CPM and the revised issued date for the conduit promes. Upon review ofyour request based on your CPM, HNTB can not recognize the statement that the critical path was affected by the re-issue of the conduit profiles caused by the change in criteria required by TXU and DWU. The CPM show that the conduit services would start on Aug. lB. 2004 and ftnish by Sept. 9. 2004 with a float of 12 days. The next item on the critical path is the storm water box culvert showing a start date of Sept 10th• Base on our records, Archer Western began the installation of the box culvert on September lOth, which is shown to be the early start for this critical path item. In review. there is no delay to the critical path. The Town ofAddison has indicated that ifArcher Western Contractors, Ltd. does not agree, that this issue wou1d be subject to discussion at a later date. but at this time. no addendum will be considered for Change Order #2 and will be process as is. Please advise us ofany actions you will take. 􀁔􀁨􀁡􀁮􀁫􀀢􀀧􀁩􀁾􀁾 􀁾􀀻􀁴􀁡􀁵􀁬􀁥􀁮􀀠HNTB Corporation Cc: Steve Chutchlan, Town ofAddison Jerry D. Holder. HNTB Corporation Michael Ebeling, HNTB Corporation FUe Archer Western I Contractors JUN 03 2005 HNTB CORPORATION DALLAS, TEXAS June 2,2005 Letter: HNTB -46 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr, Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No, 04-22 Change Orders 2 & 3 Dear Guy: Attached are the signed change orders #2 & #3, from the Town of Addison Arapaho Road Project. The unit prices for items 1210,1211,1212, & 1213 are in error, The items should have the following unit prices: $96,33, $77,56, $71,74, and $2579.43 respectively, The revised unit prices include compensation for bonds and insurance that was not included in the current prices, Item #1205 "Concrete Stabilized Sand for TXU Conduit" did not include a time extension of 23 days as reflected in our letter dated 919104, Please make these adjustments to change order #2, If you require additional information, please contact Andrew at our field office, Sincerely, 􀁾􀀬􀁾􀀠Ben w2'􀁾􀀭􀀭􀀭􀁯􀀮􀁢􀀮􀁟􀀠 Project Manager XC: Andrew Schneemann Don Good File L \ \ ."""."""YI..tott-P 􀁊􀀧􀁬􀁊􀁾􀁬􀀢􀀠 t 􀀺􀀺􀀮􀀬􀀮􀁾􀀠2121 Avenue J, Suite 103 A Member of The Walsh Group Arlington, Texas 76006 An Equal Opportunity Employer Phone: 817,640,3898 Fax: 817,640,8734 www.walshgroup.com TOWN OF ADDISON, TEXAS ARAPAHO ROAD -PHASE 111 Project No. 04-22 CHANGE ORDER NUMBER: 02 1. CONTRACTOR: Archer Westem Contractors, LIII. 2. Change Order Worl< limits: Sta. 􀁟􀀮􀀮􀀺􀀭􀀱􀀡􀀮􀀺􀀫􀁾􀁚􀁓� �􀀺􀀮􀀮􀀮􀀮􀁟􀀠to Sm. 114+15 3. Describe the work bei revised: _eral item of worl< were ""1'-by the Town of Addison for public noVeilication and modification for future <1 􀁾􀀠 --------􀁾p,et 􀁾\'\IC4Ie 8' Gaff: ...."m, M C",II'h>" !MM. 􀁔􀁏􀁔􀁁􀁾􀀮􀀠. a.5O 􀁾􀀮􀁾􀁾􀀠.􀁅􀁾􀀠. ..:=..-= 􀁾􀁳ANY OISCOUNTSONMmRIAL INVOICES SUBTOTAL MATERIAl. COST 25,50 COMPENSATION {SUSTOTAl MTl. COST AT 15%) '.S3 TOTAl MATERIAl COST 2U3 , ,, P"" , Town of Addison 204059 􀁾.. SUBCONTRACT.. UNIT EST. en'. TIVt.ki Concrete 10 􀁾􀀮􀀠CD f-1 UN!TPRlCE , $45.00 S• TOTAL "00 , 4-May-05 SUSTOTAL SUBCONTRACTOR COST COMPENSATION (SUBTOTAL SUB COST AT 15%) TOTAl SUBCONTRACTOR COST s s s 45.00 6,;'5 5U'S TOTA,LCOSTOF ADOEOITEM UNIT PRICE (TOTAL COST DIVIDED BY EST, Oll'.) s Pago5 lKlrn@rno MAY 05 ZOOS May 4, 2005 HNTB CORPORATION Letter: HNTB -39 DALLAS. TEXAS HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control Plan for Erection of Span 9 Beams and Arches Dear Guy: Archer Western will utilize the traffic control plan on sheets 30A and 30B for the erection of the Span 9 beams and arches. If you require additional information, please contact Andrew at our field office. /. /Ben Withered fiJ Project Manager Eflsfe?"w J9-' XC: Andrew Schneemann Don Good File 15150 Surveyor Blvd. Telephone (972) 361-0064.....coc..... Ua Facsimile (97Z) 361 • 0065The HNT6 Companles Addison. TX 15001 www.hntb.comEngineers Architects Planners Archer Western Contractors, Ltd. 2121 Avenue"r HNTBSuite 103 Arlington. TX 76006 Request for Information Response May 10,2005 Originator: Andrew Scheennann RFINumber. R-AW082 Subject; Retaining Wall RW4 Wall Mounted Luminaries Request; Plan Sheet 157 shows 4 Wall Mounted Luminaries along Retaining Wall RW4. The note on this sheet states that "Cable and conduit shall run in Retaining wall" to provide power to these lights. Since retaining wall RW4 is built with pre-cast panels, the cable and conduit cannot be placed "in" the Wall. Please provide details for the location ofthis cable and conduit from the pedestrian light pole to these wall mounted luminaries. In addition. the plans do not indicated an elevation for the placement of these lights on the side of RW4. Please provide an elevation or height above sidewalk/finish grade to centerline oflight fIxture. See attached drawing. Please expedite the answer and details needed to constmct the wall mounted lominaries, as we currently constmction this wall. Response/Action Taken: Place conduit and junction boxes in T-4ooncrete railing similar to the bridge light pole conduit circuits. J-boxes to be placed at the same station point and located 12" below top of concrete rail Request wall light type YAMO series by Lumec-Schreder be substituted by Kim Lighting "Wall Director Series" Model # 70HPS240 in platinum silver finish. Substitute 4 each fixtures at retaining wall RW4 and substitute 2 each YAM4 at retaining wall RW3. Install oonduit and J -boxes at same points and 12" below bottom ofthe coping, through the wall panels from behind the retaining wall at RW3. Please provide the credit differences betweenitOO5ts ofthe wall mounted light fixtures for Item 311. By: Guy Van Bau1en. EI 􀁩􀁢􀁾􀀺May 10,2005 HNTB Corporation Cc: File Steve Cbutchian, Town ofAddison Jerry D. Holder, HNTB Corporation Mike Preston, HNTB Corporation HIf1'B Cot..... n 15150 Surveyor Blvd. Telephone (972) 361 -0064 The HNTe ComplJnies AddIson. TX 75001 facsimIle (972) 361-0065 Engineers ArchItects Planners www.hntb.com Archer Western Contractors, Ltd. 2121 Avenue T HNTBSuite 103 Arlington, TX 16006 Request for Information Response May6,2005 Originator: Andrew Scheermann RPI Number: R-AW080 Subject: Bridge Control Joint Archer Western is proposing to utilize the ZIP CAP control joint former to create the control joints over bents that do not have expansion joints. Please review the attached product data and installed sketch Please approve atyou earliest convenience. Response/Action Tiken: As indicated on the contract plans, control jOints or construction joint are to be over the inv. tee bent cap as seen on sheet BR-41 to BR-52. In reference to the provided Sketch, this is in conflict with the detail provide on contract sheet BS-7, page 315, which show a 1-1/2" zip strip. Please 􀁰􀁲􀁯􀁾􀁡􀁣􀁫􀁵􀀺􀀱ui]:. 2" strip and any certiftcation that this product meets TXDOT requirements. By: &auIen,EIT 􀁾􀁾􀀠Date: May 6, 2005 HNTB Corporation Cc: File Steve Chutchian, Town ofAddison Jerry D. Holder, HNTB Corporation Rene Tullier, HNTB Corporation · IIIITII Corpomloll 15150 Surveyor Blvd. Telephone (97'2) 361 􀁾􀀠0064 The HNTB Companies Addl,on. 1)(75001 FacsImile (972) 361-0065 EnC}lneers Archlteds Planners www.hntb.com Archer Wesrern Contractors, Ltd. 2121 Avenue"r HNTBSuire 103 Arlington, TX 76006 Request for Information Response May 3. 2005 Originator: Andrew Scheermann RFINumber: R-AW059 Subject: Drainage of Mapsco Parking lot Request: Please review the final grading contours from station 54+50 to 55+50 Archer Western has discovered that the drainage contours between the Mapsco Parking lot and Inlet B-8leave less than I' of cover over Storm Sewer lines A & B and in some areas less than 4" of cover. Please review the proposed drainage contours and direct Archer Wesrern whether or not to proceed with the proposed grading. Response/Action Taken: Please see attached Sheet with revised grading and change in throat elevation of the Y-inlet for lateral B-8. Ifneeded an electronic copy ofthe sheets can be e-mail to Archer Western upon request BrMS:LHNTB LHNTB Corporation Date: May 3. 2005 Cc: File Steve Chutchian. Town of Addison Jerry D. Holder. HNTB Corporation Karura Curry. Grantham Assoc. 􀀢􀁣􀀾􀀭􀁾􀁟􀁟􀁟􀀠-0.1 6 10>-----610 􀁾􀀧􀀠􀁾􀀠􀁾􀀠􀁾􀀠-. '.... ,..". -;;;; ._-􀁾􀀢􀀠=.IHI n RFURflikE eolHT 1625 􀁾􀀠620 􀁾􀀠"". "-""-. , ' , , 615 , 610 c 'l:'M"Ilii""\ 605 􀁾􀀠,, 􀁩􀁾􀀠\ 600 􀁾FIJ L/·_-t--_· 595 􀁾􀀠590 􀁾􀀠::> 585 580 ; 575 : . 􀁾􀀮􀀠". 570 15..:on 16-1-00 DllLlS lRU. RAPID TIWISIT PROPDtY ACQ,UJSn'lON 􀁃􀁏􀁒􀁐􀁏􀁾􀀧􀁮􀁯􀁈􀀠611 612" 􀀢􀀱􀀭􀁾_ 􀀶􀀧􀁾􀀠􀁾􀀨-----" ( 􀀭􀁾􀀠! 'i PROP. -7 I . , .... v. f",.o.• i 1! 􀁾􀀠7+00 18+00 , ,•..:on Q 􀁾􀀠I:'" 􀁾􀀠625 620 1615 1610 605 600 1595 1590 􀁐􀁕􀀺􀁾􀀠]IJ STOIIIIi 61!WE11 '8' ITA. 11<00 TO STA. 200100 TOWN OF .. , --_..... DlOI_'.''C SHT. 15SW 1 , . I ' I '"*"􀁓􀁔􀁾􀁡􀁊􀁉􀁩􀁉􀁉􀁟􀀡􀀮􀁊􀁬􀀠INtO BUifItHC£ Mbff 610 ...,. " ..".....605 600, 1595 590 􀁾􀀵􀁾􀀸􀀵􀀪􀀭____􀁾􀁾__􀁾􀀭􀀫______􀁾______􀁾______􀁾􀁾__􀁾...􀁾􀁾􀁾􀁾__􀁾􀁾...􀁾􀁾__􀁾__-+__􀁾� �. In , i STOIUiIIlmlI';:;:'; YO ST.......A.. _--0-;580 􀀵􀁾􀀠􀁬􀁾􀀠l 􀁾􀀠s 􀁬􀁵􀁟􀁾􀁏􀁆􀀠􀁾􀀵􀁾􀀷􀀰􀁾____􀁾􀁾____􀁾____􀁾􀁾􀁾___􀀭􀁾􀁟􀁾􀁟􀀢􀁟􀁾􀀢__􀁾􀀭􀀽􀀢􀁾􀁾􀁾􀁾__􀁾􀀧􀁾__􀁗􀁦􀁴􀁾____􀀭􀀽􀁾􀁩􀁩􀁾 􀀭􀀭􀀭􀀭􀁾􀀺􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀮􀀢..􀀽􀀭􀀢􀀭􀀭􀁙􀁾􀀠􀁾􀁾􀀠15+00 16+00 17+00 18+00 􀀮􀀬􀁾􀁶􀁶􀀠􀁾􀀠 HNTB Corporation 15150 Surveyor eNd. Teiephone (972) 361 -0064 The HNTB Companies Addison, TX 75001 Fa:simile: (912) 361 0065 Engineers Archijects Planners www.hntlJ.COffi Mr. Ben Withered Project Manager HNTB Archer Western Contractors, Ltd. 2121 Avenue "J" Suite 103 Arlington, TX 76006 Re: The First and Second Prime Coats ofRailings April 29, 2005 OearBen: Since it's the Towns' position that the railings should be painted to the specifications outlined in the original bid, requiring the railings to be painted with a Primer coat paint that is to be applied in a minimum of two coats to achieve dry film thickness of3.5 to 10mii. Town has requested that Archer Western provide two part primer coat system to be applied to the railings. A first primer coat, utilizing a Sherman Williams Zinc Clad II HSB69Series a rate of 3.Omil OFT and a second primer coat using a Epolon II Epoxy Primer, tinted slightly lighter then "Frank Blue" at a rate of3.0 mil OFT. This primer coat sys tern will work with the request of the Town to provide a Sherman Williams paint appearance coat. It is the Towns' position that the total rate ofapplied primer coats falls within the specifications outlined in the original bid and will only recognized any difference in the cost of the primer paint. Thank you, Guy Van Baulen HNTB Corporation Co: File Steve Chutchian, Town ofAdd ison Jerry O. Holder, HNTB Corporation Michael Ebeling, HNTB Corporation 1+7, 4stb o8aJ 􀁧􀁾􀁊􀁤􀀠yc) JriJ.t; .!)'ic.'!' HNTB Corporation 15150 SUNeyorBlvd. Telephone (972) 361 -0064 ,t The HNTB Companies Addison, TX 75001 Facsimile (972) 361 -0065 􀁾\ 'f-Engineers Architects Planners ---􀁾􀀠􀁜􀀧􀀩􀀶􀀱􀁾􀀧􀁩􀁬􀁾􀀠Mr. Ben Withered Project Manager '-􀁑􀁾􀁜􀁊􀁦􀁊􀀠HNTB Archer Western Contractors, Ltd. 2121 Avenue "J" Suite 103 u.f Arlington, TX 76006 Re: "Frank Blue" Appearance Coat April 29, 2005 Dear Ben: Please be advised that in reference to the cost proposal for the painting ofthe T-4 Railing and Pedestrian Railing, I have been advised by the Town that it is unacceptable in its present form. It is the Towns' position that the railings should be painted to the specifications outlined in the original bid, which required the railings to be painted with an appearance coat that has a minimum of2.0 mil dry film thickness. In addition, the Town has requested that Archer Western provide a revised proposal utilizing a Sherman Williams Poly-Lon 1900 Polyester Polyurethane paint which is able to be tinted "Frank Blue". The new proposal is to include only the difference in the cost of the paint. They have advised me that they will not pay for any additional costs associated with the labor for this project, since they believe that it should have already been included in the original bid. 􀁖􀁾􀀠􀁯􀁬􀁩􀁾􀁾􀁾􀀠Thank you, \"AS G WaJ)Q Guy Van Baulen 􀁾􀁾􀀠􀀰􀂰􀂰􀀭􀁾􀁊HNTB Corporation 􀁾􀂮􀁬􀀨􀁾􀁾􀁊Cc: File Steve Chutchian, Town ofAddison Jerry D. Holder, HNTB Corporation Michael Ebeling, HNTB Corporation .....COOpoa.Hca 15150 Surveyor Blvd. Telephone (972) 361 -0064 The HNTB CompanIes AddisOn. TX 75001 r.",lmlle (!rIZ) 361 -0065 EllQfneers Arch!tects Planners www.hntb.com Archer Western Contractors, Ltd. 2121 Avenue «r HNTBSuite 103 Arlington, TX 76006 Request for Information Response May 17.2005 Originator. Andrew Scheermann RFI Number: R-AW085 Subject: Bridge Approach Slab -Standards Request: Archer Western can not fwd a detail sheet, in the contract plans for the Bridge Approach Slab. Please provide the bridge approach slab detail as soon as possible. Response/Acrion Taken: Attached is the TxDOT BAS-94 standards sheet for the bridge approach slab, which applied at the lilne these plans were put together. Jf.l6L--./􀁇􀁕􀁙􀁾􀁂􀁡􀁵􀁬􀁥􀁮􀀧􀁅􀁉􀁔􀀠 HNTB Corporation Cc: File Steve Chutchlan, Town ofAddison Jerry D. Holder. HNTB Corporation Cliff R. Hall, URS Corporation By: Date: May 17. 2005 1;",'..... CQII'/RQI.lEll I.CHCIMllIAI. .!Oliff IlUAIL lH£ TOP JOlHT lMr lit! SAIlrD PRCNU8I' .. t.UIKT IIElmfT $A, IS: USC) -lntlft •taRS fI Pl..AoC8I1)I1. " twn' $A.INt CPIb'r CIt sHALL • usa>.. 'ftC $NIl tNt w.u15 I.DS 'fK\M .,.. wlSIE. lMr CHMf1:H $HlU BE PUCO 10 82. 􀁾􀁟􀁭􀀮􀀧􀁴􀀠 NlOM't II£"tMXM nI£ l.CNIlnlUtw. BOn'<»-Sl'I'I1.. A R£FI.IiIINCE Lire SHAU. BE lSTAllLl$IC£O TO 1-"£ tHAT TfC lH$D1' CIA SA. cut IS DIRtC1l.Y AfIQIWI M C'fIMIFS,R,. M'NCA AOMNiln 1M THIii: A AID a 'IIIa$ 􀀤􀁐􀁁􀁃􀁃􀁾􀀠MAT .. REOJIRf.O TO INSN 'THAT 'Ott JOl", wtLL 1£ AI'fIftOX.!w.fQ.Y 2-f'RCII 1Mt: w.c LlHE AND NOT ADO¥E A AEbIF'CRel1l) lISt. TYPE II REINFORCING LAYOUT FOR GUTTER S(CTION AT (1)-(1) TYPES X • II GUTTER < ....,"' ...or .. _ ......." I/M T'l91c:.u. 􀁾􀁬􀀻􀀱􀀧􀁊􀀨􀁉􀁉􀀠 􀁾􀁾􀀮􀁾􀁾􀁶􀀭􀀺􀀭􀀮􀀮􀁾􀀠􀀾􀁾••" ........... if.. ". 􀁾􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀠"'"< SL.a I.. \..._""_ stClIIIII AT @-@' fife" I!QlEI I. llOARS AT CQe'ftIIUCTlOlt JOI:HTS . SKALL IIEE1' TIlE AEUJUDOfTlIS ltD 310., "CIH::RtTI Pl'4lllUf... t.lr I trE rs rs USC) fit _ 􀁾􀀠 " ae wnw tElGK'I' All) biStOE FAC£ _lOIlNG 'H 􀁾QJIIl& lKiW. lIE USED OM lJi£ 􀁾sua. ll£ CtJ!S SH».O tAPSl't YO '" t10 ltfQf H!IGIIT 􀁾It TIJIIlMAno AT THE. Ell)OF nc sua (II .T 'M. ClRAltW)£c:unu.,. IF" lIRA.,... GII'I'T£R 1s USED. So OITAILS .QG OUIlMTlTlU FC'l CJ.N ME: TO IE AS 'SHCIIt4 ILstHJII' 1M 1Ml i'UIC!. .... T1Pt 1: 1iIJ'tTtR S1(U.Q 8£ USED 1M LttU Of' TIP£. :a; GU'fTOIt ..,. • .Itt KllMIT'S. So WID n_ C(ICS1'IIIlICTIOM 1$ usa to 1!U1LD A PClfITlotl OF " IIR'OOI. M LONGItWJ:Kq. CQtIJl1lUCTIQM JOINTS OF 'THE JPf'ROlCM SUIt SIWJ. A.IClt .Int Tlt[L'>l'Ii ZlIWJ;...., .E 􀁾..ii!l N 1011,"00 gj .... 􀀬􀁾􀁪􀀩􀀻􀀠-Ii 11.11>4 􀁾􀁾􀀺􀁲􀁾􀀻􀀮􀀺􀀠􀁾􀀻􀀺􀁾􀁡􀀺􀀺􀀠fB!] 􀁾􀀠􀀻􀁾􀀻􀀺􀀺􀀻􀀻􀀠􀁾􀀬􀀬􀀺􀁴􀁭􀀱􀁾􀁾􀀠! I1W.'H 􀁾􀁾􀁾􀀽􀀺􀀠, 􀁭􀁅􀀢􀀧􀀱􀁾􀀬􀀱􀁉􀁉􀁩􀀠am ,. 'Qotff,Jf , 1t»IJ.)l;ij1 􀁾􀀺􀀽􀀻􀀠tU::= 􀁾􀁈􀁕􀁉􀁩􀀩􀀧􀀢􀀠§i1 :=ft em 􀀺􀁾􀀽􀀺􀀠§i 􀁾􀀽􀀡􀀻􀀠t" liE! 71 '01","􀁾􀁾􀀺􀀽􀀧􀀺􀀠[EJ:' 􀀺􀁾􀀺􀁾􀀠8::=: ffi] 􀁾􀀠􀀺􀁾􀀻􀁾􀁾􀀠:m1 􀀺􀁾􀁾􀁾􀀠i!. 1141L4 􀁾􀀢􀀧􀁾􀁴􀀷􀀧􀀱􀀠i!§} M \O;&kZJE. 􀀱􀁾􀀱􀀲􀀡􀀠I; ,112Uol 1m: 􀁾􀀠::.: mB:;= [i11 􀁾􀀠􀀺􀁾􀀺􀁾􀀠􀁾􀁾􀁾� �􀀺􀀺􀀠Ii'8I N 􀀧􀁾􀁕􀀧􀀠i:D M 􀀱􀁴􀁾􀀮􀀷􀀵􀁾􀁾􀀺􀁾􀀺􀀠--' 􀁾􀀠,fllI:tM IF!I 􀁾􀀠􀁾􀁾􀀺􀀠Iiil 􀁾􀀠􀀺􀁾􀁾􀁾􀀠􀁾􀁾􀀠􀁾􀀺􀁾􀀡􀀺􀀠I! 11M.U i DRS May 11,2005 Mr. Steven Z. Chutchian, P.E. Assistant City Engineer 16801 Westgrove Drive Addison, TX 7500 I Re: Arapaho Road Bridge at Midway Road Arch Span Erection Seqnence Dear Mr. Chutchian: We have recently received the "Arch and Beam Erection Plan Span # 9" and have perfonned a cursory review. It should be noted that the erection plan only covers the erection ofthe falsework, beams and arch and neglects the stressing of the hanger strands and the impact that the Contractor's means and methods will have on the final structure. In addition, this erection plan proposes a different method for the construction sequence ofthe arch span from what was assumed during design. Without a complete erection analysis of the structure, the impact ofthis change cannot be assessed. Please be advised that the Contractor is to provide a detailed erection sequence plan for the arch span and hanger stressing as a requirement ofthe construction plans and specifications. As stated above, we do not believe what was submitted by the Contractor is adequate for this deliverable. It is critical to the successful construction of the arch that the Contractor prepare this detailed erection sequence for approval before erection of the arch commences. To assist the Town ofAddison, we have provided below the requirements as stated in the construction plans and specifications. Per drawing BR-37, "Main Span Erection Sequence", Erection Note I: The infonnation shown on the erection sequence drawings conveys the assumptions made by the Designer in designing the structure. All infonnation shown is for the Contractor's infonnation only, and the Contractor is responsible for selecting the means and methods used to construct the structure. The Contractor shall submit for review and approval to the Engineer, calculations ofthe influence of his erection sequence, loads and details on the structure, in accordance with the project specifications. These documents shall be signed and sealed by a professional engineer ofthe State of Texas. Project specification Section SSH, "Steel Structural Hangers", Item SSH.2 (3) (b) states in part: Drawings and narrative shall be submitted which describe the erection sequence, the maximum allowable stress on each hanger, and the means by which the Contractor will assure that the maximum allowable stress is not exceeded. URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Tel: 972.406.6950 Fax: 972.406.6951 URS Project Specification Section BC, "Bridge Construction" references TxDOT Standard Specification, ) 993. TxDOT Specification Item 441, "Steel Structures", 441.3(2) "Erection Drawings" also outlines requirements ofthe Contractor for erection drawings. Sincerely, CliffR. Hall, P.E. Vice President Project Manager URS June 2, 2005 Mr. Steven Z. Chutchian, P.E. Assistant City Engineer 16801 Westgrove Drive Addison, TX 75001 Re: Arapaho Road Bridge at Midway Road Revised Detail for U-Beam Splice, Span 9 Dear Mr. Chutchian: As requested we are writing this letter to provide an explanation of the events that created a redesign ofthe detail used to splice the U-Beams in Span 9 ofthe Arapaho Road Bridge. We have attached copies ofthe email correspondence received and sent by URS from the period ofNov 24, 2004 through Dec 21,2004 when revised drawings were issued. It is and always has been our contention that the original detail is constructable and that the redesign was at the request ofthe contractor to acconunodate his desire for a detail that he could construct easier. r:::I/::::;During design, we understood that the contractor would h r 􀁾􀀠I,...-{../forcement between beam-ends aligned correctly. To accomplish this, we had _....􀁾􀀮􀁾••􀁾􀁵􀀬􀁾􀀮􀀠􀁵􀀮􀁾􀀠u-U •. .' cc; "Jerry Holde(' , "Guy Van-Saulen" 11/241200401 ;58 PM• Subject; FW; RFI 38 Cliff, this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not So, we need you to verify that these adjustments at the ends of the beams are allowed. This is a pressing issue, so if you can answer this quickly, it would be helpful. Call me if you have any questions about it. Daniel -----Original Message---From: Schneemann, Andrew [mailto:aschneemann@walshgroup.com] sent: Tuesday, November 23, 20044:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use ofthe individual or entity to whom they are addressed. Ifyou are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying ofthis e-mail is strictly prohibited. 􀁾􀀠Arapaho Road P3. RA 3B.pdf IREQUEST FOR INFORMATION PROJECT No. Arapaho Phase III RFI # ____􀁾􀀳􀁾􀀸􀁾___ Date: November 23, 2004 Archer Western Contractors, Ltd. HNTB 5910 W. Plano Parkway. Ste 200 Plano, Texas 75093 Gu Van Saulen Andrew Schneemann U-Beam modifications to allow for Rebar Couplers Civil Please reference the aUached Unil4 U-Beam Shop Drewlngs. Archer Westem and Texas Concrete, the U·Seam Precaster, need to modify the reinforcement In the splice end of beams 1b,2b,3b,& 4b for unil4. The reinforcement needs to be modified to allow room for the rebar spliea couplers. The following bars where modified: Bars V, Wand OS were at 1 􀀳􀀱􀀴􀁾􀀠and were sel back to 6". Bars Y were et 3 1/2" and were set back to 11 1/r. Bars R were at 􀀳􀁾􀀠and were set back to 11", These adjustments were needed in order to avoid conflict with the couplers required at the coupler connection as required by the conlract plans. We are ulilizing are Dayton Superior Bar locks rebar couplers. Please approve the attached changes at your earliest convenience. Page 1 "Daniel Filer" To: ce: Subject: RE: FW; RFJ 38 11/2912004 11 :05 AM worst case scenario i will bring or have couriered a copy ofthe shop dwg's --Original Message---From: ClifCHall@URSCorp.com [mailto:CliftHall@URSCorp.com] Sent: Mon 1112912004 10:34 AM To: Daniel Filer Cc: Guy Van-Baulen; Jerry Holder Subject: Re: FW: RFI38 Can you send (scan, fax, etc.) me a copy of the sbop drawing? Is the only change the distance from the end ofbeam to these bars? CliffR. 􀁈􀁡􀁬􀁾􀀠PE Engineering Unit Manager URS Corporation Graystone Centre' 30I0 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filerll To: cc: "Jerry Holder" , "Guy Van-Baulen" 11/241200401:58 PM Subject: FW: RFI 38 Cliff, this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not. So, we need you to verilY that these adjustments at the ends ofthe beams are allowed. This is a pressing issue, so ifyou can answer this quickly, it would be helpful. Call me ifyou have any questions about it. Daniel -----Original Message----From: Schneemann, Andrew [mailto:aschneemann@walshgroup.com] Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFl 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, Or copying of this e-mail is strictly prohibited. (See attached file: Arapaho Road P3 -RFI 38.pdf) Cliff Hall To: "Daniel File(' cc: "Guy Van-Baulen" , "Jerry Holde(' DRS 11/29/200405:48 PM Subject: Re: FW: RFI 􀀳􀀸􀁾􀀠If we understand this RFI correctly, the contractor is proposing to move the end block reinforcement away from the end of the beam and provide block-outs for couplers. We cannot accept this change. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" "Daniel Filer" To: cc: "Jerry Holde(' , "Guy Van-Baulen" 11/24/200401 :58 PM Subject: FW: RFI 38 Cliff, this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not. So, we need you to verify that these adjustments at the ends of the beams are allowed. This is a pressing issue, so if you can answer this quickly, it would be helpful. Call me if you have any questions about it. Daniel -----Original Message----From: Schneemann, Andrew [mailto:aschneemann@walshgroup.com] Sent: Tuesday, November 23, 20044:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F -(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use ofthe individual or entity to whom they are addressed. Ifyou are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. 􀁾􀀠Arapaho Road P3 -RFI 38.p "Daniel Filer" To: ce: "Guy Van-Baulen" , "Jerry Holder" , 1112912004 06:33 PM Subject: RE: FW: RFI 38 Cliff, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by fmding a coupler that would fit, but was unable to do so. Ifa coupler cannot be found to fit, you will have to advise on the constructability of the beams to accomodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 ifyou wish to discuss this. Also, if you feel a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel ---Original Message-From: ClifCHall@URSCorp.com [mailto:Cliff_Hall@URSCorp.coml Sent: Mon 11129120045:48 PM To: Daniel Filer Cc: Guy Van-Baulen; Jerry Holder Subject: Re: FW: RFI 38 Ifwe understand this RFI correctly, the contractor is proposing to move the end block reinforcement away from the end ofthe beam and provide block-outs for couplers. We cannot accept this change. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LID Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406,6950 Direct: 972.406.6976 Fax: 972,406.6951 "Daniel Filer" To: ce: "Jerry Holder" , "Guy Van-Baulen" 1112412004 01:58 PM SUbject: FW: RFI38 Cliff, this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not. So, we need you to verify that these adjustments at the ends of the beams are allowed. This is a pressing issue, so if you can answer this quickly, it would be helpful. Call me if you have any questions about it. Daniel -----Original Message----From: Schoeemann, Andrew [mailto:aschneemann@walshgroup.coml Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Schoeemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. Ifyou are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying ofthis e-mail is strictly prohibited. (See attached file: Arapabo Road P3 -RFI 38.pdf) Cliff Hall To: "Daniel Filer" ce: aschneemann@walshgroup,com, "Guy Van-Baulen" 'DRS 111301200410:47 AM 􀀼􀁇􀁖􀁁􀁎􀁂􀁁􀁕􀁬􀁅􀁎􀁾􀁨􀁮􀁬􀁢􀀬􀁣􀁯􀁭􀀾􀀬􀀠"Jerry Holder" Subject; RE: FW: RFI 􀀳􀀸􀁾􀀠Please see the following website: http://www.erico.com/products/LentonPosition.asp#p9 Cliff R. Hall, PE Engineering Unit Manager URS Corporation G raystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" "Daniel Flier" TO: ce: "Guy Van-Baulen" , "Jerry Holder" , 11/291200406:33 PM Subject: RE: FW: RFI 38 Cliff, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by fmding a coupler coupler that would fit, but was unable to do so. Ifa coupler carmot be found to fit, you will have to advise on the constructability ofthe beams to accomodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 ifyou wish to discuss this. Also, if you feel a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel -----Original Message-From: Cliff_ HaIl@URSCorp.com [mailto:Cliff_ Hall@URSCorp.comJ Sent: Mon 1112912004 5:48 PM To: Daniel Filer Cc: Guy Van-Baulen; Jerry Holder Subject: Re: FW: RFI 38 If we understand Ibis RFI correctly, the contractor is proposing to move the end block reinforcement away from the end ofthe beam and provide block-outs for couplers. We cannot accept this change. CliffR. Hall, PE Engineering Unit Manager DRS Corporation Graystone Centre 3010 LBI Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 IIDaniel Filer" To: cc: "Jerry Holder" , "Guy Van-Baulen" 1112412004 0 I ;58 PM Subject: FW; RFI38 Cliff; this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrele sign offon this, but they would not. So, we need you to verilY that these adjustments at the ends ofthe beams are allowed. This is a pressing issue, so ifyou can answer this quickly, it would be helpful. Call me ifyou have any questions about it. Daniel --Original Message--From: Scbneemann, Andrew [mailto:ascbneemann@walshgrouRcoml Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Scbneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 36\-0063 M-(S17) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use ofthe individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended reCipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying ofthis e-mail is strictly prohibited. (See attached me: Arapaho Road P3 -RFI 38.pdf) "Schneemann. Andrew" To: . "Daniel Filer" , "Jerry Holder" group.com> Subject: RE: FW: RFI 38 121011200405:57 PM Cliff Here is the Lenton F9 & F8 coupler Installation guide Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.com] Sent: Tuesday, November 30, 2004 10:47 AM To: Daniel Filer Cc: Schneemann, Andrew; Guy Van-Baulen; Jerry Holder Subject: RE: FW: RFI 38 Please see the following website: http://www.erico.com/products/LentonFosition.asp#p9 Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" To: cc: uGuy Van-Baulen" , "Jerry Holder" 11/29/2004 06:33 , PM Subject: RE: FW: RFI 38 Cliff, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by finding a coupler that would fit, but was unable to do so. If a coupler cannot be found to fit, you will have to advise on the constructability of the beams to accornodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 if you wish to discuss this. Also, if you feel a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff_Hall@URSCorp.comj Sent: Mon 11/29/2004 5:48 PM To: Daniel Filer Cc: Guy Van-Baulen; Jerry Holder Subject: Re: FW: RFI 38 If we understand this RFI correctly, the contractor is proposing to move the end block reinforcement away from the end of the beam and provide block-outs for couplers. We cannot accept this change. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filerll Holder" , "Guy Van-Baulen" 11/24/2004 01:58 To: cc: "Jerry PM Subject: FW: RFI 38 to so they Cliff, this issue has come about because the couplers are too long fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not. So, we need you to verify that these adjustments at the ends of the beams are allowed. This is a pressing issue, if you can answer this quickly, it would be helpful. Call me if you have any questions about it. Daniel -----Original Message----From: Schneemann, Andrew [mailto:aschneemann@walshgroup.com] Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer: Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use/dissemination, forwarding, printing, or copying of this e-mail is strictly prohibited. (See attached file: Arapaho Road P3 -RFI 38.pdf) 􀁾􀀠 lenton p8!.p9 coupIers.tij INeTALLATION INSTRUCTIONS POR LENTON·P8-P8 POSITION COUPLBRS' $al'cty 􀁾􀁉AIlIIi\ty rer,uliItiona RqUinId by IfIo jcJbaIt.lmIIt be obIerved. SpecIa1emmllon 8I>ould be givtlllO the lbIkwIbIi iNUW:tlou: I. 0lIB0rw all FedallMUitOOlll sdIty replltkms 2. Willi'''P'd bat. 3. W.gIoVCllIO _illsplln1m IIIId ems. 4. WNrINll'tty glllSlc$lUlllimes. S, Buwn of,..-lwOJldllg above, below. amllII'OWld. INS'tALLATl9N STEP 1􀁾􀁒􀁣􀁣􀁄􀁃􀁍􀁬􀁢􀁡􀁲􀁃􀀡􀁄􀁬􀁬􀀢􀁃􀁉􀀠􀁣􀀺􀁬􀀱􀁉􀁃􀀧􀀨􀁴􀁅􀁾􀀠􀁾􀀠lrisJ*t'lllnlldecl1lld'IIIIIdbaSIII'e tInIiIIIu W""lIPd·1MUi heofUlllCle\lt, rust. or oCher CODlIIII\lIIIlI. TIle _of.. wlalllro* may110 1IIqWn;d. STliP1·IIIIpt.ct pm II\IIIIIIcr 011 􀁾􀁉􀁥􀁲10 iliaD SUN i.t'slfla conectsla fi:Ir bIII'J bciDg spliced (lee I:I\aIt btIow). r.rtthe coupler01110 IfIo bet lIIId roIaIo 􀁾\IIICIIIWId"lf&!it (1jIp'OX-4 • 4 11.2111111a). 8m:1 • u.iD& a!lmu:lard pipe 'RtIII1eb, _IyIf&\I!eIIdie coup1m' 10IfIo 􀁾1111*' IIrreIided rebar... sm4 -RQIr'lO STEP I mr lilt_nnr....... llIIortscc:ond bar ID'IO die GII1IpIer. GII1IpIer. STEP ". • WhIle lIoIdlag!be"uppot bar", q*$IlIIIdanI pipe 'Im:IIch 􀁾tho Q"lIlIlfOIOf I!IId oftho CU1IpIIll' ill aCOIIIIfeI\. cloetwla 􀁾fO 􀁾􀁤􀁧􀁉􀁉􀁴􀁥􀀼􀁉rlIe .-ably.• 8m6· U&Iag slllllldord pipe 􀁾􀀬􀀱􀁉􀁉􀁉􀁃􀁉􀁉􀁉􀀧􀁬􀁉􀁬􀁹II&iItIID ilia jam _ ap/mItllle bod,t. + 8m7 • Verl1)t tIWIIm.IIDI& poovs h IIClviIiblo<_ below). .. TIl.. LIlNTON 1.aspcc:1io4 WreIIIlh may be used bylID fII'J*bW 10 per!odlGaIly dJcI:k 1IIb1I(-chait}. PDF051D ;)HI rolla Cliff Hall To: "Schneemann, Andrew" cc: "Daniel Filer" . "Guy Van-Baulen" 1JRS1210212004 09:47 AM . . "Jerry Holder" Subject: RE: FW: RFI 􀀳􀀸􀁾􀀠Andrew. From the web site. the P8 is the coupler that would be used when axial movement is restricted (i.e. can't put the bar into the coupler). This coupler extends to engage the second bar. We are still looking at welding and will advise later; however. we stili believe that you can acheive this connection with the P8 coupler. Applications Designed to splice two curved, bent, or straight bars, when neither bar can be rotated • P8 &. P13 -designed to splice bars where the ongoing bar is restricted in its axial movement or can not be rotated and length adjustability of the coupler is required. Cliff R. Hall. PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway. Suite 1300 Daltas. TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Schneemann. Andrew" "Schneemann, Andrew" To: , "Daniel File," , "Jerry Holder" group.com> Subject: RE: FW: RFI 3812101/200405:57 PM Cliff Here is the Lenton P9 & P8 coupler Installation guide Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.com] Sent: Tuesday, November 30, 2004 10:47 AM To: Daniel Filer Cc: Schneemann, Andrew; Guy Van-Baulen; Jerry Holder Subject: RE: FW: RFI 38 Please see the following website: http://www.erico.com/products/LentonPosition.asp#p9 Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" To: cc: "Guy Van-Baulen" , "Jerry Holder" 11/29/2004 06:33 , PM Subject: RE: FW: RFI 38 Cliff, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by finding a coupler that would fit, but was unable to do so. If a coupler cannot be found to fit, you will have to advise on the constructability of the beams to accomodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 if you wish to discuss this. Also, if you feel'a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff_Hall@URSCorp.com] Sent: Mon 11/29/2004 5:48 PM To; Daniel Filer Cc; Guy Van-Baulen; Jerry Holder Subject: Re; FW: RFI 38 If we understand this RFI correctly, the contractor is proposing to move the end block reinforcement away from the end of the beam and provide block-outs for couplers. We cannot accept this change. Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976· Fax: 972.406.6951 UDaniel Filer" Holder" , HGuy Van-Baulen" 11/24/2004 01:58 To: cc: "Jerry 38 PM Subject: FW: RFI Cliff, this issue has come about because the couplers are too long to fit between the beams. I originally tried to have Texas Concrete sign off on this, but they would not. So, we need you to verify that these adjustments at the ends of the beams are allowed. This is a pressing issue, so if you can answer this quickly, it would be helpful. Call me if you have any questions about it. Daniel -----Original Message----.rom: Schneemann, Andrew [mailto:aschneemann@walshgroup.comJ Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RFI 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity to whom they are addressed. If you are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, disseminationJ forwarding, printing, or copying of this a-mail is strictly prohibited. (See attached file: Arapaho Road P3 -RFI 3B.pdf) > --Cliff Hall To; "Schneemann, Andrew" cc; "Daniel 􀁆􀁩􀁬􀁥􀁾􀀧􀀠, "Guy Van-Baulen" DRS12103/200401 ;25 PM , "Jerry 􀁈􀁯􀁬􀁤􀁥􀁾􀀧􀀠 Subject: RE; FW; RFI 􀀳􀀸􀁾􀀠Andrew, We have reviewed the possibility of using a welded splice detail as you requested to replace the mechanical couplers. We have attached sketches of a preliminary detail that could work. We are still finalizing this and would appreciate any comments you may have. Note that the number, size and location of rebar for this detail has changed and all rebar to be spliced will need to be ASTM A706 Grade 60 weldable. Arap1.pdf Arap2.pdf Arap3.pdf Arap4.pdf Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 o x o 2 q: .J'----=--_-. " .. J ,....... """"\"-' IlJv \J I/) (fl --::: .... V\ To: ce: Subject: RE: FW: RFI 38 12107/2004 03:31 PM Cliff Here the bolt up plate I talked to you about Andrew Schneernann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361-0063 M-(817) 822-7207 -----Original Message----From: Cliff Hall@URSCorp.com [mailto:Cliff Hall@URSCorp.comj Sent: Friday, December 03, 2004 1:26 PM To: Schneemann, Andrew Cc: Daniel Filer; Guy Van-Baulen; Jerry Holder Subject: RE: FW: RFI 38 Andrew, We have reviewed the possibility of using a welded splice detail as you requested to replace the mechanical couplers. We have attached sketches of a preliminary detail that could work. We are still finalizing this and would appreciate any comments you may have. Note that the number, size and location of rebar for this detail has changed and all rebar to be spliced will need to be ASTM A706 Grade 60 weldable. (See attached file: Arapl.pdf) (See attached file: attached file: Arap3.pdf) (See attached file: Arap4.pdf) Arap2.pdf) (See Cliff R. Hall, PE Engineering Unit Manager DRS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 􀁾􀀠Span 9 Beam Connection.pdf ::-"., 1.", Len'ton "'eld COI,Ipling 000 III " "i:1 '" "i " : \ "\ \ \ steel Bot't Up Pla.w to " to .. <) (> (> " I \ " .. I \. " " III • ".J"'---------_.-/􀁬􀁉􀁉􀀼􀀩􀁮􀀡􀀡􀁬􀀢􀀡􀀡􀁉􀀡􀀡􀁉􀁯􀁾􀁾􀁾􀁾􀁾􀀼􀀩􀁏􀁏􀀠0 00 I"''' ,:I:I" 1(> I Sptu:'lr Hecwy "'0.1\ Pip ""It "Daniel Filer" To: cc: "Schneemann, Andrew· , "Jeri)' Holder' , "Guy Van-Baulen" 121121200405:33 PM Subject: Reissued Sheets Cliff, as we discussed, we would like for you to' reissue the sheets that will correct the beam-en coupling situation. As I said, we do not wish for you to "cloud" the revisions, but a revision triangle with a number is required, along with the revision being listed in revision box on lower right of sheet. Call or email me if you have any questions. Daniel J. Filer HNTB ARCHITECTS ENGINEERS PLANNERS 5910 W. Plano Pkwy, Suite ZOO Plcna, TX75093 Office: (972)661-5626 Mobile: (214)1168-6412 Fax: (972)661-5614 dfJler@hnfb.cam This e-mail and any files transmitted with it are confidential and are intended solely for the use ofthe individual or entity to whom they are addressed. Ifyou are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or copying ofthis e-mail is strictly prohibited. Cliff Hall To: "Schnee mann, Andrew" , "Daniel 􀁆􀁩􀁬􀁥􀁾􀀧􀀠DRS12121/200404:51 PM cc: Subject: Arapaho Revised U-Beam Details Unit 4 PDF Andrew & Daniel, Attached is the PDF of the revised U-beam splice detail. The original mylar will be sent tonight to Daniel at the HNTB office. The U-beam manufacturer should consider using continuous #11 bars through the ends of U-beam "a" into the end of U-beam "b" and cutting these bars after the concrete is cured. This should help ensure that the bars will align properly to make the welded connection in the field. u-beam details unit 4.pd Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 < 􀁾􀀠􀁾􀀠, t , t), f-,,,,, +j OW -----" 􀁾􀀢􀀭C Jr .-.: . He" 􀁾􀁱􀀠••N_ -+---,􀁾􀁾􀀠r i-... "'a t 􀁾􀁓􀀢􀀧􀁉.r"'-!I z... eIl t f1􀁾􀀠-l!-' ! t.oQ:􀁾􀁤􀀡􀀠I, " 􀁾􀀠I I ;; 0 􀁾􀁩􀀠0 :L 0 􀀭􀁾.􀁾􀀠, u « 􀁾􀀠.... .... -« t-0« Wt-O 0W 00 0 w' 0 􀀽􀁾􀀠0<" w'. 0 UN 􀁾􀀠iii·.. 􀁾􀀠:z 􀁾􀀠􀁾0 0 -I-􀁾U 􀁾....:z:z 􀁾0 " u 􀁾􀀠I-m :z •2 :c '" " S< 􀁕􀁾􀀠! iu:z 􀁾􀀠« !\1, a.. 3 􀁾iI i ::l jco« I 􀁾􀀠:z t-§03 t--􀁾􀀠,􀁾􀀠􀁾􀀠u􀁾U ;wW i 􀁾􀀠 .' cc: •Jeny Holder" , "Quy Van-Saulen" 1112412004 01:58 PM• Subject: FW: RFI 38 Cliff, this issue has come about because the coupler.;; ,are too long to fit between the beams. I origintsm and 􀁔􀁾􀀵Concn:tte. the U.Be.,1n ProG&&tif, I'lQo1td ID modify tlw m1n'oftW!l'r.ent irllhe IIpl!ce enG of bouma 1b.2:b,3b.& 4b for IIr'1'ii 4, Tho relnro1Comai1t I"IIll'ed$ 10 be modltl&d to eUow roam far tharebar splioe covJ»Grs. The rol!O'!Wlg bat$ whore modliled: BsraV. W and OS 'iftro at 1 3/i. aM 􀁷􀁥􀁾5of: b"'l:k 106". 􀁂􀁡􀁮􀁯􀁖􀁷􀁡􀁴􀀸􀀮􀁴􀀹􀀱􀁦􀀲􀁾;mdw.... J6t bade 10 11112-, Bal1lR 􀁜􀀱􀀱􀀱􀁩􀀬􀀮􀀮􀁴􀀳􀀢􀁾􀁮􀁤􀀠w,,..,et 􀁢􀁬􀁬􀁃􀁫􀁴􀀨􀁬􀀱􀀱􀁾􀀬􀀠 ThsA 􀁡􀁤􀁪􀁬􀁂􀁬􀁾􀁭􀁳w.m l1eedad in order_avoid conflict with 􀁉􀁊􀁕􀁾􀀠Mi.lpier'$ rvqulted &t tl!f!! IXIUPkM' eonna:Uon •• r'&Ql1inIdo by the con.tr';td ploM. Wear. uhlizing SI'1II! Dayum Suporior Bar locks lebar «IUpfet'$, '" , 􀀮􀁾􀀠"-,,.., ;r.,.....,l,. ..,,-*􀀬􀀬􀀧􀁟􀀻􀀺􀀬􀀻􀀻􀀬􀀺􀀱􀀻� �􀀺􀁾􀁾􀁉􀁗􀀮􀁴􀁌􀀮􀂱􀀬􀀠 9729882D42 H95 P005un-02-05 02:58pm Fr.m-URS Corporalio. "Daniel Filer' To: ec: Subject: RE: FW: RFI 38 11/2912004 11 :05 AM wotst case scenario i will bring or have couriered a copy ofthe shop dwg's --Origmal Message-From: CliffJ/aIl@tJRSCorp.com [mailto:Cliff31"II@URSCorp.comJ Sent: MOll 1112912004 10:34 AM To: Dmiel Filer Ce: Guy VIIII-Baulen; Jerry Holder Subject: Re: FW: RFI38 Can you send (scan, fax. etc.) me a copy oftbe 'hop drawing? Is the only cb8Jlge Ibe dislllJlce from tbe end of beam to these bars? CliffR. Hall. PE Engmeering Unit Manager URS Corporation Graystone Centre' 30U)LBJFreeway. Suit. 1300 Dallas. IX 75234 Office nt: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.695 I "Daniel Filer" To: ...: "leTT)' Holder" . "Guy VIln-BauJen" 111'2412004 01 :58 PM Subject: FW: RFl38 Cliff, Ibis issue bas come about because lb. couplers are too long 10 fit between lb. beams. I I originally tried 10 bav. Texas Concrere sign offon this. buttbey would not. So, we need you 10 verilY that Ibese adjustmems 111 lbe ends oftbe beams are allowed. This is a pressing issue, so ifyell can answer this quickly, it would be helpful. Call me if you bave !Illy questiollS about it. T-m POD. F-OI2J'n-OZ-05 02:59pm Fro.-URS Corporation Daniel ---Original Message--From: Sclmeemann, Andrew [mailto:ascbneemann@walsbgroup.com] Sent: Tuesday. November 23, 2004 4:39 PM To: Daniel Filer; Guy Va.n-Baulen Subject: RFI 38 1 need 8!lllJlswer ASAP Andrew Sc!lJlecmann Archer Western Contractors, Ltd. W-(972) 361-0062 F-(972) 361·0063 M-(Sl7) 822-7207 This e-mail and any filcs rnmsmitted with it are confidential and are inl""ded solely for the use ofilie individual or entity to whom they are addressed. Ifyou are NOT the intended recipient or Ibe person responsible for deliv.ring the e-JIlIbI to the inrended recipient, be F1dvised ilia! you have receivFld iliis e-mail in elTor and thar8!lY use, dissemination, forwarding, printing, or copying ofiliis e-mail is strictly prohibited. (See attached file: Arapaho Road P3 -RFI38.pdf) T-495 P DDT9TZSSB2042J"0-02-05 02,53pm ,rom-URS Corp.rat,on ClilfHall To: "Daniel File(' cc: 'Guy Van-BauSe!)" , •Jerry Holder"1JRS 111291201» 05:48 PM «JHolder@hntb.com> Subject: Re: FW: RFI 3811!:1 If we understand thiS RFI COrrectly. the contractor is proposing to move the end block reinforcement away from lhe end ofthe beam and provide block·outs for couplers. We cannot accept this chantje. Cliff R. Hall. PE Engineering Unit Manager URS Corporation Graystona Centre 3010 laJ Freeway. Suite 1300 Dallas, lX 75234 Office Tel: 972.406.6950 Direc!: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" 'Daniel File... To: cc: • Jerry Holde(' , 'GtJy Van-Baulen" 111241200401:58 PM Subject: FW: RFI 38 crlff. this issue has come about because the couplers are toe long to fit between the beams. ) originally Iried to have Texas Concrete sign off on this, but they would not So, We need yOIJ yOIJ to verify that Ihese adjustments at the ends of the beams are allOWed. This is a pressing .issue, so if you can answer this qUICkly, it would be helpful. Call me if you have any questions abOut it. Daniel ----Original Message---From: Schneemann, Andrew [mait\o:aschneemann@walshgroup.comJ Sent: Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy Van-Baulen Subject: RA 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western Contractors, Ltd. W-(912) 361-0062 F-(912) 361-0063 M-(817) 822-7201 This e-mail and any files tral'ISnrirted with it are confidential and are intended solely for the use ofthe individual or entity to WhOOl they are 91Z8SSZ04Z T-495 P.D08 F-OI2Jun-OZ-05 OZ:58pm Fr••-URS Corpo,alio. addressed. Ifyou are NOT the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error and that any use, dissemination, forwarding, printing, or \:opying ofthis e-mail is strictly prohibited. 􀁾􀀠Arapaho Road P3 • RFI 36.p ammMl 1-415 POOl HI2J,n-02-05 02:58pm From-URS Corpor,tion "Daniel Filer" To: co: 􀀢􀁏􀁵􀁹􀁖􀀢􀁮􀀭􀁥􀁡􀁵􀁬􀁾􀀢􀀠, "Jerry Holder" , 11129/2004 06:33 PM Subject; RE: FW: RFI38 Cliff, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by rmding a coupler that would fit, but was unable to do so. Ifa coupler cannot be found to fit, you will have to advise on the constructability ofthe beams to aceomodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 ifyou wish to discuss this. Also, if you feel a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel -Original Message-From: C1ifCHaU@URSCOJp.com!mailto:ClJfCHa.\I@URSCoIp.com] Seat: Mon 1112912004 5:48 PM To: Daniel Filer Ce: Ouy Van-Seulen; JerrY Hold.,. Subjett: Re: FW: RFI3S Itwe UllderliWld this RFI comctly, the contnlCror Is proposing 10 move Ibe end block reinforcement away ftom the end ofllie beam and provide block-<,uts ro, couplers. We cannot accept !his cbange. ClitfR.. Hall. PE Engineering Unit Manager URS COJporation OraYSlone Centre 3011) LBI Freeway, Suite 1300 Dallas, TIC 75234 Otru;. Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" To: cc: "Jerry Holder" , "Guy Ven-Baulen" 1112412004 01:58 PM Subj.c" FW: RFI 38 T-49! P.0IO/032 FoOll9728992042Jo,-02-05 02:59pm From-URS Corporation Cliff. this issue has come abOUt because lb. couplers are 10Q long to fit between the beams. 1originally tried 10 bave Texas Concrete sign Qffon this, but they woule! not. So, we need you to verifY iliat Ibes. adjustments at rhe ends ofthe beams are allowed. This i. a pressing issue, so if you ean answer thi. quickly, it would be helpful. Call me ifyou have any questio/lS about IL Daniel ---OrigiDal Me,sage-From: Sci>neemant!, Andrew [maUto:..,,,hneomann@walshgroup.comJ Sent: Tuesday, November 23,2004 4:39 PM To: Daniel Filer; Guy Van-aoulen Subject: RFI 38 I need an """wer ASAP Thanks AIldrew Sehue.mann Archer Western Conttacton,l.td. W-(972)361-0062 F-(972) 361-0063 M-(817) 822-7207 This .-mall and any files tnmsmitted with it are confidential and are intended solely for Ibe use ofthe individual or entity to whom they ... addressed. ICyou are NOT lb. intended recipient or the person responsible for deliveriDg the .-mail to Ibe intended recipient, be advised Ihat you have received this .-mail in error and that any use, dissemination, forwarding, printing, or copying o(Ihis .-mail is strictly prolUbited. (See attached file: Arapaho Road P3 -RFI 3a.pdf) 9TZ888Z04ZJ.n-OZ-05 OZ:59pm From-URS Corporat,on Cliff H"n To: -Daniel Filer" . "Jerry Holder- Subject: RE: FW: FlFI381ll! Please see the following website: htlp:llwww.enco.comlproductsllenlonPO$ition.asp#p9 Cliff R. Hall. PE Engineering Unil Manager URS Corporation Grayslone Centre 3010 lBJ Freeway. Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filef' "Oaniel Film" To; ce: "Guy 􀁖􀁾􀁮􀀭􀁂􀁡􀁵􀁬􀁥􀁮􀀧􀀠•"Jerry 􀁈􀁯􀁬􀁤􀁥􀁾􀀧􀀠. 1112912004 08:33 PM Subject: RE: FW: AFt 38 Cliff, I belir:ve you are tmderstanding the change correctly. With that being the case, we must now ask that you provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation by finding a coupler that would fit, but was unable to do so. Ifa coupler cannot be found to fit, you will have to advise on the constructability ofthe beams to accomodate any alternatives since you do not accept their proposed alternative. You can reach me on my cell at 214-868-6412 ifyou wish to discuss this. Also, ifyou feel a conference call or meeting is necessary, let me know and I will arrange. thanks, Daniel ---Original MessBge-From: ClifCHaII@URSCorp.cotn [tnaiJto:ClifUiaU@URSCOtp.comJ Seal! Mon 11129/2004 5:48 PM To: DlIlIiel Filer Ce: Guy Van-BaulcD; Jeny Holder Subject: Re; FW: RFI 38 If we Wlderstand tbls RFI correctly, the To; c:c: "Jerry Holder" , "Guy Van-Baulen'l 11/2412004 0 I :58 PM Subject: FW: RFI38 Cliff, lids issue: has come about because /he couplef'$ are too lOll!: to fit between the beams. ! originally tried to h.ve Texas Concrete sign off on this, but they wO\Ild nOlo So, we need you to verifY that these adju,,,,,eots at the ends of lhe beams are allowed. 'This is a 􀁰􀁲􀀮􀁳􀁳􀁩􀁄􀁾􀀠wue, 50 ifyou ClIn answer this ,!uickly, it would b. helpful. Call me Ifyou have any questioll! about it. Daniel ·-Qriginal Message··From: ScJmeemann, Andrew (maillo:aschneemann@walsbgroup.comJ Sent; Tuesday, November 23, 2004 4:39 PM To: Daniel Filer; Guy 􀁖􀁡􀁮􀂷􀁂􀁡􀁵􀁬􀁾􀁬􀁉􀀠Subject: RFJ 38 J need an answer ASAP Thanks Andrew Schn.oeDlllJln Arcber Western Contractors, LId. W·(912) 361-0062 ,·(972) 361-0063 M·(811) 822-7207 T-495 p,013lO!f F-OI2 .Jun-02-05 01:59pm From-URS Corporation m8882042 This .-mail and any DIes transmitted with it are confidential and are intended solely for the use ofthe individual or entity to whom they are addressed. Ifyou are NOT the intended Ie.:ipient or the petson responsible for delivering the 􀀮􀀭􀁭􀁾􀁩􀀱to the intended 􀁲􀁥􀀮􀀺􀁩􀁰􀁩􀁥􀁮􀁾􀀠be advised !hat you bave received this .-mail in error III1d thaI ony use, dissemination, forwarding, printing, or .op)ling ofthls .·mail is strielly proliibited. (See attached me: Arapaho Road 1'3 -RFI 38.pdf) omUZ04Z T-495 P,QI4/03Z F-OIZJun-02-05 QZ:59pm From-URS Corporati,n "Schneemonn, Andrew" To: . ·Oaniel Filer" cDFller@hnlb,eom> <8schneemann@wol.h cc: "Guy Van-Beuren" cGVANBAULEN@hntb.rom>. "Jerry Holde(' group.com> Subject: RE, FW: FlFI38 12/0112004 05:57 PM cliff Here is the Lenton p9 , P8 coupler 􀁉􀁮􀁳􀁴􀁡􀁬􀁬􀁡􀁾􀁩􀁯􀁮􀀠guide Andrew SChneemann Archer Western Contractors, Ltd. w-(972) 361-0062 F-(972) 3t'n-OOf;, l1-(817) 822-7207 -----Oriqinal 􀁍􀁥􀁳􀁳􀁡􀁧􀁥􀀭􀀭􀀭􀀭􀁾􀀠􀁾􀁲􀁯􀁲􀁮􀀺􀀠Clit, Hal10URSCorp.com [rnailto:Cliff Hall@URSCorp.comJ Sent: Tuesday, November 30, 2004 10:47 AM To: Daniel E"iler CC! Schneemann, Andrew; Guy Van-Baulen; Jerry 􀁾􀁯􀁬􀁤􀁥􀁲􀀠Subject: RE: FW: RFI 3B Please see the following website: 􀁨􀁴􀁴􀁰􀀺􀀯􀀯􀁷􀁷􀁷􀀮􀁥􀁲􀁩􀁣􀁯􀀮􀁣􀁯􀁭􀀯􀁰􀁲􀁯􀁤􀁵􀁣􀁴􀁳􀀯􀁌􀁥􀁮􀁾􀁯􀁮􀁰􀁯􀁳􀁩􀁴􀁴􀁯􀁮􀀮􀁡􀁳􀁰􀀣􀁰􀀹􀀠Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 􀁾􀁂􀁊􀀠Freeway, 􀁓􀁵􀁩􀁾􀁥􀀠1300 Dallas, TX 75234 Otfice Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filer" To: cc; "Guy Van-Baulen' , "Jerry Holder" 11/29/2004 06: 33 , PM Subject: RE: FW: RFI 38 T-495 p.Ol./0)Z F-OIZ07Z8882042Fr••-URS CorporationJun-OZ-05 02:59pm Cliff, r believe you are understanding the change correctly. With that being the case, we must now ask that 􀁾􀁯􀁵􀀠provide a coupler that meets allowable spec's that can fit between the ends of the beams. The contractor tried to avoid this entire situation 􀁢􀁾􀀠finding a coupler t:hat would fit, but was unable 1:0 do so. If a coupler cannot be found to fit, you will nave to advise on the constructability ot the beams to accomodate any alternatives since you do 􀁮􀁯􀁾􀀠accept their proposed 􀁡􀁬􀁴􀁥􀁾􀁮􀁡􀁴􀁩􀁶􀁥􀀮􀀠 You can reach me on my cell at 2l4-B66-6412 if you wish to discuss this. Also, if you feel a 􀁣􀁯􀁮􀁦􀁥􀁾􀁥􀁮􀁣􀁥􀀠call or meet!ng is neces5ary, let me know and I will arrange. thanks, Daniel -----Original Message----From: Cliff Hall@URSCorp,com [mailto:Cliff_Ha11@URSCorp.com) Sent: Mon ll/29/2004 5:48 PM To: Daniel Filer Cc: Guy Van-Baulen; Jerry Holder Subject: Re: ow: RFI 38 If we 􀁵􀁮􀁤􀁥􀁾􀁳􀁴􀁡􀁮􀁤􀀠this RFI correctly, the 􀁣􀁯􀁮􀁾􀁲􀁡􀁣􀁴􀁯􀁲􀀠is proposing to move the end block reinforcement away from the end of the beam and provide block-outs for coup1ers. We oannot accept this change. Clift R. Hall, FE Engineering unit Manager ORS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, XX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 􀀹􀀷􀀲􀀮􀁾􀀰􀀶􀀮􀀶􀀹􀀵􀀱􀀠 flDaniel Filer" 􀀼􀁄􀁆􀁩􀁬􀁑􀁾􀁀􀁨􀁮􀁴􀁢􀀬􀁣􀁯􀁭􀀾􀀠To; Holdel;'1f , "Guy Van-Baulenfl 11/24/2004 01:58 􀀼􀁇􀁖􀁁􀁎􀁂􀁁􀁕􀁌􀁅􀁎􀁀􀁨􀁮􀁾􀁢􀀮􀁣􀁯􀁭􀀾􀀠PM Subject: rfl: RF! T-495 P 016/03Z F-OIZ9728882042Jun-02-QS Ol:59pm Froo-URS Corporation 39 to so th.ey th.at Cliff, this issue has come about because 􀁾􀁨􀁥􀀠couplers are too long fit between toe beams. I originally tried to have TeKa. concrete sigo off 00 this, but they would not. 50. we need you to verify that these adjustments at the ends of the beams ar" allowed. This is a 􀁰􀁲􀁾􀁳􀁳􀁩􀁮􀁧􀀠issu e. if you can answer this 􀁾􀁩􀁣􀁫􀁬􀁹􀀬􀀠it would be helpful. Call me if you have any questions about it. Daniel -----Original Message----From: Schneemann, Andrew [mailto:aschneemann@walshgroup.com] Sent: Tuesday, November 23. 2004 4:39 PM To: Daniel Filer: Guy Van-Baulen Subject: RFI 39 I need ao answer ASA2 Thanks Andrew Schneemann Archer Western Contractors, 􀁌􀁴􀁤􀁾􀀠 w-(972) 361-0062 F-(972) 361-0063 M-(S17) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual or entity tQ whom are addressed. If you are NOT the intended recipient or the person responsible for delivering the 2-mail to the intended recipient. be advisea 972998ZD42 T-495 P.OIT/OI2 F-OI2Jun-02-05 02:,9pm from-URS Corporation you have received this e-mail in error and 􀁴􀁨􀁡􀁾􀀠any use, .dissemination, forwarQin9, prineing, or coPyin9 ot this 􀁾􀀭􀁭􀁡􀁩􀁬􀀠is strictly prohibited. (See attached file: Arapaho Road P3 -RFI 36.pdf) Jun-02-05 02:59pm From-URS Corpor,tion IN_A' , ATiON INS1RUCTIONS FOR LENTON-P8· P8 POSITION COUPLE...· Safety1IIItIuIIoIII<􀁁􀁉􀁬􀀮􀁾n:r;alIrims rcqoIIcd by.IolmI*m......lIIIMm:cI. SpecIal eIIaIIIoIIlIbaooId ... Si"JIIlIO 1/10 foIlawtq 􀁾􀀠I. o.n..uF...wnI....:I to...J Mt:y repl""', 2. WlI.rab.ll1l .... 3. 'W_&IoV1f1O noidsplilltliHIId CIIIB. 4. WearIllI'e1U__1& all times. S. a..wcacd'pmDllU/wOltil!aalKm, !IeIo", &lid_II. • PDFOl1D 9129982042 T-49S p.Ole/OJ2 F-OI2 INliTALLADON 311l'1 -lIl:aIovc lI.ulI4piDlbctOc 􀀨􀁩􀁦􀁾vtsu.IIY. 1asp Il1o ".1dIIIIi1IpIr Ilu .red ftIIIr. • ST£P 4 -"19S1EP I IhfIednn"""'a ID-"Itsec.md bAr laID 1IIc GII'lIpJet. STU 5 • WblIc holdlag Ib "u\IPIIt bIr"', milea -.ftIdpip: wnueiI_1flo O....• .. ulld oflfll: coupllt. a_ . clo<:twile dirIo:Uoa CO -Ii'I/slr(IIq die 􀁟􀁾􀁬􀁹.• SJIlI>f· 􀁕􀁟􀀮􀁾􀁰􀁪􀁰􀁥WNIIdI.IDnftIy Ii&/IIIID die ./tim II1II tIpIasltlla bocII. • SnJ>1·VCJII) 􀀭􀁬􀁉􀁭􀁬􀀮􀁕􀁾􀁄􀁏􀀧􀀢isIIOtvioiblo(sco....). ;l'jI o:mllJ T-495 P.OIS/O'! F-OIZJo.-OZ-05 􀁏􀁚􀀺􀀵􀀹􀁾􀀠Fr••-URS C.rper.tion Cliff Halt To, "Schneemann, Andrew" """schneemann@walshgroup.com> cc: -Danial File," , "Guy Van-Bauten"1JRS121021200 4 09:47 AM 􀀼􀁇􀁖􀁁􀁎􀁥􀁁􀁕􀁌􀁥􀁎􀁾􀁮􀁴􀁢􀀮􀁣􀁯􀁭􀀾􀀬􀀠"JelT)f Holder" Subject: RE: FW: RFI 381§l Andrew, From the web site. the PS is the coupler \hat would be used when axial movement is restricted (I.e. can·t put the bar Into the coupler). This coupler extends to engage the second bar. We are sijillooking at welding and will advise later; however, we still believe that you can achelve this connection with the P8 coupler. Applications Designed to splice two curved, bE!nt, or straight bars, when neither bar can be rotated • P8 & P13 -designed to splice bars where the ongoing bar Is restricted in its axial movement or can not be rotated and length adjustability of the coupler is required, Clilf R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, SUite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972A06.6951 'Schneemann, Andrew" 'Schneemann,Andnwf To: , "Daniel Filer" , "Jerry Holder" group.carn> Subject RE: FW; RFI 3111210112004 05:57 PM Cliff Here is the Lenton 􀁾􀀹􀀠& pa coupler 􀁉􀁾􀁳􀁴􀁡􀁬􀁬􀁡􀁴􀁩􀁯􀁮􀀠guide Andrew Sonneemann 􀁁􀁲􀁣􀁨􀁥􀁾􀀠Western Contractors, ltd. 1'1-(972) 361-0062 F-(972) 361-0063 M-(617) 822-7207 -----Original Mes5age----From: Clitf_Hall@URSCorp.com !rnailto:Cli££_Rall@URSCorp.com] Sent: Tuesday, November 30, 2004 10:47 AM Ju.-02-05 03:00pm Fr..-URS Corporation mem042 T-495 PD20/D32 F-012 To: Daniel 􀁆􀁩􀁾􀁥􀁲􀀠Cc: Schneemann, Andrew: Guy Van-Baulen; Jerry Holder Subject: RE: FW: R.I 38 Please see the following website: http://www.erico.com/products/LentonPosition.asp#p9 Cliff R. Hall, PE Engineering unit Manager \lRS CorporaUon Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 "Daniel Filexh To: cc: "Guy 'lan-Bau1en" , "Jerry Holder" 11/29/2004 06:33 , PM Subject: RE: FW: 􀁾􀁲􀁉􀀠38 C1lf!, I believe you are understanding the change correctly. With that being the case, we must now ask that you provide 􀁾􀀠eoupler that meets allowable spec's that can fit between the endS or the beams. The oontraotor tried to avoid this entire situation 􀁾􀁹􀀠finding a coupler that would fit, but was unable to do so. If a 􀁾􀁯􀁵􀁰􀁬􀁥􀁲􀀠cannot be found to fit, you will have to advise on the constructability Of the beams to accomodate any alternatives since you do not accept their proposed alternative. You 􀁾􀁡􀁮􀀠reach me on my cell at 214-668-6412 if you wish to discuss this. Also, if you feel a 􀁣􀁯􀁮􀁦􀁾􀁲􀁾􀁮􀁣􀁥􀀠call or meeting is nece33ary, 􀁬􀁥􀁾􀀠me know and I will arrange. thanl Holder'l To: cc: "Jerry PM Subject: 1m: RFI Cliff, this issue has come about because the couplers are too long to fit. between the beams. I ori9inally tried to have Texas Concrete sign off on this, but they would not. So, We need you to verify that these a.;ijustments at the ends of tbe beams are allowed. This is a pressing issue, so if you Can answer this quickly, it would be help£ul. Call me if you have 9729982042 T-496 P.022/032 F-OI2Jun-02-06 03:00pm From-URS Corporalion any questions about it. Daniel -----original Message----From: Schneemann. Andrew 􀀨􀁭􀁡􀁾􀁬􀁴􀁯􀀺􀁡􀁳􀁣􀁨􀁮􀁥􀁥􀁭􀁡􀁮􀁮􀁀􀁷􀁡􀁬� �􀁨􀁧􀁲􀁯􀁵􀁰􀀮􀁣􀁯􀁭􀀩􀀠Sent: Tuesday/November 23. 2004 4:39 PM 􀁔􀁯􀁾􀀠Danial Filer: Guy V.n-Baulen subject: RFI 38 I need an answer ASAP Thanks Andrew Schneemann Archer Western ContractorS. Ltd. 􀁗􀀭􀀨􀀹􀀷􀁾􀀩􀀠361-0062 F-(972) 361-0063 M-(S17) 822-7207 This e-mail and any files transmitted with it are confidential and are intended solely for the use of the individual Or 􀁾􀁮􀁴􀁩􀁴􀁹􀀠to whom they are addressed. If you are NOT the intended recipien, Or the person responsible for delivering the e-mail to 􀁾􀁨􀁥􀀠intended recipient, be advised that you have received this e-mail in error and that any· use, dissemination, forwarding. printing, or copying of this e-mail is strictly prOhibited. (See attached file: Arapaho Road P3 -􀁒􀁾􀁉􀀠3B.pdf) 97Zaa9!04! T-49S p.oza/O.z F-Ol!Jun-O!-05 03:00pm From-URS Corporation Cliff Ha" To: ·Schneemann, Andrew" cc: 'Daniel Flier" . "Guy Van-Baulen"URS 12103/2004 01:25 PM . "Jerry Holder' Subject: RS: FW: 􀁒􀁆􀁉􀀳􀁡􀁾􀀠Andrew, We have reviewed the possibility of using a welded splice detail as you requested to replace the mechanical couplers. We have attached Sketches of a preliminary detail that coUld work, We are still finalizing this and would appreciate any comments you may have. Note that the number, size and location of rebar forthis detail has changed and aU rebar to be spliced will need 10 be ASTM A706 Grade 60 weldable.-.,.,..Arllpl.pdf Arap2.pdf Arap3.pdf Arap4.pdf Cliff R. Hall, PE Engineering Unit Manager URS Corporation Ornystone Centre 3010 LaJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 H95 P.m/oU HI29128992042From-URS CorporationJ ..... 02-05 03:00pm '" .; ", . ". ;-. .. .. " .... . . :':. " .,",.-. , ," ..... ',L ..􀁾􀀠. ;,: .' -, .,. .. 􀀬􀀮􀁾􀀠," .... J.n-02-05 03,OOpm From-URS Corpor.tion 9728882041 POIS/Oll F-OI2 ".Ut" 􀀻􀁾􀀢􀀠...$:, 􀁾􀀠;. ". .,; "". ,.' ....', 􀂷􀂷􀀩􀀻􀁾􀁦􀀬􀀠. '. '.', ; 􀀺􀁾􀀠.... 􀁾􀀧􀀢􀀠.. ",. 􀁾􀀬. ..-'"'' ",' .. , ..... '. ., . . '; 􀁾􀀬􀀠. ',:,' memo42 1-495 P,OU/032 F-m Jun-02-05 03:00pm F,om-URS Corporation " " ' ,,' " , " , " ",<: .. -" ,', '!c<" , , " " ...... ," ," '" .,-;". " ;,,' ,:", . ."" ....' ."". :.;. ," .... . ';' 􀀧􀁾􀀢􀀠" , ( ,,, .. ' ,"" ,', " ' " ,:". ', , ',' .... 􀀬􀁾􀀠:.. , " , *""'\'r.' Jun-02-05 03:01pm Fro.-URS Corporation 9129962042 T-495 P,027/032 F-OI2 '.' 1 \I'} Q \ -! tJ 􀁾􀀠,\I ..\ A II(jl c 􀀧􀁾􀀠'v 􀀧􀀭􀀧􀀭􀀭􀀭􀁾􀀭􀀧􀀧􀀢􀀧􀁜􀁩􀀠<> :-I-" \l .;;,'" SlIbject: RE: FW: RFI38 1210712004 03:31 PM Cliff Here the bolt up plate I talked to you about Andrew Schneemann Archer Western Contractors, 􀁌􀁴􀁤􀁾􀀠 w-(972) 361-0062 F-(912) 361-0063 M-(817) 822-1207 -----Origina1 Message----From: 􀁃􀁬􀁩􀁦􀁦􀁟􀁈􀁡􀁬􀁬􀁾􀁕􀁒􀁓􀁃􀁯􀁲􀁰􀀮􀁣􀁯􀁭􀀠􀁛􀁭􀁡􀁩􀁾􀁴􀁯􀀺􀁃􀁬􀁩􀁦􀁦􀁟􀁈􀁡􀁬􀀱􀁀􀁕􀁒􀁓􀁃􀁯􀁲􀁰􀀮􀁣􀁯􀁭􀁬􀀠Sent: Friday, December 03, 2004 l:26 PM To: Schneemann, Andrew Ce: Daniel Filer; Guy Van-Baulen; Jerry Holder Subject: RE: FW: RFI 38 Andrew, We have reviewed the possibl1icy of using a welded splice detail as you requested to replace the mechanical couplers. We have attached sketches of a preliminary detail that could work. 􀁾􀁥􀀠are still finali2ing this and would 􀁡􀁰􀁰􀁲􀁥􀁾􀁩􀁡􀁴􀁥􀀠any comments you may have. Note that the number, size and location of rebar for this detail has changed and all rebar 􀁾􀁯􀀠be spliced will need to be ASTH A706 Grade 60 weldable. (See 􀁡􀁴􀁾􀁡􀁣􀁨􀁥􀁤􀀠file: Arapl.pdfl (See attached file: Arap2.pdf) (See attached file: Arap3.pdf) (See attached file: Arap4.pdf) Cliff R. Hall, FE Engineering Unit Manager URS Corporation Graystone Centre 3010 LBJ Freeway, Suite 1300 Dallas, TX 75234 Office Tel; 912.406.6950 Direct: 972.406.6976 Fax: 912.406.6951 [!J Span 9 Beam COMlICt;Orl.pdl mem042 T-495 P.029/032 F-OllJun-Ol-05 03:01pm From-URS Corpor.tion Lef"I"t1:m VtlCII cOI.IpUng iJ 0 \) (10..,! I • •• •: l . .\ . \\ . \ • • J , ••••• -• *1 o ."7rro-;.......-.-o"ii""o .. St.il:U=h" HI.'DV)' 'IIo.n PIp Bolt gmaaZD4Z T-495 P.DIO/DS! F-OI,Jun-OZ-05 01:01pm From-URS Corpor.tion "Daniel Filer" To: cc: -SChneemann, Andrew" ••Jert)' HoiCler" , -Guy Van-Saulsn" 1211212004 05:33 PM Subjec:l: Reissued Shaots Cliff, as we discussed. we would like for you to 'reissue Ihe sheets that will correct the beam-en coupling sitIJation. As I said. we do not wish for you to 'cloud" the revIsions. but a revision triangle with a number is required, along with the revision being listed in revision box on lower right of $heet Call or email me if you have any questions. Daniel J. Filer HNTB ARCHIT£CTS ENGlNE6It "Daniel File(' URS 12121/2004 04:51 PM cc: Subject: Arapaho Revised U-Beam Details Unil 4 PDF Andrew & Daniel, Attached is the PDF olthe revised U-beam splice detail. The original mylar will be sent tonight to Daniel at the HNTB office. The U-beam manufacturer should consider using continuous #11 bars through the ends of U-beam "a" into the end of U-beam "b" and cutting Ihese bars after the concrete is cured. This shOUld help ensure that the bars will align properly to make the welded connection in the field . .. u-beam detail. unit 4.pd Cliff R. Hall, PE Engineering Unit Manager URS Corporation Graystone Centne 3010 LBJ Freeway. Suite 1300 Dallas.1X 75234 Office Tel: 972.406.6950 Direct: 972.406.6976 Fax: 972.406.6951 :: ! •• Fr••-URS CorporationJ"0-02-05 03:01pm T-4Q5 P.032/Dl2 F-OI2 • • • 0 • 0 •w' •o • 􀁾􀀠L 􀁾􀀠􀁾􀀠r I I 􀁾􀀠.,-J, .,I• =,􀁧􀀺􀁾􀁾􀀺􀀬􀀡􀀭􀀭􀀭􀀬􀀺 , -. i 􀁾􀁴􀁈􀀧􀀠I ___ f-io-L . ;.-1 􀀮􀁾􀀠"1. •• w ;i • :;!0• • <;I <;I u il • -'-'" .... \oJ CI .0 c-t-t \21 􀁾􀀮􀀠J. :.# ""a .. <;I m <;I -' zl 􀁾-N: SHT. SW-3 :-, '585 j., . 580 m .120-0;t .0:: ::C:::',',.•'Z!r. 􀁢􀀢􀁃􀁾􀀠􀀢􀁾􀀢􀁇􀀺􀀠l.o;OSluPro2 AEA'PA}iO Ref-.r! ?HASt: iII 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠a 􀁾􀁾􀀠;;; .. ! 􀁾􀀠􀀮􀁾􀀠􀀢􀀧􀁾􀀠;",xl'2 " 􀁶􀁾􀀠."􀁩􀁾􀀠􀀼􀁾􀀠􀁾􀀠􀁾􀀠-r 􀁾􀁩􀀺􀀺􀀮􀀠•􀁾􀁾􀀠" 􀁾􀀠"-,2t:t LF'. OF CONCRrTr BOX CUt,vrRT 167 I 1 _____________􀁾􀁾􀁾__________________􀁾􀀶􀁾􀀫􀁾􀁏􀁾􀀰___________ _________􀀷􀁾􀀫􀁾􀀰􀁾􀁏􀁾􀀬___ 8+QO. 9+00L. 􀀭􀀬􀀭􀀭􀀭􀀭􀁾􀀬􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀮􀀽􀀮􀀠" --'"--'" 15150 Surveyor Blvd. Telephone (972) 361 0064wIDf1'B Cool pen " w􀁔􀁨􀁾􀀠HNT8 CompanIes AdaisQI\ TX 75001 r"esimlfe (972) 361 0065 Engineers Archftects Planners www.tmtb.com Mr. Don Good Project Manager HNfB Armer Western Contractors, Ltd. 2121 􀁁􀁶􀁥􀁮􀁵􀁥􀁾􀁲􀀠Suite 103 Arlington, TX 76006 Re Railroad Grade Crossing for Roadway Pavement May25,2005 Dear Don: On May 23M, Town ofAddison held a meeting with the Dallas, Garland & Northeastern Railroad on the work schedule for the grade crossing on Arapaho Road at the old Brickyard area. During this meeting the Town and HNTB were notified that the Railroad would be changing the type of steel rail to a heavier gage, which would raise the height ofthe rail approximately 2 inches. This letter is to confirm our conversation during the weekly progress meeting held on May 24th, requesting Archer Western to hold up on the placement of the flex-base material within both side ofeach railroad grade crossing until such time, that a Railroad work crew can makes the final grades adjustment to the existing tracks, the track are surveyed and adjustment are made to the pavement elevation for the future Arapaho Road to meet the new track grade crossing. Th"'1 i,6J-Guy Van Ba'i HNTB Corporation Cc: File Steve Chutchian. Town ofAddison Jerry D. Holder, HNTB Corporation : :: , HIITD Coapoaat.... 15150 Surveyor Blvd. 1 efephone (972) 361-0064 The HNfB Companfes Addl's:ot\. TX 75001 Facsimile (972) 361 • 0065 Eni}inem Architects: Planners www.hntb.com Archer Western Contractors. Ltd. 2121 Avenue"r HNTBSuite 103 Arlington. TX 76006 Request for Information Response May 25. 2005 Originator. Andrew Scheermann RFI Number. R-AW086 Subject: Securing Stinger Nuts Reqnest: Please reference the Response to RFI 69 Arcl1er Western received a response to RFI 69 -Arcl1 and stinger bolt torque requirements, the requested a method of securing the bolts of the stringer. Arcl1er Western proposes to tack weld the end of the bolt to the nut and spray the weld with cold galvanizing spray. Please approve this method as soon as possible. Response/Action Taken: This method of securing the Stinger ancl10r bolt nuts is acceptable. By: 􀁬􀁾􀁦􀀻􀀺􀁌HNTB Corporation Date: May 25.2005 Cc: File Steve Chutcl1ian. Town of Addison Jerry D. Holder. HNTB Corporation Cliff Hall. URS Corporation 􀁈􀁉􀁉􀀧􀁔􀁉􀁉􀁾􀁟􀀠15150 Surveyor BlVd. teJephone (972) 351 􀁾􀀠0064 The HNtB Companies AcdJ,on. tx 75001 Facsfmile (972) 361-0065 Engineers An;hitecU Planners W'WW.hntb.com Archer Western Contractors. Ltd. 2121 Avenue"r HNTBSuite 103 ArlingtJ 􀁪􀁄􀁾􀀠Guyvan;;kn HNTB Corporation Cc: File Steve Chutchian, Town ofAddison Jerry D. Holder, HNTB Corporation Cliff Hall. DRS Corporation URS May 19, 2005 Mr. Steven Z. Chutchian, P.E. Assistant City Engineer 16801 Westgrove Drive Addison, TX 75001 Re: Arapaho Road Bridge at Midway Road Installation and Tensioning Procedures Structural Strand Assemhlies Dear Mr. Chutchian: . We have recently received the "Installation and Tensioning Procedures Structural Strand Assemblies" and have performed a cursory review. We are returning this submittal as "Rejected". It should be noted that this stressing plan has not been coordinated with the Contractor's erection methods that have been previously discussed. In addition, the procedure has not been signed and sealed by a licensed professional engineer in the State ofTexas. As advised earlier, the Contractor is to provide a detailed erection sequence plan for the arch span and hanger stressing as a requirement of the construction plans and specifications: This erection sequence must be coordinated with and consistent with the "Installation and Tensioning Procedures" and these procedures must consider the influence of the erection sequence, loads and details. We do not believe what was submitted by the Contractor is adequate for this deliverable. It is critical to the successful construction of the arch that the Contractor prepare this detailed erection sequence for approval before erection of the arch commences. Sincerely, CliffR. Hall, P.E. Vice President Project Manager URS Corporation Graystone centre 3010 LSJ Freeway, Suite 1300 Dallas, TX 75234 Te!: 972.406.6950 Fax: 972.406.6951 May 23. 2005 Letter: HNTB-45 HNTB 5910 W Plano ParkWay Suite 200 Plano. Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Location of Stinger Access Hole Dear Guy: On Friday May 20. 2005, Archer Westem set the stinger on north side of bent 9. We discovered that the Stinger Access Hole wi!! be approximately 4" into the span 8 bridge deck concrete. The installation and location of the access holes was detarmined by HNTB, Town of Addison and King Fabrication. Archer Westem was told that modification to the stinger where being discussed between HNTB and King Fabncation. A shop drawing was submitted by King Fabrication and was approved by HNTB. but Archer Westem was not given any requirements for these modifications. Archer Westem will be pouring the concrete on Span 7 & 6 on Friday May 27, 2005. Please provide Archer Western a solution as early as possible, as not to delay the project schedule. If you require additional information, please contact Andrew at our field office. XC: Andrew Schneemann Don Good File IREQUEST FOR INFORMATION PROJECT No. Arapaho Phase 111 RFI # __-,,6"'-.6__ Date: May 23, 2005 Western received a response to RFI 69 -Arch and Stinger bolt Torque Requirements, the requested a method of securing the bolts of the Archer Western proposes to tack weld the end of the bolt to the nut and spray the weld with cold galvanizing spray. approve this method as soon as posslble. Page 1 IREQUEST FOR INFORMATION PROJECT No. Arapaho Phase III RFI # 85 Date : May 5, 2005 Western can not find a detail sheet, in the contiact plans for the Bridge Approach Slab. Provide the bridge approach slab detail as soon as possible. Page 1 --------Conduit Layout per Plans South T-4 Rail South Edge of Decking North T-4 Rail North Edgo of Decking Condo Circuil Pg.# Descriplion Condo Circuil Pg.# Description Cond. Circuit Pg.# Description Condo CircUit Po.# DeSCription 314" Pvc .􀁅􀀦􀁾􀀠.•.. '. :lS!;. 􀀻􀀺􀀮􀁒􀁾􀁾􀁐􀁜􀁾􀁾􀁾􀁾􀀮􀀠:314" RMC 0 335 A·2 Fixtures 314"PVC G 335 .. E,1&A.1 Fixture 314"RMC C&D 339 C·l Drivers 3/4" .pvc: E:' 343';, 􀁾􀀮􀁩􀂷􀀻􀁨􀁾􀀮􀂷􀁾􀀧􀀺􀁩􀀶􀁅􀀮􀁫􀁮􀀠314"RMC E&F 339 C-2Rxtures 314"PVC H&J 335 Receptacles 3WRMO Output 339 C·j OUlpul • 􀁾􀀱􀀴􀂷􀁒􀁍􀁱􀂷􀀠. B 341 B Fixtures 314"PVC D .343 ,F.5.·F.19,G,c7,8,9· 3/4"RMC A 341 B Fixtures ,,;:, '-'I' ,', ,: , ' , ' , ,'" , , , •. 􀁾􀀱􀀴􀀺􀁾􀁒􀁍􀁃􀀠B Control 341 B Fixture Cnlt1 314"PVC" C .· .. 343 F·1·F·3; G'f:6 3/4"RMC .B Conlrol 341 B FixtureCntri 􀁩􀀴􀀧􀁒􀁾􀁃􀀧􀀠Outplit C-2 Fixt. Output339 Total CoridiJi!"-::::·'.2 . . I·· Total Conduits: 5 Total Conduits: 4 Total Conduits: 4 .;;' ARCHER WESTERN CONTRACTORS, L TO. 2121 Ave J, Ste. 103 Arlington, Texas 76006 PH: (817) 840-3898 FAX: (817) 640-8734 SUBMITTAL Date: April 26. 2005 Submittal # :1..1___..:6:..;1;.;,1___....1 New Submittal: X To: HNTB I Town ofAddison Re..submittal : 16801 Westgrove Addison, Texas 75001·9010 Project: Arapaho Road Phase III ANJ# 204059 (972) 451)..2886 Engineer: HNTB Attn: Guy Van,Boulen Submittal Specification Reference: 2x2 Plaque Description of Submitted Item: 2 x 2 Plaque Manufacturer/Sub/Supplier: Southwell Company Related Section /Drawings: Additional Comments: Contractor's Certification "Having Checked this submiSSion, we certify that IT conforms to the requirements of the Contract in all respects, except as otherwise indicated." Sign: Asst. Project Manager Reviewed by: Andrew Schneemann Date: April 26. 2005 Copy: File r.J o o 24" 􀀱􀁉􀀺􀀺􀀺􀀺􀀺􀀺􀁾􀁴􀀺􀀠{no oorreotiDlfsJ IIi as noted resubmit date: CUSTOMER: ARCHER WESTERN CONTRACTORB. LTD. 2121 AVENUE J. SUITE 1011 ARLINGTON. TX70006 SHIP TO: ARCHER WESTERN CONJ1(ACIQRp LTO. 1510 SURVEyOR ADDISON. TX 75001 AnN: ANDREW 5CHNEEMANN CAS'T BRONZE PLAQUE 2.4" W X 24" H ARAPAHO ROAD PHASE III October 2005 City Council R. Scott Wheeler, Mayor Tom Braun Glynda Turner Jimmy Niemann Joe Chow Fredric M. Silver Gregory S. Hirsh Ron Whitehead, City Manager Director of Public Works /City Engineer Mike Murphy, P.E. Construction Manager HNTB Corp. Designer Roadway-HNTB Corp. Bridge-URS Corp. General Contractor Archer Western Contractors, LTD. \'ilUR IJRIlER WILL BE PRODUCED Fl10M THE ARTWORl\ YQU SEE HERE. IF YOIj APPI10VE THIS AATWORK AND IT CONTAINS ERRORS. YOU WILL BE HELD RN#lCIAllY 􀁒􀁅􀁓􀁐􀁯􀀮􀁾􀁓􀁉􀁂􀁌􀀡􀀠FOR iii! WORK WE 00. PLEASE CAAEFULLY CHECK THAT All IS CORRECT REGARDING SPELLING, DESIGN. COLOR AND 81YOll ARI! "11 E(liNn 􀁐􀁒􀁏􀁏􀁆􀀧􀁬􀁕􀁬􀁁􀁉􀁉􀁾􀁮􀀠8 OXIDIZED TEXTURE OOfWER AND __ " ,::»,,* SAriN FINISH QUOTE: 􀁾􀁯􀀺􀁾􀀽􀀽􀀽􀀠FILE NAME: 04·461.19.CDR JOB #...! DATE PLEASE SPECIFY M()IINTINt:l ATTAr.f.4MFNT!,1 ...... eoc... UIIl 15150 Surveyor Blvd. 􀁔􀁥􀁾􀁰􀁨􀁯􀁮􀁥􀀠(972) 361-0064 The tiNTS Companies Addison. TX 75001 Fa.,lmll. (972) 361-0065 Engineers Arthltet;:ts Planners www.hntb.com Archer Western Contractors. Ltd. 2121 Avenue"J" HNTBSuite 103 Arlington, TX 76006 Request for Information Response May 23. 2005 Originator. Andrew Scheermann RFI Number: "K'" Subject: Location of the North Two-Grate inlets at the ends ofthe Bridge Request: Archer Western has discovered base on the provide coordinates that the two grate inlet back of the inside wall will be approximately 2 ft from the face of the T-4 Railing. The question was asked ifthis location would be acceptable, since the water running offthe bridge would be able to flow by the inlet and in the wheel path of traveling vehicles. Response!Action Taken: In the field, Archer Western was directed to move the inlet up against the T -4 Rail. to prevent the grating from being in the vehicle wheel path and to allow the storm water runoff to be collected. Attached please fmd a sketch showing the location of the two-grate inlet and the adjacent T -4RaiI showing to re"erse the 'V' rebar to avoid conflict with the inlet 􀁬􀁊􀁢􀁾􀀠By: GUY7. Baulen. EIT HNTB Corporation Date: May 23. 2005 Cc: File Steve Chutchian. Town ofAddison Jerry D. Holder. HNTB Corporation Made by Date 5"-ZtJ-05GI/6 Job NU2'57t..);􀀱􀀺􀁉􀁾􀁩􀁩􀀽􀁊􀀠Checked by DateTbe HHTB Com/uHllrs Sheet Number Backchecked by DateFor Z-GiA-T£. INL.£r NDR.nJS}t.>€ SK-z,.. .. 4' . II l • 1,.􀁾􀀠􀁾, r -., " ,,;..' , . , -, • ..... • ..:l A r THE.. TWO. 􀁾􀀠􀁾􀀠J>. Fofl r}' It-Il..Er ,4, .d RAILcONe. PP,E C.A$T 􀁴􀁯􀀧􀁦􀀧􀁩􀁎􀁾􀀠M5E. PANE!... Yz. E)(.P. JT f\"IA1"ERiAl ! May 18, 2005 ill 􀁀􀁾􀁇􀁾􀁻􀁧I) MAY 19 2.005 \-I"'1'S 􀁃􀁏􀁒􀁐􀁔􀁏􀁾􀀬􀁴􀁚􀁾􀁏􀁎CALLAS. /HNTB 5910 W Plano Parkway i Suite 200 i Plano, Texas 75093 ! ; Attn: Mr. Guy Van-Baulen :f ! RE: Town of Addison i , Arapaho Road Phase III Project No. 04-22 HNTB Letter concerning MSE Wall #2 Dear Guy: Letter: HNTB -43 Archer Western received your letter dated May 11, 2005, concerning the MSE Wall #2. Archer Western acknowledges that the western most step of MSE #2 was detailed on the shop drawings incorrectly and will be revised. In regards to the wall extension, Please provide a revised plan sheet which shows the wall revisions and any drainage revisions required. Archer Western has provided as-built elevations in this area as requested by your office. The letter states that the work will be compensated under contract bid item 143 -Furnish and Place MSE Retaining Wall TxDOT Item 423. In accordance with the contract, this bid item is to compensate Archer Western for direct costs but does not compensate for remobilization and lost production. Archer Western will await detailed direction from HNTB and Town of Addison on the work required at the West end of MSE Wall #2. Please provide this information as soon as possible as to not delay the work, as we are currently preparing the roadway for concrete paving in this area. If you require additional information, please contact Andrew at our field office. A_---for 􀁓􀁣􀀮􀀮􀁾􀁩􀀢􀁉􀀧􀁲􀀢􀁾􀁾􀁁􀁊􀀮􀀧􀁲􀀢􀀱􀀠XC: Andrew Schneemann Don Good File \ /J I I 15150 Surveyor Blvd. Telephone (912) 361 • 0064I lit!s Addison. TX 75001 facsimire (SI72) 361 «0065J ects Pl4nners www.hntb.com I j ,I ! j " i J !, ;i I , , f/l J ,! i ithered .anager Nestern Contractors. Ltd. venue) HNTB .03 .gton. 'IX 76006 . Bridge Haunch Construction .1ay27.200S Dear Ben: For Several weeks. I have been talking with Archer Western about the construction of the bridge deck. In particular. the construction of the Bridge deck haunch over the U54-Beams. This standard requirement can be found in the contract drawing on sheet BS-ll. page 319. I had received three detail sheets and a copy ofa letter from TXDOT to Archer Western on the methods of construction for haunches on other TXDOT contracts in which you plan to utilize on this contract. This information was forwarded to URS Corp. for review of intent of constructing of the bridge haunches. On May 24,h, I received an e-mail from the Bridge designer rejecting this construction method that Archer Western has proposed and is performing in the field. This e-mail was than given to Archer Western Superintendent There are presently conflicts in the method of construction and the details provided in the contract plans for the haunch. The dimension between the pre-stress concrete deck panels and U -beam which are greater than 1-112"and being supported by 2n thick extruded polystyrene. This is an alternate method which has not been submitted for approval by the engineer of bridge design. Secondly. this height between the pre-stress deck panels and the U-beam has reached up to 4 inches. requiring the installation ofadditional rebar at each Bar R in the U-beam and withio the haunch. This additional rehar has not been submitted for review of size & quantity to the bridge engineer of approval. Until a proper construction design change proposal for the haunch is submitted by Archer Western and reviewed and approved by the Bridge Designer. The placement of the concrete deck for spans 7, 8, 10 thru 14 can not be placed. Any delay encounter to satisfy the Bridge Design Engineer concept of the bridge haunch due to Archer Western alternative construction method will not be recognized by the Town of Addison. Tbak)/. 􀁤􀀮􀁢􀁾􀀠Guy Van Baul';;1 ANTB Corporation Cc: File Steve Chutchian, Town of Addison Jerry D. Holder, HNTB Corporation CliffHall, URS Corporation Weekly Meeting Agenda Date: Tuesday June 7, 2005 Arapaho Road Phase III Time 10:00 A.M. Location: Field Office I. Safety Issues I. Maintain traffic control at Midway Road. 2. Traffic at Surveyor. II. Submittals III. Old Business 1. AlW received revised blow off details from HNTB on 3/9/05. We are pricing and proceeding with this revised detail. AlW is also preceding with the pricing and installation of the 3" Air Release Valve per HNTB direction. After discussions with DWU Field Personnel, the 3" air release will not be required and the 10" flanged opening will be blind flanged and grouted. AiW will Issue RFI to confirm, AiW needs direction from HNTB and Towns of Addison on where to locate the 10" air release equipment. AiW still has not received a revised plan sheet to where the 10" air release valve is to be located or that reflects the changes to the valve orientation. Guy will call eassy at DWU 4-26-05. Stillllave not received revised plan sheets. 5-03-05,5-11,5-18,5-24,6-1,6-7. 2. AlW still has concerns about the roadway grades at the rail road crossings. AiW plans on installing per the latest plan sheet. HNTB requests asbuilt elevations. Given to HNTB on 5-18-05. DGNO has been working on the tracks and all elevations have changed. HNTB lias taken grade shots on the rails and are working on revised plan sheets.6-1. AiW lias stopped all work in tltis area awaiting these plan slteets as of5-26-05. 3. Dirt Grades at R.W. # 3 will need to be revised due to the shortening of the wall length Guy said lIe is working on it. 5-24-05. Nothing yet 6-7-05. 4. Irrigation line at Charter needs to be caped. AiW will cap tllis week.6-1-05. 5. There are still several piles ofRR ties, in site grading areas, at the brickyard that need to be removed. DGNO will remove witllin a month.5-24-05 HNTB stated tflat DGNO will start on tlte crossings soon and will remove at this time. IV. Change Orders I. Ben would like to schedule meeting with Addison and HNTB to discuss Paint Pricing. Jenny will set up a meeting. Meeting was held Wed. 4-13-05. Archer Western is waiting on a response from URS and Jerry Holder. Ben said this is becoming a critical matter due to the primer spec. changing. Jenny said she will contact today. 4-26-05. NW received a letter from HNBTB on 4-29-1)" Another meeting is being schedule;:' Tile painting system has been ' • .:Ided on andAIW will submit :Jricing and proceeding. Waiting on Ben 6-1-05/.-1-05. V. New 􀁂􀁬􀁬􀀧􀀻􀀺􀀺􀀺􀁾􀁯􀁳􀀠1. HNTB requests that R. W. #2 be extended to the limits ofthe T-4 rail. NW has taken field measurements and elevation shots. Texas Welded Wire will be contacted to start the drawings. NW does request a letter directing us on the extending ofthe wall. 5-3-05 NW has not received a letter yet. 5-11-05. NW received a letter from HNTB on 5-11-05. Additional information is needed ASAP. NW requests additional information on the Rep and Inlet as well as removal of existing inlet. This work is scheduled for this week. 5-24-05 AIWhas received revised drawingsJrom HNTB. The work on tI,e wall is completed. V. Misc. I. The DWU manholes are too high; we have contacted DWU and are working on a solution. 2. Dave Wilde requests that weep hole be placed in the grouted riprap at the DWU flume, due to excessive ground water. VI. Schedule 1 Review Weekly Schedule 61712005 ..􀁾􀀮ARAPAHO ROAD '.--.. "...-.-_....-CUrrent Week Next Week Activity Description Prod M T W T F SIS M TW T F 6 7 8 9 10 11 13 14 15 16 17 Dirt and Utilities Excavate/Embank Brickyard Waiting on grade changes Ctean & Patch Unes A & B Ix X X xix X Flex Base East WaiUn on grade chan es Flex Base West X X X X X X Blue Top Flex Base X X X X X X Site Grading Under Bridge X X X X X X X X X X X Clean 66" RCP (Ill Brick Yard X X X X X X BridgeWork Decks /OverhanQ$lSEJ-s X X X X X X X X X X X Deck Rebar X X X X X X X X X X X Place Decks X Set North Arch Set Beam Shore Towers Set Beams Span 9 Splice Beams Span 9 Diaphrams Span 9 T4Raii X X X X X X X X X X X Paving SUN Box Cro5sina Replacement X X X X X X Pave SUIYevor to East X X X X Retaining Walls Level Pad I Coping X X X X X X X X X X X Miscellaneous Inlets X X RioRaD/Pilot Channel at 10x6 X X X X X X X X X Surveyor Crossing 􀀬􀁾􀁾􀁩􀁴􀁣􀁨􀀠Traffic as needed---...---....---......--L.... ___ --L.. ._-L.. ,-,-L-'L-LSIS M 18 20 X X X X X X X X X X X L Following Week T W T F SIS 21 22 23 24 25 X X X X X X X X X X X X X X X X X X X X X X X X X X 􀁾􀀠--􀁾..;:.+J__________ 5 Weekly Meeting Agenda Date: Tuesday June 7, 2005 Arapaho Road Phase III Time 10:00 A.M. Loeation: Field Office I. Safety Issues 1. Maintain traffie control at Midway Road. 2. Traffic at Surveyor. II. Submittals III. Old Business 1. A/W received revised blow off details from HNTB on 3/9105. We are pricing and proceedii:::; with this revised detail. AlW is also preceding with the pricing and installation of the 3" Air Reka2C Vf!lve per HNTB direction. After discussions with DWT: Rield Personnel, the 3" air release will not be required and the 10" flanged opening will be blind tlanged :!nd grouted. AJW will Issue RFI to confinn. AlW needs direction from HNTB and Towns of Addison on where to locate the 10" air release equipment. AlW still has not received a revised plan sheet to where the 10" air release valve is to be located or that reflects the changes to the valve orientation. Guy will call Cassy at DWU 4-26-05. Stili have not received revised plan sheets. 5-03-05,5-11,5-18,5-24,6-1,6-7. 2. AJW still has concerns about the roadway grades at the rail road crossings. AlW plans on installing per the latest plan sheet. HNTB requests asbuilt elevations. Given to HNTB on 5-18-05. DGNO has been working on the tracks and all elevations have changed. HNTB lias taken grade shots on tile rails and are working on revised pian slleets.6-1. AIWlias stopped aii work in this area awaiting these pian sheets as of5-26-05. 3. Dirt Grades at R. W. # 3 will need to be revised due to the shortening of the wall length Guy said he is working on it. 5-24-05. Not/zing yet 6-7-05. 4. Irrigation line at Charter needs to be caped. AIW will cap tilis week.6-1-05. 5. There are still several piles ofRR ties, in site grading areas, at the brickyard that need to be removed. DGNO wili remove Wi/lzill a montll.5-24-05 HNTB stated that DGNO will start on the crossings soon and will remove at this time. IV. Change Orders 1. Ben would like to schedule meeting with Addison and HNTB to discuss Paint Pricing. Jenny will set up a meeting. Meeting was held Wed. 4-13-05. Archer Western is waiting on a response from URS and Jerry Holder. Ben said this is becoming a critical matter due to the primer spec. changing. Jenny said she will contact today. 4-26-05. NW received a letter from HNBTB on 4-29-05. Another meeting is being scheduled. The painting system has been decided on andA/Wwill submit pricing and proceeding. Waiting Ofl Bell 6-1-05,6-7-05. V. New Business l. HNTB requests that R. W. #2 be extended to the limits ofthe T -4 rail. NW has taken field measurements and elevation shots. Texas Welded Wire will be contacted to start the drawings. NW does request a letter directing us on the extending ofthe wall. 5-3-05 NW has not received a letter yet. 5-11-05. NW received a letter from HNTB on 5-11-05. Additional information is needed ASAP. NW requests additional information on the Rep and Inlet as well as removal ofexisting inlet. This work is scheduled for this week. 5-24-05 A/Whas received revised drawings from HNTB. The work on the wall is completed. V. Misc. 1. The D WU manholes are too high; we have contacted DWU and are working on a solution. 2. Dave Wilde requests that weep hole be placed in the grouted riprap at the DWU flume, due to excessive ground water. VI. Schedule I Review Weekly Schedule 6f712005 ,-"·4ARAPAHO ROAD 􀁾•.Current Week M T W T F SIS MActivIty Description Prod 6 7 8 9 10 11 13 Dirt and Utiliti •• Excavale/Embank Brickvard Waifino on orade chanaes Clean 1\ Palch Lines A & B Ix X X xix X F!ex Base Ei.ast Waitin on grade chan es Flex Base West X X X X X X Blue Top Flex Base X X X X X X Site Grading Under Brid_ge X X X X X X X Clean 66" Rep @Brick Yard X X X X X X BridgeWork Decks /OverhangslSEJ's X X X X X X X Deck Rebar X X X X X X X Place Decks Set North Arch Set Beam Shore Towers Sel Beams Span 9 Splice Beams Span 9 Diaphrams Span 9 T4 Rail X X X X X X X Paving Surv Box Crossin Re lacement X X Pave Surveyor lo East Retaining WaUs Level Pad I Coping X X X X X X X Miscellaneous Inlets X X RipRap/Pilol Channel 0110x6 X X X X X Surveyor Crossing S\vitch Traffic as needed Next Week T W T F SIS M 14 15 16 17 18 20 X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X Following Week T W T F SIS 21 22 23 24 25 X X X X X X X X X X X X X X X X X X X X X X X X X X --, .. --,--SUBS/NOTES ARAPAHO ROAD PHASE III FUNDING UPDATE Updated March 22, 2005 Project Balances as ofDecember 31, 2004 Comments Fund 41 -Street Capital Project Fund $ 1,247,842 Fund 46 -2000 Capital Project Fund Fund 44 -2002 Capital Project Fund 803,744 Fund 47 -2004 Capital Project Fund Total Project Balances Project Requirements "s of December 31, 2004 Under Conlract: AroherWestem Conlractors Ltd. $ 12,028,332 Por 12120104 Invoice -Original conlract was $16,702,578,42 plus $8,509.00 change order. HNTB Design Conlract 56,381 Por 10115104 Invoice -Not received and paid until February 2005. HNTB Construction Inspection Conlract 310.310 Per 01128105 Invoice -Invoice was for $124,376.16 going back to 011231021!1 HNTB Landscape Arohitecture Conlract 4,365 Per 04109104 Invoice -Remaining of ortginal $87,291 contract. HNTB Shop Drawing Conlract 55,964 U Contract approved by Council in August 2004. URS Bndge Shop Drawing Conlract 20,668 •• Contract for $24,900 approved by staff. 12,476,020 Additional Work Authorized: Archer Western Change Orders #2 & 3 160,750 TXU Electric Utility Relocation 282,950 sse Utility Relocation 39,000 Farmers Branch Water Une Relocation 107,410 "Increased by $18,690 due to unexpected increase in material cost. 590,110 Additional Worl< Identified: ArcherWestem Incentive Payment 200,000-¥)iW Future Archer Western Change Orders 250,000 HNTB Additional Construction Inspection 149,000 ''This amount raduced from $269k. DGNO Railroad Crossing 1,300,000 Lagal fees Assodaled with Conlesled ROW 30,000 1,929,000 Total Project Requirement $ 14,995,130 Project Balance $ (952,920) Potential Resources: South Quorum/Inwood Road Parl< 518,260 BeftHne Resurfacing Savings Future Interest Earnings 2006 Bond Sale -Arapeho Rd. Tollway Intersection 200,000 50,000 i" 750,000 e ..,M. ConservaUve estimate, may approach $500k. 2006 Bond Sale -Belt Line SPUI 2,200,000 $3,718,260 Revised: 9:37 AM "" '9 'v" 1 jIIo. 'iCi'J;tIJO 1000 􀀡􀁕􀁴􀁊􀁉􀁾􀁹􀀠Locates 10, 01 100: , I :􀀬􀀮􀁌􀁟􀁾􀀠􀀢􀁟􀁾􀀬􀀮􀀢􀁾..,.._____.___ 􀀮􀁾􀀮􀁟􀁾􀀮􀀬􀁟􀀮􀀠􀀬􀀮􀀬􀀢􀁴􀁈􀀢􀁾􀀢􀀠.,. ..,,---'-1020 IDelivery Beddin'g Malerial 8' 01 100: , ! I I ---'10s;'-􀀭􀀭􀁾􀀶􀀰􀀠􀁗􀁾􀁴􀁥􀁲􀁩􀁩􀀻􀀻􀀮􀀭􀁓􀁨􀀻􀀻􀀻􀀧􀀻􀀧􀀻􀀧􀀻􀀠􀁔􀁾􀁴􀀭,,-r'" -8:---0]--,00.:-: : ! I : 1030 􀂷􀂷􀂷􀂷􀀭􀁬􀀶􀀰􀀧􀁖􀀻􀁉􀁾􀁾􀁍􀀭􀀻􀁴􀁥􀁮􀁡􀁬􀀠􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀺􀀭􀂷􀀧� �􀁡􀀮􀀭􀀭􀁯:---"-1'001'-_. 􀁾􀀠􀀮􀁾􀀮􀀠,-_._«1-._-----_. .,., ..,-:i 􀁍􀁉􀀤􀁾􀀭􀀸􀁹􀁾􀁾􀀧􀀻"and Air release 􀁾􀀠1040 100:5 01 􀀡􀀭􀁾􀀺􀀺􀀺􀀠􀁍􀀺􀀻􀁾􀁨􀁾􀁉􀀻􀀭􀁯􀁾􀁩􀀻􀁾􀀻􀀻􀀧􀀢􀀠8'-''''01 laO'1050 􀁾􀀠! ' ____ j.1_"_,_",, '-.. " ".. 1010 I Pipe DerMlry 4, 01 100 1190 ip;••;';;;bi.􀁖􀁾􀁾􀀻􀀻􀁾􀁾􀁤􀁁􀁤􀁩􀀠􀀢􀀷􀁾􀀭􀀭􀀭􀀷􀁲􀀠' , ,,--ii􀁾􀀰􀀳􀀯􀀰􀀸􀁉􀀰􀀵􀀠: Fittings ,L ""__,_,__, __ ,'___,,,'_ ,_ ,,",,'_ " ..__ ,_,...1._____ ..1170 iShutDown60Waterline I' 4' 4i 0103/101ll5' ,􀁾􀀠􀁾􀀬􀀮􀀠_. _.. ...__.__􀀢􀀮􀁾􀁟􀀮􀀮􀀠,_._.! _.._____ ....__L ' ..___....:..... 1200 !,Knock Hole fn Pipe @'18 In III 2, 2i 0031101115 ; ! 􀀮􀀬􀀮􀀬􀁾􀀠.., 􀀮􀁟􀁾􀁌__ "... --, ._.......!... 􀀮􀁾􀀭􀀮􀀠1210 Dewarer Pip. Un. 5', 0;0311010581 i .. -.--..􀀭􀀮􀀭􀀭􀀭􀀭􀁟􀀮􀁟􀁾􀁾􀀮􀀠__....___ 0. 1180 !\lerify waterline shut dClWr1 2. 2 0'03110105 1230 !Excavate Existing Tie point #2 2: °i03/101ll5 1250 l'Excavate new Walel1ine to Joint 􀀴􀁾􀀭􀀭􀀭􀀴􀀺􀀢􀀠-0'03111105 85 i 􀀭􀀭􀀻􀀲􀀶􀀰􀁾􀀻􀀻 􀀻􀁾􀁾􀁩􀁩􀁾􀁧􀀭􀁰􀁩􀁰􀁥􀀠􀁀􀀭􀁮􀀻􀀻􀁩􀁾􀀭􀁐􀁔􀀠I""" "4'-4' -iiTii3il1ro5 i#l I ' 􀀭􀀭􀀭􀁾􀀢􀀭------------------􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀬􀀮􀁾􀀭-..,. -􀀭􀀭􀀭􀁔􀀭􀀮􀀭􀁾􀀭􀀮􀀭􀀬􀀮􀀮􀀮􀀭􀀭􀀭􀀭􀀭􀀬􀀭􀀭􀀭1270 ,DiglLay/Bed 60 Bl to A4 ! 10, 10: 0103/11105 .......L." ...___.._____.. ___,___..,_,-, ...L, ...___\-_____ ." __ " __ c..,,, _". 1400 !lnstaliPadunderGarevalve , 121 12: 0,o3112105 __􀀮􀁟􀀮􀁯􀀮􀁟􀁾􀀠__..j 􀀮􀁟􀀮􀁟􀀮􀁟􀁾􀁟__ _ _ ___ ,,___􀁾􀁟􀁾􀀮􀁟􀁾􀀬__..􀁟􀁾􀀭􀀭􀀮􀀭􀀮􀀭􀁾􀀮􀀭..---._+_.___._!, ..-,. ° 1310 IWeid B1 toM 12' 12: 0103/12105 I ! , 1290 􀁪􀁄􀁩􀁧􀁩􀁌􀁡􀁹􀁴􀁩􀁩􀁾􀁤􀀠60 B5 to B9 􀁾􀀭􀀭􀀭􀀻􀁯􀁩􀀠10:--"0 03l12ro5· , . __.t.. 1280 : Demo Existing Pipe @11e in PT #2 .".-.---....􀁾􀀠.. -...-..􀀭􀀭􀀭􀀮􀀭􀀭􀁾􀁾􀀭... 􀀢􀁾􀀭􀀭􀀢􀀠 1300 IOlg/LayIBed60Bl0&CS11 © Primavera Systems, Inc. IUtility Locot.. ' Delivery Bedding Malerial I 60 Watanlne Shutdown Test :60 Valve Material l Mise: Bypass and Air release materal Precast Manholes Delivery Pipe Oellyery 03109105 _ Preassemble Va1ve and Adj Fittings 03111105 _ Shut Oown 60 Walerll"!' ,03110/05 I Knock Hole In Plpe@11e In #1 .. " .._.._._---_._.._-_._-03111105 _ Oowaler Pipe Line 03110/05 I Verify waterline shut down 03111105 _ Excavate Exi,ting TIe point #2 ,03111105 I Excayate new W'ateriine to Joint 85 '03111105 • Oemo Exls!!ng Pipe @ne In PT #1 . ------1'" 03112105 ---"oiiilC.ililed 60 Blto A4 '03114105 • •••InsteU Pad under Gate Valve 03114105 ___Weld Bllo A4 --03IW05___ DlglLaylBod 60 B5 to B9 __III Oemo Exlllting Pipe @Tlo In PT #2 .'Oigll.ayIBed-t;OB10& CSl1 .....-.-, ..􀀭􀀭􀀭􀁾􀀮􀀠Sheet 1 or 2 , 􀀬􀁾􀁾􀀬􀁖􀀮􀁬􀀧􀀮􀁜􀁑􀀡􀀺􀁉􀀮􀀠􀁾􀀡􀀮􀁾􀁾􀂣􀁾􀁾􀀬􀀠􀁾􀁐􀀮􀀡􀀹􀁙􀀡􀀡 􀀧􀁟􀀠." ••0,,, ° 1-·_····· Classic Schedule layout 􀁾􀁡􀁍􀁹􀁁􀁾􀁖􀁾􀁾􀀢􀀠I '􀀮􀀭􀁾􀀺􀀧􀁜􀀢􀀠􀁁􀁣􀁴􀁬􀁾􀁾􀀠• j",ng.1 Kern l % 1 t:a,rty . MFfnh3ih. 􀁉􀁄􀀼􀁾.. , .... 􀀬􀁟􀀬􀀻􀀻􀀬􀀻􀁉􀀩􀁪􀀩􀀮􀁣􀁾􀁰􀁕􀁯􀁮􀀠__􀁾􀁾􀁪􀀺􀀠􀀮􀁬􀀧􀀮􀀱􀁊􀁦􀁟􀁌􀁾􀁾􀁅􀁌􀀺􀁟􀀺􀁪� �􀁟􀁾􀁬􀀻􀁉􀁲􀁴􀀠..\L::i=:9dQ , 􀁬􀁩􀁩􀁾􀁾􀀱􀁩􀁔􀁉􀀴􀀨􀁩􀀵􀀠􀀬􀁾􀁾􀀻􀀲􀀺􀀠18 ; 􀁾􀁩􀀮􀀲􀁾􀀺􀁾􀀺􀁾􀀬􀁩􀁌􀁾􀀧􀁾􀁾􀀻􀀡􀀠26,27 128,29 􀀬􀀳􀀰􀁾􀁬􀀠_ Weld 65 tQ691320 ,Weld 65 to 69 12' 12! 0;03l1411l5 !03115105 6: _ Weld Test 61 to A4 1340 Test 81 toM 0.03114105 i 03115105 ·,1,·--.• ... Form & Pour ThruS! Blocks1500 :Form & Pour Thrust BloCKs 8 003115105 :03116105 _ Weld 610 & CS111330 :WeldBl0&CS11 12 °03/16105 '03117/05 • Weld Test B5 10691350 Weld Test B5 to 89 6 ° 03116105 03/16105 _ Grout lnternal Joints1370 Grout Internal Joints 12 ° 031171115 0311 al05 ... Grout External Joints 1380 Grout External JOints 12, 0:03l1711l5 03/18105 , I WeldT••1610&CS111360 Weld Tost Bl0 8. CSll 6 6 0 ;03117105 03117105 .l."".. 􀁾􀁾􀁾􀀮􀀠• Install Manhole @GateValve Operator 1410 !Install Manhole@GateValve 4 4 0!03I16105 03/18105 ::􀁏􀁾􀁥􀁬􀁩􀁬􀀮􀁴􀁾􀁾􀁾􀀢􀁾􀀬􀀮􀀠,_,_,... ,'" -1--,,," II Clean Pipe 1440 iCle.n Pipe 01°3115105 03118105 , •• , .. -----, 12 12l 0!0311Sro5 . ... Back Fill Pipe 1390--!BacK Fill Pipe 0311911lS, 1 I "1420!i;;:';lall Manhole @􀁡􀁽􀀮􀁰􀁡􀁾􀀻􀂷􀀧􀀠4 4i'--OTii3i1BIOs ,03118105 • Install Manhole@Bypass _ Install Air release Valve 1430 . Ti;'iailAI,'':';i;;-ase Valye Oi0311611l5 :03119105 ! 10' -'1ot·, -I ! ..􀁾􀀭􀀭􀁴􀀭􀀮􀀠 1450 1Fif! Pipe With Water 4 4: iii 03119/05 '03121105 • ••Fill Pipe With Water , , I i _ Clorlne Slug Pipe1460 ICionne Slug Pipe 24 24[ 0[03121105 !03l2211l5! ••• j f... 􀁾􀀮􀀭􀀮􀀢􀀠•••• Pull Bacteria Test 1470 ipull Bactens Tesl i 46 48i o031221115 􀁾􀀰􀀳􀁊􀀲􀀴􀀱􀀰􀀵􀀠, L. o 03I2411l5 ----T03124105 • Return to ServIce1480 iReturn to ServIce s 8!, Sie.M: Oolte 12127104 Sheet 2 of 2Eany Bar BOWl Finish Dalr:t OOJ24105 Archer Western Contractors, ltd. Date 􀁒􀁾􀀧..ision ..____ql..􀁾􀁾􀀠; 􀀬􀁾􀁾ProQmssSarData Dai-'.""/"1 • · Dale: \lZS\C6 '. '" NrmitNo.· .. ,IlL) ,ifL.:The undersigned petitions the City ofCartollton (or pctmiSSioD to worle, install, 􀁣􀁸􀁾􀁡􀁶􀁬􀁬􀁴􀁣􀀠or cut at the location described below in ac:cotdincewithCity Control Procedum anti provision as stated berein. Contraclllr: :rr"",'rJ· .'c£ f'-OO,;:Q..J . Mailing Address: It II po! . I j @1ls£.v'le; .. ' .. Responsible 􀁓􀁵􀁰􀁣􀁲􀁶􀁩􀁡􀁯􀁴􀀺􀀮􀁾􀁴􀁊􀀮􀁄􀁢􀀱􀁲􀀶􀀮􀀧􀀪􀀢􀁍􀁗􀀧􀁌􀀠Phone; DaymMbmqbNigbt"t12, 􀁾1-=1-13 · Project N!I!Ic:. 􀁾􀁾􀀺􀀻􀁳􀀠Project Address: .11 ,i?o' 4'f1DCq,w/tf PUIpOseofWOlk: 'fC.T. \,\g£.D....?Y, 11)I\""11ifJ LAlE; BiZI!' ofWork: Longth . :3 .width .3 . Depth 􀁟􀁾______􀁾􀀭􀀭􀀭􀀬􀀬􀀢􀀢􀀠 Work To Be Per.fonned By: (. ) Gcriow Contractor (. ) Ulilil)' 􀁃􀁯􀁮􀁴􀁲􀁡􀁾􀁴􀁯􀁬􀀢􀀠. ( ) Paving ContrllCtor . ( 􀁾) Ci1y (JOther · Type Eltoavauon: ( . ) Slrtct Bon: (. v)Ground Surface 􀀨􀁦􀁫􀀶􀁲􀀮􀁾􀁓􀁴􀁲􀁥􀁥􀁴􀀢􀀺􀀧􀀠COIl1lrete/As phalt . CitytdR.epJace! ( l,ubbascIllidSllrl'llce( )SurfB.i:eOnly. (> .'. }None' :,., WORK AS AU"l'HORIZED UNDER mE APPR.OVED PERMIT REQUEST SHALL BEGIN WITHIN SIXTY (60) CALENDAR: DAYS FROM THB APPROVED DATE, OR APPLICAnON FOR PERMIT· MUST BE .!tEsUBMrtI'Ep. ' . . 􀀬􀁾􀁴􀁩􀁭􀁡􀁴􀁥􀁤􀁃􀁡􀁬􀁥􀁮􀁤􀁡􀁲􀀠Days ofBloqe: \. 'D'()!.:> w OeJL , , "'" . 􀁂􀁾􀁣􀁡􀁤􀁥Sketch Attached: ( '. ) YES ( 􀁾􀀠)NO 􀁾\ !A COn1ractor to suppI . des as leA{uired by stare and local 􀁣􀀺􀁯􀁤􀁣􀁾􀀮􀀠The 􀁡􀁰􀁰􀁬􀁩􀁾􀁩􀁬􀁬􀁉􀁴􀀠a&knowledges hisliability, .. hazards. The contractor is responsible for relocation or replac:cmellt oftrees and uired to be moved in COIIlleotion with the permit work. Phoiie: llzklfikO . EStimitcd 􀁃􀁯􀁭􀁰􀁬􀁾􀁴􀁴􀁩􀁯􀁮DIite; . •. e eslimaled compIe&iqn dale .bah lIofmltlly be fi&a1 (I S) worting 􀁤􀁡􀁹􀁾􀀠t'rom·dllte'ofissuc. However. 􀁦􀁯􀁲􀁬􀁬􀁬􀁬􀁧􀁥􀁪􀁾􀀮􀁥􀁸􀁣􀁣􀀺􀁰􀁴􀁩􀁯􀁄􀁳􀁄􀁬􀁡􀁹􀁢􀁥􀀮􀁣􀁯􀁬􀁬􀁬􀁩􀁤􀁥􀁲􀁥􀁤􀀮􀀠idc.A(G5 (3 9iOGAH ON f':');,!f",dj:j InSpector Assi(f1led:1:rJli6l;r vJOCE{l . 􀁐􀁨􀁯􀁮􀁾􀀻􀀠. 􀀹􀁮􀁾􀀴􀀶􀀶􀀮􀀳􀀲􀀰􀀰􀀠..' •(. \<: )Applovcd . ( .)DiS4pPtOved Date Issucd: /-;"6-:-d5. .... ...... .'. ii:6M1isNTs: CONTAwCT lNSPECl"OR BE"IWEEN 7;30 -8:0i! AM FOR INSPECT[ON. CDntiwt Public Works Dcpartmelll far 1in.cloCaticms in field -972-466-342S.Corttact T􀁮􀁩􀁉􀀱􀁩􀁃􀀺􀁾􀁣􀁰􀁡􀁲􀁴􀁭􀁣􀁩􀁬􀁦� �􀁯􀁲􀀠 lill" locatiWlS in field -911-446-3606. Contact all Public Utility 􀁃􀁯􀁭􀁰􀁡􀁮􀁩􀁾􀁳􀀠for line locati.ons. . J. Ot;liIIl' -0..1....(whlll) 2. , ..p.c.... (plnl!) WILLal: UTlLlZI!D. '.' 3. 􀁾􀁉􀀮􀁦􀁴􀁯􀁴􀀠II.... (,...,,) ALL WOJU( TO BE INSJ'lOCTEI! BEFOJU: ... W.1c:r ».,t. COVEIIlNG. !I. Trim. TOTAL ?01. on DatA!: Note: • • • • • 􀁊􀁈􀁎􀀭􀁤􀁢􀀭􀁾􀁾􀁾􀁾􀀠􀀱􀁾􀀺􀀱􀀱􀀠LJIY Ur LHkKULLIUN 􀁾􀀮􀁾􀁬􀀯􀁾􀁬􀀠d'. ,\.\fI\ vi# CITY OF CARROLLTON, TEXAS Nt'" 􀁋􀁁􀀭􀁾'v \)C!" CONSTRUCTION PERMIT A /I . .2 'a3 􀀭􀁪􀀻􀁾􀀠PUBLIC RIGIIT-OF-WAY /STREET CUT /EXCAVATION I 9 H({IJ! J' I􀁾􀀠OFFSITE UTILITY INSTALLATION PERMIT 􀁾􀀺􀀺􀀮􀀮􀀮􀀮􀀠\lzslos--PennitNo. ________ The undersigned petitiollS the City of CmoJlton for pennission to work, install. excavate or cut at the location described below in accordance with City Control Procedures and provision as stated herein. Contractor: :n)<..;n-l! pF 􀁾􀁄􀁉􀁾􀀠 Mailing Address: It" eo! ! .!.ii:%Tb 􀁾􀁶􀀢􀁾􀀰􀀺􀀺􀀭_________________ . Responsible Supervisor; ,\eNr+JrllCEiSf'.....OGL Proj ect Name: !\?1\ffi\:'o 􀁾􀁴􀀭􀁜􀀺􀀧􀁳􀀺􀀻􀀺􀀻􀀠 Project Address: 11 aT'>Q I U..;,f]Dlt.aib"i'f' Purpose ofWork: iliT IiaE O,...?y, !;)I\"(6U.!NG 􀁓􀁩􀁺􀁥􀁯􀁦􀁗􀁯􀁲􀁫􀀺􀁌􀁥􀁮􀁧􀁴􀁨􀁟􀁾􀀮􀀮􀀮􀀮􀀳􀀠Width 3 . Depth ____-'-_ 􀁾􀁟􀁾􀀠 Work To Be Perfonned By: ( ) General Contrector ( ) Utility Contractor ( ) Paving Contractor ( v-) City ( ) Other Type Excavation: ( ) Street Bore ( t--) Ground Surface (f'oeo,et¥Street -Concrete/Asphalt City to Replace: ( ) ,Subbase.md Surface( ) Surface Only ( ) None WORK AS AUTHORIZED UNDER THE APPROVED PERMIT REQUEST SHALL BEGIN WITHIN SIXTY (60) CALENDAR DAYS FROM mE APPROVED DATE, OR APPLICATION FOR PERMIT MUST BE RESUBMITfEJ;). Estimated Calendar Days of Blockage: 􀁟􀀭􀀬􀁜􀁾􀁢􀁾􀁾􀁾􀀧􀀭􀀾􀀢􀀭􀀭􀀬􀀬􀁷􀁾􀁯􀁾􀁦􀁚􀀮􀀮􀀬􀀺􀀻􀀺􀀻􀁉􀀺􀀮􀀮􀀮􀀻􀀼􀀢􀀧􀀽􀀭􀀭􀁟􀁾__________ Banicade Sketch Attached: ( ) YES ( ;< ) NO N \ I':l.. Contractor to supply' . cades as required by state and local codes. The applicant acknowledges his liability for the work and ate hazards. The contractor is responsible for relocation or replacement of trees and lUW!:fillif 􀁾􀁯􀁶􀁥􀁴􀀠hich are uired to be moved in cOlUlection with the pennit work. + + . • on Date: Estimated Compleotion Date: 􀀺􀀭􀀭􀀭􀀺􀁟􀀭􀀺􀀺􀀺􀁾􀁟􀀭􀀺􀀭􀀺􀀭􀁟􀁾􀁟􀀠e estimated completion date shall normally be fifteen (15) working days from date ofissue. However. for large jobs, exceptions may be.considered. Inspector Assigned: __--'--____-______Phone: __""-9...,72o.;;-"'46""'6""-3""2"'O.!<.O____ ( ) Approved ( ) Disapproved Date Issued: COMMENTS: CONTACT INSPECTOR BETWEEN 7:30 -􀀸􀀺􀀭􀀺􀀺􀀰􀀺􀀭􀀺􀀭􀀰􀀭􀀭􀀺􀁁􀀭􀀺􀀺􀀭􀁍􀁾􀁆􀀽􀁃􀁏􀀺􀀺􀀭􀀺􀀺􀁒􀀺􀀭􀁉􀀽􀁎􀀭􀀺􀀭􀀺􀀺􀁓􀀽􀁐􀀽􀁅􀁃􀀭􀀺􀀺􀁔􀁾􀁉􀁏􀁎􀀮􀀠 Contact Public Works Department for line locations in field -972-466-3425. Contact Traffic Department for line locatio1lll in field -972-446-3606. Contact all Public Utility Companies for line locations. 1. Orisinnl-Cu,tnmer (whire) WHEN TRAFFIC IS RESTRICTED FLAGMEN 2. In,poe••, (pink) WILL BE U7lLIZED. 3. Street Dept. (canary) ALL WORK 70 BE INSPECTED BEFORE --..􀁾􀀭􀀮􀀭􀀭􀀭4. Water Dept. COVERING. 5. Tram, TOTAL P. 01 • • • • • • • • • • • JRN-26-2005 15:11 CITY OF CARROLLTON P.0U01 CITY or CARROLLTON, TEXAS CONSTRUCTION PERMIT PUBLIC RIGHT-OF-WAY ISTREETCVT I EXCAVATION I OFFSlTE UTILITY INSTALLATION PERMIT Dare: __________􀁾____􀁾__________ PenmtNo. __________________________"____ _ The undersigned petitiollS the City ofCmolltoll for penmssion to work, install, excavate or cut at the location described below in accordance with City Control Procedures and provision as .stared herein. Contractor: ________________--_________________________ Mailing Address: _____________________ _____􀁾_____􀁾______􀀮􀁾􀁟􀀠Responsible Supervisor: 􀁾􀀮_________􀁾___ Phone: Day _______ Night _____ Project Name: ______________________________ Project Address: ___________________________ . Purpose of Work: _________-_______________-____________ Size ofWork: Length ________ Width Depth ___________ Work To Be Performed By: ( ( ) General Contractor ) Paving Contractor ( ( ) Utility Contractor ) City ( ) Oilier Type Excavation: ( ) Street Bore ( ) ) Ground Surface ( ) Street Concrete/Asphalt City to Replace: ( ) Subbase and Surface( ) Surface Only ( ) None WORK AS AUTHORIZED UNDER THE APPROVED PERMIT REQUEST SHALL BEGIN WITHIN SIXTY (60) CALENDAR VAYS FROM THE APPROVED DATE, OR APPLICAnON FOR PERMIT MUST BE RESUBMI'ITED. Estimated Calendar Days ofBlockage: ____􀁾_______􀁾􀀠Barricade Sketch Attached: ( ) YES ( )NO Contractor to supply barricades as required by state and local codes. The applicant acknowledges his liability for the work and related hazards. The contractor is responsible for relocation or replacement of trees and existing ground cover which are required to be moved in connection with the permit work. ________________________Phone: ____􀁾__________ AppllcIIIII'S Signatun: Expiration Date: Estimated Completion Date: ;:---,---,:c:---".,.---Nore: The estimated completion date sball nontllllly be fifteen (I S) working days from dare of issue. However, for large jobs, exceptions may be considered. 1llSpettol Assigned: ______________Phone: __􀀮􀀮􀁺􀀮􀀹􀀡􀀮􀁊􀀷􀀲􀀻􀀺􀀺􀀭 􀀴􀁾􀀶􀁾􀀶􀀺􀀡􀀬􀀧􀂷􀀳􀁾􀀲􀁑􀁉􀁉􀁬􀁑􀁾____ ( ) Approved ( ) Disapproved Dare Issued: ______________ COMMENTS: CONTACT INSPECTOR BETWEEN 7;30 -8:00 AM FOR INSPECTION. Contact Public Works Department for line locations in field -972-466-342S. Contact Traffic Department for line locations in field -972-446-3606. Contact all Public Utility Companies for line locations. I. Orilinal-C...t....er (nile) WIlEN TRAFlIIC IS RESTRICTED FLAGMEN 2. la.p••lOr (pink) WIl.L liE tlTILlZED. 3. S_IIhopt. (....a.y) ALL WORK TO BE INSPECTED BEFORE 4. Water Dept. COVER.ING. 5. Tram. TOTAL P.01 ---15150 Surveyor ell/d. Telephone (972) 361-0064 The HNTB Companies Addison, TX 75001 Facsimile (972) 361-0065 En9int'!l'!rs Archlte<:ts Planners www.hntb.com Mr. Ben Withered HNTBProject Manager Archer Western Contractors, Ltd. 2121 Avenue"J" Suite 103 Arlington, TX 76006 Re: Shutdown of 60" DWU main January 19, 2005 Dear Ben: Yesterday the Town ofAddison was notified by Farmer Branch that the instal.led "interconnect" would not satisfy the requirements of the City of Farmers Branch water supply system while the 60" water main is shutdown. At the present time the Town of Addison is making arrangement to hold a meeting with Dallas Water Utilities and designers on a possible solution. The Town of Addison is requesting Archer Western Contractors, Ltd. to reschedule the work on the 60· DWU main until such solution has been work out with Dallas Water Utilities. At the present time the Town ofAddison is attempting to expedite a solution so the work may began on/or about January 25, 2005. Please advise us of any any actions you will take. Thankjl iJSJ---Guy Van Ba4n HNTB Corporation Cc: Steve Chutchian, Town of Addison Jerry D. Holder, HNTB Corporation Michael Ebeling, HNTB Corporation Archer Western Contractors January 19, 2005 HNTB 5910 W Plano Parkway Plano, Texas 75093 Attn: Mr, Guy Van Baulen RE: Town of Addison 60" Water Main Delay Dear Guy: Archer Western Contractors has received your letter dated January 18,2005 requesling that we reschedule the installation oflhe 60" waterline starting on or after January 19,2005, At this time we can not proceed as your letter stated, because we have contacted DWU operations manager David Robinson this morning and he is unaware ofany request by the Town of Addison to schedule a shut down of the 60" waterline, My previous letter dated January 11,2005 asked for written authorization to begin work when all items have been resolved. We can not begin this work due to unresolved issues of the Town ofAddison and DWU. Please forward this approval immediately. Upon receipt, time Archer WeStern Contractors will reschedule this work ilem and evaluate Ihe impact that this delay has caused to our production costs and to our schedule. If you require additional additional information, please contact me aI817-640-3898 or 817-401-7202. Sincerely, 􀁾􀀠Ben Withered Project Manager Cc: Don Good 2121 Avenue J, Suite 103 At1ington. Texas 76006 Phona: 817.640.3898 Fax: 817.640.8734 WVNI.walshgroup.com A Member of The Walsh Group An Equal Opportunity Employer IUIT8 CotJlOl.tIow 15150 Surveyor Blvd. Te(ephone (97.(.) 361-0064 The HNTS 􀁃􀁯􀁭􀁰􀁡􀁮􀁬􀁾􀀠Addl$Ol\ TX 75001 Facsimile (972) 361 • 0065 EnQineers Archftects Planners WW\¥,hntb.com Mr. Ben Withered HNTBProject Manager Archer Western Contractors, Ltd. 2121 Avenue'T' Suite 103 Arlington, TX 76006 January 18. 2005 Dear Ben: The Town of Addison had requested Archer Western Contractors, Ltd. to reschedule the work on the 60" DWU main until such "Interconnect" can be completed. At the present time the Town ofAddison has completed this work and anticipate the testing by Farmers Branch to be completed by January 19, 2005. This letter is to notify Archer Western Contractors. Ltd. to reschedule the work for the lowering of the 60" DWU main to start on or after the January 19th• At the present time. the Town of Addison is submitting a formal request the Dallas Water Utility for the shutdown of the 60" main on or after January 19th for this contract. Please advise us ofany actions you will take. Thank you, 9f I. 􀁾􀁾􀁾􀀷􀀠􀀬􀀰􀁾􀀠Cc: Steve Chutchian, Town of Addison Jerry D. Holder, HNTB Corporation Michael Ebeling. HNTB Corporation III(1'8ICowpw lla_ 15150 Surveyor Btvd. Telephone (912) 361 􀁾􀀠0064 The HNTS COmpaniu AddTson. TX 15001 F...lmJl. (912) 361 • 0065 www.hntb.com􀁅􀁾􀁮􀁬􀁲􀁥􀁲􀀵􀀠ArcNttcts Plamers 􀁍􀁾􀀮􀀠David Robinson HNTBOperations Manager Pumping Division 2900 White Rock Road Dallas. 'IX 75214 Arapaho Road -Phase illProject January 12. 2005 Dear David: Three weeks ago. Archer Western Contractors. Ltd. scheduled a meetiog with you on the procedures for the loweriog of the 6O"main and to schedule a test shutdown for the section of the DWU 6O"maio and the associated valves. Duriog this preparation for ,the test shutdown of the 6O"main that next day. DWU notified Archer Western Contractors. Ltd. that a issue had arose with the shutdown of the 60"maio. DWU found that the water supply connection for the City of Farmers Branch was on the closed side ofthe valve. which would tum off the water to the City of Farmers Branch Marsh Lane Pumpiog Station. Since that time, The qtyofFarmers Branch has been performing tests on their system to determioe ifthey would be able to maiotaio pressure and volume wben the 60" valve is closed on their system. The City of Farmers Branch has determioed that they will not be able to maiotaio the required pressure beyond 48haUl'S. Upon the notification of this issue. the Town ofAddison and the City ofFarmers Branch began working on an "interconnect" that would supply Farmers Branch duriog the work on the 60"maio line. This "interconnect" must be installed and operational, prior to the shut down of the 60" maio line. The Town of Addison has requested Archer Western Contractors. Ltd to reschedule the work on the 60" DWU main until the referenced "interconnect" can be completed. At the present time the Town ofAddison iSiattempting to expedite this work and anticipates this work to be completed on or about January 19. 2005. We wanted to keep you informed of this matter. 􀀬􀀮􀀢􀀮􀁾􀀠,p tiD . 􀀧􀁾􀁁􀀴􀁈􀀠􀁾t-Guy Van Bauler-EIT HNTB Corporation Cc: Sieve Chutcl1ian, Town ofAddison Erling Holey. Dallas Water Utilities Cassia Sanchez, Dallas Water Utilities Katura Curry. Grantham & Associates Jerry D. Holder. HNTB Corporation Michael Ebelin2. HNTB COl'J)oration .•, ))) 􀀮􀀬􀀬􀁾􀀠 Archer Western Contraotors January II, 2005 HNTB 5910 W Plano Parkway Plano, Texas 75093 Attn: Mr. Guy Van Baulen RE: Town of Addison Project No. CM 95 (150) 60" Water Main Delay Dear Guy: Archer Western Contractors has received your letter dated January 10,2005 requesting that we delay the installation of the 60" waterline until an "Interconnect" can be installed by the Town of Addison and the City of Farmers Branch. This work was originally scheduled to be started November 2004 but already has been severely delayed due to the numerous changes by Grantham & Associates and DWU. As a result our utilization ofequipment, schedule and other resources has been severely impacted due to these repeated delays. Our revised schedule shows that we were to begin work on the 60" waterline again beginning January 10, 2005 as was coordinated with HNTB and DWU. However, at your request Archer Western Contractors will cease all operations pertaining to the 60" waterline until we receive written authorization to begin work. At that time Archer Western Contractors will evaluate the impact that this delay has caused to our production costs and to our schedule. Ifyou require additional information, please contact me at 817-640-3898 or 817-401-7202. Sincerely, 􀁾􀀠Ben Withered Project Manager Cc: Don Good A Member of The Walsh Group2121 Avenue J, Suite 103 An Equal Opportunity EmployerArlington, Texas 76006 Phone: 817.640.3898 Fax: 817.640.8734 Archer Western Contractors Januaryll, 2005 -HNTB 5.910 W Plano Parkway Blano, Texas 75093 Attn: Mr. Guy Van Baulen RE: Town of Addison Project No. CM 95 (150) Traffic Control at Midway IDearGuy: Arcber Western Contractors received your letter dated January 8, 2005 concerning the Midway Road traffic detour. Archer·Westem has reviewed you request to adjust the low profile concrete barriers at the Midway detour and offers no objection to this proposaL However, the traffic striping and lane width will remain as it was originally outlined due to the construction phasing requirements. We will adjust the barrier backwards slightly from the current I' offset to allow more room for navigation. In addition Archer· Western requests approval to place work zone pavement markers consisting ofa 4" white solid edged line which was not shown in the original drawings. Archer Western Contractors requests that the Town ofAddison increases the traffic enforcement in the Midway work area to help reduce the speed of the traveling traveling public and to increase public safety in the work :rone. Archer Western Contractors also stands by our original proposal to reduce the traffic to one lane each direction wbich would promote the safe, efficient passage through this :rone and we request that HNTB re· evaluates this proposal for approval. Ifyou require additional information, please contact me at 817·640·3898 or 817·401·7202. Sincerely, Project Manager Ben Withered Cc: Don Good 2121 Avenue J, Suite 103 Arlington, Texas 76006 Phone: 817.640.3898 Fax: 817.640.8734 A Member of The Walsh Group An Equal Opportunity Employer ....ICO'JIIIiI I'I 15150 􀁓􀁾81vd. T.I.phone (972) 361-00Q4 The HNra Companfn: Addison. TX 75001 Facslmlle (972) 361-0065 Engineers Architects PJmners www.hntb.com Mr. Ben Withered HNTBProject Manager Archer Western Contractors. Lui21i1.1 Avenue jn Suite 103 Aiiington, TX 76006 January 10,2005 Dear Ben: DUring testing for the shutdown ofthe 60" DWU water main, it was detennmed that the water supply to the City of Fanner Branch was on the closed side ofthe valve. Siilre that time, 'The City of Fanners Branch has been perfonning test on their system to detennme ifthey would be able to maintain pressure and volume when the 60" valve is closed on their system. 'The City of Fanners Branch has detennined that they will not he able to maintain the required pressure beyond 48hours. At this time. the Town of Addison along the City ofFarmer Branch are working on an «interconnect" that would supply Fanners Branch during the work on the 60"main line. But this "interconnect" must be inStalled and operational. prior to the shut down of the 60" main line. 'The Town ofAddison is requesting Archer Western Contractors. Ltd. to reschedule the work on the 60" DWU main until such "Interconnect" can be completed. At the present time the Town of Addison is attempting to expedite this work and anticipate this work to be completed on or about January 25. 2005. Please advise us ofany actions you will take. 􀀧􀁔􀁨􀁾􀀱􀁊􀀠d􀁾􀁮􀁾􀀶􀁾􀀠HiNTB Corporation «__􀁪􀁬􀁾􀁩􀁩􀁾􀀮􀁾􀁩􀁾􀀮􀀿􀁦􀀡􀁩􀀵􀁾􀁧􀁾􀀡􀀺􀀯􀀠Jer ry D. Holder. HNTB Corporation Michael Ebeling. HNTB Corporation J 5150 Sun"eyor Blvd Addi.w:m, TX 15Df)I1:1= ,., i i=JARCHITECTS ENGINEERS PLANNERS 􀀹􀀭􀀲􀀭􀀮􀁊􀀶􀀡􀁾􀁦􀀩􀀰􀀶􀁊􀀠F.·l"'-9";2-.56/·1)0(,5 􀀻􀁮􀁆􀁾􀁬􀀢􀀮􀁩􀁬􀁬􀀱􀁬􀁾􀀮􀁣􀁯􀁭􀀠December 22, 2004 Archer Western Contractors, Ltd. 2121 Avenue "J" Suite 103 Arlington, TX 76006 Attention: Mr. Ben Withered Re: StOml SewerLine 'C' RCP pipe lDear, Mr. Withered In an attempt to prevent existing ground water from infiltrating into the above referenced 􀁤􀁲􀁡􀁩􀁮􀁾􀀠s[Vstem, the Town ofAddison is requesting Archer Western Contractors, Ltd. to proceed with the installation of the Confined Groove Joint (O-ring) Reinforoe Concrete Pipe for all RCP to be used between the Station 0+68 to Station 6+00 on the above referenced system. Archer Western Contractors, Ltd. is directed to proceed with the work described above not to cause any delay in the job schedule. All work and material is required to confoml to the contract specification. Thank you. Regar:& dbJ----GuyVanBa+ I1!NTB Corporation Attachments: I, ,': ct:: Project File Jerry D. Holder, HNTB Corporation TheH!NTH CompanllU 􀁏􀁦􀁆􀀡􀁃􀀧􀁅􀁓􀀺􀀧􀁁􀁛􀀮􀁅􀁘􀀬􀁜􀁽􀀬􀀱􀀩􀁒􀁲􀁾􀁜􀀠VA: 􀁁􀀮􀀮􀀭􀀧􀀺􀁾􀀬􀁜􀁰􀀨􀀱􀁉􀀮􀁬􀁓� �􀀬􀀠􀁾􀁉􀀧􀁄􀀺􀀠Alt.\»,'A GA; AlISTI}/'. 1X n,\TON II/'Jt.'E. C,\! KM_$'\'s CITY. Telephone (972) 361-0064 Engineers Architects Planners Addison IX. 7$001 facsimije (972) 361-{)065 Tn. HNTB Compo_"'" 15150 Surveyor Blvd. www.hntb.com HNTB Job • 25768 VIA Arnpaho Road· Ph... III Datto loo.aty19,2005 To: Steve ChutthianLetter of Town ofAddi"", :-INTBTransmittal P.O. Box 9010 16801 Westgrove Drive Addison, TX 75001 CPM Schedule We ..... fo..enllnQ to Y'" Estimates Plans X Prints Reports Shop Drawings Samples __ Change Order Disk Copy of Lett.r Book Other [~E_ # of Copies Drawing ** Last Dated Code Description 10122/05 L ICPM Schedule (24'x 36' me) JO{22105 􀁟􀁌􀁾􀁾􀀠I CPM 􀁓􀁣􀁢􀁥􀁤􀁾􀀮(FuIlslze) ___􀁾_____ The..«e tren.mJHed: For approval As requested Copies for distribution 􀁾 For your use Resubmit For Review & comment Return Copies for review No exception taken Corrected prints Submit Amend and resubmit Make corrections noted By: GuyVanBa.Ien,EIT 􀁾􀀠Copy to: File ):]VC page 1 or I Guy Van-Baulen From: Cassia Sanchez [casanch@mail.1 􀀢􀀭􀁾􀀠tv usl Sent: Tuesday, January 18, 2005 8:41 To: 􀁫􀁣􀁵􀁮􀁹􀁀􀁧􀁲􀁡􀁾􀀮􀁮􀁥􀁴􀀻􀀠Guy Van-Ba Cc: Tonia Lichtenberg Subject: Re: DWU 60" Air Release Val\\, I The fonowing is the contact informatil which deals with all DWU customer cities: /Tonia Barrix Wholesale Services 4AS Dallas City Hall 1500 Marilla DaJ1as,TX 75201 PH. 214-670-5886 Email: 􀁴􀀱􀁩􀁣􀁨􀁴􀁦􀁀􀁭􀁡􀁬􀁬􀀮􀁣􀀻􀀺􀁩􀀮􀁾􀀮􀀮􀀡􀁬􀀱􀁡􀀡􀀮􀁾􀁴􀁸􀀮􀁵􀁦􀀠»> "Katura Curry" 01/10/05 11􀀺􀀺􀀼􀀺􀀬􀀬􀁾􀀮􀁟􀀠Guy I Andrew, I just got off the phone with Cassia at DWU. She sent RFI #49 regarding the air release valve onto the Distribution Department for review. Their comments were as follows: 1. Type '2' • they would like to see it moved under the sidewalk, as the original plan indicated. It looks like this would be possible even using the current location of the flange off of the 60" RCCP. 2. Type '2' • the air vent should be extended onto the DWU property behind the fence, per the plan notes. 3. Type '2' -to understand the drawing belter, dimensions are needed. 4. Type '1' -dimensions are needed. The manhole can not extend more than 4 feet above the ground level. Please let me know if you have any questions. t.diu 􀁾,,). 􀁾􀀠Cassia -please correct or add to this as needed. 'to\, "Soh" 􀀮􀁯􀁾􀁉􀁬􀀺􀀡􀁲􀀢􀁾􀀠Thanks, Katura ChArles 0'.l-t lI')7Y< --Katura Cuny, P.E. Grantham & Associates, Inc. (972) 864-2333 ""3't1n rJ .1s0(\ KrwJ.'a 􀁦􀁰􀀮􀁹􀁾􀁹􀁜􀀠 fl"AV)k. 􀁢􀁲􀁾f) 1/18/2005 PAGE 01/03GRANTHAM9728642334Dl/34/20D5 08:52 ... Facsimile Transmittal Date: 01 I0 3/05 From: Fax To: :TE"II\IY h-II ce VtJl1t-,IDf:i2.. Of: :JQiA.IN Df-IEolsotJ Fad (:'172.)450-2857 Ref: 􀁁􀁧􀁾-PDI r:sr5 IDJ Ita\LIe:. # ofPages (inclllding tbis sheet):,5 Fax From: Comments: Grantham & Associates. Inc. 1919 S. Sbiloh Rd. Suite 310, L.B. 8 Garland, Texas 75042 Tel. (972) 864·2333 Fax (972) 864-2334 Email: In[o@gra-ce.net _IlIIi'om disct....", ••d,.-.ppliubl.l.w. UtiIc: _.rllli>""""",,;.no( tiIc: !....dcd ,..ip!..􀁾􀀠or til< cmplQ)"" '".....' 􀁾􀀢􀁢􀁴􀁣(gt dc1i'lt::liaC_ k mcI$$Ir;e 19 􀁾ink:ndQlS m:ipiCllt. )'OlI1Ih: hcn:by noUfied tlIit'lRl" dW<¢miftatioA. dLstribuDO'l Of' UJPrmc at thiS cotmUlk:sti. it lItrictly prohlbikd. If)'W blve ro:.dYDd this: t.oft't'Unic.alkin in crt1X'. pteuc:notil) '"' 􀁩􀁭􀁲􀁮􀁯􀁤􀁩􀁡􀁫􀁬􀁬􀁾tdq,hOtK. and 􀁾􀁉􀁵􀁭􀀠the orIeintl mc:w,c 101) Wla\ 􀁌􀁨􀁣􀀮􀁾􀁾via Ute U.s. tostl1 SeMef. Thlnk)'Otl. 1 ,\ \ ",\ 1 I h \ \, \ I ,\ I I I 􀁾􀀠\ I I \\ : I J \ " I I i \ \! I 􀁾􀀠 II 􀀮􀁾􀀠l i\ \ 'I,\! I \ \ I I \ \ \ \! \ i I I II ) \ ! r' I It o i! i 1: \ ! I I II \; I i I, \\:! I II I I , II , /1 I II f I II 1 I I !I 1 I /1 , II /1' ,. II I !I J I 1 I II ,: : I!/1 1 \ \ 1 \ \ 1 \ \ \ \ 1 \ \ 1 \ \ \ \ 1 I \ 1 I I 1 I I 1 I 1 I 1 1 1 1 1 1 1 I \ 􀁾􀁶KYJI"P' STA 35+00 (Line A STA -1+14) (View Looking East) 8" PVC = 595.24' Existing Ground Elev = 596.53' ExiSting 3" Condeit 􀁾􀀠Existing i2" WL Top PiPe 5Q4. 22' \ iii I 􀁾Appro> Top Pipe • 5Q5. 74" I 􀁾􀀠7_SJi 7__{$ Existing Phone Line Top Pipe: 594.22' Existing 24" WL Top Pipe = 586.12' Line 8 FL Elev = 588.30' Line A FL Elev = 588.30' EXisting 66" Storm Drain (3 Each: Typ)FL Pipe = 588.40'􀁾􀁾􀀯􀀱􀀠-) r-,:;,-r .. PIU'P, 8 '/(Af)PI's(JIfI) e(JIIIC£rm:8l.t?lKIN(j p, v,C: ItBIfVI'>/J1V ext;r, 1Ji!V>r f£}((Sr. B' II (", v. c. (AOO/5P/II) g"c,x eAST 8t.III'('/<:W'i (It P1)(51P1V)vAl.V€ • fJF PRIPP; TeG' C"II''CR€'fli'' rHf!!V>T t3 l. ""'1<: lAIr;; . . L ''\..0fRPP:g,;''X'8'1I !f..1.H-:..tI'I-If, ;)//1pf'(;Yfi S(. 􀁾􀁥􀁹􀁇􀀧􀀠(f1RtI1€RSeR/lAlcH) . ¢ VAt. vc ;ll/t::ITE: CIPtf,rTACr A<...L r'tFFI!ECTEt:> Pff!PPI!EIProposed 8" Water Interconnection START ,pr.AddisonIFanners Branch COIV.s.rRI/£ T(QA.-January 2005 IREQUEST FOR INFORMATION PROJECT No. Arapaho Phase III RFI # ____􀁾􀀵􀁾􀀰_____ Date: January 3, 2005 Schneemann 12" Waterline · sec Phone Line · 8"Force Main -Abandoned -Possible casing for Rail Road Intercept · 3" Gray conduit -Unknown line A Station -1+59 3" Gas Line (PVC) -Top of Gas Line 594.03' -Top of Line A & B 10x6 RCB 594.89' IThe SanilarySewer line from the Pump Station Building is in conflict with the pipe and Inlet on Lateral 2. Direct us how to Proceed with these conflicts Page 1 CHANNEL T H R E E p R o D u c T o N s January 7, 2005 Ms. Jenny Nicewander Town ofAddison P.O. Box 144 Addison, 1X 75001 Dear Ms. Nicewander, In order to minimize the costs for this project, I will hald offon sending VHS dubs and CD's after each shoot -they would eventually start cluttering your office anyway! Instead I will wait and put several shoots on one tape and one CD, unless ofcourse you desire otherwise. So far, I have been out to the job site 4 times sinee December 91h and have billed a total of$925 (which averages $231.25 per shoot/week including materials). I spent a little extra time at the onset to capture all that had taken place and now can focus on just significant developments. So, in short, I think we are track with getting what you need for an eventual award-winning video while controlling costs. Should Charter Fumitute agree to let us install the time-lapse camera, rwould like to work with you on the budget because I still feel this would add a great deal to the video. As far as costs, looking at my proposal, the total for installation/materials/labor is $4,000 plus the camera which rput in $2,000 for, but I can buy that back from you. Then I budgeted an how: and a half a week for one-year to monitor and maintain the time-lapse, but it could probably be accomplished in only a half how: per week, which would cost only $2,600 over the cost ofa year. This totals $6,600 plus the cost ofa carnera, which I can buy back from you. Let me know ifthis helps at all. I appreciate you keeping me informed with yow: needs on this project. Please do not hesitate to contact me with any questions or requests. 􀁓􀁩􀁮􀁊􀁦􀀺􀁐􀀧􀀯􀁾􀀠􀁂􀁲􀁾􀀦􀁥􀁫 􀁢􀁥􀁲􀁧􀀠President 1103 N. COTTONWOOD DR, SUITE 1 • RICHARDSON, TX 75080 (972) 671-4466· Fax (972) 671-9364 http://www.channeI3.com •• 1/11/2005 ARAPAHO ROAD T Current Week Next Week Following Week Artlher'Al!!g!ern ccrrtmctMlST W F T SISM T W T SIS T SIS M W T FF MActivity Description Prod 11 12 21 26 27 28 SUBS/NOTES10 13 14 15 17 18 19 20 22 24 25 X X IXExcavate/Embank Brickyard X X//Box Culvert Line A (Surveyor) 0 N 0 I DH /\ \ 􀁾􀀧􀀮􀁜􀀩􀀠f>rul 􀁢􀁾􀁾􀀠VBox Culvert Line A (east) X XX X X X X X X X X XX X X X //Box Culvert A ( Midway) 0 N H 0 L D //􀁃􀁍􀁯􀁴􀁾􀀠(Box Culvert Line B 0 N H 0 L D //Ml.LJ r"" .1. uRoadway Embankment X X X XX///􀀮􀀺􀀺􀁲􀁾,d' .t_O.1Lower 16" Water Line Q. \..; \ X X X /."" rn C\LJ h" 􀁉􀀧􀁾􀀠rz;f-1.-IB ., /1/d10" Sanitary Sewer X XX X X X XX X X Line C & Laterals X XX X X X X X X X X X XX X X /Laterals Line A & B X X X X XX X X X X XX X //X 1/X /-/' /' X X X X X X X X ,Trenched Retaining Walls i f\ \Livyl eM. X X LoneStar Trenching \.)CIP Retaining Wall X,,/X X X X /' i /' L L !Drilled Shafts X w, . ..L lG ATSX L Caps XX X X X X X X X X X X X XX X X X /' ,Bent # 10 Cap X X X X X X ,/X X ,,//' Bent # 9 X X X X XX X X X X X X X XX X /' i/' /' XI'60" Water Line (DWU) X X X XA\ 􀁾􀀠X II ! " b,...P -r'" ----Weekly Meeting Agenda Date: Tuesday Janll, 2005 Arapaho Road Phase III Time 10:00 A.M. Location: Field Office I. Safety Issues 0.Keep up maintenance on orange fence .• .V'2.Maintain 4" reflectors. Several reflectors have came up. 􀁾􀁣􀁫􀀮􀀮􀀠liliorl 􀁾peU 3. HNTB 􀁲􀁥􀁱􀁵􀁥􀁳􀁴􀁳􀁾􀁤􀁩􀁴􀁩􀁯􀁮􀁡􀁬message boards be added to the Midway detour and left up for an,undiscioseTarnount oftime after the traffic is routed onto the detour. A/W will be compensated for the message boards. A/W will write a letter requesting compensation for the message boards. A/W picked up four ofthe five message boards on Monday 12-27-04, per HNTB. HNTB requested A/W to set reset the four boards on 1-3-05 for two more weeks. Additional striping was added to the Midway detour on 12-28-04. When are we to remove the message boards? II. Submittals 1. Bar lock samples were given to Daniel Filer. Texas Concrete must sign off on block outs. A RFI needs to be generated for Cliff Hall to sign off on. A RFI has been sent, Cliff Hall has not signed off on it yet. 11-30-04 The RFI was verbally not approved by DRS. AJW requested a product to use.lI-30. We have received a weld detail for the splice on 12-3. A/W is reviewing the detail. Additional details between A/W and HNTB need to be resolved. CliffHall will stamp drawing 12-17. Received Revised Plan Sheet -Shop Drawing Being Revised The documents were received by HNTB on 1-3-05. 2. The MSE wall shop drawings have not been returned to A/W. A/W should have them by Friday perHNTB. Have Not received Shop Drawing received Revised Wall Sheet for Wall #3 12-23 Revised Shop Drawings for Wall #3 will be here 1-5 HNTB is requesting a running bond pattern. wdf 3 -.wt vn &rJ:5 .w/fI.:m :Jkd 􀁾􀀠NChJr' 􀂣􀁩􀁾􀀠&-. III. Old Business 1. A new Irrigation plan sheet for Comfort Suites is forthcoming. AJW received the revised plan sheets on 12-2. American Landscaping is pricing. HNTB should have this by 12-21. HNTB should have pricing from Andrew by 1-7-05. 2. The Town asked about the paint submittal for the arches. Ben explained that system II paint is not tenable. A similar painting system will be submitted. A letter from Sherman Williams has been given to the Town.II-2. The Town is leaning toward the Tnemec paint for the arches. 11-30. A meeting was held on 12-1 for the rail painting. 12-7 HNTB said to proceed with thll Tnemec paint. , Ben is reviewing pricing. Lotil(l /tIf2R..i 􀁾􀁾P;1 :}tt¢ 3. The roadway grades at the brickyard will not tie into the Railroad tracks. Jennie is looking into this. 10-26. HNTB needs a RFI from AJW. The grades will be adjusted. 11-2. Andrew and HNTB will review the grades today. 11-2. AJW has requested a revised plan sheet for this area. 11-30. HNTB is in the process ofrevising plan sheets. Nothing yet.l2-28. No reply yet 1-04-05. IV. Change Orders 1. Irrigation lines at Comfort Suites. HNTB should have pricing by 1-7-05. 2. Tee for irrigation line off 16" line. HNTB should have pricing by 1-7-05. V. New Business I. A traffic control plan has been submitted to the Town for detouring Surveyor Blvd. during construction at this location. The town does not want to salvage any ofthe plants at the pump station. Has this TIC been approved? -==> 2. After field verifying the elevation of the relocated SBC line, there are several areas where the new line will be in direct conflict with the slotted under drain pipe, the retaining wall, and inlets or laterals. 11-23-04. Guy asked that Chris go with him to the various locations. Work needs to proceed on these items. What is being done about the following phone line conflicts? # 1. Lat. A-SD # 2. Lat. AS-C # 3. 12" slotted drain #4. RW. #2 HNTB has said that SBC will have labor help at the site during the laying ofthe CMP to move the line ifnecessary. There are defendant conflicts, why can't SBC move the line now? 3. The location ofLat. B-7 and the Y inlet need to be verified so this work can be completed. An answer was received by AfW, but a problem still exists (b"SS 0'< 􀁢􀁾􀁃􀁴􀁕􀀠􀁴􀁬􀀯􀀧􀁾V. Mise. 1. A RFI has been sent to HNTB about gas,water,sewer and telephone. conflicts, with lines A & B, at Surveyor Blvd. VI. Schedule 1 Review Weekly Schedule IREQUEST FOR INFORMATION PROJECT No. Arapaho Phase III 􀁒􀁾􀁉􀀠# __-=5:::.2__ Date: January 11. 2005 ReYlewthe attached Plan view and section. iArc:h.., WostE 􀂷􀀩􀀧􀀺􀀻􀂷􀀧􀀺􀂷􀁾􀁩􀀠-􀁾􀀺􀀬􀀧􀀢􀀠􀀻􀁾􀀻􀀠,.>;, .-' '. ': . _": ,', 􀀢􀀭􀀺􀀺􀀻􀁾􀀧􀀻􀁜􀀠\;:.-'" .􀁾􀀭􀀻􀀭􀀻􀀻􀀭􀁳􀀭􀀻􀀮􀁾􀀬􀀠Surface Conditions: ·New Fabril;ated. Steel Total S.F.: 4603 System: SSPC -SP6 Blast, 1 Coat 2 niils DFT Sherwin WiIliaJ1)s 3.0 -5.0 mils DFT, Finish is Sherwin Wi!1iams Fast Clad Urethane, 6.0 -9.0 rriils DFT, Color is frank Blue Prep. Reg. 􀂷􀁉􀀺􀀮􀀾􀁃􀁉􀁘􀁉􀁾􀁉􀀠SP-6 1>"<:1><] Other: AllchorProfile Tape Inspection: Standar!f QAlQC Reports to job File 􀁾t;:. 􀀧􀁾􀁜􀀢􀀬􀀧􀁟􀀻􀀻􀁜􀀧􀁩􀀼􀁜􀀺􀀮􀁲􀀭􀀻􀀺􀀬􀀻􀀺� �􀀺􀀬􀀬􀀺􀀻􀀧􀀻􀀮􀀺􀀻􀀻􀀮􀀢􀀺􀀬􀁊􀁴􀁜􀀧􀁚􀀧􀀺􀁾􀀧􀁦􀁨􀁾􀀧􀀭􀀢􀁓􀀬􀀮􀀻􀀮􀁲􀀻􀀧􀁾􀁾􀀺􀀭􀀺􀀺􀀧􀀱􀁴􀀻􀀩􀀱􀀬􀀻􀁾􀀧􀁬􀀧􀀷􀀧􀁩􀁾􀁾􀀪􀀺􀀧􀁩􀀱􀁊􀁾􀀺􀁉􀀮􀁾􀁲􀁾􀁾􀁴􀁾􀀡􀁛􀀢􀁾􀀢􀀢􀁦􀁩􀁲􀁾􀁬􀀻􀀧􀀺..􀁾􀀺􀁜􀀭., ';. -':-: ""U.\:·i,;:i' \". "'. 􀀺􀁾􀁆􀀠-'-.,-?!,:".-􀁾􀀬􀀬􀀭􀁟􀁾􀀯􀀬􀀪􀀭􀀬􀀠􀀧􀀺􀀺􀁏􀁾􀀬􀀧􀁩􀁾􀀧􀀻􀁾􀀠":';,"" 􀀬􀁾􀀠';: 􀁾􀁩􀂷􀁾􀁾􀁬􀁜􀁾􀂷􀀧􀀺􀀧􀀮􀀧􀀯􀀠􀂷􀀬􀀺􀀢􀀺􀀢􀀮􀀬􀁾􀀬􀀮􀀬􀀬􀂷􀁴􀂷􀀬􀀬􀀠,j," , 􀀬􀁜􀁾􀀮􀀧􀀠,,..' .': -'.'-􀁾􀀢􀀻􀀧􀀮􀀢􀀢􀀢􀀢􀀠Paint Specs: Mfr: Sl:ierwin Williams Primer: Ziny Clad III liS MiLS Wet . 5.0 -. 8.0 MILS Dry 3.0 .. 5.0 Gray-Green 2nd Coat: Fast Clad Urethatte MILS Wet 10.0 -15.0 MILS Dry 6.0 -9.U Frank Blue 3rdCoat MILS Wet MILS Dry...;.___ Other MILS Wet MILS. Dry 6.07Industrial ZINC CLADTM III HSand ORGANIC ZINC-RICH EPOXY PRIMER Marine PARrA 869A100 BASE PARTB 869V100 HARDENERCoatings PARTF 869011 ZINC DUST PRODUCT INFORMATION Revised 2/03 ZINC CLAD III HS is a ihre!H:Omponent, polyemide epoxy, For use over properly prepared blasted steel. zinc-rich coating. Hhas a low VOC level and contains 90.5% • Fabricellon Shops by weight of zinc dust pigment in Its dried film. • Bridge and Highway Siructures • Meets Oass B requirements lor Slip Coefficient and Creep • Stadiums and Sporls Complexes ResIstance, .52 • Onlllng Rigs • Provides cathodic protection • PIping • Damaged film exhibits "self-healing" propEllties • Refineries • Fast Recoat Time • BaJl)eS and Ships • Contains Micaceous Iron OxIde • Shop or Aeld Applicatlons • Not recommended lor immersion ..Nice. Finish: Aat System TlNIIed: (unless otherwise indicated) Subetrate: SteelColor: GraYil_n Surface Preparallon: SSPC-SP10 1 ct. ZInc Cled III HS @5.0 mils dft Volume Sollde: 60% ± 2%. miXed 1 ct. Macropoxy 648@5.()"10.0milsdft Weight Solids: 90% ± 2%, mixed 1 ct. Acrolon 218 HS @5.0 mil. dft VOC (EPA Method 24): Unraduced: 336 gil; 2.80 IblgBI Adhesion:mixed Reduced 5%: 360 gil; 3.00 Ibigsl Method: ASTM 04541 ZInc ConlDnt In Dry Aim: 90.5% by weight Result 2403 psi Oo""810n Weathering MIx_o; 3 components, "",measured Method: ASTM 05694, 13 cycles, 2016 nouns3.25 gallons total Result; Retlng 10 per ASTM 0610 for rusting Recommended Spreading Rate per coat: Reting 10 per ASTM 0714 for blistering Wet mils. 5.0 • 8.0 Dry Haat Resletenc&, zinc only: Dry mils: 3.0 • 5.0 Method: ASTM 02485 COverage: 190 -320 sq fIIgal approximate Result 300"FNOIe: Brush appllcallon Is for stripe coating and smalla...as only. MOIsture Condensation _ialence: Method; ASTM D4585, l00"F, 4000 hounsDrying Schadul&i 5.0 mils wet@50% RH: Result Rating 10 per ASTM 0610 for rusting To touch: minutes 30 minutes 10 minutes 40"F @7T'F @120"F Rating 10 per ASTM 0714 for bllstertngTo handle: 2 houns 1 heur 30 minutes Pencil Hardness. zinc only:To fecoat*: Method: ASTM 03383minImum: 4houns 2houns 1 heur Rasult 2Hmaximum: 1 YINIr 1 year 1 year To ...... : 10 deys 7 days 7 days Selt Fog Ree1eten...: Pot life: 6 houns 4houns 2 heuns Method: ASTM B117, 4500 heuns Sw""t.(n-llme: 1 heur 30 minutes 15 minutes _ult Rating 10 per ASTM 061 0 lor rusting Rating 10 per ASTM 0714 for blisteringDIylngtimels _pemlure, humidity, endlllmlh_dependent Slip Coefficient. zinc only:􀀧􀁎􀁏􀁔􀁅􀀺􀁆􀁬􀁬􀁭􀁭􀁬􀁬􀁓􀁴􀁢􀁥􀁟􀁯􀁦􀁟􀁾􀁨􀀮􀁲􀁤􀁡􀁮􀁤􀁦􀁬􀁬􀁭􀀮􀁗􀁨􀁥􀁮􀁲􀁵􀁢􀁢􀁮􀁤􀁷􀁬􀁴􀁨􀀠Method: AISC Spec!flcation for Structu",1 Joints Using ASTM A325 or ASTM MOO Bolls Shelfllfe: ParlsA. B, & F -24 monihe the lace of. coin or knife thafllm should polish but notllakn or chip. Result Class B, 0.52unopened. at 7T'F Flash Point: 56"F, Seta Flash, mixed Reducer/Clean Up: Below 6O"F: MEK, RSK10 Above 6O"F: Reducer iI58, R7K58 or MEK,RSK10 Zinc Rich 6.07 COnllnuad on back 6.07Industrial ZINC CLADTM III HSand ORGANIC ZINC·RICH EPOXY PRIMER Marine PART A B69A100 BASE PARTB 869V100 HARDENEROJatings PARTF 869D11 ZIHc DuST PRODUCT INFORMATION _.poIyumttoano topcoat: Surface must be clean, dry, and in sound condition. Remove 1 ct. Zinc Clad III HS @3.0 -5.0 mils dft all oil, dust. grease, dirt, loose rust, and oiher foreign material 1-2 cts. AcroIon 218 HS @3.0 -6.0 mils dIIIct to ensure adequate adhesion. Steal, catalyzed epoxy topcoat Refer to product Application Bulletin for dstailed surface prepa1 ct Zinc Clad III HS @3.0 -5.0 mils dft ration Infonnation. 1-2c1s. Macropoxy646@5.0-10.0mllsdlllct Minimum recommended surface preparation: Slael, cstalyzed epoxy topcoat: Iron & Steel: SSPC-SPS, 2 mil profile 1 ct Zinc Clad III HS @3.0-5.0 mils dft Galvanizing: SSPC-SP7 1-2 cts. TIIe-Clad HS @2.5 -4.0 mils dft Wealhered Zinc Rich Primer. Clean. dry, sound Steel, acrylic topcoat: 1 ct. Zinc Clad III HS @3.0 -5.0 mils dft 2 cis. DTM Acrylic Coaling @2.5 -4.0 mils dIIIct or 1 ct. Fasl Clad HB Acrylic @5.0 -6.0 mils dft 00 not tint. Steel, waler based epoxy topcoat: 1 ct. Zinc Clad III HS @3.0 -5.0 mils dft 2 cts. Watorllasad TII&-Clad Epoxy @2.0 -4.0 mils dIIIcl Steel, water·ba_ polyumttoane topcoat 1 ct. Zinc Clad ill HS @3.0· 5.0 mils dft Temperature: 40°F minimum. 12O"F maximum 1 ct. waterbased Tila-Clad Epoxy @2.0 -4.0 mils dft (air, surface. and malarial)1-2 cts. CenturIOn WB Urelhane@2.0. 3.0 mils dIIIet AI leasl 5"F above deW point Relative humidity: 95% maximum Refer 10 product Application Bulletin for dalalled application imonnation. Packllglng: 3.25 gallons mixed Part A 1 gallon PartB 1 gallon Part F 73 Ib Zinc Dust Weight per galton: 27.63 ± 0.2 lb. mixed Refer 10 the MSDS sheet before use. Published technical data and instructions are subject Iochange wiihout notice. Contect your Sherwin·WIIlIams representativeThe systems listed above am represanlative of the product's usa. Olhar systems may be appropriate. for additional technical daIa and Instructions. 6.07AIndustrial ZINC CLADTM III HS and ORGANIC ZINC·RICH EPOXY PRIMER Marine PARrA B69A100 BAsE PARTB 869V100 HARDENERCoatings PARTF 869011 ZINC DuST APPLICA"rION BULLETIN Revised 2103 Zinc rich coatings require direct conlllCl between the zinc pig-Temperature; 40'F minimum, 120'F maximum ment in the coating and the matal substrate for optimum per(air, surface, and malelial) formance. Surface must be dry, free from 011, dirt, dust, mill At least 5'F above dew point scale or other contaminants to ensure good adhesion. Relative humidity: 95% maximum Iran & SIll'" (atmospheric service) Remove all oil and grease from surface by Solvent Cleaning 􀁴􀀽􀀽􀀽􀀽􀀽􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀀽􀀽􀀽􀀽􀁪per SSPC-SP1. Minimum surface preparation is Commercial Blest Cleaning per SSPC-SP6. For betiler performance, usa Near White Metal Blast Cleaning per SSPC-SP10. Blast clean all surfaces USing a sharp, angular abrasive for optimum sur· face pro1lle (2 mils). Coat any bare steel the same day as it Is cleaned or before tilesh rusting occurs. Galvan ..... d Steel Allow to weather a minimum of six months prior to coating. SoiventClean per SSPC-SP1 (recommended sOlvent Is \lM&P Naphtha). When weathering IS not possible, or the surface has been treated with chmmelas or sl1lcalas, first Solvent Clean per SSPC-SP1 and apply a last patch. Allow paint to dry at least one week before _09 adhesion. If adhesion is poor, brush blasting per SSPC-SP7 Is necessary to remove these treatmanls. Rustygalvanlzlng requires a minimum ofHand Tool Cleaning per SSPC-SP2, prime the area the same day as cleaned or before flash rusting occurs. Weathered ZInc-Rich Primer Remove zinc salts by either high pressure water washing and scrubbing with stiff bristie brush or sweep blest followed by water flush. Allow to dry. Note: If blast cleaning with steel media Is used, an appropnala amount of steel grit blast media may be lnoorporalad into the wori< mix to render a densa, angular 1.5 -2.0 mil surface profile. This method may result in Improved adhesion and performance. The following is a gUide. Changes in pressures and tip sizes may be needed for proper spray characteristics. Always purge spray equipment before use with listed reducer. Any reduction must be compatible with the existing environmental and 􀁡􀁰􀁰􀁬􀁾􀀠cation conditions. ReducerlClean Up Below 6O'F ................... MEK, R6K10 Allove 6O'F ................... Redueer#58, R7K58 or MEK, R6K10 Alriess Spray (usa Teflon pacldngs and continuous agitation) Presaura ........... ""...... " 2000 -2300 pai Hose .".......................... 318'10 Tip """"""'''''''''''''''''''' .019" Filter ............................. none Reduction ..................... As needed up to 5% by volume Conventional Spray (continuous agltatlon required) Gun ............................... Binks 95 Fluid Nozzle .................. 68 Alr Nozzle .................... , 68P Atomization Pressure ... 50 psi Fluid Pressut& .............. 10-20pai Reduction ..................... As needed up to 5% by volume Keep pressure pot at level of applicator to avoid blocId09 of fluid line due to weight of malanal. Blow beck coating In fluid Iina at Intermittent shutdowns, but continue agllation at pressure pot. Brush Brush ............................ Small areas only; natural bristle Reduction ..................... Not recommended If spec!flc application equipment is Iislad above, equivalent equipment mey be subatitulad. Zinc Rich 6.07A continued on back Industrial and Marine Coatings Surface preparation must be completed as indicated. Zinc Clad III HS comes in 3 premeesured containers which when mixed provides 3.25 gellons of ready-ta-apply melerial. Mlxtng tll$lructlons: Mix contents ofcomponent A and B Ihoroughly with power agItator. Make certain no pigment remains on the bottom of the can. Then COmbine 1 pert by volume of Pert A with 1 pert by volume ofPartB,then add Part F (73lb zinc dust). Thoroughly agitate the mixture with power agitation. After mixing, pour through a 􀀳􀁾􀀰􀀠mesh screen. Allow Iha material to sweat-in as Indicated. Re-stlr before using. ff reducer solvent is used, add only after components have been thoroughly mixed, after sweat-In. Continuous agitation of mixture during application Is required, oIharwise zinc dust will qUickly settle out. APply peint at the recommended film thickness and spreading rate as Indlceted below; Recommended Spreading Rate per coat; Wet mils: 5.0 -8.0 Dry mils: 3.0 -5.0 Coverage: 190 -320 sq II/gal approximele Nots: Brush applicatiOn Is for stripe coating and small areas only. Drying Schedula@5.0 mtla _@50% RH: @4O"F @77'F @120'F To touch: 45 minules 30 minutes 10 minules To handle: 2 hours 1 hour 30minules To recoat': minimum: 4 hours 2 hours 1 hour maximum: 1 year 1 year 1 year To cure: Pot life: 10 days 6 hours 7 days 4 hours 7 days 2 hours SWaaw...nm&: 1 hour 30 minutes 15 minutes Drying Vme Istemporeture. humidity, endfllm thlckn.ss dependant 'NOTE: Film must be fige ofsolvent. hard end firm. When rubbed with the face ofa coln or knKelhe fllm should poIlsll but notflaks or chip. Application of coating above maximum or below minimum recommended spreading rate may edversely affect coating performance. Clean spills and apaftem Immedlatelywith MEK, R6K10. Clean tools immediately after use with MEK, R6K10. Follow manufacturer's sefaty recommendallons whan using any solvent 6.07A ZINC CLADTM III HS ORGANIC ZINC-RICH EPOXY PRIMER PART A B69A100 BAsE PARTB B69V100 HARDENER PARTF 869011 ZINC OUST APPLICATION BULLETIN Stripe coat all crevices, welds, and sharp angles to prevenl early 1IIIIure in lhese areas. When using spray appUcallon, use a 50% overiap with each pass of Iha gun to avoid hOlidays, bare areas, and plnhol.... H necessary, cross spray at a right angle. Spreading rales are calculated on volume sends and do not Include an application loss factor due to surface profile, roughn.... or porosity of the sulfece, skill and technique of the applIcator, method of application, various surface irragutari.es, meteriatlosl dunng mixing, spillage, overthlnning, climatic cor>dillons, and e_iva film build. Excessive raduolion of matenal can affect film build, appearance, and performance. Do not mix previously catalyzed material with new. Do not apply the material beyond recommended pot life. In order to avoid blOCkage of spray equipment, clean equip.. ment before use or before periods of _nded downtime with MEK, R6K10. Keap pmssure pot at level of applicator to avoid blocking of fluid line due to weight of material. Blow back coating in fluid line at intermittent shutdowns, but continue agltallon al pressure pot. APplication above recommended film thickness mey result In mud cracking. Refer to Producllnforrnation sheat for additional performance chare_os and properties. Refer to the MSOS sheat before usa. Published technicel data and Instruction. are subject to change without notioa. Contact your Sherwin-Williams representaIlve for edditlonal technical data and Instructions. 5.26Industrial and FAST CLADTM URETHANE 865-950 SERIES SEMI-GLOSS Marine 865-960 SERIES GLOSS B65V950 HARDENERCoatings PRODUCT INFORMATION Revised 2J03 FAST CLAD URETHANE Is a fast dry, Single coat, aliphatic polyuraa urethane speci1icaily formulated for accelerated maintenance painting. • Fast drying minimizes dust and gm "pick-up" • Allows enUre malntenanca coating systems to be completed in one shift • Single coat application • High build • No "outgassing" Flnlah: Sernl-gloss or gloss Color: Wide range of colors posSIble Volume Solids: 64% ± 2%, calculated and mixed May very by color Walght Solids: 30% ± 2%, mixed vee (EPAMethod 24): 289 giL; 2.4 Iblgal. unreduced 335 gil; 2.81b1gal. reduced 10% (with RSK10) Mix RatIo: 4:1 by volume Recommended Spreading RelAl per coat: We! mils: 10.0 -15.0 Dry mils: 6.0 -9.0 Coverage: 116 -174 sq IlIgel approximate Dfylnll Selledule@10'0mll.....t@8O%AM: @3S'F @T1"F @120'F To touch: 1-112 hours 30 minutes 15 minutes To handle: 3 hours 45 minutes 30 minutes To cure: 4 days 2 days 24 hours PotUfe: 3 hours 2 hours 30 minutes SWeat-ln-T1_: None None None IlIyInglime10 iemperalu'e, humldll¥. sndfllm thiCkneSS dependent. ShelfUfe: Pert A 24 monlhs, unopened. at 77"F PartB 24 moolhs. unopened. al 77'F FlashPolnl: 20'F. PMCC, mixed Reducer/Clean Up: Balow80'F: R6Kl0(MEK) Above 80'F: R7K216 Brush and roll: R7K216 Ideal for use as a finish coat for projecls requiring rapid retum to service, such as bridge maintenance painting. Use diradly over organic zlnc nch primers. Can be used in var10us coatings applications where fast cureto-service Is desired, such as: • Bridges • Hand rails • Structural steel • High visibility areas System Tested: (unless otherwise indicated) Substrate: Blasted steel Suri'ace Preparation: SSPC-SP10 or SP6 1 ct. Comthaoe I Galvapac @3.0-4.0 mils dft 1ct. Fast Cled Urethane (semi.gloss) @6.0 9.0 mils dft Teeled In """"odDnco with NTPeP (National Transpona. don Product EvalusUon Program) requlrementa a. ouUlnad by AASHTO DBa/llnalion 􀁒􀀳􀀱􀁾􀀲􀀮􀀠Requiremenlll: Requiremenlll: Abrasion Reshl!anco: MeIhod: ASTM D4060 CS17 wheel, 1000 cycles, 1 kg load Result 90 rag loss Adhesion: Method: ASTM 04541 Result: 825 psi ColTOlllon Weathering: Method: ASTM 05894. 15 cycles Result Rating 10 per ASTM 0714 for Bllatering Rating 10 perASTM 0610 for Rusting FreazelTbaw StebIIIty: Method: 30 cycles Result: No los.s of Patti Adhesion Sell Fog 􀁒􀁥􀀮􀁾􀀠Melhod: ASTM B117. 5000 heum Result Rating 10 per ASTM 0714 for Blistering Rating 10 per ASTM 0610 for RustIng 5.26Industrial and FAST CLADTM URETHANE PART A 865-950 SERIES SEMI-GLOSSMarine PART A 865-960 SERIES GLOSS PARTB 865V95O HARDENERCoatings PRODUCT INFORMATION Surface must be claan. dry. and In sound oonditicn. RemovaSt .... I: all oil. dust. grease. dirt, loose rust. and oilier foreign malarial 1 ct. Corolllane I GalvaPac Zinc Primer to ensure adequata adhesion.@3.0 -4.0 mils dft· 1 ct. Fast Clad Urelhana @6.0 • 9.0 mils dft Refer to productApplication Bulletin for detailed surface preparation Information.Steel: 1 ct. Macropoxy 646@S.O-10.0 milS dft Minimum recommended surface preparation:1 ct. Fast Clad Urethane @6.0-9.0 mils dft "Iron & Slaal: SSPC-SP6. 2 mil profile tiConcrel:elMasonry: 5SPC-SPl3/NACE 6 Concnrte. masonry: "AlumlnumiGalvanlzing: SSPC-SP1 1 ct. Kem Cetl-Coat HS Epoxy Fillar/Sealar Spot Prime JTouch-up: SSPC-SP3@10.0 -20.0 milS dft 1 ct. Fast Clad Urethane@6.0 -9.0 mils dft tiprimer required A1umlnumIGalvanlzlng: 1 ct. DTM wash Primer @.7 -1.3 milS dft 1 ct. Fast Clad Urethane @6.0 • 9.0 mils dft 1101 with 844 colorants only Into Part A at 100% tint strength. Five minutes minimum of mll!Ing on a mechanical shaker Is required for oomplata mixing of color. 'Other acceptable zinc rich prim.lll: Zinc Clad III HS Zinc Clad IV TemperalUre: 20"F minimum. 120"1' mal!lmum (air. surface. and malarial) AI least S'F above dew point Relative humidity: 85% mal!lmum Refer to product Applioallon Bulletin for detailed application Information. Pad-W1l11ams representative for additional tsohnlcal data and Instructions. Archer Western Contractors NOV 09 2004 HNTB CORPORATION DALLAS. TEXAS November 9, 2004 Letter: HNTB -18 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr, Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No, 04-22 Metal Painting System PC0#24 Dear Guy: In accordance with conversations with HNTB and the Town of Addison, Archer Western is submitting product and pricing information the following paint systems for the steel parts of Arch, Stinger, T -4 Rail and Pedestrian Rail: 1, Devoe -Devshield 4328 -Without Clear Coat = $33,357.29 2, Devoe -Devshield 4328 -With Devthane 379UVA Clear Coat =$47.267.45 3, Tnemec -High Build Epoxoline 66 & Endura-Shield II 1075 W/O Clear Coat =$69,705.23 4. Tnemec -High Build Epoxoline 66 & Endura-Shield II 1075 W Fluoranar 1076 Clear Coat = $132,262.60 These prices are minus the Costs for the TxDot System II Paint. The Paint Product information is enclosed If you require additional information, please contact Andrew at our field office. Sincerel w Schneemann Ass!. Project Manager Enclosure XC: Ben Withered Don Good File 2121 Avenue J, Suite 103 Arlington, Texas 76006 Phone: 817.640,3898 Fax: 817.640,8734 www.walshgroup.com A Member alThe Walsh Group An Equal Opportunity Employer • TXDOT SYSTEM II BID PAINT SYSTEM PAGE 63/28ll/aS/2664 a9:43 2812a91774 KING FAB TX DOT 810-E PRIME COAT (SYSTEM II) B69AVJ002 SIZE CODE 36Industrial andMarine CoatingY 8690210 Tx nor81()'E:Prime Conl!gn material to MSun. adequate adhesl!ln. Refer to bOOT Tape Test fot addIIIanal OMiace prIII)Gta!ion lnfonnaUQn. Minimum rnoomtnetIded SW1i.Iea preparation: T.ooT CI_ A Siasl Clean. R0 ... 􀁾􀀹􀁁􀁊􀀱􀀠1 gallon hardnar 8e9VJI 1 KeG BS90210 Weight par unit 631b per keg unit 8690210 18.4511> per box (basei hardner) Refer fD !he MSDS sheet before -. PUblished technic:al data and inll1!\lCtiOOs "'"subjoctlochange TIl& 􀁡􀁾􀁳􀁴􀁥􀁭􀁳􀀠Ifsted above are !1!pl'eaGnta1ive of !he product's ; wi1IIout noUce. Contact your ShtlfWir!-Wll!lams 􀁾􀀠...... OIhar sysI1ImS 􀁾be appropr!a!&. ,Ifat additional technical data and inslnldlom. 􀀬􀁾􀀠 PAGE OS/2811/65/2004 09:43 2812091774 KING FAB TX DOT 810·E PRIME COAT (SYSTEM II) 869AVJ002 SIZE CODE 36 B690210 Industriol andMarine Coatings APPLICATION BULLETIN 5ur1i1c:e musl be clean, dry, and n scond condition. Remove 4O"F minimlrn. 100'F maximum (air. 􀁾""II malerial) TxDOT ClaIR; A BlIISI Clean. RemOVll 1IIsIbie rust, paint, 􀁢􀀽􀀽􀁾􀀠l1li 􀁯􀁾􀀬􀀠dust, greaae, 0Irt. ICIose rust, and other fonlign material to eo""", adequate adhesion. Refer to TxOOT Tllpe T86t MInimum """""mendad sulfaQl pmpara1iorr. mill scale, and OIIIor10_ <>fcontsm!naticn. The blaslild anIS .IlaD exIlIbIt auniform surface appesmnce .nviewed wfth ihe unalded ElY" (20-20 vision).Slmilar 10 Nea...wnil.e BlIISI CleanIng. 8.SPC-SP10 OR NACE 2. At loast 5'F above dew point Relative 􀁨􀁴􀁊􀁭􀁬􀁤􀁾􀀠85% "",,"mum Do n"UII coIculatBd on wNme solido and do not include an appllcat/ot! loss fador due ID surface jl!t>fife. ",ughness of pCIfOslIy of th.. surface, sidll and ladIoique of !he applicator. method of application. vnUII surface itregulari!ll!s, mlll:erial lost durtng mbclng, spillage, O\IBI1hinning. tllrnllllc oondl!lons. 11M exce!!!liVe film build. !Wetto Product 11I[u""atton sheet fur addilfonsl perfoo1l laOOO ohIIracterl$1lc& and properti.... ReIer IIJ the MSDS shMt bldmaIe D!ylng Sdtedula @4.0 I'IlIa _ @50% RH: @7M' To touch: 30 mlnu\es To handle: 2 hau", hlfUfa: 12 month!!, unopened, at 7rF FIaah ""'lit! 78 oF, !>Mee Rel!uClll'la.n Up: )(pma, Mek(l(etcnes PAGE 08/28􀀱􀀱􀀯􀁾􀀵􀀯􀀲􀁥􀁥􀀴􀀠09:43 2812091774 KING FAll TX DOT 742 H GRAY APPEARANCE COAT Industrial andMarine Coatings B29AJ100a PRODUCT INFORMATION Over prepond sysIBm I or n I ooat B29AJ1000 @:2 mils dI't. Nola: System I or II OOIIlings, including field IOIIcIHJP. sl10uld be allowed !D 1119 """ be c!etarmlnad by tile !clawing test. Using modmate to MIlVY pressure, place thumb deW p Srush ............................ N_I emile Raclucllon ..................... Nat recommended Roller Cover ............................ 318"..1/Z' _n WIU! p/lonollc core RacluCiion ..................... Not recommended If spe<:Ifte application equlpmel1t f. lilted abcw. equlllllient squfpment may be subs!ll!.!b3d. Nata: !!rush and ..,..,. applical;cn will mqulnl use of a sloW AramaUc !IOIvent. 2812691774 KING FAB PAGE HI/28 TX DOT 742 HGRAY APPEARANCE COAT B29AJ1000 Spmdlg rates a", c:aicllllllSd on volume scid:s and do nat include an appIit:aIIon lossfactDr dlJlll!> SI.lIf.Ica polite. raughness Sity of 􀁴􀁨􀁾􀀠SI.Im-, slduc! ll1fannaIIon sheet lor edd!UlCI'.IW!ng tsot Using l'IlOdemtB 10 heavy JIAII'SUI'G. place thumb on paint SIIrfiK:G and apply a 1w1stIng./IIOIIon. If the paint film gm Of twists with 1M lbumb. the coaIlng is I)Q\ lhoroughty cured. APPLICATION BULLETIN MlllIlllllnstnll,tlOI1B; MIx pUtt U1ornugh!y by btlldng and DEVOE PAINT SYSTEM 􀁾􀀧􀁊􀁬􀁪􀀧􀁬􀁾􀁬􀁆􀁪 􀁾􀁈􀀧􀁇􀁈PERFORMANCE .. 􀁪􀁩􀂷􀀧􀀻􀀧􀁉􀁉􀁾􀁴􀀴􀁏􀁪􀀠 PRODUCT DESCRIPTION Generic: Aliphatic Acrylic Uretnane Genera' QtseriptjtJno A high performance, two-compo .. nent chemically-cured clear aliphatic urethane finish for use in 􀁡􀁲􀁾􀀠where maximum gloss retention is reqUired. Typical Uses: For use on properly prepared and primed steel, concrete or steel floors, masonry, drywall, plaster, metal, concrete block, galvanized, aluminum, poured concrete, and glazed brick. Ideal for use on exterior or interior strucb..ual steel, piping, metal buildings, control · cabinetry, conveyors, pumps, storage tanks, motors, machinery, and transportation vehicles, Can also be used in the hard service areas of food processing plants, dairies, schools, restaurants, hospitaJs, correctional facilities, factories. stadiums, arenas, and amusement parks. Special QualificatjOns· Suijable for use on structural surfaces or surfaces where there is a possibilijy of incidental food contact in commercial food preparation establishments, food processing plants and iederally inspected meat and poultry plants. USDA no longer requires or furnishes product certification letters. FEATURES Advantages: • Exceptional gloss retention .. Excellent abrasion and chemical resistance • Higher solids and higher film build than typicalurethane finishes • VOC compliant urethane " Easily applied by brush, roller Of spray " Excellent resistance to marring, chipping, and scratching • Provides added protection to urethane color coats and epoxies where used on floors. " Gloss Cisar contaings UV absorber • Gloss Clear may be used over Devthane 379 Enamel for improved weather resistance • 􀁐􀁥􀁲􀁦􀁯􀁲􀁭􀁡􀁏􀀨􀀺􀁾􀀠alternate for DsvthanE> 369 and 4708 §mIfiti Resiota""e: ExceJIen! resistance to most graffiti materials such as spray paint, magic markers and lipstick. GentaCl your ICI Devoe Geatings Representative for more information on !he grnfflti removing cleaner 10 service your needs. Umitation" of.Use: CoIqr "'i'Y change as temperature approaches 250'F (121 'C) limij, but the film will remain intact. Not recommended for exterior use over epoxies, alkyds or oil-base paints. Not recommended for inlErior use ever alkyd or oil-base paints. Flat Clear should nOl be used for graffiti AbraSiOn ReSistance" (ASTM D 4060) -Very Good Humidity Resistance: (ASTM D 2247) -Very Good IiIl"F (lti"C) 8O"F (Z7"C)Substrate Temperature 4tl"F (4"C) 3 Hours Dry Hard Minimum Recoat 10 Hours U Hours 18 Hours Marimum Recom >32 Hours 24 Hours Sell 2WeG::ks 2 Weeks 2 Weeks Ventilation, film thicknsss. humidity. thinning and olhCr factors can Inftuence the r:;lte 01 dr)t Warnioo· Tile above table provides guidelines only. Always cor'lsull your ICI Devoe Coatings SpeCialist tor appropriate recoal windows since the maximum aged recoal time of this product may be significantly shortened Or lengthened by avariety of conditions, including, but not limited to humidity, surface temperature, and the use of additives or thinners. The use of accelerators or force curing may shorten the aged recoat of individual cOalings. The above recoat windows may not apply if reooatlng with aproduct otller than those listed above. If the maxi· mum aged recoat window Is exceeded, please consult your ICI co Industrial Coalings Specialist for appropriate recommendations to enhance adhesion. Failure to observe these precautions may result in intercoat delamination. Shelf Life: Over 24 months at 77'F (25'C) -unopened Hardn,,,,, IASTM D 3363, 7 day cure @IT'F(25"Cl: 4H Mix Ratjo BvVolume: 4 (base): 1 (converter) -see mixing instructions, . Induction: None required -see mixing instructions. Pot Ute; 4 hours @77'F (25'C) & 50% R.H. DEVTHANETM 􀀳􀀷􀀹􀁕􀁖􀁾􀀠 Clear Aliphatic Urethane Finish Cat. # 379K0036 Gloss Clear Cat. # 379K0020 Flat Clear SPECIFICATION DATA Color: Clear Finish: Gloss -90 units minimum @60'(379K0036), Flat"" 30 units maximum @85'(379K0020) Reduction Solvent: T-9 for spray, T-17 for brush or roller. Clean-up Solvent: T-9 Thinner Weight/Gallon: 8.5 Ibs./gal. (1.01 kg/L) VOC (EPA 24): 3.0 IbsJgel. (360 gil) Solids ByVolumQ; 57% Theoretical Coyerage. at 1 0 Mil (25 microns) Drv· 914 sq. ft. (22.4 mOil) Recommended FilmThickness: 2.0-3.0 mils (50-75 microns) dry -4.0-6.0 mils <100-150 microns) wet Systems: Please consult the appropriate system guide, the particular job specification or your lei Devoe Coatings' Industrial Coatings Specialist for proper systems u.ing this product, Systems must be selected considering the particular environment involved. SeN;" Tempemure Umits-250°F (121 °C) dry Mlnlmym oryTIme (ASTM D 1640\-At 3 mils (75 microns) DFT -----------"", .......... .......-._-_...... ..::.r GENERAL SURFACE PREPARATION 'All .urfa""" must be sound, dry, clean, Iree of oil, grease, dirt, 􀁾􀁩􀁉􀀾􀁕􀁬􀀧􀀡􀁹􀀠l'lIintl!d Surfaces: May be applied as a prote¢tive mildew, form release agents, curing compoundsj lOO5G and 􀂢􀁨􀁾􀁡􀁲􀀠coat to two<'COlTlponent cotored 􀁰􀁯􀁉􀁹􀁊􀀮􀁬􀁲􀁾􀀱􀁨􀁡􀁮􀁥􀀠coatings and flaking paint and other foreign $ubstanoes. epoxies for interior US!!. Not recommended over alkyd or ai!besed paints. DIRECTIONS FOR USE IiIlliJl.g; DO not·tint. Thinning: Thinning is not nonnally required. However. depend· ing on local VOC and air quality regulations, small amounTS (5% or less) 01 the solvenls on the reverse page may be added. Small amounTS (5% or less) 01 Devoe Coatings T-17 Thinner will improve roller or brush applications. If local VOC and/or air qualIll' regulations are not an issue. and depending on the Individual set-up of the spray equipment, addHional1l1inning may be allowed 10 obtain the desired Individual finish. Contact your local ICI Devoe Coatings Representative for additional information. Mixing: DEVTHANE 379 Enamel is a two-comllilnent product supplied in 5 gallon or 1 gallon kits which contain the proper ratio 01 Ingredients. The entire contents of each container mu.t be mixed !oge!her. 11 is imllilrlantlhat all miXing equipment 1$ free of moisture and that moisture does not contaminate the coating. Mix lhe base Ililrtion to obtain " smoolh, homogeneous condition. AIt&r mixing tlhe base portion, add 111. 􀁯􀁯􀁮􀁶􀁥􀁲􀁴􀁾􀁲􀀠slowly 􀁷􀁾􀁨􀀠c0ntinued agitalion. Mix thoroughly. 1l1e pot life Of tlhe mixed malarial 1$ 4 hours at Tr (21;·C). Higher temperatures will reduoE> working life 01 the coa!lng; lower temperatures will increase It. Application! Apply by airles. spray, air spray. rollar or brush. For ainess spray, any air, electriC, or gas operated airiE>ss ,player capable of 3,000 psi (207 bars) and able to support a .011" to .017" np sizes can be used. Multiple guns and long nuid lines require pumpe wiIh adequate capecity. For air spray applire!ion, use a Gmeo 11800 gun; a .070" or larger fluid lip. Adjust fluid and air prassu"" 10 gel a good spray pa1tem. NllIII: 6e sure all spray equipment and fluid lines are clean, and free of water or solvents. For brush application, use good quality, dry, clean brushes. For roller appJic.ation use new, short nap mohaIr rollers.. Do not apply over we! surfaces or under very humid condftlons where condensation or fog could sel1le on the coating during the cure process. SpmAdlng Bate! For maximum protection in corrosive areas, apply at 335 sq. ft, per gallon (13.2 m'lL) or 3.0 mils (75 microns) dry-4.8 mils (120 microns) wet. In mild to modetate exposures. apply at soo sq. ft. per gallon (12.21; m'/L) or 2.0 mil. (SO microns) d1)l""3.2 mils (80 microns) wet. Make allow'mce for any 10SllllS due to ove!'Spray or surface irregularitles. Dry 11m..: At 8O"F (27'C) & 50% R.H., dnes to recaat in.S hours and dries hart! in 16-24 hours. .Clean-up· Use T-9Thinner. Cute Acceleration; Devthane Cure Accelera!or 070AOOOO may b. used to accelerate cure of this urethane at or below 4O'F (5'C). 070AOQOO us prepackaged (5 fiuid ounces in a onehaH pint oontainer) for field addition. The addition 01 one to two ounoes par gallon of urelhane (one !o two comainers per liVe gallons of urethane) will decrease the dry hard lime approxi, mately one-third to "n",half respectively. The pot lile will be reduced one,haH to mree·fourths. Utr:a·Vio!et Ught /ll;!lIQTtwrs (UVA)' DevI!1ane Utta-Violet Uight Absorber OSQAOOOO is already contained in Devthane 379 Clear Gloss. Additional <3193'$ Ralantion Enhancer is not required nor desired. DeVlhane Gloss Retention Enhancer is not recommended in Devthane 379 CI.", Flat. PRECAUTIONS For industrial use only. Keep out 01 reach of children. Consult Material SlifeI)' Oata Sheets appropriate for this proouellor important health and salsly information prior to use. HMIS DATA Freight CI.soIflcallon: Flash Point: Packaging: SHIPPING Paint. 3, PG III. UN128a (Rammable Liquid) 80'F (27'C) 1 gallon kit (3.785L) 5 gallon kit (18.9.25Ll 0.80 gallon base 4.0 gallon bilse 0.20 gallon converler 1.0 gallon converter Shipping WliUhl: 4 -1 gallon kits -40 Ibs. (18.2 kg) 5 gallon kit -49 Ibs. (22 kg) • 01__• Ohio, U.S.A. 􀁾􀀲􀀶􀀱􀀶􀀠www.dlWOeooatings.com It>6OO£6lBC : 'ON Xtl.:l DEVSHIELDTM 4328 Interior/Exterior Alkyd Urethane PRODUCT DESCRIPTION G!!!'!e,lc: Alkyd-Urethane General !)escriplion: A premium quality interior/exterior alkyd-urelhane gloss enamel for use on wood or above grade concrete porches or floors not laid 􀁤􀁩􀁲􀁥􀁣􀁾􀁹􀀠on damp or water bearing sumces. May be used on Interior ..cr extenor,abCl/B.grade sunaces. Also goon tor woodwork, radiato",. omamental Iron, boat docks, fire escapes, etc. Features good resistance to abrasion, oils and washing. lilpeclal QI/lillficallons: Suitable for use on stru.ctural sunaots or surtares where there 1$ a possiblfily of incidental food contact In oommercial food preparation establishments, food processing plants and federally inspected meat and poultry plants. USDA no longer requires or rurnishes product certffication letters. FEATURES Advantages! • Durable high gloss finish • Interior or exterior usage • Excellent flow and leveling • Easy application -brush. roll or spray • Ready for us. the day after spplicetion • Resists marrtng, weathering and water spoiling • Performance alternate for Federal Specifications TT'E-487E, TT-E-489H. rr-e'506K, and \T-E-505A. Umjta!loQ§ of Usa: Not for use in highly alkaline or chemical areas. Gloss Enamel Cat. 1# 􀀴􀀳􀀲􀀸􀁾􀁘􀁘􀁘􀁘􀀠SPECIFICATION DATA Colo.; White, custom & ready-mil< colors EiIlilill:; Gloss. 70 􀁵􀁮􀁾􀁳􀀠minimum @60' Clean.up Solvent; Mineral Spirits or VM&P Naphtha WeightlGallon-10.0 Ibs.lgal. (1.20 kglLJ -varies with color 􀁾3.:?'1 IbsJgal. (385 gil) -lIaries wim·color Solid. By Volume: 51 % ± 1% -varies with Gaior Th!!OrBtical COlII!!Olge al1.0 Mil pry: 818 sq. fllgal. . (20.n01L) practical Coverage; Apply at 400-500 sq.ItJgal. (10-12 m2fL). Actual COIIerage may vary depending on substrate and application me1hod. Recommended Film Thic!mes$; 1.6-2.0 mns (4D-50 microns) dry -3.2-4.0 mils (So-loo microns) wet Systems: Please consult the appropriate system guide, the particular job specification or your lei DevoeI Coatings' Industrial Coating. Specialist lor propsr '1 systems using this product. Systems must be selected 1 conSidering \he particular environment involved. S.rvi<:e TemDe@ttJre Limi!: 200'F (93'C) in air Flame §",md Rating: Class A (0-26) over non" combustible surfaces1• Flash Point: 10S'F (41"C) 11 Dry Tim .. @U'E(26'm&SO%BH: To touch -6 hours j To ""coat or light loot traffic -16 hours J.,. 􀁾lhe 3.bOw fable pn:wldes gensrni guidalinee only. Alw-dYS COrl" suk your tGI Devoe Coatitlos: SpacialiIil for eppl"t91iale ntcoal 􀁾􀀠slllCfI1hs mbimum aged recoat tims of Itiis prodUct may be. eignffleenltyi shortened Qr Jongthenod by a variety of cootllooru;. indLMfIt\9. 􀁢􀁾􀀠nclJim· ited to I'u..Irnldity, Ihuface tampGr41Urt• .and lhellU oi 􀁡􀁯􀀧􀁤􀁬􀁤􀁾􀀠or thin·l : nfJ/'$. "['he usa ot acceJerawl'5 or roru curing may snol1en"'a aged 1,1 reec.at 􀁾indivCiusl earnings. The above recoat wfndOWS: may not 􀁾􀁹if I 􀀨􀁾􀁷􀁩􀁴􀁨a pfOdLICI Other than those 􀁾􀁾􀀮Hthe fIlaiIJmwn I &gad mooat winDoW IS-exceeded. please COOSUIi your JCllndustltaJ Coatings SpeQtaIist tor appropnlLie appropnlLie reoommootialione; IQ .nnence adhe&ion. Failure to ODSetve tl!ea$ 􀁐􀀱􀁾􀁯􀁮􀁳may rooutt in InteteGat dalami! men.1-"'",-"""'--"-"" PERFORMANCE DATA PROPE!!TY TESTMImIOp RESULTS Adhesion ASTM D 3959 Excellent 5A No peeling or removal Direct Impact Resistance ASTMD2:794 Good: > 10 in -Ibs. Abrasion Aesl$tance ASTM D 4060 Good l0 391;!d SlN111d I:)I In£889ElL 09800 Back. 􀁐􀁡􀁧􀀹􀁾􀀠4328-XXXX , GENERAL SURFACE PREPARATION All surfaces must be sound. dry. dean and Iree of oa. grease. dirt. IT'IIldew. form release agents, curing compounds. loose and flaking paint and other foreign substances. N!!W Surfao"", Concrete (concrete floors) and Masonry Do not use on ffoors subiect to dampness from the g",und. Cure at least 30 days before painting. pH must be 10.0 or lower. Roughen unusually $lick poured or precast concrete by acid etching or sandsweeping. Follow acid manufacturer's appliClition and salety instructions. Rinse thoroughly with water and allow 10 dry. Remove loose aggregate. Prime properly prepared concrete floor!> less than ana year old with soillenlbome primer DEVSHIELD 4130. Worxl -Prime with this produot. Steel· Prime with solventborne metal primer DEVSHIEI..D 4130. Galvanl>:ed Metal and Aluminum· Prime with solvent· borne metal primer DeVGUARDTM 4120. Previously Painted SurtaCK: Wash to remove contaminants. Rinsa thoroughly 􀁗􀁾􀁨􀀠water and allow to dry. Dull glossy areas by light sanding. Remove sanding dust Remove loose paint Sorub heal'\' chalk exterior areas and overhead areas such as eaves with .cap and water. All eXISting mildew must be r ... moved by washing with a solution of 1eoz. (47$ mL) liquid household bleach and two oz. (59 ml) non·ammoniated fiquid detergent per gallon (3.785 L) 01 water. Rinse surfaces clean with water and allow to dry lor 24 hours. Pl1me bare areal> with primer spedfled under New SUrfaCilli. DIRECTIONS FOR USE Tinting' Tin! the appropriate base with lei Oolorants. Sp",mllng Rate: Apply at 400.500 sq. 11./9101. (10·12 m21L) or 3.2-4.0 mils wei (1.6-2.0 mBs dry). Actual coverage may vary depending on substrate and application method. For best hid· ing. tin! primers toward fini$h coat color. Cenain $hades of yel· low. orange. pink and red may reqUire multiple coats. IMPORTANT; Alkyd or alkyd urethane enamels may yellow in 􀁾􀁭􀁥􀀠in tile absence 01 light. especially sunlight. Appllcat!9n: Mix thoroughly before use. May be applied by spray. roll or spray. Brushing and rolling may require multiple coalS 10 achieve correct film Ihickoe.ss and/or hiding. No thinning required. FOr alrless spray use a .015" tip. Adjust pressure as neaded. Do not apply when surface or air 􀁴􀁥􀁭􀁰􀁥􀁲􀁡􀁴􀁵􀁾􀀠is below 4Q"F (4"C). Two ooats are &uggaslad lor bast results. Surfaces coated with this product may become sliQpery when wet. For adcUtiona! slip rss.istancQ in i!!'fWi of p@deS1rianttaftic , add pne pound per gallon of coarse pumice Of other texturing materiaL DnllngTime, At 77"F (ZS'C) & 5p"k R.H.. dnBl> to touch in six hours, to light foot traffic and recoal in t 6 houlS. Low tempera· wre, high humidity. thick films or poor venUiation will increase Ihese times. Clean-up, CliOarl immediately with mineral spirits or YM&P Naphtha, PRECAUTIONS DANGER! COMBUSTIBLE UQUID AND VAPOR. HARMfUL OR FATAL IF SWALLOWED. ASPIRATION HAZAR!) -CAN ENTER LUNGS AND CAUSE DAlllAGE. HARMFUL IF INHALED. MAY CADSE COORAL NERVOUS SYSTeM EFFECTS, INCLUDING DIZZINESS, HEADACHE !)R NAUSEA. CAUSES EYE. SKIN ArID RESPIIIATORY TRACT IRRITATION. OVEREXPOSURE MAY CAUSE UVER, KlDNEi'DAMAGE.. WHEN TINTED. CONTAIII$ ETHYLENE GLYCOL WHICH CAN CAlISE SEVEIIE KIDNEY DAMAGE WHEN INGESTED AND HAS BEEN SHOWN TO CAUSE BIRTH DfFECTS III LAl!ORATOIIY ANI· MAI.s. USE ONLY WIIH AIIEOUATE VENTILATION. KEEP our DF lHE REACH OF CHILDREll. NOTICE: Products In 1111; seriR may cnnlain solllBnIs. Flaports nave associated repeatea and prolonged 􀁯􀁣􀁣􀁾􀁰􀁡􀁴􀁬􀁯􀁮􀁡􀁬􀀠overexpOSlIre to solvents with pellllllll,nt blllin and nervous system damage. Intentional misuse by deliberately concentraUng and inhaling tIls conlBnts may be harmful or lalal. For emergenC'j' information Gall (000) 545·2643. filr additional safely information, reler 10 the Matenal Salety Data Sheet for this prodllCt, Keep ilW)' from heat, sparks and flame. Do ltD! smoke. Vapors may ignit6. Extinguish alillames, burners. stoves. IlaalBrs and pilot lights and disconnect all eleetrical metors and appliances before use and until all vapors vapors are gone. II sanding i. dOne. wear adUSlIl1iSK to avola breatillng 01 sanding dust. Do not brealile vapors or SPIlIY mist. If yOU experience eye warering.headaches. or dilzlness. leave the area. If Pmpflrly usBd. a respirator may offer additio!1;ll protection. Oblaln profesSional advice befoll! I.ISillg, Close container aHet aacn use. FIRST AID: In _ of skin roolact. wash 011 quiCkly willi plen1Y of soap and waIllr. ram""" contaminate!! Clothlllg. Iilreye comact flush Immediately willi iargf! amounls of waI8r, for at least 15 minull!s. OlrlaiR 􀁥􀁭􀁾me4Ic:a1 tJealment. ItswallClWlld. alrlafn medieal InlIIImBnl imDlflllialllIV. Hinhalation causes physical cliscomlort. remove 10 fresh air, If discomfort persists or a!lY breathing difficulty oocurs. gel med· lcal help. NolII; Thlifi waminplIIII:omjlUllillc prudlld ..n... PriIIrfD USB, IlIll11 and lollow pmdgd SllKllie MSDS and 111101 Inlormatlon. ......• SHIPPING f18j,ht Classilleallon: Flash Point; Pacllaglng: ?aint t05'F (41'0)1 gallon (3.7S5L) 5 gallons (1 a.925L) Shipping Weight' 4 gallon ease· 44lbs. (20,0 kg] 5gallon pall' 541bs. (24.5 kg) EB 39'<:1d 51N111d 1ClI 􀁾􀁈􀁅􀀸􀀸􀀹􀁅􀀱􀁌􀀠 11JB5/26a4 69:43 2812091774 KING FAB PAGE: 13/28 PRODUCT DESCRIPTION Generic: Modnled Epoxy 0en!!!'l!1 pmrlption: A high performance, modified epoxy, rust inhibitive. metal primer. Provides excellent corrosion protection and rusty metal adhesion tar superior 10 alkyd primers. Ughl gTay color permits good cowlag" with one finish ooat, Use under alkyd. lalex or modlfleo epoxy finishes. Also makes an excellent alkali resistant masonry bonding primer. Typical US!!S: Ideal for structural steel, tanks. piping and equipment. Special Qualifications: Suitable for use on structural surlaces or surtaces where there Is a possibility of Inci. dental food contact in commercial food preparetion establishments, food processing plants and fedel'8l1y inspected meat and pouHry plants. USDA no longer requires or fUrnishes product certification letters. FEATURES Advantages: • Excellent corrosion resistance • Good penetration of surfaces that cannol 􀁾well cleaned • Ideal for old, rusty galvanized metal surfaces • Excellent alkali resistant bonding primer for masonry • Helps block effiorescenoe • Performance altemate for Federal SpeoificaHons TT-C-530B, TT·P·6150. and TT,P'645B PROPERTY Adhesion Pencil Hardn .... F1exibilHy Humidity/Corrosion Assistance DEVSHIELD1M 4130 Rust Penetrating Metal Primer Cat. it 4130-6130 SPECIFICATION DATA 􀁾􀁕􀁧􀁨􀁴􀁇􀁲􀁡􀁹􀀠Rnlsh: Flat P.lMo-l!P Solvent: Xylene WelghtlGallo.n: 1 1.1 Ibs.lgal, (1.33 kgll.) llQQ;, 3.50 IbsJgal. (420 giL) ma)(imum So!lcts By Vulum9! 47% '" 1% ll1.!lo.!:e.ll«al CovBra9" at 1.0 Mil Rl:l!.; 754 sq. ft.lgal. (19 rn'.,IL) P",ctieal Covemms using this product. Systems must be seiecled t:Oru!iderlng the particular SrMronment Involved. Service Temoera!J,l[!t Limit: 225·F (107'C) In air Aame Spread Rating: OIa!;8 A (0.25) over noncombustible surface. Fbl$h !>oint: Over 102'F (39'0) pryTime @T7"F (25"C\ & 500.. BH: 'Ib touch -S hours To recoa.t -Overnight 􀁾􀁉􀁮􀁧􀀺The above Iable provki§ getU)fal 􀁾􀀡􀁤􀁥􀁬􀁩􀁮􀁥􀁳􀀠only. Alwt!l»'£ consult your tel DBYOE! CosJIngs SpecialiSt for apptQPfll;Ue 􀁾Windows ames thn maxImum aged recoal 􀁾Of til" product may be sig!1tftcarrtl:y shortened or longtl'lcm:d by a va;rtety of CIO!1ctt1one. i!'dud!"g. btrt not 1m· tted 10 fwmldlly. &urtaca Ml'I'IllQratUre. and It'I.e 􀁾of sddltlwa or 􀁴􀁨􀁬􀁮􀁾􀀠oors. The use or 􀁾􀁯􀁣􀁥􀀴􀁵􀁭􀁴􀁯􀁭􀀠or tonw CUrfna may $t\Orterl1'tle aged taecat of indllllctual coarirtgS, The above reCOil' windows Mi\)' nol il:WIY t1 recoatlng wtth. a produc:t: other Ulan ltIoso 11$tMi «bave. It the ma.imum aged recoat window Is 􀁥􀁸􀁾􀀬please consuil your lei InduStrlal Coatings SpooIall$t 10r3PPrt.l'rlat9 recommondariom; to enhance.iSheelon. Fallure to obsGrve 􀁜􀁴􀁉􀁥􀁥􀁾􀀠preceiJ1.k;lna m8¥ rsSUlt in Inlt'!n:03t 􀁷􀁴􀁡􀁭􀁾􀀠t1atlcn. Shelf Life: 1 year minimum -unopened PERFORMANCE DATA TEST METHOD RESULTS ASTMD4541 600 psi ASTMD3363 H ASTM 0 522, Method 6, 1/6" ASTM D4565, 3000 hours No cracking or fiaking No blistering or delamination of !he fllrn, slight rust staining al scribe 09800 • Read label and Materl3l e. PSf2-o19O 11J05/2ea4 09:43 2812091774 KING FAB PAGE 14/28 tAW"· ...,,,,· .............. GENERAL SURFACE PREPARATION All surfaces must be sound, dry, clean and free of oil, poured or precast concrete by acid etching Of sand· grease, din, mildew, form release agents, curing sweeping. Follow acid manufacturers application and compounds, loose and flaking paint and other foreign safety instructions. Rinse thoroughly with water and substances. allow to dry. Remove loose aggregate. Prime with this paint.New Surfaces: Steel • Best results are obtained over a surtace sandblasted to a Commercial Blast (SSPC-SP6). Previously 􀁐􀁡􀁩􀁮􀁴􀁾􀀡􀁌􀁓􀀡􀁬􀁲􀁦􀁡􀁣􀁥􀁳􀀺􀀠All spots tailed by Performance over hand or power·tool cleaned surfaces rusting. peeling, blistering. etc. shall be wire brushed and is dependent on the degree of cleaning. Old Galvanized scraped to remove all loose or loosely aahering material. Metal • Old rusty. galvanized metal surfaces must be Spot prime bare areas. For optimum pertomnance in wire brushed and scraped 10 remove loose rust and more corrosive areas. entire surface should be abrasive primed with this paint. Concrete, Plaster and Masonry -blast cleaned. Cure at leest 30 days before painting. pH must be 10.0 or lowar. Remove laitance and roughen unusually slick DIRECTIONS FOR USE 􀁉􀁊􀁮􀀮􀁾May be tinted with up to two oz./gal. of lei in damp weather or when the surface or air temperature Colorants. is below or expected to be below 4O"F WC). Brushing and raDing may require multiple coats to achieve correctSpreading Rate: Apply at 285-400 sq. fUgal. (7-'0 film thickness anellor hiding.m'll) Or 5.0-8.0 mils wet (2.2·3.5 mils dry). Actual cover· age may vary depending on SUbstrate and application Drying Time: Al77·F (2S"Cl and 50% R.H., dries to method. touch in six hours and to recoat overnight. Low temperature' high humidity. thick films or poor ventilation will Appllcetlon: May be applied by brush, roll or spray. increase these times.Apply liberally. For air1ess spray, use a .015" tip. Adjust pressure as needed. No thinning required. Do not apply 􀁾Clean immediately with xylene. PRECAUTIONS IJANGERI COMBUSTIBLE UQIJIO AND VAPOR. HARMAll OR FllTAL If SWAllOWED. ASPIRJmON HAZARD -CAN ElillR LUNGS AND CAUSE DAMAGE. HAAMfUllF INIIALED. MAY CAUSE CENlIIAL NERVOUS SYSmII EfFECTS, INCLUDING DIZZINESS, HEADACHE OR NAUSEA. CAUSES EYE, SKIN AND IlESPiMrOIIYTlWrr IRRITATION. OVEREXPOSURE MAY CAUSE UVER, KlDNEI' DAMAGE. CONTAINS CYRSTAllINE 􀁓􀁬􀁬􀁬􀁃􀁾􀀠WHICH CAN CAUSE LUNG CANCER AND OlHER llJHG DAMAGE IF INHALeD. CUnTAlNS 􀁍􀁉􀁃􀁾􀀠WHICH CAN CAUSE PNEUMOCONIOSIS. WHEN TINTED. CONTAINS EIlIYl.EHE GLYCOL WHICH CAN CAUSE SEVER!: KIDNEY Il/IMAOE WHEN INGESTED AND HAS BEEN SHOWN TO CAUSE BIRl1l DeFfClS IN LABORAIlIR'f ANIMAlS. USE ONLY WITIf ADEQUATE VENTILATION. KEEP OUT OF THE REACH OF CHlUJREN. NOTICE; Products in litis series tOnIain solVtntll. Reports have associated repeated and prolonged occupational overexposure to solvents wi1h permanent brain and nervous system damage. Intentional misuse by oollllerateo/concentrating and inhaling Ifle conteo1s may be harmful or 1ataI. For emerge1lC)' In!ollnation can (600) :;45--2643. Keep away from 􀁨􀁥􀁡􀁾􀀠sparks and flame. Du no! smokll. Vapors may Ignite. Exlinguish 􀁡􀁾􀀠llamas. 􀁢􀁵􀁭􀁥􀁾slaVeS. heaters and pilot Ilgtils anG (ilsoonnect all electrical motors and appliances before llSe and until all vapors are gone. If sanding is done. wear adust mask trJ avoid brealh· ing of sanding dUst Do not breathe vapors or spray mist If you !!)(jli!rience eye watering, headaohes, or dizziness. leave Ifle area. If properly tJSeII. a respirator may offer additional protection. Obtain professional ildviCli before USing. Close container after each use. FIRST AID: In case Of skin oontact, wash off 􀁾􀁵􀁬􀁣􀁬􀁤􀁲􀀠wiIf1 plenIY of soap and water, remove contaminated clalhlng. For eye contllltliush Immediatel, l'Ii11llargt amounts of water, for at lea$l15 mlnutl!s. DbIlIIn emergeD", medicallmllmell1. II swall0we9, olIhlln I118dlcallmtmen! Immedlalely. If Inhalation causes pl!ysical diseomll:irt rBfTKJve 10 1Tesh air. 11 disonmll:iJl pemisls or any breathing diffICUlty cecum, gill medical help. Nate: Tllese waroln!lll enllllll1paBS 1110 prmlucl series. Prior 111 use, read and lollow plOlillcHpecifi. MSDS and label illlomlatiun. ""'"'' • SHIPPING Freight Clasaificatlun: Paint Shipping Wefght 4 galion Gase -481bs. (21.8 kg) Flash Point: Over 102°F (39·C) 5gallon pail-59 Ibs. (26.8 kg)Packaging: 1 gallon kH (3.785L) 5gallons (18.925L)) LiMITATION OF lIABlU'TV,: Ta the be11 of our 􀁫􀁮􀁄􀁷􀁩􀁈􀁾􀀬􀀠IhI technIcal dlw oontalMtl hl!refl1 lilt!! InlP. Inri :+cclIrnte !\11I1e Gate Of lssuanco but ilre SlJbied, to change wllnout Pi'll)( nOltCt, Wo auarilntt:e t1ur I)rCC!JC'l1o COnfDrm to the spsctilCJtions CGntalned tw!nln. WE MAKE NO ornER WARRANTY DR aUARAm'EE Of ANY KINO. EXPflESS OR IMf'I.IED. INOLUDING MEACHANTA81Lm MO FlmESS FOR f'IIJiTlCULM f'UAPOSf. Uability. 11 An)'.1$ limned to 􀁲􀁰􀀮􀁰􀁾􀁲􀁮af 11M! pmdL4M rstulUl nf1be 􀁰􀁬􀁬􀁾pl'lU, 􀁉􀀮􀁮􀀮􀁡􀁭􀁾􀀠OR COST OF 􀁌􀁍􀁏􀁾AND liTHER CON5EQUErlTrAL nAMA.'. ME HEREBY EXCUlIJEO. TNEMEC PAINT SYSTEM 11/02/2004 16:56 972-312-8468 TNEMEC-BARRV GROUP PAGE Fluoronar'"' Clear SERIES 1076 -II 1'''11 F..\lflC PRODuCT PROfILE G!lIERfC DESIllP!laK Advanced 1:'h=oset Solution Fluoropolymer Clear ® OlMMON 1ISAGE COLOI FINISH An Cl(rerior cleat fluoropolymer finish coat 􀁾􀀤􀁰􀁥􀀺􀁣􀁩􀀮􀀧􀀱􀁕􀁹􀀠designed to enhance the extt.'fior weo.n1etamIity of Fluoronnr and HydroFlon. Fluoronar ClC$'f has outstanding resIstance to ultra-violet light providing 􀁾􀁤􀁥􀁤c.:olor and gloss retention, A:n indicator dye.is provided to .aid in 􀁾􀁰􀁰􀁬􀁩􀁣􀁮􀁴􀁩􀁯􀁮􀀮􀀠Clear. Note. 44·500 will cl1_" me appe1U"ancc to • Yiole' tint 􀁤􀁾􀁲􀁬􀁮􀁧􀀠.ppHcation. After. period of up to 7Z nours of sunUght exposure, 'pp_"""''''' will be cleat. High Sloss PillO!,\Wjrf Crulrul ExtensiVe t! 24 h""'" I YOlAlll£ ORGAIIK CIlMfOUNGS • Maximum rt:coat! 7 dayS. Curing time van.e;:i with sutfuce temperature, a1t mO'V't:'ment, humidity .nd fllm thickness. UntbjnnM 5,18 Ibs/galloo (381 gr.".,./litre) 'I1litlru:4 S% 3.37 Ibslgallon <404 gramsllitn'l) THEORETICAl COVIRAGE HUMaER OF COMroHEHlS 910 mil sq fr/pl (22.3 m'll ar 25 mie",ns). See APPllCATION for covernge "".... '!Wo; Part A and Part B MOONG 0010 By volume; Four (part }J to one (Pan B) PACl'A6IN. . HEf WElGIlHER 6111llN srollAliE lEMi'fRAllJRE 1!MI'ruIlIRE RESlSrAHIl SHElf UFi ruSH i'tJIHf.SffA HooN &SAFEI'( Sman ro.. Cooslst:; of a partially rUled ""..gallon C!ln of Part A. • qllal't 01\'1 of PaIt 13 and a foil ' l"'d ofcb;ldreu. L r 􀁍􀁜􀁬􀁾􀁬􀁴􀀠,«Mi(o/" d'lllCd 􀀡􀁍􀁬􀁯􀁯􀁾lit nlOtrf 10 din" 1!i1k!11 􀁮􀁾􀁬􀁉􀁑􀀱􀀧􀀬􀀠till lI.liq tonlea al 􀀮􀀭􀀧􀁉􀁮􀀮􀁊􀁭􀁟􀀨􀁑􀁾􀀠tkJdil 􀁾/flttlm4 for fho fIlOS( >V!RM! ,.MCQ[ tell! 􀁾􀀮􀁤􀀠􀁉􀁡􀀻􀁉􀁍􀁉􀁉􀁾􀀠Of 􀁲􀁬􀁬􀁾􀀠"!if t(lllitl 􀁾􀁾lQ(lIm l'ft',,,aMttIrflf! 􀁴􀁉􀁉􀁉􀁦􀁑􀁾􀁬􀀠I' ldale,1 􀁾Old 􀁩􀁲􀁮􀁬􀁊􀁾􀁴􀁬􀁩􀁏􀁲􀁵􀀺􀁟􀀠C IMtcil 2004, by Tnemcc CQmp:ui}'. 1m:, 1076 11/62/2BB4 16-56 972-312 8468 TNEMEC BAR PAGE 62 SERIES 1076 􀁆􀁬􀁵􀁯􀁲􀁯􀁮􀁡􀁲􀀡􀀳􀁾􀀠Clear Al'PllCA:flO:>i ! Dry !\fils I Wet Mils SqFllGal (Microas) (Ml<:t'Oas) , (o>'/GolJ i SIlAAe:;;:tt:d 2.0 (50) I 3S (9Q) 449 (41.7) I Minimum 1.5(4j)) I 2.S (65) 599 (55.6) I I MiiJdmum 2.0 (50) I :;.; (90) 449 (41.7) I ..Atlow fQr o\-en.pmy and t:>'Utfare rl7egulanul!!:S. Film 􀁴􀁨􀁬􀁣􀁫􀁮􀁾􀀠is rounded to rhe nll:.'af't:S{ 0.5 mil or '5 MIXIKG POT UfE THINNING SURfACE ltMP!RATllif Al'IUCAlJON WUII'MEHT ",boos. Appllcatlon of """'Ilng bd<>w mlntmum or abooe maximum """""",ended dry film thl<:knesse9 may adve.rsely all'«t coatWg 􀁾􀀠 Slll:Ill Kit. Add con!l!l\t5 of me Vial of 44-500 TO PM A while under agitation. Mix thoroughly. Add con"""" of the qUM can marked Pan B 10 rhe m;ltion. Continue .glration until ;ill campen""'" are thoroug/ll!' mixed. Imp<>rtlItIl: MIxing ratio l$ four (Palt 1V to :,me C'Pn wj!b No.2 'Thinner. 'fhinning io required f(>, proper application. Qwt;o", Do 00< .dd lhinr 80'F Cl7"C): 2 hOllTS 9O"F (,3Z'C): I hour lOO"F (3R"C): 30 minut .. If the coating if> expo$ed to 􀁭􀁯􀁪􀁾􀀧􀁻􀁵􀁲􀁥􀀠before the prcCt':ding cure 􀁰􀁡􀁲􀁡􀁭􀁣􀀮􀀺􀁴􀁉􀀮􀀮􀁾􀁲􀁮􀀠are met, dull, flat or spott;'-appearjnt; areas filay develop. Acrual tiro<:n w$11 V,tty with air movement, tUm thk:kness 􀁾􀁭􀁤􀀠humidIty. !UrSpray I Gun Fluid !UrCap I Air Hose I Mat'! 􀁂􀀨􀀩􀀮􀁾􀁥􀀠Jl,tomlzlng I Pot i 'J'lp i ID ID Pressure 􀁐􀁾􀀢􀁴􀁯􀀢􀁕􀁲􀁥􀀠IDeVilbis.o; E 78 I 5/16" or 318" , 3/8" or 1/2" 75,90 psi I 10.20 psiMile (7.9 or 9.5 mm) l (9.5 or 12,., mm) tS,2·6.2 b:l.T) i (0,7-1.4 b:lf'J Low tftmpetaturet> or longer 􀁨􀁯􀁾􀀺􀀻􀀠require: 􀁨􀁾􀁨􀁥􀁴􀀠pot: pressure. Use appropriate tipJatomi?..ing 􀁰􀁲􀁴􀀮􀀮􀀮􀁾􀁲􀁥􀀠for <..-qv:ipmemt iipplicator tl::cnniqul;; .mcl weath<.."T conditlon..r;. Ronen Use 114" {GA mm) synthetic nap COlfet'. Do not 􀁕􀁾􀀠medium or long nap roUer ccwers. BrusJ>, Use high quality ru1tlm1l 01' syruhetic nt'i5t1£ bru$I"",. Flush and dtr.\n aU equipmt::nt 􀁬􀁭􀁭􀁥􀁤􀁪􀁬􀀱􀁾􀁥􀁊􀁹􀀠:U'ter u...;,e with thr,;:: Tecomrnended thinner or .MEK. . ,' ......llI[,1tf{ CUllt,UV I_COIPQUIlD 4100 (OUDUn: 111/Yf. 􀁕􀁩􀁓􀁾􀀠(fIr, 􀁍􀁾􀁏􀁢􀁉􀁊􀀠64120.1312 Ttt 1 BDB JIlEIoi( I '4'WW.foemcwm , PAGE 03TNEMEC-BARRV GROUP11/02/2004 16 54 972 312-8408 Endura-Shield'!' n SERIES 1075 PRomTr pROFILE 􀁇􀁅􀁎􀁅􀁾􀀨􀀠DESCRll'l10N Aliphatic Acrylic Polyurc"tlume OOAWON USAGE A coating highly 􀁾􀀢􀀧􀀱􀀺􀁩􀁬􀁊􀁬􀀮􀁴􀀠to abroLSion, wet cOl'lditions, corrosive fumes and t:'Xterror 􀁶􀀮􀀭􀁥􀁡􀁴􀁬􀀧􀁬􀁥􀀮􀁲􀁾􀀠lng. High build quality combines With pt'\)iect SpOciflC primers for two-c""t, Iab"r savlng sy'"'Stems. 􀁆􀀺􀁬􀀮􀁾􀀠GuriDg options ate :iVrufablc; see Curing Time below. PtQdllct 􀁴􀁾􀀠some applications as a direcr to metal ntlish. Contact your Tncmec rep,l.'e:lil:mmtivc: fot more dettills. NOT FOR IMMERS'JON SERV1CE. COlORS l\efer to Tn¢mec Color Guide. Note: Certain colors mOly J'equire mwtltple CQrtts depending on mc1hod of application .nd tmi!ih com colot. When feasible. the preceding co.t sho\lld be in the same color family, but no,ieeubly dlff",,,,,t FINISH Seml-g!o>S SPEGAL aUAUfllATIONS NOli!:< Serie$ 1075 ,=c:aH!iomia's SCAQMD, Rule 1U3 definltion for ',Rust P,."" ..... tive Coating" when used for 􀁭􀁭􀁾􀀧􀁴􀁡􀀮􀀮􀁉􀀠sunaces (Jtlly or for '"E.."i5eJ'irl:all'llbiic Service," $eties 1075 also meets the ""luiremem:< of SSPC-36 Pain! Stlndard. PERfllRIMN(E (RIllRlh ContaCt your Tnemec n;presenra:cl;v"e fot Specific 􀁲􀁥􀁾􀁴􀀠resultS. COATlXG S'YS"t.E!lf I'RlMERS' S1ecl; Series 20, FC20, Z'l. 66. N68, N69, 91-H,o, 90-97. 104, 135. 1'140,161,530 Galvanized S">cl and Non·Pet'1'()US Metab Series 66, N69, 161 Concre,,,, Series 66, N69. 84. 104, 161 oro, 54-660. 130. Intermediate <:Q.t required. Note: Udore roptO";ltjOg with Series lOiS, Series 530 t.:Xtertot exposed tl\Ql'«;: chan 24 hO\ln> 􀁭􀁾f.Lt'St be 􀁾􀀱􀁦􀁬􀁥􀁤􀀠or rt."Ceive an jntc.:rmediare coat of Tnt!tneC poly.:amide epoxy. 􀁾􀀠Series N68 exterior ""posed for 21 days or S<.'I'ies N69, 104, Nl40 or 161 exre:rlor expol1SIlitl'e) 0Si grnms/lirrc) 005 granWlltre) THIOR£lIGllI;OV!!AG!" 􀀱􀀮􀀲􀀰􀁾􀀠mllsq fl/gaJ (29.5 ro'I! ••t 25 microns). See Al'PUCATION for coverasc rates. LNIIMBEi OF COMPQNINlS 1'M>: P:m A and Port B [..•.MIXING RA11Il By volume, Eigbt (Part p,J to on" (PlU'[ 13) P,\IJAfjjNG Three Gan"" Kit! Cons;st, of. psrru.Uy-filled live-gallon can of Par! A "nd a partJnlly-filk'd half-gallon cao of Pan S. When mixed, yields three gallons (11.41.). One Gallon Kit; Consist. of • partially·filled one-gallon <:an labeled PM A .nd a ps1tiallyfilled pint aln labeled Part B. When mixed, yields vno gallon (:l.791). NE! WlISIIT I'EI1 GAllON' 12.75 ;; 0.25 lb. (;.BO '" .ll kg) SllJIIA6f TfMPEl!ATURE Minimum 20"F (-7'C) Maxim""" 110"F ('!I'C) TEMlWJURE IESISWlCE (!ley) Continuous 25O"F (121'C) Intcrmit"'n, 275°F 035"<:) Mlh,d llmid d&!g en! 􀁩􀁍􀀱􀀱􀁉􀁉􀁛􀀬􀁪􀁬􀁬 􀁾􀀱􀀠􀁾!uijm tr> '.ange tfllhw! noll,,_ tM tlllillt (mlaD ill ....􀀬􀀢􀁎􀁕􀁃􀀮􀁴􀁾􀀧􀀢􀀠til.;!'!! It 􀁈􀁴􀁬􀁬􀁴􀁾􀁴􀁴􀁤􀀠mlit 􀁾􀀧􀁉􀁉􀀮􀁉􀁉􀀠􀀬􀁾􀁉􀁦􀁕􀁉􀀠Juh!lltal ftll1' ud 􀁩􀁾􀁬􀁬􀀱􀁬􀀨􀁪􀀱􀁯􀁍 􀀠9f 􀁬􀁒􀁾􀀠ftI5f (1II101! roW! TUNf IlfllUl\lalm 1M UIIMlJ 􀀡􀁏􀀨􀀡􀀻􀁮􀁾􀀱􀀱􀀠􀁩􀁾􀀬􀀠PM IMlinfiillJ. o 􀁾􀁢􀀮􀁲2002. b'f Tnemcc COiUP;ltl}'. inc. 1075 TNEMEC-BARRV GROUP PAGE 04 TfCBNICAL OATA comirm<:d FlASII !'Oml· SffA Part A: 95°, (55'0 P-Aft 13: 155'F <57'0 ',-SHElf UfE 12 months at rect)1Jl11lended stot'age temper.,ture. HEAUH &SAFm 􀁔􀁨􀁌􀁾􀀠product contains chdl'lfcat It'Ign::dlet'lUi wltiC'h arc 􀁣􀁯􀁮􀁾􀁪􀁤􀁥􀁮􀀻􀁤􀀠bs.znrc!ol,ls, Read eontiUncr label warning at\d material $;1fery data sheet for impol'tWlt health Hnd 􀁾􀀢􀀬􀁦􀁥􀁴􀁹􀀠infor1't.latiot'l prior to the use of thl. product. Keep Odflce 􀁁􀁴􀁯􀁭􀁩􀁚􀁩􀁮􀁧􀁾􀀠Mat'l Bose ID Msnlfoldl'iIIt 0.009"-1>.013" (2110-330 microns) 3000·5500 p5l (207,241 bar) 114" or '18" (6.4 or 9.5 mm) 100 mesh (150 rolClCr>.') , Dry lIWs IWet Mils I SlJ. FtlGal Dryllllls "''''Milo 􀁓􀁱􀁆􀁴􀁬􀁇􀀼􀀱􀁬􀁾􀀠(lIIl. 􀁾""'Y ad.verscly atrtct ctmlng pedi:>rman<::eStir con.t:cnts of the conta1!ler nlarked Part A. roak:ing sure no pigment (t:mainf; on the bottOm. Add the Contents of the can nlat'kt:ci Part B to Pan A while under -.tgitation. Contln\Jt; agitad.on until the 􀁾􀁯􀀠cornpoot:nts are thoroughly mixed, W'ht:'n used "",1m 44-7l0 Urethane AccderatOf. first blend 44-710 infO Part A under agitation; continue .as a.bO'fe. Do not use mbc.c::d mncerial beyond POt life limits. Cantion: 􀁐􀁾􀁲􀁴􀀠B is moistu!'e-Sc::l\sitive I'm will n:act with aUlloSpheric fimlStuce. Unused 􀁭􀁡􀁾􀁮􀀮􀁬􀀠tl'lUST be kept tighrly closed at 􀁾􀀱􀀱􀀠rimes. lVl hours at 77°F (25°c) untb.inne.d Z bours at nOr (2S'C) thinned .For :nk or wIess :''Pray, thin up to 15'% Or llA pines (570 mt) per gallon with No. 42 Thinner if temperarun:$ are below 8{)1)F (ZrC), use No. 4S Thinner for temperatures abovu aOl>f (27"C). For brush .nd roll",. thin 15% or 114 pims (570 ",1.) per ll"llon with No. 59 Thinner. Note, Thinnlnz is 􀁲􀁥􀁱􀁵􀁩􀁾􀁤􀀠fOl' proper application. Omtlon.: Do not add thinner if mOie than &> minutes have elap",d aft., n"tlXing. Minimum 55'F (2'C) MmtJmum 120°F (49'0 The .umoe .mould be dry and at 􀁾􀁴,'F (,3'G) above the d.", point. Jf coating is 􀁥􀁸􀁐􀁬􀁬􀀤􀀨􀀮􀀮􀁾􀀠to rooistul"e before tile appUc.'\ble cure paramt;1:ers w<..: met, doll, flat or spotty 􀁾􀁴􀁰􀁰􀁥􀁡􀁲􀁩􀁮􀀬􀁧􀀠􀁾􀁳may devdop. Actual cure time will vary witl'l air movement, film thickne"s and humidity. Air Spray GUn Fluid AkCap AlrBose Maelaose I AtomiZing Pm Til' 10 In I """"sure Preosure OcV"dblSs E , 78 5/16" or 018' 318" or 112' I 75-90 psi 10-20 psi , MJlC (7,9 or 9.5 ••ol (9.; or 12.7 nun). 1 (5.2-6.2 bar) (0.7-104 bar) I ! lo\v ternperdture:t; or longer 􀁢􀁯􀁳􀁥􀁾􀀠requux higher pot pressure. Alri S->\>l1IY .. ..U:;c appropnate op/atollllZJ%lll pressure for equIp",.nlf applICator rechnltjue ""d ..,<:ather ccnditions . lIoII= !iii<) 1/4" (6.1 mm) syntnctlc 􀁮􀁾􀁰􀀠cover. Do'"ot use mediUtti or long nap ",U.,. ""'...,.. Two co.ts are requiresh, Recommended for small areas only. PSI: high QUality namral or 􀁓􀀩􀀧􀁬􀀱􀁴􀁨􀁾􀀧􀀱􀁬􀀼􀀺􀀠oo,-cle brushes. Two coats are required to obWtl r.comn:lI:nded flIm thlclrne.. above 3.0 milS 05 microns). CLFAl/UP Flush and clean alJ equipment imaleWotel, after U>c with the recom.tn<:nded thinner or MEK. .. Values may vary ......ith color. )IW{ (omn 􀁉􀁾􀁃􀁏􀁬􀁴􀁬􀁊􀁬􀁭􀁄􀀠 4100 COII'O«Tt MM, lAWS (11T, 􀁉􀁬􀁉􀀤􀁓􀁏􀁾􀁴􀁬􀀠t.mr.HJ12 Tn: I aou llIEMft 1 􀁗􀀧􀀱􀁦􀁻􀀮􀁴􀁭􀁬􀁭􀁾􀀬􀁑􀁬􀁭􀀠 11/133/2004 PAGE 02 PRODUCT PROFllE GENERIC 􀁄􀁦􀁓􀁃􀁾􀁐􀁔􀁉􀁏􀁎􀀠COMII.ON USAGE COIJlIlS -Q. FINISH SPBJAI. OUAUfICAnOOS II 􀀧􀁊􀀧􀁾􀂣􀁍􀁅􀁃􀀠COATING SYSTHf PRIMERS Polyamide Epon."y Indu.tty s!llntlard for .pm.:y coadtlgs for over 􀁾yellfS. Known for its forgiving aI'pJication d)aracte:il.'tic$ in adverse and vaned COnditions, 2nd for benchmark performance:, lWf'e.r to Tnemec CalOE Guide. Note.: Epoxies chalk with extended e>;;posurc to sunlight and may yellow on aging. :t.a.ck of ventilation, incompfett.: .rnixingt mi1>cata!yzation or the use of hestc:.rs that emit carbon diox.ide and carbon monoxide during applic-dtion and initial stagt.::s of curing msy accelcmte any potential yellowing. Satiu Moe" the performance n:qUiremeno; of 􀁁􀁾<: Z10 (not for polllble water .:ontact). 􀁃􀁯􀁮􀁲􀀮􀁾􀁣􀁴􀀠your Tnemec representative for system recommend:ttioos. Extensive (t;st data 􀁴􀁜􀁾􀁩􀁩􀀺􀁡􀁢􀁬􀁥􀀮􀀠Contua )'Pur 'I'nemec repn;sent:ltlvc for :;;pecific test results, ste<:J, Self-priming or Series 20. 3tH. N69, 90. 91.-H,0. 161,530 Gal'l>llJl.ized St<;el and 􀁎􀁯􀁮􀀭􀁬􀀻􀀮􀀢􀀮􀁊􀀺􀁏􀁵􀁾􀀠Mct:!h Self.priming Concrete, Self-priming, 54-<560, 201. 216, 216 eMU. 54-562. 54.660, 130, 216, 21R Drywall; 51·792 for dt:')l" interior environment:> 46H-41" 66, N69, 73, 1)4, 104, n3, 114. 161. 175,262. 265. 291. 1074, 1075 Rubstnlte and 􀁥􀁾􀁬􀁬􀁲􀁥􀀠 conditions, Coma.c{ yoUt TndUec l'epr:csenca:tive or Tnemt;c Technical Services. Contact your Tnemec representative 01' Tnemec 'Technical Services. Allow new COncrete to cure 2S days. Al),.....ive bl""t referencing SSPC-SP13/NACE 6 Surfilce Preparation of Concrete s.nd 􀁔􀁮􀁥􀁭􀁾􀀧􀁳􀀠􀁓􀁵􀁲􀁦􀁑􀀬􀀢􀁾􀀠Preparation at'l.c.1 Application Guide. Allow mortar to CUre fot 28 chys. Level protrusions And mortar spatter, Non-Immersion 5e:t"v.icc:::.Ask your Tn;mec repn:sent::ltivc fur specific recommendations. Must be dean, dry and free of oil. grea,e and other co""_",,. 56.0 ± 2.0% (mlxed) 2.0 to 6.0 mlls (SO to 150 microns) per COOt. Note, Nw:nl>er of c03l$:and 'lhidwess 􀁲􀁥􀁾wm 'Vary .....tt.. 􀁳􀁵􀁢􀁳􀁴􀀮􀁴􀀭􀁾􀀠ap plli:atlon method aad expos..,..,. Contact }'QUI' 1'n<:mee represenlatl.... . Texnpera!:llre To Touch To Handle 'to Ilt:coat Immersloll I 7,oF (24"C) Z hoy'" 10 hOUQi 12 hOOts I 7 day. CUring time 'Wlries with surface tempe1:'"..tture, a.ir movement, hUmidity and f11m thlclcness. Unlhin.ned Thiruled 5'/. Thinned 10% 􀁾􀀮􀀰􀀴􀀠los/gallon 3.221bs1gaJlon 􀁾􀀮􀀳􀀹􀀠lbslgallon (364 gr.unsIlitrc) (3SS grrun$ll(tre) (406 gmmslHtrel 896 Ill" sq ftlgal (22.0 m'IL .t 25 microns). Set APPUCATION for cov=ge r.lres. ']\v", Part A and Pm B 5 galion (18.91.) p:ws and 1 gaU"n (;.791.) cans -Orde,· in multiple, of 2. 12.50 ± 0.25 lb. (5.67 ± .11 kg) (mixed) Maxlmum 110"l' (43"C) MI1Jl1,d 􀀱􀁉􀁣􀁾qlD IMiMlnl(lIm lIro uLjed" 􀁴􀁨􀁄􀁾􀁾􀀠􀀢􀁩􀁴􀀦􀁾􀁴􀀠IJQlkt, lho Mil,. 􀁾􀁉􀁬􀁣􀁦􀁾􀁾􀀠II 􀁮􀀢􀀢􀁬􀁦􀁉􀁾􀁭􀁡􀀺􀁴􀀮􀀧􀁴􀁉􀀡􀁬􀀠melli' bm tllfwtn!td lei flii /lOS! 􀂫􀁊􀁈􀀸􀁦􀁴􀁬􀁬􀀢􀁩􀁮􀁩􀀬􀁾􀀱􀀠Hlv ond ond f:)fI1ditn> 􀁾􀁦􀀠rt"1lItI'I 􀀨􀁾􀁮􀁬􀁴􀁬􀁴􀀠ttYl TnlrMtt 'IIp1wli;'\lo!lT4 hll 􀀨􀁾􀀱􀁉􀁩􀀠latluoiffi fl.!tD 􀁾􀁾􀁤􀀠iQ1ltutIlOliI. f:. JOtlt' :t002, hy 'fnetl'lll'c COfnp:ltty. tnQ. 66 03 TEClL'ilCAL DATA continued Ifl!l!!AIDRE ifSlSTAHCE (Drf) Cootimlou. .. 250"F (\21"C) Intermittenr 27S"F (135"C) 􀁓􀁈􀁦􀁬􀁈􀁾􀁅􀀠Part A: 24 months; Part B: 11 months at 􀁲􀁾􀀨􀀮􀀻􀁏􀁭.."nc:nded 􀁳􀁲􀁯􀁾􀁧􀁥􀀠kmpermure, fL\SH POIII!· 􀁓􀁅􀁔􀁾􀀠fort '" 82'F (!R'C) P." B, 64'F (lS'C) HElIlH t S!ffIY P.s.int products contain cht.:rnical ingrecHeots wllk,""b are cuol;lic1e:e:d haZi MIXING FOT lifE THINNING SUifA£! llMPEi!tIM! APPUOOIQN EOOIPMENT Notet The above reflects 􀁴􀁨􀁾􀀠[!)\:.Il 􀁲􀁡􀁮􀁧􀁾􀀠tt) which Series 66 call he: ...ppJied for spetific :o:ppli.i;;ation.", To inS\lfe th.c proper thickness and number of CQats is specified for Certain subsrr.J.tC!6 3.nd expOlWres. como-ult the "ncroec Guide Specifications; and/or cont;tcr Ytlur Tnemec tt;przsellt&tivt:. Note: RoUer or brush appliC!Ltioo may rti!ujre twO or more C(,at=, to obmin re:t:Q,mmendt::tl film tl1ickne.,<;s. Allow fc)r ()\'I:::rsprny and svrfuce irre::;ulariries. film thicknea :Is rounded t() the nellt1!S( 0:5 mil Or !) mjcmns. A?pli<':<'tlon of coating l,)eJow rrdnimum ()r :.;:t,ove-ma....imvm recolYlmcn<£ed dry fUm thickness:::s mll)' adverse:1y 􀁾􀁦􀁦􀁥􀁣􀁴􀀠coating performance. Po,,""\:[ nllx C(lntt:ntt' of each container. making: ,$ute no pih'rn<.m[ .I-emWnt; on 􀁴􀁨􀁾􀀠bu{[nm. POUI' a t!'lt:'.f-...iJrccI 1UnmJnt: of Part B intt;; ;l clean Ct.;nl.aice.r larse enough to hl)}d both component:;, Add an e:qu:ll volume (1f Part A to Part B Mlilt:: under 􀁾􀁕􀁬􀁴􀁴􀁯􀁮􀀮􀀠COntinu e 􀁾􀁺􀁩􀁴􀁡􀁴􀁪􀁯􀁮􀀠l.lntU the twO components are Uu:1ro\,lghly mixed. Do nut 􀁕􀁾􀀠J'tli'red matl..'Tial beyond pot. life limiu. Noit::: Both components shuultllx; above SOc,P (1D"C) prior tt, mixing" For appiicjtion to 􀁳􀁵􀁴􀁦􀀧􀀮􀁌􀁃􀁃􀁾􀀠􀁢􀁥􀁲􀁷􀁾􀁣􀁲􀁴􀀠􀁾􀁆􀀬􀀠to 6DI'F (10°(; to 􀀱􀀶􀁾􀁃􀀩􀀮􀀠atlc:rw miXed m:llcn31 to stand thirty (30) 30) .m.inutes and restir berme: u.,oting, For optimum Jppliclltlon propelties, blended comp£lm::nfS should be: abo;.-c 600f (16°(:;), Mbtit:Ig ratio i." one to one by vohmte. 20 hour$;tt 50°F (10°(:) lO hO\.lfS ar 77"1" (25°C) 4 hO\lfS at 100°f 􀀨􀁾􀁃􀁊􀀠􀁴􀁊􀁾􀀠1\0,4 'I'hlnm:r. llot' ai:' sPr'.J.Y, thln up to 􀀱􀀰􀁾􀁜􀀠Of 􀁾􀀠pint (£S80 mt) 'Per g.:lllon. For aIrlt:I>s "1'r.'-y, roller or brush, thin up to 5% or 􀁾􀀠pinc (190 mI.) per 􀁾􀁬􀁬􀁯􀁬􀀩􀀬􀀠 MinimUnl 􀀵􀀰􀀡􀀩􀀱􀁾􀀠OOlle) M,U::imUill 􀁬􀁾􀁗􀀧􀁆􀀠(S79 C) Tile!: 􀁾􀁵􀁲􀁦􀁾􀁣􀁾􀀠􀀵􀁨􀁯􀁜􀁊􀁬􀁴􀁬􀁬􀀻􀁴􀁾􀀠dry and at least ,oF (;OC) abvvc rhc dew pclinL. Coating VIm not cure below mill.1nlLlln Kur'fute telUper'J;t\lJ"e, Air Spray I Gun Fluid lAir Cap! Air .!lOSe Mat'llWse IAtomizlnll i Pot jTl:p 'lD m 􀁾􀁵􀁲􀀮􀀠i P""""ure I DeVilbiss E 76, I5/16-"'r 5/S" 518' or 112' 175-100 psi i 10-20 psi , lMllc orlGA I or 79 (7.9 "" 9S rom) (9.5 or 12.7 mIn) (5.2·6.9 !lac) i (0,7.1.4 h.r)' Low teotpetkltutTtS or luoter hoses n!tjU1!"C htgher 􀁰􀁯􀁾􀀠pressure. Airless Spray 0.015--0.019' (380-485 m;c-rons) 1500-3000 psi (124-207 bar) I 1/4"' or 3/S" (6,4 or 9.5 nun) I 60 mesh (250 micro••) Use appropriate tip/lltomizine; prt.:$wre for 􀁥􀁱􀁬􀀮􀁴􀁜􀁰􀁭􀁥􀁴􀀮􀁉􀁾􀀠appllcmor tec:hnJque and weather (:nndltlons. Ncm=: AppiiQltioo over fOOIg..'\Oic Zinc-ridl primers: 􀁁􀁰􀁰􀁬􀁾a ""et mist l,;(lat 􀁾􀁮􀁤􀀠allt)\V tiay bubhlC$ ro fO:n}1, When bubo"", c: with tilt' rccommf:'ntie:d thinner or J'rIEK. +vruUC.ti may vary with color. wamm &U'«!OOlUM 􀀡􀁬􀁾􀀠stUIt's mlllUN; inm< ttmpClly, 11K. 􀁍􀁴􀁴􀁉􀁈􀁬􀁉􀁾􀀠fl.+( ilK:t Its [.tlIt\l 􀁮􀁉􀁾􀁤h.UM mtd '" 􀁦􀁾􀁦􀁭􀁶􀁢􀁩􀁵􀀠􀁊􀁬􀁾􀀢 (It IlIuu", 􀀨􀁐􀁬􀁉􀁉􀁐􀁾􀀱􀁴􀁦􀀮􀀠!tv.. iiIf WAIURtY nUtillrtiUlll1t 􀁕􀁾􀀧􀀧􀁜􀁾􀁾􀁗􀀧􀀡􀁦$1Wt It ,. UW Of An (lnlte 􀁾􀁲􀀬ImtSSto OR IMPlIED, lK{tmJlG BUi mrr UJ!rrtt roo Alif IilfUto WUWll"t 􀁏􀁾􀀠,m(jWIlelUnOR flfMSi 􀁦􀁾􀁾􀀠 IAffl(UW: I'IIWOSE. JIlEKi' Ilt NO WAitllilUS 1m mUID 􀀸􀁦􀁭􀁬􀁬􀁾'!HI: O&ilr1l01l 0Ji lin fACE Ill®f. U, 􀁫􀁴􀁴􀁬􀀧􀁷􀁾ONJ 􀁴􀁊􀁤􀁾􀁩􀁎UIII';dy 􀁾􀁬􀁬􀁬􀁦􀁾􀀨􀁇􀁬􀁉􀁉􀁉􀀪􀁉􀁾􀀬􀀠111(.111'" hi fll 􀁦􀁴􀁾􀁦􀀱􀀡􀁜􀁕􀁉􀀠tI tAl D(ODW-j., tile _ Ctml:l1n lII.ft olbJ!Oirla 􀁾􀁾􀀢􀀱􀁉􀁴􀁦􀁉􀁉􀀱􀁾􀀠.1l51 t6Il th: 􀁴􀁊􀀻􀁤􀀢􀀧􀁾􀀻􀁬􀁉􀀧􀂻􀁉􀀡􀁖􀀠mlR flO1t.M laiWlIl 'l1AllI'IIl9\I.--,oJe 1lliln;!Ii ll'lflllt( i:; 􀁾􀁉􀀮􀀧􀀡􀁉􀁉􀀠I( IIlniLirfMU'lllb1t _CfllQ1'l1 􀁾􀁯􀀱􀁴􀁲􀁯􀁬􀁫􀁴􀁾􀀮􀀠liO Olllli ROOm tt.\1WI!iG, M 􀁉􀁉􀁉􀁉􀁲􀁴􀁬􀀮􀁬􀁬􀁬􀁬􀁬􀁴􀁬􀁬 􀁬􀀮􀁬􀀧􀁎􀁴􀁬􀁄􀁂􀁉􀀧􀁨􀁬􀀧􀁾􀀠􀁾􀂻􀁍􀁕􀁊􀀺􀁩􀁾􀁓􀀠IDIMJ rroms. 􀁕􀁉􀁓􀁬􀁓􀁾􀁴􀁓􀀮􀀠UUUrtllmRSDIl(1g HIJPEtn, W1'!kOkbllmllllJUPJElOUMY 􀁄􀁬􀁬􀀡􀁴􀁴􀁬􀁾􀁃􀁭􀀡􀀺􀁋􀀧􀁲􀁵􀁯􀁴􀀠{tI1iSRlulJlnu IDS!) SlW.l at: mlWU 10: b!E BUTiL 􀁬􀀺􀀮􀁣􀁦􀁬􀁾􀁉􀀨􀁃􀁜􀀠r...I 􀀧􀁲􀁐􀁾􀁴􀁬􀁬􀁤􀁮􀀠􀁩􀁾􀀢􀁾􀀹􀁦􀁴􀀡􀁮i, Of"wc III ltoo;wplJ!S! of dIlIH",,*,g t ItMM pMldl d tho rulint lIh:I JIIO!OI tcttmo 􀁴􀁉􀁪􀁉􀀺􀁾􀁜􀀨􀁉􀁮􀀠911tdllm, 􀁲􀁾PtifuMIOICII 􀁴􀁭􀁬􀁬􀁾􀀠wmfllltutlll: 􀁾􀁨􀁾􀁾􀁴􀀴􀀮􀀱􀁉􀁴􀀱􀀱􀁬􀁴􀁬􀁬􀀧􀁜􀁬􀁘􀀠􀁾􀀱􀁊􀁘􀁬􀁾􀀠\ltdcim 􀁦􀁢􀁴􀁩􀁬􀁬􀁴􀁥􀀺􀁾􀀠􀁉􀁾􀁊􀁲􀀠wm: olm)em. 􀁯􀁘􀀨􀁾􀁬􀁴􀁬􀁴􀁬􀁲􀀠􀁾􀁃􀁬􀁗􀁬􀁦􀁤􀀡􀁃􀁬􀁗􀁩􀁬􀁬􀀡􀁬􀁬􀀧􀁋􀀱􀀧􀀡􀀻􀀬􀀠M Q.Ii=, 􀁾􀀡􀁵􀁲􀁴􀁬􀀢􀀻􀀡􀁉􀁉􀀧􀁬􀁉􀀡􀁥􀀡􀁩􀁉􀁾􀀠fNlmcuo 􀁗􀁩􀁉􀀩􀀧􀁾􀀨􀁏􀁲􀁦􀁬􀁲􀀮􀀠i. (JnII 􀁾Mnu:iKd i\ 1!it:te1crK«\IIIi 1M J lit 􀁊􀀺􀁬􀀱􀀡􀁬􀁉􀁾􀀡􀁉􀀮􀀠filllllDl51l1A.L un liliiT, illfAfi (OJMAk'f 􀁉􀁬􀁩􀁲􀁯􀁴􀁐􀁏􀁾􀁾􀁈􀁉􀀡􀀠 6100 (!Ii/OW! IIllVl. WlSAS mY, MI5S0lJll 04121H312 f![: I iOlJ T/iEMR I Iff/ld,cmeUDlll PAGE 64TNEMEC-BARRV GROUP11/63/2604 13 9 972 312 8468 Tnenle-Zinc 90-97 PRODt'CT PROFILE GINfRI< DfSCRIPIlON Aro.tru:ttk Urethane. 2inco.Ricl1 CO/MIOl1 USAGE An wvanced tedmologf, two-COmpOIlCIDt, moistUrt':--cured. zinc-rich primer providing exnnordinary pefor:trutnce. It's user friendly 􀁾􀁮􀁤􀀠r.4pid curiJ'lg 􀁾􀁯􀀠that c.:henlica1-and COtTO5ionw(csistant topec.us can be appUed thG ""Sa.m.t." height of work, ",••ther conditiOt\S and equipment adjustment. le>w temper.orure ,. of particular concern, Test for each application as ['OlIow", Spray from 15 to 25 feet [(,ward. paint OOOtainer, The marerial thon shollld readily wjpe off. 1'1otoo H<:a' can 􀁦􀁾􀀢􀀬􀀬􀀭􀀼􀁬􀀱􀀧􀁊􀀧􀀠o"""pray to surfaces. AlwaY" CCU!S. Be aware til" SUtf4Ce tempcratute$ COU1 be higher than air temperature. COV!!AGE ItI.lf5 QVcrsptay and FHtn CO 􀁴􀁨􀁾􀀠nearefi.t 0.5 mil O.I' 5 micron:;. Application of coating minimom or above maximum rt:commended dry rufO thiclme.«es may adver.",ly affect c'Oatinj) performance. MIXING Always use tbe entire CQnl<:nts of A and B comporn:nt!i. Use an air-ttion, keep under low RPM agitation r<) l'"",,c'!lt settling, For brush or roUer application, stir freq\lendy 10 P'''''''nt settling, Do nOI use mixed n1l1terlaJ bOyond pot life limits, I'(JT UFE 8 hours at 7i'F (25'C) and 50% R.H. caution: This prodL.lCt C1Jres wlrh moisture acting 􀁾a catalyst. lI1.corporotion of moisture or moisture laden 􀁾􀁩􀁲􀀠(humidity) during use wjJl shorten pot 􀀱􀀱􀁾􀀮􀀠Avoid continual agitatiotl at high RPM. When 􀁦􀁥􀀺􀁬􀀮􀁾􀁢􀁬􀁥􀀠k..,p containerS of mixed materi,1 covered during use. THINNING For sprny, thin up It) 10% or 'l'l pint (380 mlJ per gallon with No. 2 Thinner iftl!mperalUni$ aT<: below 80'1 O;rC), Tnin up to 10% or" pint GBO mLl per gallon wlIb No, 3 'Thinner if lWIperarures "'" above 80'1 (27"C). For brush or roUer; thin up to 10% or '>I pint 880 rnl,) 'iV1th No. 3 Thinner. 00 not thin ma'" than 2.50/, wben. air pollution "'f!'.,I.tiOWl limlt the .tmospheric discharge of volatile organic compounds (\rOC) in coalinfls to a maximum of 340 grunsl1ltre (2,80 ibslgal), SURfACE TfMPERA1URI' Minimum 35'F CZ'O Maximum 120'< (49'C) Mwrimum for Bn.>Sh &: Roller 100', (38'C) The 􀀤􀁾􀀮􀁣􀁥􀀠should be dry ll1ld at Ie-••t ,'F (3'C) .bove the dew point. APPUCATIOH EQUIPMEkT 1'1<>1<> When lloil;h COatS are white or ligbt colors, best hidin,g of tbls dark color primer Oln be achieved by spray appiict.tlon; OJ' when roner applied, by using !4" nap covers. AlrSpray i Gun Fi1:,cl All: Cap Air Rose I _'l8'_ A_g l'r!"'sure IlD II> P:I:'£;.55UteI aink> No. 66 63 PB 5/16" or :va" i 318" or 1/2" "0-50 psi 10-20 psi i lSor62· (7,9 or 9.5 rom.) <95 Qr '-2.7 mm) (2.8·... bar) , (0,7-1,4 bar) . "• {\oVlID heavy mastIc sprlflg) Low lempenlHlres or JOJ'lger hoses W'IU reqUIre addl.uooa.1 pteS.'iUre, Use pre.ruture pot equipped with at') ligitator and k.eep presmJl¢ pot at same l(:,"Ve[ or higher than tho .pray gun. Compressed air must be dIy. 􀁾less Spray 'fipOrifiO! AtomiziDg _rc _'IRosell) ManJfoId. Filter 0,011'-0.021" 2400-3000 ""I • 1/4" QC :VS" 6Om",", (450-535 enl""",) (165-207 bar) (6A or 9.5 ,nrn) 􀁾􀁄mlCl'OllS) Re"",.ibl. Tip , , . . U'" appropdste 􀁴􀁩􀁰􀀯􀁾􀁾for "'l"'pm<:ru. "ppl=r rechnique and weather conditions . Keep material agitated to prevent settling. Rolkn 'use .. 1/4" or 3/8" (6,4 rnm or 9,5 1M» S)nthetic nap cover. Stir material frequently or keep under agiratlOn to prevent settling. BrusJ>, Ure high. quality natur>! or synthenc briStle bru.>;hos. Flush opd clean aU equipment immediately after use with the recommended thinner ,,, ")'Iene. 􀁗􀁾􀁬􀁗􀁩􀁲􀀡􀁾Of SUtlfS t!I!!!.n1': 111l:11101: coawrr. 1111:. ",,",QIII' 􀀰􀁉􀁉􀁬􀁾􀀠􀁾􀁬􀁬􀁮􀁾􀁮􀁰􀀡􀁬􀁬􀁴􀁬􀀧􀁬􀁬􀀺􀁊􀀠􀁾􀀧􀀪􀁴lIu 􀁦􀁾IlonilorCi trlt¥m:r(OIIII\4r.t. 􀁾􀀠l'Iit mallfl BE5CIIU' tN tilE UM twWPllruIi If Ii lIiU Of AU OtllH w,Um. OO'UlSfD OIIIUPutD. 􀀡􀁾􀁡􀁗􀁬􀁴􀁎􀁇􀀠aliT m 1It\I,.tirQ ro,,VlJ IitUf.D 􀁷􀁾􀁲􀁍􀁬􀁬􀁬􀀠Of MttrHIlII1,U11IT ot flTb'Ui rOll tAETIOIIJf 11.1l1'DSt llltu AU HO WWRI1lIS llUT moo ifY01!J TIlE DtrolPl'lOS til TRE Uti 1I!imr. ThQ b'l'l'ff'ulli oN! Old. tt....w 􀁾􀁭􀀩􀀺􀁴􀁲􀁊􀁬􀁴􀁬􀁬􀁜􀁴􀀨􀀠c.ruCtiy, 􀁉􀁾􀀠lW" fill' 􀀱􀁉􀁉􀁾􀁉􀁯􀁣􀀬􀁍􀁴􀁴􀁉􀁬􀁉􀀠vile 􀁾􀁉e!llt Ill'Wdillmain 1lIIIdI!lold It" JI!)IiI{fJIKruIii it 􀁾􀁦􀁒􀁾􀁲􀁴􀁣􀁤􀀠It. 􀁾WlftrM lilt bml hi&.! 􀁩􀁉􀁉􀀮􀀢􀀬􀀬􀁾􀁾􀁉􀀡􀀠plilpm CI _, 'I Imurlnd!J;ll II ,JJ'I'\IIt 􀁍􀀩􀁾􀁉􀁬􀁉􀁢􀁉􀁾􀀠rlfbWhllI 􀁾􀀡􀁄􀀧􀁬􀁒􀁦􀀠I; lilt 􀁾􀀮􀁉􀁉􀁄Ollla 􀁬􀁢􀁉􀁴􀁏􀁬􀁾􀀮ilJT '1l1l1AIDUI Ttl, 􀁬􀁾􀁢􀁬􀁬􀁉􀁷OR tCNSEQl)!1!f1M. Ow.A;iS 􀁾􀁏􀁾􀀠Lon'lWlB, LOST SI,tU, 􀁉􀁉􀁕􀁕􀁒􀁾􀀠10 fWOH O. UUPfrrt 􀁏􀁏􀁉􀀦􀁏􀁾􀁍􀁦􀁭􀁌􀀠IlIlIlil50R MY OM! IHtlN/fUl rn COfiiIU!.'(HTIAl tOSSI 􀁓􀁬􀁕􀁴􀁾􀀠tE li'WBU 1lI TIll NIYU. lrddIl:IIl 􀁾􀁭􀁾􀁾􀀧􀁬􀁨􀀮􀁲􀁦􀀡􀁬􀁯􀀱􀁫􀁩􀀱􀀠milliI pnl'llilld fut ll'.6 􀁾􀀡􀁬􀁃􀁫􀀠01 􀁾􀀱􀀱􀀡agmml pJ!IIG Illite W'"i _ prlll4l urIm; IpptlOrlon ,11tt6.n. Jol 􀁾􀁤􀁯􀁭􀁾􀀮􀁉􀁴􀀺􀀡􀁴􀀺􀁬􀁴􀀠.:tII __11'10 1'l!eI!IIII;iI4IMII_II!I 􀁖􀁉􀁉􀁉􀀧􀁉􀁾􀀠(DIIII'ny.M 􀁤􀁾􀀡􀁮􀀩􀀠IIr.Ir rinse IIlIU( 􀁾􀀱􀁉􀁦􀀠􀁉􀁉􀁾􀁴􀁴􀁾􀀮􀀬􀀠􀁾􀁄􀁬􀀴􀁩􀁾􀀠􀁾􀁯􀁦􀁬􀁬􀁮􀁙􀁗􀁍􀁦• .l: 􀁑􀁐􀁰􀁉􀁊􀁃􀁉􀁉􀁉􀁾􀀠􀁴􀁴􀁴􀁾􀀬􀀭􀁬􀁩􀁌􀀠􀁾􀁗􀁟􀁢􀁲􀁴􀁯􀀡􀁾􀀠11'11 􀁴􀀧􀁉􀁉􀁉􀁙􀁩􀁾􀁤􀁬􀁃􀀴􀁤􀁴􀁲􀀬􀀠errt t'JfO 􀁊􀁾􀀢􀀬􀁾􀁬􀁈􀁤III 􀁴􀁨􀁾􀀻􀁩􀁦􀁉􀀧􀁤􀀠􀁉􀁬􀁕􀁊􀁦􀁬􀁩􀀻􀁷􀀺􀁲􀁉􀁾􀀮􀀠fOl 􀁬􀁾􀁮􀁬􀁩􀁓􀁔􀁬􀁉􀁁􀁉􀀮􀀠U5fOu't . 􀁬􀁾􀀡􀁲􀁵􀁬􀀠(OIU.IJIf 􀀡􀁬􀁉􀁴􀁯􀁬􀁬􀀧􀁄􀁷􀁴􀁾􀀠 o.!OO OI'IPOlAlt IIrlVt WS;.s CIll, IilSSQUII 􀁍􀁬􀁾􀁔􀁊􀀱􀀲􀀠lH: 18en 1!U!t 1 􀀧􀁬􀁦􀁦􀁩􀁊􀁍􀁮􀁮􀁣􀀮􀀨􀁾􀁬􀁬􀀠 From the desk oj-Jenny Nicewander, P.E. Project Manager PO, 80x 9010 (972) 450-2860 Addison, TX 75001-9010 Fax (972) 450-2837 e-maiJ: jnkewander@cLaddison.tx.us Date: __________ ..... ".', --------------------------_... COOK SURVEY , NO. 326 PLANO COMPANY 1248. PG. 3622 F (1.0289 ACRES) Jl= 􀀧􀁕􀁾! . PARCEL 10 ----._. 􀁾􀀠......-y>'-----5/8" I.R.F. -----W/'DC$A .......... { --.--. -􀁾􀀵􀀯􀀸􀂷􀀠I.R.F. -/'􀀭􀀭􀀭􀁾􀀭􀂭(' 􀁾􀁃􀁁􀁐􀀡􀀡􀁬􀀠EDWARD COOK SURVEY { 15101 ADIlS'Qff m.} ABST. NO. 326 THE FILLING STATION OF ADDISON, INC. V" VOL 94100, PG. 5577 •.j 3,666.5 SF (.OB42 ACRES) SvLTl"/1V k. C{fAtv/"f;tEDWARD COOK SURVEY j .ABST. NO. 326 /" SAULS JAMES E ,v 􀁾􀁢􀁲􀁬/j11f1.VOL 77153. PG. 1028 5/B" I.R.F. (/'" t1\ 􀁾􀀠1 33.713 SOH. (O.774, ACRES) Wj'DC$A /I?rJ. AI p.v 1 {; [ t.I r 􀁾􀁶􀀠to 􀁾􀀠(,\ ,\Q fJ t hf ( 15201 I.!)I)IS(lI RIL ) I iw.c.w:HA R!S11.W!tHT !l {l/t/f1r •....I -{\􀁩􀁚􀀧􀁾􀀧---.PARCEL 1 ._--􀀴􀁾􀁾􀀠5'011 '"M .1 I 1/2" I.R.F. PARCEL 2 ! i I I \ 'fi/!:wMf---l I g', 􀁾􀀮􀀭􀀮􀀮􀁥􀀮􀁶􀁲􀀠􀁉􀀢􀀧􀁾􀀧􀀠'1' -y--_._.-I 􀁾"King Fabrication 􀁓􀁰􀁥􀁣􀁩􀁡􀁬􀁩􀁺􀁩􀁮􀁧􀁾􀁩􀁮􀀠Manne & Industrial Fabrication Providing: .. Structural Steel Fabrication .. Aluminum Fabrication .. Stainless Steel Fabrication .. Large Pipe Fabrication .. Shearing, Forming, & Burning Services For: .. Marine & Industrial Applications 􀁾King Fabrication L.L.C. + 19300 W. Hardy Road + Houston, TX 77073 + + Phone (281) 209-0811 + Fax (2811209-1774 + e-mail sales@kingfab.com + 􀁾King Fabrication Specializing in Marine & Industrial Fabrication 􀁾King Fabrication L.L.C.• 19300 W. Hardy Road. Houston, TX 77073 • • Phone (281) 209-0811 • Fax (281) 209-1774. e-mail sales@kingfab.com. 􀁾King Fabrication Specializing in Marine & Industrial Fabrication 􀁾King Fabrication L.L.C.•;. 19300 W. Hardy Road 0) Houston, TX 77073·:. .:. Phone (2811209-0811 .;. Fax (2811209-1774·;· e-man sales@kingfab.com':' 􀁾King Steel &Supply Warehousing, Distribution & Sourcing Carbon, Stainless & Aluminum Structural Shapes ( W, s, WT, M, C, MC, L) ASTM A36 -ASTM A572 ASTM A588 -ASTM A992 All Shapes and Sizes Available Stock Lengths are 20' -60' Cut To Length in 5' Increments Carbon Plate Low Carbon AISI1008 Medium Carbon AISI1045 Hot Rolled Structural Quality ASTM A36 ASTM 283-C High Strength Low Alloy Plates ASTM A572 Grade 50 ASTM A588 Grade A ASTM A656 Grade 50 Pressure Vessel Quality ASTM A515 Grade 50 ASTM A516 Grade 70 Structural Quality -High Strength Alloy ASTM A514 Grade 70 Floor Plate ASTM A786 Abrasion Resisting Alloy Plate AR225 Please Call for stock sizes Sheet and Coil Hot Rolled ASTM A569 ASTM A570 ASTM A36 High Strength Low Alloy ASTM A606 Type 4 ASTM A607 Grade 50 Cold Rolled ASTM A366 Coated ASTM A653 CS and LFQ: Galvanized and Galvannealed ASTM A463 Type 1 Aluminized Please call on available Plate and Sheet sizes in stock. Bar Grating Carbon -Stainless -Aluminum, All grating may be ordered in full panels panels or fabricated to your specifications and plans. Carbon Tubing and Pipe All Schedules Hot Finished Seamless Cold Drawn Seamless DOM (Drawn Over Mandrel) Cold Drawn Butt weld A512 ERW A513 ERW Hollow Structural Tubing Sold in Mill Lengths Carbon Steel Flats and Bars Commercial Quality Low Carbon AISI 1018 AISI1020 Medium Carbon AISI M1044 AISI M1045 Structural Quality ASTM A36 ASTM A529 Grade 50 High Strength Low Alloy ASTM A572 Grade 50 ASTM A588 Grade A Stock Length is 20' Fittings Forged Steel -Socket Weld Pipe Nipples -Weld Fittings Flanges -Hammer Unions Stud Bolts -Gaskets -Weld Studs Stainless & Aluminum Fittings Fasteners Threaded Rod Hex Bolts & Machine Bolts U-Bolts & Grating Clips All Grades of Carbon, Plain and Galvanized, Stainless and Aluminum Available ! ." Galvanizing & Coating Services Available Visit Us On The Web at http://www.kingsteelandsupply.com Or E-Mail toinfo@kingsteelandsupply.com 􀁾􀀠King Steel &Supply L.L.C.•:. 19300 W. Hardy Road .:. Houston, TX 77073 .:• •:. Phone (281) 209-0811 .:. Fax (281) 209-1774 .:. www.kingsteelandsupply.com .:. 􀁾King Steel &Supply Warehousing, Distribution & Sourcing 􀁾􀀠Carbon, Stainless & Aluminum Stainless Plate Type: 304, 304L, 31SL Stock Widlhs: 3/1S" -3" Standard Lengths: 8 ft., 10ft., 12 ft., 20 ft. random Stainless Sheet Type:304,304L,31SL Stock Gauges: 10 Ga., 11 Ga., 12 Ga:, 14 Ga., 1S Ga., 18 Ga., 20 Ga., 22 Ga., 24 Ga. Call for stock sheet sizes Stainless Tread Plate Type 304 Thickness: .125" -.250" Call for stock plate sizes Stainless Angles T304, T31SL Stock Length is 20' -24' Random Stainless Flat Bars T304,T31SL Sizes: 1/8" -1/2" Stock length is 12 ft. Stainless Square Bars T303, T304, T31SL Sizes: 1/2" -2" Stock Length is 12 ft. Stainless Round Bars T303, T304, T31S, T31SL, T41S Sizes: 1/8" -8" Stock Length is 12 ft. Stainless H -Beams T304 All sizes in 19' -20' Random Stainless Channel T304, T304L, T31S, T31SL All sizes in 19' -20' Random Stainless Pipe Assorted Grades & Schedules Single Random Lengths Aluminum Plate Non Heat Treatable 5083-H321 5052-H34 Heat Treatable 2024-T351 SOS1-TS51 7075-TS51 Stock Sizes 1/2" through 3" Call for stock plate sizes Aluminum Sheet Common Alloy 3003,5052 Heat Treatable 2024, SOS1-TS, 7075-TS Stock Sizes: .020" -.190" Call for stock sheet sizes Coils are also available in: 36". 48", 60" Widths .020" -.250" Thick Aluminum Tread Plate 3003-H22, 508S-H11S, SOS1-TS Thickness: .125" -.250" Call for stock plate size Aluminum Pipe SOS1-TS Stock Sizes: 112" -12" Schedules 40 & 80 Other Grades & Schedules Available Stock length is 20 ft. Aluminum Angle SOS1-TS,508S-H111 Stock Sizes 3/4" x 3/4" x 1/8" -S" x S" x 112" Stock lengths based on mill availability Aluminum Flat and Square Bar 2024-T351, SOS1-TS, 7075-TS Stock Sizes: 1/8" -S" Stock length is 12 ft. Aluminum Round Bar 2024-T4, SOS1-TS, 7075-T351 Stock Sizes: 1/4" -S" Stock Length is 12 ft. Aluminum Structural Shapes SOS1-TS I-Beams, H-Beams, WF-Beams Channels, Tees, Zees, Tubing Stock length and sizes are based on mill availability Call for stock shapes and sizes 􀁾􀀠King Steel &Supply L.L.C.•:. 19300 W_ Hardy Road .:. Houston, TX 77073 .:• •:. Phone (281) 209-0811 .:. Fax (281) 209-1774 .:. www.kingsteelandsupply_com .:. 􀁾King Fabrication Specializing in Marine &Industrial Fabrication (. Material Processing Services .: • • AWS Certified Welders. Carbon. Stainless. Aluminum • • Skids. Pipe Racks. Structural Steel. Large O.D. Pipe • • Pipe Fittings. Miscellaneous. Docks. Walers • • Bollards • Fenders • Bumpers • Dolphins • • Shearing • Forming • Burning • Sawing. 􀁾King Fabrication L.L.C.• 19300 W. Hardy Road. Houston, TX 77073 • • Phone (281) 209-0811 • Fax (281)209-1774. e-mail sales@kingfab.com • 􀁾King Fabrication Specializing in Marine & Industrial Fabrication .:. Material Processing Services .:. Member American Institute of Steel Construction AISC Certified Fabricator Complex Steel Building Structures In-House Structural Detailing -AutoCAD@2000 Domestic & Overseas Shipping 􀁾King Fabrication L.L.C.•:. 19300 W. Hardy Road .:. Houston, TX 77073 􀀮􀁾􀀠.:. Phone (281)209-0811 .:. Fax {2811 209-1774 -:. e-mail sales@kingfab.com.;. King Steel &Supply Warehousing, Distribution & Sourcing Carbon, Stainless & Aluminum Plate Beams Piling Pipe Sheet Tees Tubing Fittings Flats Angles Grating Fasteners Bars Channels Rail Marine Accessories 27,000 Square Feet to; 􀁾􀀠Overhead Crane Yard 01 lOT 22,000 Square Feet 1􀁾􀀠Under Roof lOT With Overhead Cranes 􀁾􀀠lOT 13 8 Acre lOT Laydown Yard I..(') ",crl""&&1=::Co , I F< Beltway 8 􀁾􀀠, Houston 􀁾King Steel & Supply Co. + 19300 W. Hardy Road + Houston, TX 77073 + + Phone (2811 209-0811 + Fax (2811209-1774 + e-mail kingsteel@mmcinc.com + . :. " . :'. : . ,:' ..' 􀁾􀀮􀀠, ,"-; ,', ."" ,', .'," 􀀮􀀭􀁾􀀬􀀮􀀠' , , ' .1'" -:'." '. :... '" ' ... ,,.," 􀀢􀁾􀀠ROBERTSON ENG INC '. _. ., ..... . , , '. '. " . ' ;', '.-'. . ;.'; .-'.' ',: ." . ,", . 􀁭􀁾􀁀􀁾􀁏􀁗􀁾􀁛􀁉􀁄􀀠DEC 29 2004 HNTB CORPORATION DALLAS, TEXAS December 29, 2004 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen Letter: HNTB -26 RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control Plan for Surveyor Blvd. Dear Guy: Archer Western is submitting the attached traffic control plan for the RCB pipe crossing and pavemenl replacement for Concrete paving. We propose to swilch traffic on Monday, January 3, 2005. If you require addilional information, please contact Andrew at our field office. A rew Schneemann Ass!. Project Manager Enclosure XC: Ben Withered Don Good File Traffic Control -Surveyor Blvd. 1) Work Prior to Phase I Traffic Switch a) Saw Cut Existing Roadway Paving b) Excavate Westside of Surveyor Blvd. for Temp Asphalt c) Install 8" Temp Asphalt 2) Phase I a) Traffic is moved to the west side of Surveyor Blvd. b) We will install line A & B to +/-Centerline of Surveyor c) Install Lateral '2' d) Install 8" Temp Asphalt e) Switch Traffic 3) Phase II a) Traffic is switched to the east side of Surveyor Blvd b) We will Install Lines A&B to Station -1+79 c) Install Permanent Paving without curb on west side of Surveyor Blvd. d) Install Temp Asphalt west side ofsurveyor 4) Phase III a) Traffic is switched to the west side of Surveyor Blvd. b) Install Permanent Paving on East side of Surveyor Blvd. 5) Phase IV a) Single Lane Closure with Flagger b) Remove Temp Asphalt c) Install Permanent Curb on west side of Surveyor Blvd. , """'" 􀁾􀀠"""'" ""---. ! //" f : , ' GENERAL TRAFFIC CONTROL NQTES I. 'tHE' TRAme eOJ'{fAOI.. S>fOWH ON THESE: P\.AHS IS 1'OR THE PREPAUTI(lN "NO CO).fP.u-4VEWElU IoIAAXINGS. ,IlOolOvt: TnoIPORNI'( PAIlEMon \WlKINGS ANO ACTIVATE nv.mc SIGw.t.S (HO SEPARATt PAT) _____________ "If 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭/􀁾CUlVCftT CONstRUCTION Non' n:!ACTOR; SH.4t.l IJ£ PtNifTE!) TO Clost ONE HAlF OF SUtrlEYOR in.VO. A' A TIME 'JIIOoI1U; 􀁗􀁁􀁬􀁦􀁲􀁴􀁔􀁾􀀡􀁈􀁃􀀠OHE HI-FOOT TRAFFIC lANE FOR o,cH ()fq£CTJON ; ! ; I /1 J I J-----f--------------", I I /I I I "., " I, I I , ; p', ---"----SHT. TC-l G(NERAL TRAF"F"!C CONTROL NOTES .' t. THE TR.lFFlC CONlf(Ol,. SHOWf.l ON THESE PLANS IS FROY.!... IN Ocr.l!... A CONSTR:UCl101" SCH£DU!.L SEQUtNCt or CONSTRUCTION ANO ntlFRC CONTROL Pl.4H THAT muu.. CAuSE ),I!HIWU\.i INfERf"EREHC£ WlfH TRAmC AlONG. ACROSS AHO AOJACENT TO THE PROJ£CT CURIHG COHSTRUCTIOH. IF' THt SCHEDULE O.R SEOlJ£KC£ 8£COWES UIlWOR1Ooet..£ OR UN$..I.1!SF'ACTOItY M. WORK PROCEEDS. A£lJUSTWtNTS SHAU. 8£ MAOE• ./z.. ACcm TO Au.. 􀁓􀁉􀁏􀁾􀀠S1'RErn AND PRIYA1t PROP£RTY "lofUST BE loU.!NTAINED AT ,\LL TholES UNLESS OTM£RWISE 􀁁􀁉􀁊􀀢􀁦􀁩􀁉􀁏􀀧􀁎􀁚􀁾􀁏􀀠IN WIlffiHG BT TH£ TOWH OF ADOISOH. 3. UGlm:D 8.utRIC.\OtS. TtWPOIVoI!Y PAY£)JENf WARKINC$ AHO ctfA/'fflEUZlJ«; DE.VlttS C:OHfOStI.tl.HG TO THE CURRENf £0(1'10/11 OF THt W.U.T.t:..,. SHALl. at USED DURINe AU. STAG£:'> OF' CONS'll'1JCT10N TO CON'flI:OL TRAF'flC F'I.OW Tf-IROUGH THt WORK ZOM£S. A.. WAlN1'AUf A IotIHIWUW RADIUS OF' :ro FEET OH AU. STRUT COHlrlECTlOHS .t.N0 10 r£rr ON AU. URJvt'W4Y CONNEC7!ONS IiURING COH'S'l'RUcnON TO A-CCOWWOOA-Tt THE: TRAmc USIHC nit ROADWAY DURING COHSTRUcnOH. S. C:OKTRACTOR 'SHALL 8£ RESPOHSlSl.( rOR TEWPORAR'I' loURJI(JNCS. I)HTlL 'SUCH nw:t SlGN1'\LS CAN BE ACl'rYA1tO. 1$. AT om Of ALL P.HAS('S Of COIosrRUCTlOH. COH'J'RACTOft SHAll. couPt£f£ rtNAl. PA\'tWOU MARKINGS. RnI0VE 􀁾􀁐􀁏􀁉􀁗􀁮􀀧􀀠P"V£MOO WARKIHCS AND AcnvATE TV.tFlC SlCNAlS (HO SEPARATl: PAil 0 􀀭􀁾􀀭􀀭􀀽􀀭􀀭............ ............ , , 􀁾􀀠, 1 􀁾􀀠, 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀁾􀀠, , --------------------------------/􀁾􀀠1" 1 /20 /,I ..I} /l'" I /I ,, I I I I rI __ l f 1 1 SHY. TC-1 􀀮􀁾􀀠-," "'" 􀀢􀀭􀁾􀀧􀀭􀀭􀀭􀀭􀀭J..9Hj Ipr'CfS I 0'r,'r! ?t)'h?S NO. OF COPIES SHEET NO. LAST DATED DESCRIPTION 3 12/29104 Traffic Control Plan Surveyor BlvdJor Box Culvert Crossing ········..··········· ················ ...·1···············....................... ·f······································ ·1····················································........................................... ....................................... ....... ...... ..·········.. ··· ..·..·····..·..··1.. ·············· .......................................................................................... ............................... ..... ..... THESE ARE TRANSMITTED: l!!fFor approval D Resubmit __capias for review D No exceptions taken (NE) D For your use D Submit __ copies for distribution D Make corrections noted (ME) D As requested D Return __corrected prints D Amend and resubmit (AR) )8(For review and comment D D Rejected -See remarks (RE) PLEASE NOTE: 􀁾􀁾􀀼􀀺􀀺􀁩􀁜􀁬􀁴􀀺􀁾..􀀡􀁩􀁉 􀁊􀀮􀁾􀁾􀀮􀁾􀁾..􀁦􀀨􀀩􀁾..􀀡􀁲􀀮􀁾􀁣􀀮􀀮􀁣􀀮􀁯􀀮􀁾􀁴􀁬􀀺􀀨􀀩􀁬􀁧􀁾􀀮􀁾􀀮􀀨􀀩􀁬􀁬􀀺􀁧􀀮􀁾􀁬􀁉􀁲􀁹􀁾􀀨􀀩􀁲􀁽􀀧􀁬􀀱􀁜􀀧􀀴􀂷􀀮􀁀􀀮􀀬􀀡􀀺􀀵􀁑􀁰􀁊􀁅􀀮􀀬􀀠COPY TO: File Michael Ebeling, HNTB Corporation File rMrn@rnowrn@DEC 29 2004 HNTB CORPORATION DALlAS, TEXAS December 29, 2004 Letter: HNTB -26 HNTB 5910 W Plano Parkway Suite 200 Plano, Texas 75093 Attn: Mr. Guy Van-Baulen RE: Town of Addison Arapaho Road Phase III Project No. 04-22 Traffic Control Plan for Surveyor Blvd. Dear Guy: Archer Western is submitting the attached traffic control plan for the RCB pipe crossing and pavement replacement for Concrete paving. We propose to switch traffIc on Monday, January 3, 2005. If you require additional information, please contact Andrew at our field office. A rew Schnee mann Ass!, Project Manager Enclosure XC: Ben Withered Don Good File Traffic Control -Surveyor Blvd. 1) Work Prior to Phase I Traffic Switch a) Saw Cut Existing Roadway Paving b) Excavate Westside of Surveyor Blvd. for Temp Asphalt c) Install 8" Temp Asphalt 2) Phase I a) Traffic is moved to the west side of Surveyor Blvd. b) We will install line A & B to +/-Centerline ofSurveyor c) Install Lateral '2' d) InstallS" Temp Asphalt e) Switch Traffic 3) Phase II a) Traffic is switched to the east side of Surveyor Blvd b) We will Install Lines A&B to Station -1 +79 c) Install Permanent Paving without curb on west side of Surveyor Blvd. d) Install Temp Asphalt west side of surveyor 4) Phase III a) Traffic is switched to the west side of Surveyor Blvd. b) Install Permanent Paving on East side of Surveyor Blvd. 5) PhaseIV a) Single Lane Closure with Flagger b) Remove Temp Asphalt c) Install Permanent Curb on west side of Surveyor Blvd. , , , "'<"". 0 􀁾􀀠---------, ", , " , , '" ',;11' //1 iea .' :1 ,',i , tt-􀁊􀀧􀁾􀁾􀁚􀁟􀀠􀁾􀀨􀁩􀁬􀁩􀀿􀁴􀀺􀁬􀀠􀀮􀁍􀁲􀁁􀁾/.' GENERAL TRAffiC CONTROL NOTES L THE TUrriC CONTROL SHOWN ON m.:st P'I.AKS IS rOR 'nIE PIi£PJdtA,TIOH AMO C!)IoiPARISQM Of!' SIOS ON!.Y. SORrOR TO TIle STARi or CONSTRUCTION. TH£ CONTRACTOR SHAU. ilMLOP Ml:tern.' T C!!:J11l"'eCiJlf'SW TT W T F SIS M T T F SIS M T W F SISMActivity Description Prod 15 20 27 28 29 31 1 SUBS/NOTES Excavate/Embank Brickyard 13 14 16 17 18 21 22 23 24 25 30 X XX X X X X X X LX /' V XBox Culvert Line A X X X X X X X X X X X X X X VX /' Box Culvert Line B X X XX X XX /' V :Roadway Embankment X X X X XX X X X X XX X VX /' X /' Midway Median Detour Work X X XX /' /' V. 10" Sanitary Sewer X X X X X X XX X X X X X VX /' X /' Line C & Laterals W A I T I N G /' V Laterals Line A & B X X X X X X X X X XX X X X V/' X /' Bent 10 Arms X X /' /' V Trench Sub :Trenched Retaining Walls X X X X X XX X XX //' /CIP Retaining Wall X X XX X X X///Drilled Shafts X X ATSX X X XX X X X X X X XX //' /.Columns XX X X X X X X X/' /' /Caps X XX/' /' /' Bent #9 X XX X X XX X/' /' /' /X )( v v v v ./Longhorn IJack & Bore line C e-U/.Inlet Spec. Inlets _.SENT BY: FINANCE DEPARTMENT; 972 450 7096; DEC.9.0412:f3PM; PAGE 1/2 HNTB 9726615614 12/09 '04 10:42 NO.768 01/02 􀀱􀀺􀁉􀁾􀁩􀁩􀀽􀁊􀀠Fax'the 􀁩􀁯􀁾􀁴􀁦􀁪􀀠􀁃􀁉􀁴􀀢􀀧􀀧􀀧􀁉􀁦􀁾􀁩􀁵􀀠Transmittal 􀁔􀁏􀁾􀁾􀀧􀁾􀀠Dote \ 1./"'/'1 T atol Poges "Z... 􀀨􀁩􀁉􀀱􀁃􀁬􀁵􀁤􀁬􀁾􀁧􀀠Ihl$ cover)Firm To 􀁾􀀠...f. 􀁴􀁲􀀮􀁬􀀮􀁾....... Fox fI (, 1'1.) 'SO --:f.o1c., Job Number. o High 􀁒􀁥􀁳􀁯􀁴􀁵􀁾􀁯􀁴􀀧􀁬􀀠o urge"t Please notify sender at 972·61S1-5626 if pagllS ore l7.lis$ing or. if there is Qny tt1In$mi.njofl diJiiculty: Message 5910 Wm Plano PlJr/cwo),. 􀁓􀁬􀀢􀀻􀁾􀀠200 • Plano, TeXa$ 75093 Voice (9121661·3626· Fox (9721661·5614 • • • SENT BV: FINANCE DEPARTMENT; r172 450 7096; DEC-9-04 12:1aPM; PAGE 2/2tlNTB 9726615614 12/09 '04 1U:4, NO. roo U/:./Ut:. FOR OFFIce USE ONLYNON.HAZARDOUS Customa, Ace. No. _______WASTE. MANIFEST TIcklil No. GENERATOR 334453.WMI »tJie. ,􀁇􀁊􀁭􀁾􀁾􀁴􀁴􀁮􀁧􀀠􀁬􀁾􀀱􀁴􀁑􀁮􀀠MeP to: y.. JF! "t; drtlit1r'l A$i: Brian Sim,Nome lilli/A 01 Addl••n 􀀮􀀺􀁉􀁾Welt 1"1l1li10 PI4/fy. 5uil>.l 200; Pleno,􀁔􀁘􀀽􀀷􀀺􀀮􀀺􀀮􀁾􀁏􀀺􀀮􀀺􀀹􀀺􀀺􀀮􀀧􀁾___Addl'll5 Well 01 Addisanl.......,aho In! S1eta 􀁇􀁥􀁾􀀮􀀠ID No•..;".::,A:-___________Addl_TX Phon.. No_________ _____ Gen. uS EPA 10 1'4•. 􀀮􀀮􀀺􀁎􀀺􀀻􀀻􀀮􀁁􀁾__________ IWASTE CODE I􀁾􀀰􀀸􀁾􀁒􀀠I WASTE DESCRIPTION IQUANTITYIUNITS 1 YdS I I !. I CODES: D= DRUM; B '" BAG: C =CAFl'TON; P '" POUND;Y =YARDS; 0., OTHER ,htIIII!y cootilp 91ft"",'.-􀁾􀁥􀁱"""JfoI[.,,I. ( ..., "'" a h",,-.,. "'''e ..d61_by dO.CPr< P.;n 241 or ony oppIk:aCll .,••••􀁾􀀢􀀬􀀠_. _ wtSle ho, _ prq>erly dttc<1bt<1••IM1111td and flOdCllIIId. Jndis in P_'OII600. SLEEVE: Die cast glass-reinforced reSin, mechanically fastened to reflector and fully silicone gasket. SHUTTER: Injection molded glass fiber reinforced polymer. Removable with a quarter turn c/w Porcelain body lampholder, 4kV Mogul Base c/w a injection molded silicone gasket (duro 60 shore A). Adjustment to obtain the various IES distribution is tool-less. Distribution type: (SC2F), Type II, Short cut off, fiat lens. LENS: Flat protector made of c1ear'iempered glass, 0.20" (5mm) thickness and shock resistant. LAMP HOLDER: Porcelain thermo-resistant pulse rated 4 Kv mogul base. LAMP: (400MHBT28), 400 Watt Metal Halide, lamp forma! BT2S (ANSI Code M59) (not Included). BALLAST: 400 Watt Metal Halide, lamp format BT28 (ANSI Code M59), 240 Volts, high power faclor, -20·F (-30·C) lamp starting capacity, c/w polarized quick disconnect plugs with positive lock. TERMINAL BLOCK: Receives wires (#8 max,) on primary circuli c/w ground lug. ADJUSTMENT: An integral part of the housing permits an adjustment of ± 5". MOUNTING MEAN: Two brackets, formed in a single-piece, made of stamped galvanized-steel (12ga.). Accommodates tenon ranging between 1%" (38mm) to 2 3/8" (60mm) 00, fixed by 318 -16 UNC steel zinc plated. FINISH; (SC), Special Color: PC14825. Hot dip chemical etching preparation with minimum 3 milS (75 microns) polyester powder coat finish. Durable exterior finish. resistant to UV. salt spray and humidity as per ASTM G7, ASTM B117 and ASTM 02247 testing procedures. . ® 7734,DOC 07·22-2004 Registered to ISO 9001 :2000 . 'File No. A11750 Page 1/1 HP LaserJet HP LASERJET 3200 DEC-7-2004 3:18PM Fax Call Report Job 987 Date 121 712004 Time 3:17:10PM Type Send 1111l'11w.v􀁾􀀧􀁉􀁘􀀬􀀷􀀵􀂫􀀩􀀱􀀠􀁉􀀧􀁩􀁶􀀺􀁍􀀺􀁭􀁾􀀱􀀶􀁏􀀠􀁆􀁵􀁭􀁾􀀱􀀠Fax 3200se invent Identification Duration Pages Result 918172156038 1:12 3 OK TOWf1 of Addison ""-􀁉􀁦􀁉􀁲􀁲􀁲􀁴􀁎􀁾􀀽____ __I 􀁾􀀱􀀬􀀲􀀰􀀰􀀴􀀠􀀧􀁾􀀧􀀱􀀠... 50 YEARS OF FUN! 􀁩􀀡􀀮􀀻􀀺􀀻􀀻􀀺􀀻􀁾􀀺􀀧􀀺􀀧􀁾􀁾􀁾􀁾® Post Orrice Box 90B) Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this projeet, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September I", 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works!City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUNI OFFICE OF THE CITY MANAGER (972)4S0.700t 􀁾􀀠FAX (972) 450·7043 p!)st Office Bux 9{HO Addison, Texas 7SfHH-9010 5300 BI:It Line ROAd 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.cLaddison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works/City Engineer who will bc happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, 􀁴􀀼􀁾W U:t.:::::J Ron Whitehead, City Manager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER (972) 45(;..7001" FAX (972) 450·7tJ43 m6isoN ® Post Orfice Box 9010 Addison, Texas 􀀷􀀵􀀰􀀨􀁈􀁾􀀹􀀰􀁊􀁏􀀠5300 Bdt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension ofArapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.cLaddison.tx,us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. Ifquestions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works/City Engineer who will be happy to answer any questions you may have, As always, we will make every effort to be responsive to your needs and concerns. Cordially, 􀁾􀁾w'iJ;]c:::J Ron Whitehead, City Manager 50 YEARS OF FUN!.At)6isoN OFFICEOFTHECITYMANAGER f912} 450·7001. "'AX (972) 450·7043 ® POSt Office 􀁮􀁯􀁾􀀠!IOU} Addison. Texas 􀀷􀁓􀀰􀀰􀀱􀁾􀀹􀀰􀀱􀀰􀀠53flO Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any time/ine adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one of these staffmembers: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works!City Engineer who will be happy to answer any questions you may have. As always, we wiil make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUN! 􀀭􀁩􀁩􀁩􀁩􀁩􀁩􀁩􀁟􀀢􀁟􀀢􀀻􀁟􀁾__iio__oii_iii!lliii--® Post OFfice Box 9010 Addison, Texas 75001-9010 OFFICE OF THE CITY MANAGER (972) 450-7001. FAX (972) 450·7043 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staffmembers: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director ofPublic Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUNl OFFICE at' THE CITY MANAGER (!l7l) 4S(l..7001 " 'FAX 5972) 450·7043 Post OUice D!)x 9010 Addison, Texas 􀀷􀁓􀀱􀁬􀀰􀀱􀁾􀀹􀁄􀁉􀁏􀀠5300 8elt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison. lx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staffmembers: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works/City Engineer who will be happy to answer any questions you may have, As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager AI􀁾􀀠! 50 YEARS OF FUNl.ADDis'8N OFFICE OF THE CITY MANAGER 1972t 45fi,.7OO1 .. FAX t9'lZl45l)-7f)43 ® Pos.t Orrice-Box 9010 Addison. Teus 7S001w90JO 5':;00 Of'lt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1$1, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one of these staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works!City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 􀁾􀀠􀀬􀀬􀁾􀀬􀀠® 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER (9721450-7001· FAX (972) 450-71)43 Post Orricc Box 9010 Addison, Texas 7S00t-9010 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. Thcy and we -will make every effort not to interfere with the operation of your business. Thcir working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.cLaddison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1 st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, Whitehead, City Manager 8􀁟􀁾.. ·L 50 YEARS OF FUN!..AI)t)ISoN OFFICE OF THE CITY MANAGER 197Z! 450-7001 • FAX (9721450·7043 ® Post Office Box 9010 Addison. Texas 75001-9010 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that tbis project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect oftbis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutcbian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic WorkS/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUNI OFFICE OF THE CITY MANAGER (972)450-7601" FAX t9?2} 45{)..7043 Post Office BIIX 9010 Addison, Tblls 75001·9010 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themsclves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager ii!i!i-------® Post Offiee Gox 9010 Addison. Texas 75001·9010 OFFICE OF THE CITY MANAGER 50 YEARS OF FUN! 19721 45(V7001 .. FAX (9721 45{i·7043 531}0 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.cLaddison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER (972) 450-7001-FAX (972) 450·7043 Post Orrice Box 9010 Addison, Texas 75001·9010 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th , 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one of these staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager Manager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER (972) 450·700J· FAX (9721450·7043 Posl Orrice "ox 9010 Addison, Texas 75001·9010 5300 Belt Line Rond 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th , 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director of Public Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Man ager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER f272}45ij.7001-FAX (9721450-7043 P(l.st Office Box 9010 Addison. Texas 7S001·90H) 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension ofArapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ei.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1 st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one of these staff members: Steve Chmchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director ofPublic Works!City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, -􀁒􀀭􀁗􀁾... 􀁾􀀠Ron Whitehead, City Manager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER (972) 450·7001 • FAX 197;2) 450·7643 P'()j!l Office Box 9010 Addison, Texas 75601-9010 5301} Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you wili begin to see activity along the right-of-way after August 91ll, 2004. They and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect of this project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.cLaddison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager/Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, ) Ron Whitehead, City Ma nager 50 YEARS OF FUN! iii.--".iiiiiii!!ooiiioiii.-® Post Office no;\: 9010 Addison. Texas 75001-9010 OFFICE OF THE CITY MANAGER (972) 450.7001. FAX (972J 450-7043 5300 Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th , 2004. They -and we -will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1 st, 2004, Public Works staff and contractor representatives v ..:ill stop by cach affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthesc staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director ofPublic Works Mike Murphy, PE, Director of Public Works/City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager _AL 50 YEARS OF FUN! ..AI)-:[)IsoN OFFICE OFTHE CITY MANAGER (972) 450·1001 • FAX !972l 450.1043 ® Post Office Box ',H)H) Addison, TexBs 1S001·9GB) 5300 Bel! Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around August 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you will begin to see activity along the right-of-way after August 9th, 2004. They -and we will make every effort not to interfere with the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time with a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one ofthese staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public W orks!City Engineer who will be happy to answer any questions you may have. As always, we will make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager 50 YEARS OF FUN! OFFICE OF THE CITY MANAGER f972} 450-7001 • FAX (972i45ti.704)iiiiioiiiiiiiiiiooiiiiiiojiiii.---® Post Office Box 90U) Addison, Texas 75001·9010 53l.iO Belt Line Road 16 July 2004 Dear Business Owner: For some time now, you have been hearing about the extension of Arapaho Road from Addison Road to Surveyor Boulevard and the addition of a bridge over Midway Road. Construction on the $17 million project will start around Augnst 9th, 2004 and is expected to be completed in 425 days. While we are excited that this project, when completed, will reduce traffic on Belt Line Road, we recognize that you may experience some inconvenience during the construction period. We have selected the Archer-Western Company as the contractor and you \vill begin to see activity along the right-of-way after August 9th, 2004. They -and we -\viII make every effort not to interfere \vith the operation of your business. Their working hours will be arranged to minimize the effect ofthis project on your employees, customers, and guests. You will hear from us from time-to-time \vith a postcard update showing progress to date and any timeline adjustments. A link to photos and project information will also be posted on the Town's web site at www.ci.addison.tx.us on a regular basis. The project is being managed by the Town of Addison's Public Works Department who has retained HNTB Engineers for daily oversight. In the next few weeks and before September 1st, 2004, Public Works staff and contractor representatives will stop by each affected business to introduce themselves and answer any questions you may have. If questions come up after their visit, please call Public Works at 972.450.2871 and ask for one of these staff members: Steve Chutchian, PE, Project Manager! Assistant City Engineer Jim Pierce, PE, Assistant Director of Public Works Mike Murphy, PE, Director of Public Works/City Engineer who \viII be happy to answer any questions you may have. As always, we \viII make every effort to be responsive to your needs and concerns. Cordially, Ron Whitehead, City Manager