• 1.a C> Jim Pierce From: Mike Murphy Sent: Friday, October 24,200310:04 AM To: Chris Terry Cc: Kimberly Bettis; Jim Pierce; Steve Chutchian Subject: Addison Road Keller Springs Intersection Chris, As part of NTTA's response to our letter informing them of the construction of Arapaho Road Phase III they requested that we take action to acquire the necessary ROW for the improvement of this intersection in a manner coinciding with the construction of Arapaho Road Phase 1I1. .. and also complete the intersection construction. Status: We have a completed set of intersection plans that were drawn up as part of 7 eleven Jack in the Box development. We know how much ROW is required to complete this project (24,000 sq. feet). Estimated Cost of Project Including ROW acquisition: $300K for roadway and intersection improvements ROW acquisition (24,000 sq. ft) at $5.00 -$1 O.OO/sq ft) approx. $200K Enqr & Utility Relocation $125K TOTAL $625,000 Available funds $163,000 in Addison Road/Kelier Springs Improvement $211,000 in DART DART LAP Funds <.. 􀂫􀁾􀀢􀀢􀀧􀁧r...VV1 J $250,000 in Addison Road Widening (This number can be increased if needed) TOTAL $624,000 1Itike Michael E... Murph.':!. FE.. Director of Fublic Works (972) +50-2878 Work (2 I +) 2 15-5280 Mobile (972) +50-28}7 Fax E-Mail mmurph!j@ci.addison.tx.us 1 invent HP LaserJet 3200S8 HP LASERJET 3200 SEP-12-2003 3:09PM Fax Call Report Job Date Time Type Identification Duration Pages Result 397 9/12/2003 3:0B:17PM Send 92147493670 1: 17 2 OK UP LaserJet 3200se II' I,ASf.RJU ::1m S(p.II,ZW) ",32fM Fax Call Report Time T}'Pe Jdentificat101'1 Duration Paees Result 1;11 '" -;P"3J'2:t::'" «,'" 􀀭􀁾􀀠AlJI>ISON PtJBUcWOI\K$ fl' 129 &p.iI c "J>h@"'" 0""""'..... 􀁾􀀬􀀮􀀮􀀮􀁟􀀠om ceso_ 􀁾􀀮􀁾􀀠 HP Laser Jet 3200se HP LASERJET 3200 SEP-II-2003 3:32PM Fax Call Report Job Date 379 9/11/2003 Time 3:31:21PM Type Send Identification 92147493670 Duration 1: 11 TOW1iOP ADDIsoN PUBLIC WORKS To: Jti'JlJ 130&+11 From: Jim l'ieree, P.E. r Asst. Public \VIis. Dir. Compll1lY: ]IIliZ"r"" l'bo••: 91'21450-2879 FAX: 91'21450-2837 FAX#: 1; "'-7fj-3b 7u l...""'"".d.......􀁴􀁌􀁾􀀠D.t.: @-II-O::;' 16801 Wt3Igrove F.O,Box 9010 # of pages (illclDdlDg oo..􀁲􀀩􀀺􀁾􀀠 Addison, TX 75001-9010 Re: DtH!r LlfPIC/1'J5 fkqmmV o Origin_' fa uWJ 􀁾􀁇􀁑􀁲ntquli'lt 0 FYl DCdme 􀁣􀀽􀁭􀁾􀁵􀀨􀁦􀀺􀁴􀀺� �􀁾􀀺􀀠invent Pages Result 2 OK FUNDING APPLICATION FOR DART's LAP/CMS PROGRAM LAP/CMS Project No. (for DART use only) city no. project type project no. GENERAL INFORMATION Date Submitted 9-10-03 • Applicant City: Town of Addison City CIP No. • Project Eligibility Type: (see list, reverse side) Roadway Improvements • Project Name: Arapaho Road, Phase III • Boundaries/short description: From Addison Road to Surveyor Boulevard • Approx. BeginlEnd Dates: from Present to June 2005 ________ FUNDING PROJECTED COST DISTRIBUTION Current LAP/CMS Request $ 1,189,625.88 PlanninglEnvironmental Studies Previously Approved LAP/CMS Date (s) 11112/02 $ 983,250.00 EngineeringlDesign $ 1,396,722.00 Federal (if applicable) $ Right-of-way $ 3,378,000.00 State (if applicable) $ Construction $14,247,135.00 Local (if applicable) $15,416,169.12 Testing/Inspection $ Other (if applicable )Dallas County $ 1,432,812.00 OperationslMaintenance $ TOTAL $19,021,857.00 TOTAL $19,021,857.00 DETAILED PROJECT DESCRIPTION (ListlExplain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justi fication as needed.) (List/explain fund transfers, reprogramming requested ifapplicable.) See previous project description. This application is to re-program funds from our CAP account and LAP/CMS account to our Arapaho Road Phase III project as follows: Capital Assistance Program Fund: Addison RoadlExcel Way Intersection Improvements $ 236,800.00 Belt Line-QuorumlMidway Intersections Pass Project $ 321,547.83 Unprogranuned Fund Balance $ 0.61 LAP/CMS Program Fund: Addison RoadlExcel Way $ 76,500.00 Belt Line: Quorum and Midway Intersections $ 535,956.00 Unprogranuned Fund Balance $ 18,821.44 Total $ 1,189,625.88 Director ofPublic Works Title Date DART Staff Concurrence Title Date --J\I)6isoN PUBLIC WORKS DEPARTMENT (972) 450·2871 􀁾􀁾􀀠_ 􀁉􀀢􀁾􀀠___􀁾__ 􀁾􀁟􀁲􀁳􀁴􀁾􀂮􀀠Post Office Box 9010 Addirum,'l'exBs 75001-9010 July 22, 2003 Mr. Trip Brizell Capital Programming Senior Manager Dallas Area Rapid Transit P.O. Box 660163 Dallas, TX 75266-0163 Re: Addison CAP and LAP/CMS Funds Re-programming Dear Mr. Brizell: The Town ofAddison wishes to re-program funds from our CAP account and LAP/CMS account to our Arapaho Road Phase III project as follows: Capital Assistance Program Fund: Addison Road/Excel Way Intersection Improvements $236,800.00 Belt Line -Quorum/Midway Intersections Pass Project $321,547.83 Unprogrammed Fund Balance $0.61 LAPI CMS Program Fund: Addison Road/Excel Way $76,500.00 Belt Line: Quorum and Midway Intersections $535,956.00 Unprogrammed Fund Balance $18.821.44 Total $1,189,625.88 Also, I would like to know what our fund allocation is for FY 2004 as soon as it is available. Please call me at 972-450-2879 ifyou have any questions. Very truly yours, Town ofAddison tt.:ih)Assistant Public Works Director cc: Chris Terry, Assistant Ci1;y Manager Mike Murphy, Director of Public Works Randy Moravec, Finance Director Carolyn Burgett, Accounting Manager Enclosure RESOLUTION NO. R03·0SS A RESOLUTION OF THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS, APPROVING THE REPROGRAMMING OF DART FUNDS FROM THE CAPITAL ASSISTANCE PROGRAM (CAP) AND THE LOCAL ASSISTANCE PROGRAM/CONGESTION MANAGEMENT SYSTEM (LAP/CMS) PROJECTS TO THE ARAPAHO PHASE III PROJECT. WHEREAS, DART has allocated funds to the Town of Addison for various projects; and, WHEREAS, such funding has been allocated through the Capital Assistance Program (CAP) and the Local Assistance Program/Congestion Management System (LAP/CMS) accounts; and, WHEREAS, such funds has provided for completion of various street and intersection improvements projects within the Town; and, WHEREAS, remaining funds are still available on certain completed projects and low priority projects; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS: Section 1. That the City Council hereby approves the reprogramming of $1,189.625.88 from the Capital Assistance Program (CAP) and the Local Assistance Program/Congestion Management System (LAP/CMS) projects to the Arapaho Phase III Project as follows: Capital Assistance Program Fund: Addison Road/Excel Way Intersection Improvements $236,800.00 Belt Line -Quorum/Midway Intersections Pass Project $321,547.83 Unprogrammed Fund Balance $ 0.61 LAP/CMS Program Fund: Addison Road/Excel Way $ 76,500.00 Belt Line: Quorum and Midway Intersections $535,956.00 Unprogrammed Fund Balance $ 18.821.44 Total $1,189,625.88 OFFICE OF THE CITY SECRETARY R03·055 PASSED AND APPROVED by the City Council ofthe Town of Addison, Texas this 27th day of May, 2003. R. Scott Wheeler, Mayor ATTEST: 􀁂􀁙􀀺􀁾􀁃􀀽􀀽􀀢􀀢􀀢􀀢􀀺􀀮􀁌􀀮􀀮􀀭􀁬􀁉􀁁􀀺􀁩􀁨􀁾􀀫􀀭􀁌􀀮􀀺􀀺􀀺􀀺􀁜􀁎􀀬 􀀭􀀭􀂭Carmen Moran, City Secretary APPROVED AS TO FORM: By: 􀁾􀁴􀀭􀀯􀁾􀁍􀀯Ken Dippel, City Attorney' OFFICE OF THE CITY SECRETARY R03-0SS 􀁾􀀬􀁒􀀵􀀭􀀯􀀠 Council Agenda Item: ;IR5' SUMMARY: 'This item is to seek Council approval and a resolution to re-program DART funds from completed or low priority projects to the Arapaho Road, Phase illProject. FINANCIAL IMPACT: Provides additional funding for the Arapaho Road Phase illProject. BACKGROUND: Over the years, staff, (with Council's approval), has programmed DART funds allocated to the Town ofAddison in two DART accounts: the Capital Assistance Program (CAP) account, and the Local Assistance Program/Congestion Management System (LAP/CMS) Program account. The funds in these accounts were programmed for various street and intersection improvement projects in Town. Most ofthe projects have been completed. The attached spreadsheet lists the projects that we have programmed for use of DART funds, gives the amount that DART has paid per project, and gives the amount of programmed funds that have not yet been paid to the Town. Some of the programmed funds not yet paid remain allocated to projects that are completed, or are considered a low priority at this time as follows: Capital Assistance Program Fund: Addison Road/Excel Way Intersection Improvements Belt Line -Quorum/Midway Intersections Pass Project Unprogrammed Fund Balance $236,800.00 $321,547.83 $0.61 LAP/CMS Program Fund: Addison Road/Excel Way . Belt Line: Quorum and Midway Intersections Unprogrammed Fund Balance Total $76,500.00 $535,956.00 $18.821.44 $1,189,625.88 RECOMMENDATION: Staff recommends Council pass a resolution authorizing the reprogramming of $1,189,625.88 from the above referenced CAP and LAP/CMS projects to the Arapaho Phase illProject. . 􀁾􀁏􀁊􀁅􀁃􀁔􀁓FUNDING SUMMARY 4/8/03 ADDISON CAPITAL ASSISTANCE PROGRAM Total Amount Paid Programmed Funds PROJECT NAME Per Project Not Yet Paid Addison RoadfExcel Way Intersection Improvements $69,200.00 $236,800.00 Belt Une -Quorum/Midway Intersections Pass Project $452,058.17 $321,547.83 Belt Line/Addison Road Intersection. $167,846.36 MontfortlBelt Line Intersection $87,741.83 Traffic Signal Improvements (FY93-94) $20,400.00 SidewalklBus Bench Pads $38,814.30 AddlsonIW estgrove Intersection $111,592.36 Midway/Lindbergh Intersection $10,830.00 Midway/Beltway Intersection $2,925.00 Midway/Greenhill Intersection $4,280.00 Belt Line/Marsh Intersection $758,640.14 Thorofare Plan $39,486.00 Belt Line/Dallas North Tollway Intersection $262,642.00 Keller Springs/Dallas North Tollway Intersection $295,630.47 I Arapaho Road, Phase I, $4,612,602.43 Wesigrove/Sojoum Intersection Improvements $129,143.99 Belt Line Road/Business Drive $331,763.00 Staff Salaries $37,945.93 Unprogrammed Balance $0.61 Sub Total, Capital Assistance Program $558,348.44$7,433,741.98 . ADDISON LAP/eMS PROGRAM Total Amount Paid Programmed Funds PROJECT NAME Per Project NolYet Paid Arapaho Road Phase III $983,250.00 Town Wide Signals Upgrade $155,043.00 Brookhaven Club Drive@Marsh (Town share to FB) $59,053.50 Collon Belt Quiet Zones I Addison Road/Excel Way DAddison Road Widening $298,977.00 $1.555,178.001 Westgrove/Sojourn Intersection Improvements $40,000.00 • 1 Keller Springs/Addison Rd. Intersection Improvements 1 Arapaho Road, Phase I $350,000.00 $2,497,610.57 Belt line: Quorum "& Midway Intersections $535.958.00 Bell LinelToIlway Single Point Urban Interchange $314.044.00 $102;800.00 Keller Springs/Quorum Intersection Improvements $294.175.06 Midwav/DooleyRoad Intersection Improvements $126,035.00------. Rail Road Crossing Replacement on Surveyor Blvd. $100.910.00 Technical Assistance (Staff salaries) $258,603.00 Unprogrammed Balance $18.821.44 . Subtotal. LAP/CMS Program $5,580,501.13 $2.681.455.44 $3,439,803.88Totals, Cap. Assist. And And LAP/CMS Programs $13,014,243.11 GRAND TOTAL 1 $16,454,046.99 DOIlos Area Rapid Transil p,O, Box 660163 Dallas, Texas 75266-0163 214/749-3278 March 25, 2003 Mr. James Pierce, P. E. Assistant City Engineer Department of Public Works Town of Addison P. 0, Box 9010 Addison, TX 75001-9010 Re: LAP/CMS FY 2003 Second Quarter Report Dear Mr. Pierce: Attached is the FY 2003 Second Quarter Report for the Town of Addison LAP/CMS programs. If I can be of further assistance, please can me at 2141749-2764 or Julie Rodriguez at 2141749-2831. Sincerely, 􀁾􀀠Trip Brizell Senior Manager Capital Planning & Development TB:jr Attachments --AootSON CAPITAl AsSISTANcE PROGRAMt I 􀁾􀀠􀁾􀀠AMOUNT 􀀻􀁅􀁬􀁴􀁐􀁡􀀼􀁴􀀺􀁬􀁭􀁊􀁾􀁾􀁾􀁉􀀩􀀡􀁔􀁕􀁒􀂣􀁓􀀠EXl'bilJf'ttHlt$ f!lI11'f:'HDI11JRE.9 U:PPICl1VI'IU 􀁾􀁧􀁴􀁦􀁬􀁬􀁬􀁮􀁭􀀠EXPElitIITl,IfttS aPEf'ltlm.IlreStxPOIDmJIWI 􀁾IllPI.NOI1Ufl!1i :1' TarAt 􀁩􀀺􀁾􀀭􀀭􀀭􀀭􀀭􀁾􀁾􀁷􀁲􀁟􀀮􀁟􀁾􀁾􀁾􀁊􀁜􀁉􀁴􀁾􀁾􀁾􀁟􀁾􀁾􀁾􀁾􀁾􀁾􀀠􀁾􀁟􀀡􀂥􀁰􀁾􀁷􀁌􀀽􀁾􀀠􀀬􀁟􀀭􀁟􀀭􀁾􀀭􀀽􀁾􀀠􀁟􀁾􀀻􀁲􀀺􀀺􀀬􀁴􀁾􀁾􀀽􀀠􀁾􀁾􀀠. 􀁾􀁾􀁑􀀠􀀧􀀻􀁾􀀢􀀠􀁾􀁾􀁇􀀮􀀠_ 􀁾􀁾􀁾􀀠􀁏􀁕􀀧􀀺􀁾􀁑􀀠_ 􀁾__ '_H __ 􀁾􀁾􀁾􀁾􀀫􀁾􀀺􀁾􀀠, , , iPOt t'llM!llhl\lQ,11)4.00 $G.e22i;S so,oo, 􀁓􀀲􀁩􀀺􀀱􀀬􀁾􀁯􀁯􀀮􀁯􀁯􀀠'" ,OWl>!...... ..,..'" W\2!Ql '"., """"" ()9{1AA')1 SH126.tn 11126191 􀁓􀀱􀀲􀀵􀁾􀁏􀁏􀀠""""" $8,500.00 S88JiSS.18 $14.163.23 $1,!I1l.QS"""',, r----􀁈􀁾􀁁􀁯􀁏􀁦􀁓􀁏􀁎􀁃􀁁􀁐􀁬􀁔􀁁􀁌􀁁􀁓􀁓􀁉􀀤􀁔􀁁􀁎􀁃􀁅􀁐􀁒􀁏􀁇􀁒􀁁􀁍􀀢􀀠--nO 􀁾􀀠1 I I I _com 􀁉􀁾􀁦􀁩􀁉􀁬􀀩􀁦􀁩􀁪􀁒􀁅􀀦􀀠fil>EII!lIt\JAM IOO'f.MDmlRU bf'EHQf'I'1fflEa EXPDlOfTUItE9 ElWtKOtTlJRE$ EXf'EHtllnJRE:5 􀁾􀂷􀁾􀁒􀁅􀀡􀁉􀁩􀁾􀁄􀁉􀁩􀀱􀁊􀁒􀁅􀁓􀀠UPEHllItullO EIlPfHtrnJllt-S 􀁇􀁾􀀭􀀭􀁩􀁾􀁬􀁯􀁉􀁅􀁴􀀾􀀠􀁾􀁏􀁊􀁊􀀡􀁯􀀯􀀮􀀮􀀠􀁾􀁾􀁾􀀬􀀠􀁾􀁾􀀱􀁉􀁢􀀠􀁁􀀡􀀧􀁴􀀮􀀮􀁾􀀠􀁾..􀁾.., 􀁾􀁾􀀠􀁾􀀡􀀠2!!!!N,2 􀁴􀁬􀁾􀁇􀀠􀁯􀁯􀁾􀁾􀀠􀀢􀀢􀁾􀀠DU,!!..',!G 􀁾􀁾􀀠DU..!',!O 􀁯􀁯􀀮􀀮􀀮􀀡􀁾􀀠􀁃􀁜􀁊􀀭􀀬􀀡􀁾􀁇􀀠i 􀁾􀁾􀀬􀁒􀁬􀁾􀁾􀁾􀀧􀀱􀀶􀁦􀀱􀀠,.,..., L' 'i $H),!J3.O,OO ihr􀁾􀁩􀁬􀁯􀁮11910172. $pply the I I'11I'MWIl9 lund!! II) help program rw}IlcI: j 􀁁􀁲􀀮􀁉􀁰􀁳􀁪􀁬􀁯􀁒􀁤􀀮􀁒􀁍􀁾􀁧􀁭􀁍􀁮􀁴􀁅􀁸􀁴􀀮Retrelnder ollht$ proiOOt i ]􀁾􀀧􀀽􀁾􀀺􀀺􀁾􀁾􀁾􀀺􀀠; If..''-''''''.....•"",-""orner """"" 􀁾􀀺􀀻􀁧􀀢􀀠1-=..1.. 􀁾􀁟􀀢􀀧􀁏􀁏􀁪H',MiOWAVII3El1WAYINitH§!£I.-H' i112M11 $4@.00. ---I IPayrnenl 03f17/ro $2.925,00' $2,025.00: i !P0rR0IlOkstIDnffl0172,./IWIy1!'i& , ' 1 􀀬􀀡􀀧􀁑􀁉􀁭􀁬􀁮􀀡􀁮� �􀀧􀁵􀁎􀁦􀀡􀀮􀁬􀁴􀁯􀁨􀁥􀁬􀁰􀁰􀁲􀁯􀁩􀁪􀁭􀁭􀁾􀀺􀀠I'I I 􀁾􀀺􀁾􀁾􀁲􀁰􀁾􀀻􀀺􀁾􀁾􀁥􀁤􀁢􀁹􀀠j i .! I""","',,,,,, C". """" '".m i I I , 5!lRTOTAl TWa PROTECT $2mOOIom om _,_"-, """'" ''''''''''' """'1􀁾􀀺􀁾􀁾􀁅􀀧􀁅􀁎􀁆􀁭􀀧􀁬􀀮􀁬􀁦􀁬􀁔􀁅􀁒􀁓􀁅􀁃􀁉􀀮􀀠􀁾􀁾􀁾􀀺􀁯􀁯􀁆􀀭􀀭􀀭􀁾􀁉􀀠...,.,'" $4260,00 -II Per RO"'...<1Ii,lljon fI97017a. apsI!1MHSHLN.INTERSEC, n/2Ml1 $5$(j,OOl)J)O, -I' 􀀺􀁆􀁾􀀭􀀭--1􀁉􀀢􀁾􀀠AddI\lomlFmds !)Ilft4194 250,000.001 ' i PaymG!l1 03f11ii:1S S19,590.00 ! Paymetll lMWlW $635,526.80 'I 􀁾􀀽􀀺􀀠􀁑􀀮􀀴􀀡􀀡􀀡􀁾􀀠􀁾􀀮􀀵􀀲􀀵􀀮􀀰􀀰􀀠I Pa)tMflt 􀁮􀁾pmft1:t 􀁾􀀠RoplCgmm remaining blllenGfl $11.153,07 $158.640,14iWDi9& l&tW ,""""iUn tI!$ 􀁲􀁾􀁴􀀡􀁬􀁲􀁭􀀧􀁬􀁥􀁤􀀠money 1 􀁾􀁏􀁏􀁉􀀧􀁉􀁾􀁩􀁮􀁧ID fIe.JoMlon f911:I11: 􀁔􀁯􀁭􀁾􀀠F\&ipmOIlIm$41.35i 􀁉􀁾􀀠 lhn Ara$aho Ro&t Roo:JiglImenl 􀁾􀀠 􀁐􀁦􀀨􀀾􀁪􀀦􀁩􀀺􀁴􀁉􀁄􀁾􀁾􀀠($41.359.<16 Town 01 kfdlson 􀁾LAP/CM: I lh&alJ'lOUlllot$1l!2,5l/a, Outorl '" Sl1'lOunt S?1:2, b II (efund bt'tIi I, iwhlch Ihl$n ahGuld bD 􀁾􀁭􀁭􀁥􀁤 •'''-clflof plCjoobIwV1101,... $Z1l!.OO $212. to hglp lund GIh&r """" 211101 Town 01 Addi$l.Jon i 1 􀀻􀁩􀁉􀁐􀁏􀁾􀀠02112101 􀁴􀀤􀀲􀀱􀁩􀁾􀀠..􀁾􀁾􀁾•• SWTO.IAI,,_llII.Ul\Q1 !i&I tl.if..􀁾􀀠$8.701.00􀁩􀀽􀁲􀁾􀁾􀁾􀁾􀁾N $11.701.00􀁾􀀠"",""'"􀀧􀀮􀁮􀁷􀁾� �"'''' 􀀧􀁾􀁾􀁟􀁉􀀠.___->!iI!rOTAl.:n.u ,.,"00 ·i·· THOROUGHFARf!1Jt.AN$13,760.00p,,-. $39,456-00 "',,!$3,150.00 jAddillONl io.ondJng PGr Town 01 ""ile!toifdaUKI tIZ/01101 $t,seitOO 􀁟􀀭􀀭􀀭􀀺􀁉􀁾􀀮􀁾􀁴􀁊􀁮􀁏􀁔􀁁􀁉􀀠􀁾􀁐􀁒􀁏􀁕􀀻􀁃􀁔􀀠m ..􀁾􀀠-----eaT UNEiDAlLAS NORTH TI "'WAY INTeRSEC'l1ON $262,000.00 $13,770.00 PllymOlI\ P.",.,., l1,ull1iO """'" 501,810.00 p""",,, 04I111'1i\'S; "',... $120,00 , PII)101llfl! S233211.72 i 􀁐􀁡􀁹􀁭􀁥􀁮􀁬􀁬􀀧􀀡􀁮􀁤􀁐􀁬􀁬􀀩􀁪􀁏􀁏􀁴􀁾􀀠􀁾􀀠""'$(1,022.2119'27100lolol1M , 􀀢􀀬􀁾􀁉Ad:i!iIonal!\..w1ding POI' TI'IW1I 01 ''''''''' 1 ""', ...,,,,IleMrdattlldt\alO1l(t1 t1 0fI1Q1f01 1I ""',00IPaytMnt 􀁾􀁾􀁬􀀮􀀮􀀮􀀮􀁉􀁭􀀮􀂣􀀮􀀮􀀮􀁛􀁂􀁑􀁊􀂣􀁃􀁔􀀠:em !MM9'.OSII!Wl -I 􀁾􀀠NOI 􀀻􀁾􀁾􀁾􀁾􀁾􀀠tmJro S22i!.ISO (Xli orner DAT1! .M'mOVEO 􀁾􀁾􀁾􀀭04111195""',..... ""'"""",.., ""... (W7101 $1115.105.00 ,.,.., ?V. 02116194 $" ,....... """"" ENfil:XfENSION I Tlal.:ffumld W.o75 from ttm 􀁍􀁾􀁾􀁴􀁯􀁦􀁵􀁲􀁤􀁬􀁨􀁬􀀤􀀠􀁾� �PoojIld pet f'tooolulkll'l !,.:.a.tQd $7(},12OfIomlha 􀀡􀁍􀁬􀁤􀁷􀁡􀁹􀁊􀁇􀁉􀁏􀁏􀁉􀁩􀁎􀁉􀁉􀁉􀁾􀁴􀁬􀁏􀁬􀀡􀀮􀁭􀁤􀁬􀁨􀁴􀀵􀀠!(Arapaho) pl1:l!ld per 􀁾􀀱􀁫􀁍􀀱􀀠'JlMn.," Berch Pnd, """"" """"" 􀀭􀀧􀁪􀀺􀀺􀀺􀁄􀁉􀁓􀁂􀁴􀁉􀀸􀀮􀁾􀁁􀁕􀀮􀁙􀁅􀁁􀁒􀁓􀀠$'f." 􀁾􀀬􀁾􀁉􀀢􀁨􀁮􀁾􀀠5llMMARYSTATUSRfl'0I1T; 3!311n3 (CAP ASSiSTANCE RINDS 􀁾ONin FfJNOSPRDGRAMMED $7,982,t1119.8Z Fundi AIIoelIt&d lliru F't 96 $6,l82,D2:,QO ------------"--...,'---j !Ul1"OI0Inmes 􀁾􀁔􀁕􀁒􀁅􀀤􀀠EXPQItl(IURI!$ !JQIElIIlIl\IRES UPEI!DmII'IiI'!$ £XPIlN1lIT\.!1lE9 EXPENDll'U1ltt9 I:lXI'fHIlffilRfS EXP£NOIWRU fi.XJ'f.HflIlUJlES 1 Joro\l !MlOOJIiUiglD 􀀬􀁾􀁟􀁾􀀬􀀻􀁊􀁴􀁾􀁟􀁾􀁾􀀠􀀢􀀢􀀧􀀻􀁾􀁾􀀮􀁾􀀭􀁾􀁾􀀭􀁾􀁟􀀭􀀬􀁾􀀭􀁾􀀺􀁴􀁾􀀢􀀢􀀠____􀀺􀁾􀁾􀀭􀀭􀀭􀁴􀁋􀁊􀁾􀁾􀁾􀁈􀀮􀀧􀁾􀁾􀁾􀁾􀀮􀀽􀀽􀀬􀀠."':;6. 􀁾􀁾􀁊􀁲􀀺􀁯􀁳􀁾􀁲􀁾� �$2323,)43.44 $11.437.03 .".., $255,OOO.ro 519$,100.00 $15,510,1)) SiJ:l.9Sil.oo $U;.4{l2.77 $3,123.22 .'"'' $184,715.00 $\'1.500 00 $SS3,4a2.70 $1,()14.a:!!i.00 $2.3911,\164,73 $225,000,00 $?S,OOO,oo $81.763.00 --mmuum", AODISON 􀁌􀁏􀁾􀁾􀀭􀁁􀁾􀁩􀁓􀁾􀁦􀁾􀁾􀁅􀁐􀁒􀁏􀁇􀁒􀁁􀁍􀁉􀁃􀁏􀁎􀁇􀁅􀀤􀁕􀁏􀁎􀀢􀀧􀁾􀁎􀁁􀁇􀁅􀁉􀁦􀁅􀁎􀁔􀀠􀁾􀁾􀁾􀁬􀁙􀁾􀁬􀀠FlJllrIS 􀁉􀁕􀁎􀁐􀁒􀀨􀁽􀀨􀁪􀁒􀁁􀁎􀁍􀁅􀁄􀁂􀁁􀁌􀁁􀁎􀁃􀁾􀀠SP1EHDmJRE5 􀁾EXPENt'ImJRES EX.PENDi'1lIR£S 􀁾􀀠􀁾􀀢􀀢􀀢􀀢􀀢􀀢􀀢􀁅􀁓􀁾􀁾􀀻􀀻􀀺􀂷􀁲􀀽􀁾􀀢􀀱􀁬􀁉􀀱􀀢􀁬􀀱􀁬􀀺􀁲􀁾􀀠/J.a..w::' IlIl'J'FAAUlU}\I/lfh II'ItOG:,IfAMI.Ie) SYPROJECT I DURING F'I!IT mn:uHG N0Q9 fRJRJNO FYII§' !'JURING 􀁆􀀧􀁉􀁾􀀠.,""""" --, 􀀭􀀬􀁾􀀠􀁾􀀢􀀧􀀢􀀢􀀠u, 1*D!01_ -.,_ ArapahO Road Phase III: AexUson Rd. to SUNeyor Blvd. per AesolutlonI 􀁩􀁾􀁏􀁬􀀷􀀷􀀠'Paymenti SUDT01:AJ. THIS PROp:.-cr 'Town 'Mda SignalS Upgr1!td6 I PnymlilnlISUBTOTAL nus PROTECT 'I'BfOOlIJ1aven Club Oliva ,lieconstructJon !Payment I SUBTOTAL nas PROf£CT Gotloll Belt FIR OUlelZonas pet .AesofUllooIlOHI'14aISll91'OTJU. nuS PROTECT !Addison AoadIExcei way SUBTOTAL 11IlS PRO/ECT Technical Assistanoe Program (rAP) {or Publk: WOOI's 􀁾􀁰􀁡􀁲􀁴􀁭􀁥􀁮􀁬􀀠ITransportallOn SSIaliGS_ent &aIf appf'OYed addlIIonallund"ing Payment suaroTAL nus PROJ£CT iTecImIeaI As&!stanca proqram (TAP) Payment SUBTOTAL 1lIIS PROJECT _,_ 􀁾􀁟􀁗􀀱􀁤􀀢􀀢􀀢􀀢Paymenl Addi50nal Funding pDf T Addtson. {Updets nle wi 􀁾􀁡􀁮􀁤􀁬􀁯􀁳􀁳􀀡􀁨􀁥1-2-01 lcones.} Payment AddiUooaIlurn:fing por Re'$OIulloo /#010148 SUBTOTAL THiS PKOJECT 􀀡􀁷􀁬􀁊􀀤􀁴􀁧􀁉􀁑􀁖􀁥􀁩􀁓􀁾􀁭􀀱􀁾􀀠'Improvamanl$ por Staff AppIV'Ial Th!s!s aetuslIy a trsnsfer 01 funds from Adt1lson Road/Ex(:sl Parkway _ IlnlelSe<:tion whfch is a lAPJCAP pAFF A.......afill proJecl,!O Itmd!.h1!i new projectI I iPaymenl i SUBTOTAL nilS PROJECT I m IArapaho RealignmenVExtenslon Per CAPOIICIOlmm Resolution #970172. 09fD9J97 $844,692.00 : Payment 10121197 $188,918.40 Paymenl 02/18198 $675,673.60 $0.00 AddiUonal luncllng per ResoluUon I 11980076 04,t4198 $546.280.57 : Paymen! 06lt7198 $110,256.00 1 $2,497,610.$7 07f29198 $436,024.57IP"moo,AddlUonal lunding per ResoluUon #990142 08110199 $1,058,738.00 I Payment 09f07199 $1,056.738.00 AddlUonallunding per ResoluUon I1000099 06112100 $50.000.00 Payment 07f071OO I $50,000.00 SUBTOTAL THIS PROJECT $2,497,610.57 Ben Una: Quonsm & Midway IntelSecUons Per ResoluUon OII»'PI'.03 111970172. 0910"'7 $850,000.00 Paymen! 10121197 $170,000.00 I $314,044.00 1 $535,956.00 Paymen! 01109f03 I SI44,044.00 SUBTOTAL THIS PROJECT 5850,000.00 -,-Iinterchange) Belt UneIToilway (Single Point Urban Per Resolution #970172 09lO9l97 $50,000.00 Payment 10121197 I $50,000.00 ,AddiUonellunding per ResolUUon , #980076 04"4198 $269.000.00 I Payment 06117/98 $52,800.00 $102,800.00 I $0.00 Town 01 Addison refunded LAP/eMS In the amounl 01 $122,522. Out 01 this amount, $102,800 Is B refund lor this pro]. which then should be reprogrammed to fund other projects per 217101 correspondence 01112/01 $102,800.00 Reprogram balance 01 $102,800 to help lund oUler prO/ecls per Town 01 Addison correspondence daled 217'01. 01112101 ($102.600.00)1 Reprogram balance 01 $216,200 10 help lund other projects per Town or 􀁩􀁾􀀥􀁳􀀱􀁾􀁮􀀠correspondence daled 02/12/01 ($216,200.00)1 I , SUBTOTAL TIUS PROJECT S102,800.OO ;Technlcal Assistance PrDgmm Per ! 􀀭􀀬􀁾􀀠IResoluUon #970172 09'09197 $34,000.00 i IPayment 10121197 $34,000.00 $34,000.00 I $0.00 i SUBTOTAL TIUS PROJECT $34,000.00 i iKelier Spl1ngslQuorum IntersecUon 􀀭􀀬􀁾􀀠iPer ResoluUon #970172 09109197 $250,000.00 I 'Payment 10121197 $250,000.00 I: 􀁾􀁾􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀀺􀁾􀁾􀀽􀀽􀀽􀀽􀁾􀀠􀁾􀀬􀀮􀀠FUNDS 􀀻􀁎􀀺􀀺􀀺􀀺􀀺􀁾􀁾􀀽􀀺􀁏􀁏􀀺􀁰􀀺􀀽􀁉􀁬􀀺􀁰􀀽􀁾􀁾􀀯􀁾􀁾􀁾􀁾􀀻􀀠UP&itJIl'tJFIES UPsmuntRESBYPROJECT 􀀬􀁾􀀬􀀠1 , PofASSOIUtion IJ9S0258,lransi$r remaining pettovar) funds from 2 I;LAP/CMS proJects as shown below. HowllIvar.IhIllM Will be no physical ImtiSl'arof 11l0flG)' 􀁾􀀡􀁨􀁥TOM'l Ie4mI97 $0.00 i ,ActusleootoftlJlSpMjet:t WS$ $126.D35. 􀁔􀁬􀀢􀁴􀁴􀁴􀁴􀁲􀁈􀀱􀁬􀁬􀁬􀁬􀁮􀁬􀁴􀁊􀁧􀁾􀀹􀀶􀀵1IwIII beBpp1ed mIhs KIIffIN 􀁾􀀭􀁰􀁳􀁲􀀠Rcsolu:tkml9fKJ258. T1JeTownof Addison IJa lh6 sctuslterlJIllnIng I($9,965.{')0)I""""Y, _00: Town of AddIson rallJ1"!ded lAPICMS In Iha fllfJiXml of $122,sa:2:. Out 01" IhlS fimOt.lt\!, $900. I!Ii refund fOr this proj. WhICh !him should be repfO\¥llffimed 10 lund 􀁏􀁩􀁨􀁥􀁲􀁰􀁾􀀠􀁰􀁥􀁬􀀲􀁦􀀷􀀡􀁏􀁬􀁾􀀠.Reprogram $900.. 10 help kind other IproJecls per 21711)1 Townol" Adcfison,, SUBTOTAL nns PROJECT Railroad C«J:s&lng Aaplacsment Of), Surveyor Ad. Aclust C05l D11h/t; protect WS$ $43,146. 1ba remalnh"IgSS6,860 willbesppJled to the Ke1Ier SprlngsIQuorum project per AesoIutIon 19B0258. 􀁾Tewn of Addison hBs the actusJ money. AdmlIonfll (lEIdlng p(lrTO'M"I 01" Addison's JeUer daleqTo: Carolyn Burgett Cc: Mike Murphy; Steve Chutchian Subject: RE: Dart Funds Carolyn: In answer to your question: 23301-Brookhaven/Marsh Lane Improvements $59,053.50-we will be spending these funds as soon as Farmers Branch bills us-this is a cooperative project with them and they managed the project. 62301-Midway/Quorum Belt Line Intersection $7352.17-Project complete, move to Arapaho Rd. Phase III 66300-Addlson Rd/Excellntersection $68,605.24-project cancelled, move these funds to Arapaho Rd. Phase III 76300-Addison Rd.lKelier Springs Signal $163,165.82-we will eventually spend these funds when we upgrade this intersection 84300-Addison Rd. Widen, Phase I $245,956.00-This project is scheduled to go to bid later this year 66300-Keller Springs/Quorum Intersection $245,284.52-This project is complete but I don't know why there is so much money in this account. It should have been spent on the project. You may want to investigate. Jim Pierce, P.E. Assistant PubliC Works Director P.O. Box 9010 Addison, TX 75001-9010 972-450-2879 ---Original Message-From: carolyn Burgett Sent: Monday, May 12, 2003 12:44 PM To: Jim Pierce Subject: Dart Funds Jim, I put together the attached worksheet at Randy's request. I thought you might find it useful. Will we be spending the funds from FY 02? If not, should they be moved to another project? Carolyn « File: Dart ws 33103.xls» 1 Luvt 􀁾􀀠lMve.. 􀁌􀀭􀁵􀀬􀀬􀁾􀀠􀁾􀀾􀁊􀀭􀁴􀀮􀀮􀀠􀀬􀀬􀀢􀀬􀁾􀀷􀀰􀀿􀀠􀁾􀀬􀀠I 23301 62301 66300 76300 84300 86300 30300 83300 40000 DART FUNDS i March 31, 2003 i Programmed Funds Not I Ledger Balance Yet Pd Per Dart Report I FY02 FY03 Capital Asst LAP/CMS , Balance Amounts' 􀁐􀁲􀁯􀁧􀁲􀁡􀁾􀁬􀁉􀁉􀁾􀀠Program BrookhavenlMarsh Lane Improvementli $59,053.50 Midway/quorum Belt1ine intersection $7,352.17 $321,547.83 ... $535,956.00 ... Addison RdlExcel intersection $68,605.24 $236,800.00 ... $76,500.00 ... Addison Rd.lKelier spring signal $163,165.82 Addison Rd widen, phase I $245,956.00 $1,555,178.00 Keller Springs/Quorum intersection $258,284.52 Town wide signalization upgrade $155,043.00 Arapaho Road, Phase III $983,250.00 Technical Assistance $41,330.00 Cotton Belt Quiet Zones $695,000.00 Unprogrammed Balance $18,821.44 "" 􀀭􀀭􀀭􀀭􀀭􀁾􀁾􀀠Totals $802,417.25 $1,179,623.00 $558,347.83 $2,881,455.44 • Amount recorded to revenue. Je to move to deferred revenue will be entered in April 03 . ... Per Jim Pierce -will send request to Dart to move funds to Arapaho Rd, Phase III I I ---..... fliII'I4I!II!I SM..0U43 ,""""0Qr.!1.IItI8 04i'11llli5 projects pIlr ,.,vo, fund othilr 02112101 'ROVa ,,-""00 $96.055.18 $14.163,23 􀀧􀀱􀀬􀀹􀀺􀁲􀀳􀁊􀀱􀁾􀀠 􀁾􀁾􀀠􀁪􀀺􀁾􀀠􀁾􀀺􀀻􀀠􀁾􀀠􀁾􀀠£ 􀁾􀀠􀁾􀁾􀁾􀀠􀁾􀁾􀀠S 􀁉􀁾􀀠j8 􀁾􀀠􀁾􀀠􀁾􀀠; 8 I i 􀁾􀀠lii 􀁾􀀠􀁾􀀠 -AIIOUNT 􀁅􀀱􀁊􀀾􀁾􀁯􀁲􀁲􀁵􀁒􀁅􀁓􀀠EXPENDITURES EXPEHD!11lA£!I f;XPEHDITUR£!I f;XPENDlTURES I;lCPENDITURES UPENomJRES EXPEHDlTURE9 EXPENDlTUIiES EXPENDITURES EXPEHOITURES 􀁔􀁏􀁔􀁁􀁾􀀠PROGRAMMED PROJECTI PROJECTtI'AIoIE 􀁁􀁐􀁾􀁾􀁾􀂣􀁉􀁬􀀠􀁁􀀺􀀺􀁾􀁾􀀠REPR6g:IIUED 􀁾􀀺􀀮􀀧􀀺􀀠􀁾􀁾􀀺􀀠􀁾􀀺􀁎􀀺􀀠􀁄􀁕􀀺􀁾􀁏􀀠􀁄􀁕􀁾􀁓􀀺􀀰􀀠􀁾􀀻􀀺􀁏􀀠􀁾􀀽􀁏􀀠00::0 􀁾􀁾􀁏􀀠􀁄􀁾􀁾􀁾􀁇􀀠􀁄􀁕􀁾􀁾􀁇􀀠􀁾􀁾􀁐􀁦􀁾􀀠􀁆􀁕􀁎� �􀁾􀁧􀁔􀁙􀁅􀁔􀀠Addtlonal fums Inlnsferrred lrom Bill' LlnelMonllort and Bolt Unli AddIsOll Rd. Pn;oJe<:1S Payment Paymen,.and Project Completed AddlUonal furtding parTal'm 01 Addisods 'etterdated 02/07/01 Payment SUBTOTAL TIll 􀁾􀁾􀁹􀁁􀀮􀁲􀁏􀁏􀁾􀀮􀁾􀀺􀁴􀁾􀁾􀁅􀁾􀁅I PaymentAdditional funding per Town of AddIson'sloaerdated02l07JOI Payment SUBTOTAL TIUS PROTECT 􀀱􀁾􀁾􀁮􀀷􀀠,NTERIMPV. PaymentPaymonl Payment alO proJect completed. Reproglllm balallCll per 9127190 lollor. Use Ihu reprogrammed money accordin91o Flesoll1llon '970172 per Tom Rydon: Aeprogram$45.656.Q1lnlo the Arapeho Road Realignment proJecL Projact to 􀁾􀁉􀁬􀁊􀀺􀁩􀁩􀁾􀁾􀀧􀀺􀁾􀁔􀁉􀁮􀁓􀀠PROTECT 􀁾􀁾􀁾F=IGNMENTIEXTEN510N AddilioMI Funds Payment Payment Additional Funds Payment Addillona.1 Funds per Resolution .970172 Transferred $139,170from!he MO::Iwa.vnJndborg project to hmd this (Ampaho) proJect per RIISIlILlllon 1970172 TmnslOlll1d $4.2.075 from tho MldwaylBeI1way P.890.93 .,,1.150.755.13 "".06<1.584_55 $2,469.1&1.73 _.00 ......00 ... ,,,6.649.17 :)11.001 ;:107.433.741.98 􀁾􀁡􀀮􀀳􀀴􀀷􀀮􀀸􀀳􀀠S7.43:I.741.M SUMMARY STATUS REPORT; lI3lA1.1 (CAP ASSISTANCE FUNDS· ONL YJ FUNDS PROGRAMMED $7,992.089.62 Funds Allocalod thl1.l FY 96 $6,102,392-00 ,.,,,,,,,, 11tQ2DHl 11/12102....., .."''''''' $983,25(!AJO --I! own WlI.16 i':itgnal5 Upgrade 11/12102 $155.043 $155.0;43.00 -$$9,053.50!RoconstrucUOfI OM!5I02-, ""'3010' ...,...... ZOOiS per--IReS EXPENDfTVRES TOTAL PAlO TO 􀁾􀁾􀀠FUNDS BY PROJECT I 􀁾􀀻􀀺􀀺􀀬􀁯􀀬􀀬􀁾􀁾􀀡􀀠􀁾􀁴􀁾􀁾􀀺􀀺􀀠􀁾􀁴􀀺􀀬􀁚􀁾􀀺􀀺􀀬􀁾􀀬􀀠p p Per Resolution 11980258, transler remaining (left over) funds from 2 LAP/CMS pro/ects as shown below. However, there will be no physical translef 01 money between the Town 01 Addison and DART. The Town 01 Addison will keep the money in their 􀁎􀁏􀁔􀁅􀁾􀀧􀀠own account. 11/10/98 N•• Railroad CrosslnglSurveyor: $56,860 11/10/96 • MidwaylOooIey Intersection: $8,964.94 11/10/98Note Aclusl lolsl progmmmed for this 􀁰􀁲􀁯􀀯􀁾􀁴􀀺􀀠$315,824.94 Additional lunding per Reso!ut!on tt990142 08110199 $44,115.06 $0.00\V-:,s00 $44,175.06Payment 09107/99 SUnTOTAL 􀁾􀁓PRO/ECT 􀀮􀀤􀀲􀁾􀀬175.06 Midway Road & Dooley Intersection Improvements per Resolullon , 0:?J25i97 $135,000.00 Paymenl 04/23'97 1t970046 so.OO$135,000.00 VsI26.035.00'-Actus' cost of this proJecl WS5 $126,035, The remslnlng $8,965 will be spp/od to the Keller SprIngs/Quorum proJect per Resolution 11980258. 7119 Town of Addison has the sclusl remelnlng .. ($B,985.oo)money, {sa,965.00 Town 01 Addison refunded LAP/CMS in the emoont of $122,522. Oulol this amount, 5900. Is a relund lor this pro!. which then should be reprogrammed to lund other projects per2f7/01 correspotldence 02112101 5900.00 Reprogram 5900. to help lund other projects per 217101 Town 01 Ack:I1son correspondence 02112101 {$9oo.00 SUBTOTAL lHIS PROJECT 􀀤􀀱􀀲􀀶􀀬􀁾􀀵􀀮􀀰􀀮􀀰􀀠Rallroa-d Crossing Replacement on Surveyor Rd. 10123'96 5100,000.00 􀀱􀁾􀀮􀀹􀀱􀀰􀀰􀀰􀀠$0.00$100,000.002 Actusl cost of Ihls proJect was $43,14.fl 1110 remslnfng $56,860 w/fJ be applied to the Kelfor Springs/Quorum proJect per Resolution #980258. The Town of .. Addison has the sctusl money • Additional funding perTown 01 AddisOll'S lelter dated 02107/01 02112101 5910.00 Payment 09/19101 $910.00 SUnTOTAL lHIS !,ROJECT $100,910.00 􀁾􀁉D $0.00Technical Assistance Program 1012M16 $34,000.001 $34,000.00$34,000.00 SUBTOTIIL THIS PROJECT $34,000.00 Payment 11/19/96 f'... "" $2,662,634.00$5,580,501.13$269,000.00 $2,231,872.57 51,236,906.06 $373,706.00 $66,496.00 $59,053.50 $1,:323,667.00TOTA L $8,401 ,805.13 $0.00TolaIPraho 􀁒􀁥􀁡􀁬􀁩􀁧􀁮􀁲􀁮􀁥􀁮􀁴􀁌􀁾􀁸􀁴􀁾􀁾􀁪􀁑􀁄􀀠Boundaries/short description Realign Arapaho Road from Tollway to l1arsh Lang Approx. BeginlEnd Dates: from Underway to 2004 I ! I 1If'llffPnl LAP/CMS Request 􀁌􀁁􀁐􀀯􀁦􀁾􀁓􀀠, 􀀱􀀰􀁾􀀱􀀠10/95 (ListlExPlain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fund transfers, reprogram.rning requested ifapplicable.) Arapaho Road realignment will relieve traffic on Belt Line Road and will also serve the new Transit Center on the realigned Arapaho Road. Road. The first phase of the project runs from the Tollway to Addison Road. The second phase runs from Addison Road to Marsh Lane. $28,000 is requested from 1997/98 CMS funds. The remainder is requested from reprogrammed funds as per the attached list. Total cost of this project is estimated to be approximately $18,000,000. Funds not provided by DART CMS will be provided from local sources. The project will affect all bus routes that will feed into the new Transit Center.* Pending. LAP applications attached Authorized City Sta Representative Director of Public WOrks A ust 27, 1997 Title Date Concurrence Title Date ',.¥, \." • , 􀁾􀀬􀀮􀁾􀀾􀀨􀁾􀀠I' Applicant City: Addison City CIP Project Eligibility Type: (see list, reverse side) 1. Roadway Improvements ---_............._Project Name: Keller Springs/Quorum inte£rs"'e;lc;;Jt;.Ji.cotiJnL-_____􀁾__________ FUNDING APPLICATION FOR DART's LAP/CMS PROGRAM LAP/CMS Project No. (for DART use only) city no. project type proje<:t no. -, Boundaries/short description _________________􀁾--------.-.. __ I' Approx. BeginlEnd Dates: from to .. $ $ 40,000 $ i$ 210,000 $ TOTAL 250,000 bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) II(List/,!xplaln fund transfers, reprogramming requested ifapplicable.) This project will provide for widening the.Keller Springs roadway at Quorum Drive to allow construction of left turn lanes from the east-west direction on Keller Springs. The project will ease traffic congestion at this intersection. Request funds be allocated from 1997/98 CMS funds. Bus route affected: 341 􀀮􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀀭􀀭􀀭􀁾􀁄􀀽􀁩􀁲􀁾􀁥􀁾􀁣􀁾􀁴􀁾􀁯􀁾􀁲􀁾􀁯􀀽􀀭􀁦􀁐􀀺􀁾􀁵􀀽􀁢􀀽􀀱􀀽􀁩􀀽􀁣􀁟􀁷􀁾􀁯􀀽􀁲􀁾􀁫􀁳􀁾􀁟􀁾􀁁􀁾􀁵 􀁾􀁧􀁾􀁵􀁳􀁾􀁴􀀭􀀲􀁾􀀷􀁾􀀬􀁾􀀱􀁾􀀹􀁾􀀹􀁾􀀷􀀭taffRepresentative Title Date DART Staff Concurrence Title Date FUNDING APPLICATION FOR DART's LAP/CMS PROGRAM LAP/eMS Project No. (for DART use only) city no. project t}'P" project no. Applicant City: Addison City CIP No. ___􀁾_______ Project Eligibility Type: (see list, reverse side)_..:':.:􀀱􀀮􀁾􀁒􀀢􀀬􀁯􀁾􀁡􀁤􀁾􀁷􀁾􀁡􀀺􀀡􀁙􀀭􀀽􀁉􀁭􀀺􀀺􀀺􀀡􀁰􀁴􀀢􀁲􀀺􀀻􀁯􀁾􀁶􀁾􀁥􀁾􀁭􀀽􀁥􀀮􀀧􀀮􀀡􀁮􀁴􀀺􀀺􀀺􀁳􀀺􀀺􀀮􀀮􀀮􀀮___________ Project Name: Belt Line -QuorumlMidway Intersections 'i, Boundaries/short'description Same as above. 1·1' Approx. BeginlEnd Dates: from Underway to 1/1/99 " LAP/CMS 􀁉􀁉􀁐􀁲􀁦􀀬􀁶􀁩􀁮􀁬􀁬􀁾􀁬􀁶􀀠Approved LAP/CMS 50,000 $ $ (ListlExplain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fun. ,', ·•·•.,};.(;,r.•'..􀀧􀂷􀀮􀂷􀀮􀀼􀀮􀀬􀁾􀁜􀀮􀂷..,.·.',..).,..•􀀻􀀮􀂷􀀬􀀺􀀻􀀮􀀡􀀮􀀺􀁾􀀧.••'.'••,'."'.. I' ,p." '. -....􀁾􀀮􀀧􀀠.. ' .. 􀁾􀀮􀀠􀀧􀀬􀁾􀁷􀀢􀀢􀀧􀁾􀀠. -. 􀀧􀁟􀀧􀀫􀀢􀁶􀀬􀁟􀀮􀀡􀁾􀀧􀀮􀀠;-':';""" 􀀢􀁜􀀩􀁝􀁻􀁴􀀺􀂣􀀺􀁾􀁾􀀻􀀿􀀺􀀻􀁾􀀮􀁩􀁩􀀬􀁪􀁦􀀮􀀮􀀬􀀺􀀺􀀬􀀺􀂷􀁴􀀺􀀭􀀮􀀺􀀻􀀮􀀠;'.:\ 􀀺􀀻􀀺􀀿􀀧􀀢􀀧􀁾􀀭􀀺􀁾􀀢􀀧􀁾􀁦􀀮􀁾􀀡􀀺􀀭􀁾􀀾� �􀀧􀁴􀁾􀀺􀀺􀀻􀀭􀀺􀀧􀀺􀁾􀁩􀀱􀀧􀁓􀁹􀁩􀁬􀁩􀁾􀂷􀁴􀁴􀀻􀀺􀀮􀀮􀀺􀂷􀀺􀁾􀀧􀀲􀂷􀁾􀀺􀁪􀂷􀀮􀀧􀁬􀀻􀁘􀀧􀀺􀁬􀀿􀁾􀀺􀀮􀀻􀀻􀀿􀁴􀀢􀀧􀀺􀀧􀀻􀁾􀀺􀀮􀁣􀀺􀂷-c:.'-"."""--":""'-:,:::-<;,,,";'::'-",'\':">:;"':c.,;",,>􀀬􀀬􀀻􀀺􀀬 􀀬􀀬􀀻􀁣􀀺􀀭􀁾􀀢􀀭􀀺􀀻􀀢􀀧􀀺􀀧􀀭􀀧􀀭􀀢􀀺􀀻􀀺􀁾􀀧􀀼􀀾􀀺􀀧􀀺􀀧􀀺􀀢􀀺􀀧􀀺􀁣􀁯􀀺􀀭􀀻􀀭􀀺􀁾􀀢-'-''--i'j (ListlExl'lain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fund transfers, reprogramming requested ifapplicable.) Belt Line Road bus routes 363 &400 are affected. This project is for preliminary engineering to reconfigure the existing Bert Line Road/Tollway interchange to act .as a single interchange instead of two. This will allow the simultaneous operation of left turns, east/west traffic and north;/south traffic. This should improve the efficiency of this intersection 15 to 20%. Funding·from unprogrammed 1996/97 LAP funds • __􀁾􀁾􀁾__􀁾􀁾􀁾􀁾􀀮􀀼􀀿􀁾􀀺􀁾􀀻􀁴� �􀁾􀁾􀁾______________􀁾􀁄􀁾􀁬􀁾􀀧􀁲􀁾􀁥􀁾􀁣􀁾􀁴􀁾􀁯􀁾􀁲􀁾􀁯􀁾􀁦􀁾􀁐􀁾􀁵􀁢􀁾􀁬􀀽􀁩􀁣􀁾􀁷􀁯􀁲􀁫􀁳􀀠Auqust 27, 1997 Staff Representative Title Date DART Staff Concurrence Title Date FlJNDING APPLICATI.ON FOR DART's LAP/CMS PROGRAM LAP/CMS Project No. (for DART use only) city no. project type project no. 􀁇􀁅􀁎􀁅􀁒􀀤􀁴􀁊􀀻􀁎􀁩􀀽􀁩􀁏􀁒􀀱􀀱􀁁􀀧􀁲􀁉􀁏􀁎􀀻􀀢􀁩􀀻􀀻􀀡􀀺􀁴􀁾􀁩􀀻􀁴􀀿􀁩􀁩 􀀼􀀺􀂷􀀻􀀢􀀮􀀠Date 􀁓􀁵􀁾􀁩􀁮􀁩􀁩􀁴􀁴􀁥􀁤􀀢􀀻􀀾􀀺􀁁􀀴􀁧􀀱􀀱􀁳􀁴􀀠27, .1997 􀂷􀀺􀁾􀀬􀀺􀁩􀀮􀂷􀀠Applicant City: Addison City CIP No.____________ Project Eligibility Type: (see list, reverse side) 21. Technical 􀁁􀁾􀁾􀁬􀀮􀀡􀂷􀁳􀀻􀁩􀁬􀁴􀀦􀁡􀁾􀀮􀁮􀁬􀀡􀀻􀀻􀁣􀁾􀁥􀁾􀁐􀁬􀀺􀀺􀁬􀁲􀁲􀀻􀀨􀁯􀀮􀁧􀁬􀁧􀁬􀀺􀁲􀀺􀁡􀁡􀁭􀁭_____􀁾___ Project Name: Technical Assi.=s:::.ta=n:::c=e:..·________________________ 􀁂􀁯􀁵􀁮􀁤􀁡􀁲􀁩􀁥􀁳􀁬􀁓􀁨􀁯􀁲􀁴􀀠description Engineering De.partment Sa) arj AS . Approx. BeginlEnd Dates: from 10/1/97 to 9/30/98-. 􀁾􀀠: Federal (if applicable) $ Right-of-Way $ liState (if applicable) $ Construction $ ILOCal (if applicable) Other (if 􀁡􀁰􀁰􀁬􀁩􀁣􀁾􀁢􀁬􀁥􀀩􀀠$ $ 86,000 Testingiinspection LOperationslMaintenance $ $ ITOTAL TOTAL $$ 120,000. IDET􀁁􀀮􀀺􀁩􀁧􀁉􀀩􀁩􀀾􀀮􀁒 􀁏􀁊􀁅􀀻􀁱􀀧􀁴􀀻􀁐􀁅􀁓􀁇􀀮􀁒􀀮􀁊􀁬􀀧􀁊􀁊􀀹􀂣􀁮􀀺􀀬􀀬􀁩􀀺􀁩􀀻􀁫􀀮􀁾􀁮􀀧􀀻􀁪􀀾􀀺􀀻􀀠ii· •••",b;.iid.fj;;.i :;.;.;),:'&," 􀂷􀂷􀂷􀁻􀁪􀀻􀀻􀁜􀁜􀀿􀁴􀁾􀀺􀁾􀀻􀁬􀁴􀁩􀂷􀁩􀀡􀀠􀁪􀀺􀀻􀀻􀀺􀁦􀁩􀁩􀁦􀁾􀁩􀀮􀁩􀀮􀀧􀁘􀀠.' (ListlExp!ain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fund transfers, reprogramming requested ifapplicable.) Partial reimbursement for Engi'neering Department Salaries dedicated to the Town's traffic and transportation program. Funded from 1997/98 eMS funds. Dire tor of Public Works lI11g"st 27, 1997 Title Date DART StaffConcurretlce Title Date II --------APPLICATION FOR LOCAL ASSISTANCE PROGRAM , 􀁾􀁙􀁐􀁅􀀠OF SUBMISSION (1 ) f--Capital (e) I---v-Technical (T) 􀁾􀀠Revision (Rl lAP PLICANT I' IATION f"EGAL NAI.IE (9) Town of Addison 􀁾􀁏􀁏􀁒􀁅􀁓􀁓􀀠CilY Addison (11 ) County Dallas (12) Siaia Texas (13)75001.L.fl Code (14 ) PROJECT TITLE (15) • DATE SUBMITTED (2) 8/27/97 CATEGORY CODE (S 1201 􀀺􀀺􀀡􀁬􀁡􀁬􀁾􀀠ll; 121 \ l..ru;.al S {221 􀁑􀁬􀁢􀁾􀁴􀀠􀁾􀀠123.\ Dt.BI 􀁾􀀠!:(11 lQlAI 􀁾􀀠125\ 􀁓􀁉􀁇􀁎􀁁􀁔􀁕􀁾􀀠􀁁􀀮 􀀱􀀱􀁔􀁈􀁏􀁒􀁉􀁾􀁅􀁄􀀠,EPRESENTATIYE s:G /'5", 􀁾􀀢􀀧􀁟􀀠􀀻􀀿􀁾􀀬􀀠FOR ;6PiRTUSE mi'lv .. Dale To DART Staff ToTASC TASCReview -Ending Dale (18) CONSTRUCTION .COST DISTRIBUTION r:. 􀀬􀁾􀀠-',n $ 1261 Rieht-or-Wav S 127\ 􀁲􀀮􀁮􀁮􀁾􀁬􀁲􀁈􀁲􀀮􀁴􀁩􀁮􀁮􀀠So .(26\ Other s 129\ Total S 130\ TITLE DATE SIGNED Director of public Works 92-5'-1'7 Dale To paD 􀁃􀁯􀁭􀁭􀁬􀁾􀁥􀁥􀀠paD Review Approved by P&D "" ,,_ .. -- --------L --APPLICATION FOR LOCAL ASSISTANCE PROGRAM , . 'rYPE OF SUBMISSION (i) _ Caplial (G) 􀁾􀀠Technical {Tl Revision (Rl lPPI1Cb,NT 􀀧􀁎􀁆􀀨􀀩􀁒􀁾􀁁􀁔􀁉􀁏􀁈􀀠,..EGAl NAME (9) Town of Addison ADDRESS AddisonCily (11 ) Counly Dallas {UI Siale Texas (1 3) Zf>Coda :ZSOOl (14 ) DATE SUBMITIED (2) /, ' ,8/27 97 CATEGORY CODE (sea reversal (3 ) ( 4) (5) ( S I (7) (e) "-ORGANIZATIONAL UNIT (10) Department of Public Works CONTACT PERSON Jim PierceName: ,972 1 450-2879Telephone: PROJECT 'TITLE (15) , Sidewalk/Bus Bench Pads ,NO",or o"c",pno. ANO J",nFlCAnON,J)" 7 .. This project is complete. Request $3,211.70 be reprogrammed 􀁾􀁮􀁴􀁯􀀠the Arapaho Road Realignment Extension. ' , -see' 􀁣􀁯􀁭􀁰􀁡􀁾􀁩􀁯􀁮􀀠􀁃􀁾􀀠application for 'justification and construction 􀁣􀁯􀁳􀁾􀁳• • I PROPOSED pnOJECT Stari Dale' (17 ) Ending DalG (1 B) ESTIMATED FISCAL YEAR FUNDING I CONSTRUCTION ,COST DISTRIBUTION 􀁅􀁥􀁑􀁾􀁛􀁩􀁬􀁬􀀠; In: 'Eo!lio!1e[inglIl!1:>iQD 􀁾􀀠{HI .Qity li 120' I Rinhl.nl.Wav S /27\ s; '128\COMI, $.s.tal.!L 1211 :\, . 12 9 \ 􀁌􀁑􀁾􀁡􀁬􀀠II 122' .Ollier 130\ 12681 􀁾􀀠1241 IQ161 􀁾􀀠. (25\ TITLE DATE SIGNED Dille! 􀁾􀀠i231 To!"1 S 07c:: AttTHORZ REPRESENTATIVE , Director of public Works 8-Z'5-'l? ' X ., "'-"> '.I'A -IR6R DMlT USE/ONLY r Dale Dale To DART Staff To P&D Committee ToTASC P&D Review TASCReviaw Approved by P&D --------i APPLICATION fOR LOCAL ASSISTANCE PROGRAM 􀁾􀁙􀁐􀁅􀀠OF SUBMIssION (1) r---Capital (e) fu-Technical (T) 􀁾􀀠Ravision (R) 􀁬􀁾􀁐􀁐􀁌􀀡􀁃􀁁􀁎􀁔􀀠t.lo.TIOH ..EGAl NAl.IE (9) Town of Addison ADDRESS Cily county Addison Dallas (11 ) (12) Slate 􀁾􀁥􀁸􀁡􀁳􀀠(13 ) ZpCoda 150m (14) iPROJECT TITLE (15) , ., DATE SUBMITTED (2) ,8/27/97 ..􀁾􀁾􀀬CATEGORY CODE (seo rov9,rsa) (3) (4 ) ( 5) (6 ) (7) (S) 􀀭􀀬􀁾ORGANIZATlONAl UNIT (10) Department of Public Works CONTACT PERSON Jim PierceName: 972 , 450-2879TelephonB: ( -Addison/westgrove Intersection !PROJECT DESCRIPTION AND JUSTIFICATION (16) "'is 􀀬􀀮􀁯􀁪􀁾􀀧􀀠's ","",.00. ,",,-'e 􀁾􀀢􀀬􀁯􀁧􀀮􀀭􀀢􀀠'''0 tl>. -."" Road Realignment Extension ' See companion'eMS application for justification and construction costs • • i PROPOSED PROJECT Slart Dais' (17 ) ESTIMATED FISCAL YEAR FUNDING 􀁅􀁾􀁑􀁾􀁛􀁩􀁬􀁬􀀠􀁾􀀠lal GilY $ 120' i'llalQ lI' .121) I 􀁑􀁾􀁡􀁬􀀠;Ii 1221 Qlber 􀁾􀀠􀀱􀀲􀁾􀀧􀀠DAB1 :I; 1241 IQI6L !Ii 􀀱􀀲􀁾􀁬􀀠.. 􀁓􀁉􀁇􀁎􀁁􀁾􀁏􀁆􀀠AJ1THORI;?;ED REPJESENTATIVEJ . 1/-)1/-)5,""" -9.:-.0 A/-" EQR RMlr USE 􀁑􀁾􀁴􀀺􀀺􀁙􀀠Dale To DART Staff ToTASC TASGReview .. Ending Date (1 B) CONSTRUCTION ,COST DISTRIBUTION Fnnin' ,sinn ( 221 􀁾􀀠Rlohl-ol-Way 􀁾􀀠L21.1 􀁃􀁯􀁮􀁳􀁬􀁲􀁵􀁇􀁬􀁩􀁑􀁾􀀠t 'L2JU 􀁾􀀠(29)Olher. -Tolal 􀁾􀀠(301 , TITLE 􀁾􀁇􀁎􀁅􀁄􀀠! Director of Public Works -􀀯􀁾􀀭􀀻􀀻􀀺􀀠/! /Dale To P&D Commitlee P&D RevIew Approved by P&D ,. -----i APPLICATION FDA LOCAL ASSISTANCE PROGRAM 􀁾􀁙􀁐􀁅􀀠OF SUBMISSION (1) Capital (C) I-Technical (T) fJr Revision (RJI-lA,PPIICANT IHFocll LEGAL NAME (9) Town of Addison ADDRESS City Addison (11 ) County nall gO; (12.) Siale 􀁔􀁾􀁸􀁡􀁳􀀠(13) .Z9Code :Z5QQ1 (14 ) 􀁾􀁒􀁏􀁊􀁅􀁃􀁔􀀠TITLE , . "--DATE SUB MinED (2) 8/27/97, CATEGORY CODE (set! raverse) (3 ) (4 ) (5 ) ( 6) (7) (8 ) 􀁾􀀧---'ORGANIZATIONAL UNIT (10) Department of Public Works CONTACT PERSON Jim PierceName: 972 1 450-2879TelephoO$: ( (15) Belt Line/Marsh Lane Intersection . !PROJECT DESCRIPTION AND JUSTIFICATION (16) "'is 􀀢􀀻􀁏􀁪􀁾􀁴􀀠is "_.". 􀀢􀀬􀁱􀁯􀁯􀀮􀁴􀀼􀀬􀁾􀀠,"'''''',.;.,., into the -Arapaho Road Realignment Extention. See cOmpanion eMS application for justification and,construction costs • • , PROPOSED I"flOJECT Stari Dala ' (17) ESTIMATED 􀁅􀁾􀁤􀁾􀁣􀁾􀀱􀀠.Qity ,S'a'8 !Ii $ !Ii FISCAL YEAR FUNDING [H1L 120\ /211 'oeal $ /221 􀁑􀁬􀁢􀁾􀁻􀀠􀁾􀀠1231 Qt.BI 􀁾􀀠1241 TOTAl $ /251 S'GQf􀁁􀀮􀁫􀁬􀁔􀁈􀁏􀁒􀁉􀁾􀁅􀁄􀀠􀁁􀁅􀁐􀁾􀁅􀁓􀁅􀁎􀁔􀁁􀁔􀁉􀁖􀁅􀀠'I ,X X a-n 􀁾􀁩􀀯􀁁EQWQMlI USE QtlL¥ Dale To DART Staff ToTASC TASGReview Ending Dala (18) CONSTRUCTION ,COST ;Ion S DISTRIBUTION 126\ Riohl·ol.Wav S 1271 Conslruc.lion O'h., Tnlal $ 􀁾􀀠S . '1281 (29) {3 Q1 TITLE DATE SIGNED Director of public Works 8-zs-i1 Dale To P&D Commil1ee P&D Review Approved by P&D .' APPLICATION FOA LOCAL ASSISTANCE PROGRAM , . trYPE OF SUBMISSION (I) DATE Sl,lBMITIED (2) 8/27/91 I-Capital (e) CATEGORY CODE (saa raversa)r-xTechnical(T) (3) -( 4) -(5) --I-Revision (R) ( 6) -(7) -(Il) 􀀭􀀮􀁾􀀭..􀁉􀁴􀀮􀁐􀁐􀁬􀁬􀁃􀁾􀁬􀀠I! ..EGAL NAME (9) ORGANIZAllONAl UNIT (10) Town of Addison Department of Public works ADDRESS CONTACT PERSON City Addison ( 11) Department of Public WorksCounly Dallas (12) Name: Slate Texas (13) zpCode 75001 (H) Telephone: ( 972 1 450-2879 !PROJECT TITLE (15) Westgrove/Sojourn Intersection Improvements IPROJECT DESCRIPTION AND JUSTIFICATION (IS) "''" >''-OJ.'' is """,1.,.. -.,,,e.􀀼􀀢􀁐􀀬􀀢􀀬􀁾􀀭io'" Arapaho Road Realignment Extension. , See 􀁣􀁯􀁭􀁰􀁡􀁾􀁩􀁯􀁮􀀠eMs application for justification and construction costs • • PROPOSED PfiOJECT Sian Dale . (17) Ending Dala (1 B) ESTIMATED FISCAL YEAR FUNDING CONSTRUCTION ,COST DISTRIBUTioN c, 􀁾􀀬􀀠$ (1 !l' Enei ' .,n inn $ (261 City $ /201 Rlehl-ol-Wav $ (271 State $ 1211 (,!, ," inn S '126\ _Ql;al $ 1221 Other S r2 91 QJ.b.er $ 􀀱􀀲􀁾􀀱􀀠Tn!,,1 -􀁾􀀠1301 llABJ S 1241 ITOTAI $ , 1251 SIGNATU7 AlTrHORIf;ED REFENTATIVE TITLE DATE SIGNED Q c,=< 􀁾􀀮􀀠Director of public Works B-Z5-9',);<., /r.-; 􀁾... L";/""": EQR' I:!A>RI USE; ONLY ...: f Date Date To DART Staff To P&D Committee ToTASC P&D Review TASe Review Approved by P&D APPLICATION FOR LOCAL ASSISTANCE PROGRAM , . IrYPE OF SUBMISSION (1) DATE SU8MITIED (2) 8/27/97 :--Capilal (e) CATEGORY CODE (see ravarS<;l) 'v-Technical (T) ( 3) -(:4) -( 6) -􀁾􀀠Ravision (A) ( ti ) -(7) -(e) -;,PPIICAflT 􀁉􀁾􀁐􀀨􀀩􀁆􀁬􀁍􀀢􀀧􀁔􀁉􀁏􀁈􀀠,-EGAL NAUE (9) ORGANIZATIONAL UWT (10) Town of Addison Department of Public Works iADDRESS CONTACT PERSON Pily Addison (11 ) pounlY Dallas (12) Name: Jim Pierce •.. 􀁾􀁉􀁡􀁴􀁡􀀠Texas (13) tq,COOa 75001 (H) Telephol1 ' . ...EGALNAUE (9) Town of Addison ADDRESS 􀁾􀁩􀁬􀁙􀀠Addison ( 11) pounlY _])allas (12) 􀁾􀁉􀁡􀁴􀁥􀀠Texas (1 3) !z9 COO" 75001 (14) PROJECT 'TITLE (15) , ipROPOSED PROJECT Slari Dais '. (17) ESTIMATED FISCAL YEAR FUNDING c, tI $ till \ .Gitv 5 t2nl Slate 5 (211 .m:al $ 􀀱􀀲􀁾􀀱􀀠QJ.bJu... 5 􀀱􀀲􀁾􀀧􀀠.QA8I 5 /241 IQI61 􀁾􀀠􀁾􀀠{:l5}SQ:e􀁁􀁴􀁩􀁔􀁈􀁏􀁒􀁉􀁾􀁒􀁅􀀤􀁅􀁎􀁔􀁁􀁔􀁉􀁖􀁅􀀠. , ,.g:""'...........L?'f 􀁾􀀧􀀠EQR QARI USE Qt:\t"v I Dale To DART Staff ToTASC TASC Review Endin,! Data (11l ) CONSTRUCTION COST DISTRIBUTION :inn lI: t 2 6.\ 􀁒􀁩􀁾􀁨􀁬􀂷􀁯􀁦􀂷􀁗􀀢􀁶􀀠/2 7\ .,; '" $ '/2 e \ Other lI: t 2 9\ TOlal •• /30 \ , TITLE PATE SIGNED Director of PUblic works Dale To P&D Committee PSD Review Approved by P&D . APPLICATION FOR LOCAL ASSISTANCE PROGRAM , .• 􀁲􀁙􀁾􀁅. OF SUBMISSION (1) DATE SUBMITTED (2) , , 8/27/97 􀁾􀀠Capilal (e) CATEGORY CODE (500 reversal (6 )r-Technical (T) (3) -(4 ) -l..iL Ravlslon (Rl (6 ) -(7) -(6) APPLICANT INFOR!.!,' LEGAL NAI.IE (9) ORGANIZATIONAL UNIT (10) Town of Addison Department of Public Works 􀁾􀁄􀁄􀁒􀁅􀁓􀁓􀀠CONTACT PERSON pity Addison (11 ) Counly Dallas ( 12) Name: Jim Pierce Siale Texas (13) If> Code 75001 (14) Telephone: ( 972 '; 450-2879 PROJECT 'TITLE (15) Midway/Greenhill Intersection i.PBOJECT DE RIPTION AND JUSTIFICATION (16) The re inder of this project will be funded by Dallas County. Request -$7 ,7 0.00 be reprogrammed into Arapaho Road Realignment Extension See' 􀁣􀁯􀁭􀁾􀁮􀁩􀁯􀁮􀀠eMS application, for justification and construction costs • . ; PBOPOSED 􀁐􀁾􀁏􀁊􀁅􀁃􀁔􀀠Slart Dale . (11) cnding Dale, (16) ESTIMATED fiSCAL YEAR FUNDING CONSTRUCTION ,COST DISTRIBUTION", S 1191 _L $ r26 I Citv S 1201 Riohl·or·Wav $ 1271 Siale $ -.121' CMsl1 $ 'r 281 _'ocal $ 1221 Olher S r 2 2 9 I (),her S, (231 TOlal $ !;\21 DART s (24' TOTAl S /l (251 SIG(!i:!..-AlTrHOBllED RE1::ENTATIIiE TITLE DATE SIGNED .A< ,---...)5""􀁾􀁟􀀠.£If􀁾􀀯􀁻􀁾--; Director of Public Works 􀁧􀀭􀁺􀁾􀁮. EQR/QAflI !Jl2E 􀁑􀁾􀁬􀁙􀀯l_ /Date Dale To DART Staff To P&D Committee ToTASC P&D Review TASGReview Approved by P&D .....' PUBLIC WORKS DEPARTMENT (972) 450·2871 FAX (972) 451)..2837 ® Post Office Box 9010 Addison, Texas 75001·90]0 16801 Westgrove February 5, 2003 Mr. Trip Brizell Capital Programming Senior Manager Dallas Area Rapid Transit P.O. Box 660163 Dallas, TX 75266-0163 Re: Belt Line -Quorum and Midway Intersections Dear Mr, Brizell: As you may know, the above project is complete and we have received final payment from DART to close our account. Accordingly, we want to transfer any remaining, or programmed funds not yet paid to another project. Your latest quarterly report shows $83,897.83 remaining in the LAP/CMS fund and $321,547.83 remaining in the CAP fund, This is to request that you check those figures, and particularly the CAP fund amount, I do not believe the CAP figure is correct. Please advise your findings so we can re-program the remaining funds, Thank you for your attention to this matter, Very truly yours, Town of Addison 􀁾􀁾􀁾􀁣􀀻􀀮􀀠mes C. Pierce, Jr., P.E. sistant Public Works Director cc: Chris Terry, Terry, Assistant City Manager Michael E. Murphy, P,E., Director ofPublic Works Carolyn Burgett, Accounting Manager Enclosures tund"l/'Ig par RasolulkKl -...',r -,1)11»,,,= 04114/98 $250.000.00 08117196 0S/1(W9 $100,000.00 00/(>1"" 0""'"10f21J!f7 O2'ItlW8 0411"'" O&'i7J!fS 0712MS 0SI1ll1S9 IJ9I07Il19 0611_ o7ro7100 -,lQ/21J!f1 $844,592.00 5546,280,$7 $50,000.00 04114la8 $:26S,OOO.OO oatI1198 02/12/ll1 02112101 "'"'''''1 􀀺􀁽􀁾􀀿􀁾􀀼􀁘􀀠0"","" 10121197 􀀧􀀺􀀺􀀺􀁾􀁾􀁙􀁾􀀺􀁚􀀻􀀠....." $250.000.00 10121197 -:",'" 􀀧􀀬􀁾􀀢􀀿􀀭􀁩􀀸􀁾􀀺􀀢􀀧􀀼􀀧􀀢􀀠&250,000.00 $168,919;.40 $575,673,80 $llO.2S6.00 $436.Q24.S7 $110,000.00 -$50,000,0(1 $52.600.00 $34,000.00 $2S0,OOO.oo $100,000,00 $1,05a,738.00 .􀀭􀀸􀁾􀁾􀁾􀀻􀀡􀀺􀁾􀀺􀁾􀀺􀁾􀁾􀀺􀁾􀀧􀀠$350.000.00 $0,00 $O,C/O $50,000.00 • ····c······>·•.".·.>"..:,7.;"'" $452,056,11' $102,aoo.00 >';;,:1,: 􀀢􀀢􀀢􀀧􀁾􀁅􀀭􀀵􀀺􀀻􀀺􀀧􀀢􀀠 ,I 8 a Dallas Area Rapid Transil P.O. Box 660163 Dollos. Texos 75266-0163 214/749-3278 January 31, 2003 Mr. James Pierce, P. E. Assistant City Engineer Department of Public Works Town ofAddison P. O. Box 9010 Addison, TX 75001-9010 Re: LAP/CMS FY 2003 First Quarter Report Dear Mr. Pierce: Attached is the FY 2003 First Quarter Report for the Town of Addison LAP/CMS programs. DART Finance has recently started an initiative to pay our member cities through ACH (Automatic Clearing House) a direct deposit payment program. This is a process where the member cities will send us check request letters and the back-up via Accounts Payable Business Portal at (http://ao.dart.org). You must first subscribe to this business portal before you can upload your invoice. Your request letter will be your invoice. If you have any questions, please call Sharon Riddle at 2141749-2980; she is DART's Sr. Business Analyst for the Recurring Payments project. If I can be of further assistance, please call me at 2141749-2764 or Julie Rodriguez at 2141749-2831. Sincerely, 􀁾􀀠Ttip Brilell Senior Manager Capital Planning & Development TB:jr Attachments ADDISON LOCAL 􀁁􀁓􀁓􀀧􀁓􀁔􀁾􀁎􀁫􀁅PROGRAMlCONGESnON 􀁍􀁾􀁦􀁪􀁁􀁾􀁅􀁍􀁅􀁎􀁔􀀠SYSTEM (LAP/CMS! ROORXMMElrNPROGRAMIfED BALANCFUNDS EXPENonvRES EXPENonvRES EXPENDmJRES FUNDS NOT YETBY PROJECT􀀬􀁾􀀮􀀠􀁔􀁏 􀁾􀀺􀀺􀁄􀁔􀁏PRo."", 􀁎􀁁􀁾􀀠􀁅􀁘􀁐􀁅􀁎􀁾􀁾􀂷􀁾􀀽􀁾􀁾􀁉􀁾􀁾􀁾􀀽􀁾􀀽􀀠=, -=, OIlIiIXI.OO. 􀀭􀁾􀀠􀁾􀀭􀀬􀁾􀀠􀁏􀁉􀁉􀁉􀁄􀀧􀁾􀁟􀀠-,-,-􀁦􀁉􀁔􀁲􀀺􀁲􀁾􀀠Arapaho Road Phase III: Addison Rd. 10 Surveyor Blvd. per Resolullon 1t0201n SUBTOTAL THIS PROJECT Town Wide Signals Upgrade SUBTOTAL THIS PROJECT Brookhaven Club Drive 􀁒􀁬􀁬􀁃􀁏􀁦􀁬􀁓􀁴􀁲􀁵􀁣􀁾􀁯􀁮􀀠Payment SUBTOTAL TIllS PROJECT CoUon Bell RR Qulel Zones per Resolution #010149 SUBTOTAL TIllS PROJECT Addison Roali'Excel Way SUBTOTAL THIS PROJECT Technical Asslslance Program (TAP) lor Public Works Department Transportallon Salaries Payment Staff approved addlUonatlundlng SUBTOTAL TIllS PROJECT Technical AssIstance Program (TAP) Payment SUBTOTAL TIllS PROJECT Addison Road Widening Payment AddillOllal Funding parTown 01 Addison. (Update file with 2·7.(11 correspondence and and loss the 1·2·01 corres.) Payment Additional funding par Resolullon 11010148 SUBTOTAL THIS PROJECT Weslgrove/SoJoum 􀁉􀁮􀁬􀁥􀁲􀁳􀁥􀁣􀁾􀁯􀁮􀀠ImprO'lemenls per Staff Approval. This Is aCllJally a transler 01 funds lrom Addison AoadlExcel Parkway InlersecUon ....tIlch Is a LAP/CAP proJect, to lund this new project. Payment SUBTOTAL THIS PROJECT -,-Technical Assistance per Resolution #990142 Payment SUBTOTAL THIS PROJECT 'Per Resolution 1198oo78,Iransler $64,084.43 to CAP to COlIer a lransler made earlier In the yeorwhlch left a negaUve 01 $64,084.43 In CAP funds." -,-Technical AssIstance per Resolution 11980076 11/12102 11/12102 $983,250 $983,250.00 $155,043 5155,043.00 $983,250.00 $155,043.00 0M!Ei/0204_' $59,053.50 $59,053.50 $59,053.50 $59,053.50 $0.00 10116101 $695,000.00 $695,000.00 09130/01 $69$,000.00 $76,500.00 $76,500.00 $16,500.00 08I30I0' 09/19101 10117/02 $41,530.00 $41,330.00 $82,860.00 $41,530.00 $41,530.00 $41,330.00 08112100 07/07100 08112100 07/07/00 $::17,760.00 $37,750.00 $1,229,760.00 $37,750.00 $245,956.00 $37,750.00 $298,9n.00 $0.00 1.555,178.00 02112101 09119101 IOJ18101 $53,021.00 $571,354.00 $1,854, 155.00 $53,021.00 02128100 04117/00 $40,000.00 $40.000.00 $40,000.00 $40,000.00 $0.00 09110199 09/07199 $35,993.00 $35,993.00 $35,993.00 $35,993.00 "'.00 04/14198 04114/98 $34,000.00 􀀭􀁵􀁾􀀠" iii j i Ii" 􀁾􀀠􀁾􀀠􀁾􀀠i!' 􀁾􀀠d 􀁾􀀠" i!' 􀁾i 􀁾􀀠􀁾􀀠i 􀁾􀀠􀁾􀀠0 􀁾􀀠." 􀁾􀀠􀁾􀀠E" 􀁾􀀠􀁾􀀠􀁾􀀠g 􀁾􀀠􀁾􀀠Ii' if s q 11 U II 􀁾􀀠􀁾􀀠§ !Is "Iii un 􀁾􀂧􀀠00 􀁾􀁾􀁾􀀠􀁾􀂷􀁉􀀠􀁾􀁾􀀠􀁯􀁾􀀠§􀁻 􀀡􀁬􀁾􀀠.S 􀁾􀀺􀀧􀀺􀀱􀀠;oj; 􀁾􀀠􀁾􀀠􀁾􀀠H 􀁾􀁾􀀠U §§ 􀁩􀁬􀀡􀁾􀁾􀀠􀀡􀁕􀁾􀀠d H 􀁾􀀠􀁾􀁾􀀠􀁾􀁾􀀠w ... ..,...,. NU 􀁾􀀠􀁾􀀠i )!I l! 􀁾􀀠􀁾􀀠I f 􀁾I" I 􀁾􀀠t ¥ 8 I 􀁾􀀠􀁾􀀠-.,. i II 􀁾􀀠8'" 􀁾􀀠􀁾􀀠is 􀁾􀀠Ii 􀁾􀀠l!! l!!􀁾􀀠" 􀁾􀀠is is 8 0 1Il,.. 􀁾􀀠:;; --AJ1i!i$fl& J.J 􀁾􀁲􀁍􀁧􀁒􀁥􀁊􀁀􀁩􀁒􀁁􀁍􀁬􀁃􀀺􀁏􀁎􀁾􀁾􀁾􀀱􀀧􀁬􀁏􀁎􀀠MANAGf:MEJ:!f' 􀁓􀁙􀁓􀁔􀁅􀁾􀁟􀀠(LAP/CMSJ_ , 􀁾􀁎__􀁉􀁬􀁁􀁕􀁴􀁎􀁾􀀠􀁾􀁾􀁾􀁾􀁾􀀠, OYPR(}JECT I e:::r:}:'-::': 􀁅􀀻􀁦􀀬􀁾􀁾􀁾􀁾􀀠􀁾􀁾 􀁾􀀠􀁾􀁾􀁾􀁾􀀠􀁾􀁾􀁾􀁦􀀠-􀁁􀁁􀁲􀁵􀁾􀀮􀀬􀁾􀀠"""'" I Pur ResokJUoo #980258. IrBfI$ler 􀁲􀁯􀁭􀁡􀁬􀁮􀁾􀀠(left oyer) funds from 2 LAPIC pro}GClS i)$ ShOW1l below. Howe"er, thero will be no physical translerol money between the TOW1l 01 Addison and DART, The TOW1l 01 Add1son will k&ep tha money In lhelr OWI'leccount. 1111Q198NOTE" N«II" Rallm&d Crossln¢lul'\leyor. $56.6&1 11110,196 • MTdwaylOooloy IntorseocilO!'l; N«. $6.964.94-1111G'96 Acw8i tof8I prognrmmfld trw lhIs ".,jOallunding per ResOO,lllon 1f9!l()14a: Qa/101S9 $44.175..06 Paymuni 09A)719!! $44,175.08 SUBTOTAL TmS PROJECT $294.175.06 MidWay Road & Dooley InlMlGCllon Improvemsnls per ACGQlu!lQn 3 .37001. """""'7 5135.000.00 04Ii13I97 $135.000.00 Ac1ufI c;(lSt of thispmjcct W$s -;$126,D'35. The remainIng 􀀤􀁾􀀹􀀶􀀵􀀠 iWIll be hppledwthe Keller iSprMg$!QUotum project per iResdutkm' fflfJ256. Tho Town 01 iAdd/$Oilt hU the ltClVall'#l'lWnJng 􀁾􀀠(S8,965.00)($8,96f1,OO""""Y' Town of Addisoo refunded LAP/CMS In '\he amount of $122,522. Out 01 this mount, $900. lila relund lOr this pmj. v.talch than should be teptogmmmod to fund otMt ptO/acts per 21710 1C()(l'llI$pondonoo 02112/01 $f;lOQ,QQ Roprogram $900, 10 help lund oIhot projocrs par 'ZI7/01 Town 01 Addison COfl'aspondeneo 02.112/01 ($900.00 S!IBTOTAL THIS PROJECT SI28,035.oo Rwlroad Crossing Aeplacement Oft 2 SUrveyor Rd. $100.000.00 $100.000.00,"""'"Actusl CO$t of thIs proJect MIS $43,140. The IM1BinJng$56,B6D wiN bet ltppIfed to the K.11at' 5pr1ngs/Quorom projftcf per ResoIutIO/1 1198fJ:!58. l1MI Town of h AddUan hu 11mnhtBimoney. 􀁾􀁈􀁏􀁏􀁅􀁉􀁉funding perTOWl'l 01 􀁾􀁾􀀧􀀤laller 00100 02J01!{)1 0>112/1)1 $910Jl() $9:10.00Payment 09119101 SUBTOTAL mrs PROJECT $1oo,t10.oo .,.,..,.,..1 echnicaI Assl91anCe Progmm 1Q12(l/!1' ..,.""" 11119196 $34,000.00 SUBTOTAL mrs PROJECT $34,000.00 TOTAL $$8,401,805.13 $0.00 $269,000.00 $2,231,672.57 $1,238,906.06 $373,106.00 $.53$,554.11 $59,053.601--" TOW Q/lI/nnHmttlD AN YOU'-: ,4,,'08,/J92.30 􀁅􀁘􀁐􀁾􀁾􀀠$144,044,00 rcmu. PAlDTO $2S4,175.QB $126.035.00 $100,910.00 $34,000.00 $4,852,936,30 􀁾􀀠",oo"",,,,,,rl 􀁆􀁗􀁉􀁄􀀡􀀮􀁺􀀬􀀬􀁾􀁮􀀧􀁅􀁔􀀠SO"" $0.00 SO"'" $0.00 $3,590,199.83 I -·1I 􀁾􀀠Ii II I 􀁾􀀠I,. 􀁴􀁾 􀁉􀁾􀀻 􀁯􀁬􀁾-􀁾􀁬􀁩􀁾 􀁊􀁾􀀠 􀁾􀁾􀁉􀀠 􀁾􀁉􀁩􀁾􀀠 Ii􀁧􀁾􀀠I d"1 􀀡􀁉􀁾􀀠 􀁾􀁾􀀠􀀮􀁾􀀠irI, 􀁾􀀱􀀮􀀠 II U al 􀁾􀀮􀀠􀁾􀁕􀀠 􀁾... "".... -.. ,,,,,,,. Il9t2IliOO 589200.00 """,,,, $306,' s.mAyden; 􀁒􀁾􀀤􀀱􀀳􀀬􀀴􀀰􀀷􀀢􀀶􀀴􀀱􀀢􀁢� �If>li Arapaho Road ReaUIIMlt'rltprojool ProjllCllofBrrIIIlndosed. ..""., (S13,407.64.s:UBmTALlms,.x&lmC:L___ _______ $111.59tl6 . MrDWAVAJNOBERG INi'€A:SEbt if/!!MIlSf5n:ooo:OO PaymQom tQ/17193 3HI,83().OC $10,830.00 Per R!lI:SOIi.tllol'l mOl72,lIppl)llho remaining lunda b holp progl1lmproJect: Ampaho Rd. Floallglttrfellt Ext Remal. of !his 􀁰􀁴􀁏􀁪􀁾􀀱􀀠(MldwayA.lndboto) 􀁷􀁬􀁾􀀠bI! tur4lJd by 􀁏􀁾􀁬􀁩􀁍􀁉􀀠Ct)ooty. 01050 plO)oI:I!UI( Jim SO"Plete$, 􀁾􀀠􀀨􀁳􀀬􀁾􀀬􀁾􀀺􀀠------􀀵􀁕􀀧􀁦􀀱􀁬􀀧􀁏􀁲􀀮􀁾_________􀁾􀀠􀁾􀀺􀀺􀀬􀀱􀁉􀁂􀁅􀁬􀁔􀁗􀁁􀁾􀀢􀁉􀁎􀀧􀁴􀁩􀀺􀀭􀁆􀁩􀀤􀁾􀂢􀀧􀁩􀀧 􀀬􀀠􀁾􀁗􀀦􀁲􀀠m$4S.000o(} .$2,m,.OO .,." 00 PI.It RoottlutiCUI f'9'1017/?, awIYtIMo rM1alnmofl.locls Ii) h$\) prOgnutlproiud; Arapaho RIi AealigfIfoom 􀁾􀀠AemalnOOfclprolUCt WIll ba IJ.Irwkd by Dalb!! 􀁃􀁯􀀭􀁾􀀮􀀠Clo!ifl prciOOl pit Jim 􀁾􀀠􀁩􀀤􀀴􀁡􀀬􀀰􀀱􀁾􀁾","'".,c---􀁓􀀺􀁴􀀮􀁭􀁲􀁯􀁝􀀧􀁁􀁌􀁾􀁏􀁭􀀮􀀺􀁴􀀺􀀠􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀀮p-OOH'''' 􀀮􀀬􀀬􀀭􀁾􀀠$4,200.00 ..""'.,Pm RasoIIIIicn nrol:r.!, 91!1lfy the relmlqfoods 10 􀁾􀁐􀁾􀁉􀁗􀁉􀁓􀁯􀁥􀁉􀀻􀀠Alapaho Rd. RooIigr.rnom El!1 Remaindef 01 project will bo tuma:! by D!lbsCwnty, CIooltpro}ectpefJlm -"""'􀀧􀀧􀀧􀁾􀀽􀀠i$?O.'!" .!' $0,., ...... isAI;I(Iitio/lIIIFU'fh 􀀬􀁾􀀭􀀮􀀠􀁾􀀢􀀡􀀣􀁊􀀠w,o,OOO:OOi=: 􀁾􀀠$19.soo.oo $63.5.$2UO ; Payment 041""" $5,525.00i payment ,'101,00 """""" $$.701,00 S8,70UIO SU.OO -....... SWTO.IAI nus l'ROffi:1 􀁾􀀮􀁭􀁏􀁬􀁬􀀠􀀽􀁾􀀮􀁉􀁉􀀢􀁩􀁬􀁩􀁆􀁁􀁆􀁬􀀬􀁅􀀠........... 􀁾􀀦􀁭􀀠$37,SOO..\lCl =,750.00 """"" $0.""p-11101100 S3;r6tloo AdcIhlor,,1I fl¥!dir>g pElt Town 01 Addison's '''''''''' "'....,k;\IeI (Je.IOO 02f0l'1ll1 PDymenI SustOTAt.. "".." "'......, $1,9111$00 -caT LJNEIDAlJ..A.I' NOffiHTOUWA,Y""""""'ON .,....., -,""'" J􀁲􀀮􀀺􀁾􀀺􀀺􀀺􀀠,,$13,nnoo""".., $3,810.00=: 0<1'''''' $120.00..,$238217.12 Pnym,ent and ProjractComple!Ad per-''''''''' $6,022.28 $262,EW2,OO 􀁁􀀴􀀱􀀡􀁾􀁬􀁭􀁤􀁬􀀡􀀱􀁑􀁰􀁥􀁲􀁬􀁭􀁭􀁯� �􀁁􀀺􀁫􀁬􀁩􀁳􀁯􀁮􀀧􀀤􀀠I leWdated f/lM101 """,>1 ""'..,....... """'''' _.. KSl..I.eR SPI'IINGSIOAIl.A$ NOfmi ITOU,WAV ""'RSfC11ON """'" $225,lso..oo ----ADDISON CAPITAL ASSISTANCE PROGRAM 􀁾􀁯􀁯􀁾􀀠EXPEHDlTURES EXPDlDlTURES EXPEHDlTUAES UPalDITURES EXPEHDlTURES EXPEHDlnJRES EXPEHDlnJRES EXPENDITURES EZPENDITURES EXPENDITURES EXP£NDfTURES TOTAL PAOGRAMIIEO AMOUNT PAID RJNDSNOTYETAPJ'ROVEO TOSE DURiNO DURING DURINO DURING DURING DlJRlNO DlJRlNG DURiNO DURiNO DURING DURING"re 􀁒􀁅􀁐􀁒􀁏􀁏􀁾􀁾􀁾􀀹􀀰􀀠FY!J'I.g;r 􀁾􀀮􀀢􀀮􀀠􀁾􀁾􀀠􀁾􀀮􀀠􀁾􀁾 --_._--􀁾􀀮􀀠􀁾􀁾􀀠􀁾􀁏􀁏􀀠􀁐􀁅􀁒􀁐􀁉􀀻􀁉􀁾􀀮􀁅􀁣􀀺􀁲􀀠_ .PAlo.􀁾􀀹􀁯􀁊􀁅􀁃􀁔􀁉􀀡􀀠􀁾􀁒􀀮􀁑􀀬􀁴􀁅􀁃􀀮􀁔􀀠􀁉􀀺􀁉􀁾􀁅􀀠• API'!IOVEO AM9U.NT 􀁾􀀢􀀠'-'00-$35,825:00􀁾􀀢􀀬􀀮Addlional furds translerrred from Bolt UneJMontfort BOO Belt Un&, AddIsOl1 Rd, ProjeeLS 04111/95 569,205.47 Payment """" $232,043.44 􀁐􀁡􀁾􀁥􀁮􀁴aoo Projeet ColTllleted 001"'" $27,467.03 $295,630.47 $0.00'OW96 􀀽􀁉􀁳􀁯􀁮􀁾􀁾􀁾􀀻􀁲􀀻􀁐􀁡􀁲􀀺􀁲􀁾􀁾􀁬􀁧􀁜􀀠02/12/01 $27S.OO $275,00Paymenl 00I1S'01 􀀭􀀭􀀭􀀭􀀭􀀭􀀭􀀮􀁓􀁬􀀡􀀡􀁉􀀮􀀺􀁴􀁏􀀮􀁉􀀭􀁍􀀮􀀮􀀮􀀮􀁉􀀡􀁊􀁾􀁑􀁬􀁅􀁣􀁲􀀠,29'.630.47I-or---􀁾􀁴􀁦􀁾􀀮􀁁􀀺� �􀁦􀁩􀀾􀁊􀁾􀁾􀁲􀁷􀁅PH7$E I PIIYrn8nt Ac!ditlorol fuoding per ToWll ToWll 01 Addison'slet\er'l'Il5,890,93 ::01,150,755,13 ::01,004.594.55 $2,469,164,73 ...00 $0.00 􀁾􀁔􀀮􀁉􀀶􀀬􀁓􀀴􀀹􀀬􀀱􀀷􀀠",.00 7,433,741.98 $559.;347.8:3 TOTAL DISBURSEMENTS ALL YEARS $7433741.98 PlOljor;!(tleca.,*,1Od'O aIGd SUMMARY STATUS REPORT: 12i31A12 (CAP ASSISTANCE FUNDS· OM. r] FUNDS PROGRAMMED $7,!R1,08'J.82 FuncilAJIoeated thru FY 96 $6,182,392.00 HP LaserJet 3200se TOALASERJET 3200 invent 9724502837 DEC-23-2002 2:41PM Fax Call Report Job Date Time Type Identification Duration Pages Result 902 12/23/2002 2:40:50PM Send 92147493670 0:59 2 OK TOWN OF PUBLIC WORKS From: Jim Plene,. P.E. 􀁾􀁾􀁎􀁾􀀠Am P1lc--<-o Call meo Original It! lUaU CommenU,,·________________ TOWN OF ADDIsoN FAX#: ·1-1 y..-ltf1-310 70 Date: IJ--1--3 -a '/....# of pages (including cover): ___ o Original in mail Kper your request PUBLIC WORKS From: Jim Pierce, P.E. Asst. Public Wks. Dir. Phone: 972/450-2879 .FAX: 972/450;.2837 . jpierce@ci.addison.tx.us 16801 Westgrove P.O.Box 9010 Addison, TX 75001-9010 o FYI o Call me Comments:_______________________ (971) 450.2811 FAX 450.2837 Mr. Trip Brizell Capital Programming Senior Manager Dallas Area Rapid Transit P.O. Box 660163 Dallas, 'IX 75266-0163 Re: Addison LAP/CMS Payment Request -Invoice. Agreement No. 1005780-1 Dear Mr. Brizell: This is to transmit our LAP/CMS payment request (Invoice), for the following project: Project Amount Belt Line: Quorum & Midway Intersections $144,044 This project is now complete. Please call me at 972-450-2879 ifyou have any questions. Very truly yours, 􀁔􀁟􀁾􀀺􀀺􀁴􀁌􀀭􀁾 􀁾􀀡C. Pierce, Jr., P.E. c...i:"::mt Public Works Director cc: Chris Terry, Assistant City Manager Mike Murphy, Director of Public Works Randy Moravec, Finance Director DART Accounts Payable Portal Page 1 of3 D1U..t.J,\$ JUUEA itA-PH) TiU\N$iT ACCOUf<4TS PAYJUn,e: POIlTAL ;¢.t;i<{.:;"'rV.\".... 􀀺􀁴􀀺􀀬􀁾􀀬􀀧􀀳􀀱􀀺􀀮..􀀻􀁲􀀮􀁩􀁦􀀬􀁾􀀬􀁾􀀬􀀻􀀮􀁾􀀬􀀠t[",ir.£:; 􀀷􀀷􀁾􀀤􀁊􀀭􀀭􀁷􀀮􀁊􀁽􀀬􀀧􀀾􀁽􀀿􀀠[3 HODle: JIM PIERCE TOWN OF ADDISON Invoice Status P.O. BOX 9010 The listing below represents the last three years of invoices your company has submitted to DAIADDISON, TX you desire information on invoices older than three years old, please use the search form below 75001-9010 contact DART Vendor Information at (214) 749-2727. JPIERCE@C1.ADDISON.TX.U 5 To sear<::h for a specific invoice or payment number, (1) select what you are searching for and C enter the text or number to search you desire in the field below and click the nFind It!" buttol 1. Search Using: o Check Number ® Invoice Number 2. Search For: I. To search withIn a certain date range for invoices, please select 'tading and gruIjng dates beh and click the "Search Within Date RangeH button. Invoice Number: Received: 121802 12/20/20021) Invoice Status:ilw".Pending Review Comments: No Comments Found Invoice Number: Received: ANATTA112602 11/26/2002 Payment Amount: $498.81 Comments: No Comments Found Remit To: TOWN OF ADDISON P.O. BOX 9009 ADDISON, TX 75001-1009 􀀮􀁾􀀮􀁪􀁩􀁬Invoice Status: Invoi« Number: Received: 3) ANITA102502B 11/14/2002 Payment Amount:Paid and Closed $483.13 Invoice Amount: $144,044.00 Invoice Amount: $498.81 Check Oat..: 12/3/2002 Invoice Amount: $483.13 Check Date: 11/19/2002 Estimated Chad Date: 12/21{2002 Check: 64035 Check: 63612 http://ap.dartorgfinvoicestatus.asp 1212312002 PUBLIC WORKS DEPARTMENT (972) 450-2871 FAX (972) 450-2837 Post Office Box 9010 AddisODt Texas 􀀷􀁓􀀰􀀰􀀱􀁾􀀹􀀰􀀱􀀰􀀠16801 Westgrove Mr_ Trip Brizeli Capital Programming Senior Manager Dallas Area Rapid Transit P_O. Box 660163 Dallas, TX 75266-0163 I 􀀭􀁾􀀭􀀧Re: Addison LAP/CMS Payment Request -Invoice. Agreement No. 1005780-1 Dear Mr. Brizeli: This is to transmit our LAP/CMS payment request (Invoice), for the following project: Project Amount Belt Line: Quorum & Midway Intersections $144,044 This project is now complete. Please call me at 972-450-2879 ifyou have any questions. Very truly yours, 􀁔􀀮􀀽􀁾􀁾􀁣􀁲􀁾􀀡C. Pierce, Jr., P.E.􀁾􀀺􀀺􀁡􀁮􀁴Public Works Director cc: Chris Terry, Assistant City Manager Mike Murphy, Director of Public Works Randy Moravec, Finance Director ))/l;?r-􀁐􀁡􀀻􀀯􀁾􀁾􀁍􀁣􀁾􀁥􀁾􀀲􀁌􀀠... 􀁾/(lnU 􀁾􀁾􀁾􀀺􀁴􀀭􀁁􀀡􀁦􀁾IJ-4 􀁾􀁾􀀠􀁴􀀱􀁊􀁾􀀠􀁒􀂥􀁶􀁶􀁦􀁯􀁾􀁾􀀮􀀠􀁾􀁾􀁾􀁾􀁾􀀮􀀠􀁾􀀠􀁦􀁊􀁾􀂷􀀠􀁾􀁾􀁶􀁌􀀠 􀁾􀁡􀁾􀀩􀀠PUBLIC WORKS DEPARTMENT (972) 450-2871 FAX (972) 450·2837 ADDIsoN􀁲􀀭􀁾􀂷􀀢􀀭􀀢􀀧􀁾􀀧􀀠,-,_.----.:..__􀁾􀂮􀀠Post Office Box 9010 Addison, Texas 75001-9010 16801 WestgroveDecember 16, 2002 Mr. Trip Brizell Capital Programming Senior Manager Dallas Area Rapid Transit P.O. Box 660163 Dallas, 'IX 75266-0163 Re: Addison LAPICMS Pa,yment Request -Invoice. Agreement No. 1005780-1 Dear Mr. Brizell: This is to transmit our LAPICMS payment request (Invoice), fur the following projects: Project Amount Arapaho Road, Phase III $983,250 Technical Assistance (Salary Assistance) $ 41.330 Total $1,024,580 These projects were approved by DART on November12, 2002. I have attached a resolution by the City Council authorizing filing the applications. Please call me at 972-450-2879 ifyou have any questions. Very truly yours, es C. Pierce, Jr., (Assistant Public Works Director cc: Chris Terry, Assistant City Manager Mike Murphy, Director of Public Works Randy Moravec, Finance Director Enclosures RESOLUTION NO. R02-Q68 A RESOLUTION BY THE CITY COUNCIL OF THE TOWN OF ADDISON. TEXAS. AUTHORIZING TOWN OF ADDISON STAFF TO MAKE APPLICATION FOR DART LOCAL ASSISTANCE PROGRAM/CONGESTION MANAGEMENT SYSTEM (LAP/CMS) FUNDS IN THE AMOUNT OF $1.337.659.00 FOR FY 2003. WHEREAS, the Interlooat Agreement between DART and Addison provides for an allocation of funds to Addison, from DART, based upon retum of 15% of the DART sales tax collected from Addison for the previous 12 months; and WHEREAS, this program will continue until 2004 or rail construction begins in Addison, whichever comes first; and WHEREAS. the Town's allocation for FY 2002-2003 is $1.337,659.00; and WHEREAS, the Town has three projects for assistance under this program which will utilize the funds for Town wide signals upgrade. Arapaho Road, Phase III and technical assistance; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS: THAT. the Cily Council does hereby authorize ToWn of Addison staff to make application for DART Local Assistance Program/Congestion Management System (LAP/CMS) Funds in the amount of $1.337,659,00 for FY 2003. DULY PASSED BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS, this the 27'" day of August 2002. ' ATIEST: OFFICE OF THE CITY SECRETARY R02·068 DART Accounts Payable Portal Page 1 ofl OJU.LA$ AREA ilAPID 􀁔􀁒􀁁􀁎􀁾􀁮􀁲􀀠 􀁁􀁃􀁃􀁏􀁕􀁾􀀱􀀧􀁓􀀠PA'fASUii: PORTAL W.FH·;1':1%4 ."?.'.......􀁾􀀧...􀁯􀁲􀀮􀁲􀀮􀀬􀀺􀀧􀀺􀀧􀀬􀁾􀀧􀀬􀁴􀀧􀀭I);;"r....cj 􀁾􂂬􀁾􀀻􀀻􀀨􀀷􀀢􀁽􀀷􀀷􀀠 81 HrJme JIM PIERCE Submit InvoiceTOWN OF ADDISON P.O. BOX 9010 ADDISON, TX 75001-9010 JPIERCE@CI.ADDISON.TX.US r Your invoice [121602 for TOWN OF ADDISON (100371)] was successfully submitted (voucher # 130850) Instructions: 1. Salect the applicable payment agreement from the "Payment #t1 drop down list. 2. If your particular invotce applies to a task order, please select that task order from the ''Task Order" dropdown Ust. 3. Enter the invoice amount in the "Invoice Amount!! field. Please omit any dollar symbols ($) or commas (,) from the amount. 4. Select the invoice date for your invoice. 5. Attach your invoice file by clicking on the "Browse" button next to the "lnvolce File" field. Wh DART Accounts Payable prefers PDF files, you may attach Excel Spreadsheets (.XLS), Microsoft' files (.DOC), and Text fil.s (.TXT). 6. Add a brief description in the "Description" field If you desire. 7. Submit the invoice by clicking on the "Submit Invoicell button. Payment #: 􀁉􀀮􀁾􀀮􀁾..􀁾􀀢􀀡􀁾􀁾􀀮􀁾..􀁾􀁾􀁾􀁾􀁾􀁾􀀮􀀬􀁾􀀮􀁾􀀠...................ri1 Task Order: 􀁴􀁾􀁾..􀁾􀁾..􀀡􀁾􀀮􀁾􀁾􀀮􀁾􀀡􀁾􀁾􀀮􀁾􀀠􀀬􀁾 􀁾􀁩􀀬􀁾􀁾􀀮􀁾􀁾..ii Invoice Number: I................................................. Invoice Amount: L @2002 DART, All rights reserved. http://ap,dart.orglInvoicing/invoicing,asp 12/16/2002 JIM PIERCE, P.E. Assistant Public Works Director (972) 450·2879 (972) 450·2837 FAX jpierce@cl.addison.tx.us Town ofAddison 16801 Wostgrove Dr. P.O. Box 9010, Addison, Texas 75001·9010 AUTHORIZATION FOR AUTOMATED CLEARING HOUSE (ACH) PAYMENTS Please provide the following information to authorize Dallas Area Rapid Transit (DART) to initiate ACH credit entries and/or correction entries to your Checking or Savings account (select one) as indicated below: Vendor/EmpleyeeNa_1 8+\D(..;V\ 􀁁􀀭􀁴􀁁􀁊􀁉􀁾􀀠Vendorl EmplO)'ee Nllmilw: __...!I-=D=-::0'--"'-3<-7-'-11______ Vendor Tax ID (W-9 attached): _____________ Bank Name: ___________________ ABANumber: __________________ Account Numbu: ________________________ Account Type: Checking __ Savings__ Other information vendor would like to add: Name of Authorized Official: __________________ Title of Authorized Official: ____________________ Telephone Number: __________________________ Emailaddress: _____________________ Date: __________ Note: Please attach a letter of confirmation from your depository bank with the following information: Account Name, Account Numbu and Routing (ABA) Number. Allow three weeks for ns to set up your electronic payments, after we receive this form. We also encourage you to visit our website (AP.DART.ORG) and subscribe to our "Email Notification" service for your payment advice. Please be advised that electronic payment advices will not be issued unless you subscribe to the .. Email Notification" service at AP.DART.ORG. Ifyou have any questions or need to make changes to the information listed above, please contact Shawn Ahsan at (214) 749-3018 and mail your request to the following address: Dallas Area Rapid Transit (DART) Attn: Shawn Ahsan P. O. Box 660163 Dallas, TX 75266-7222 ________________________ _ II Public Works I Engineering 16801 Westgrove • P.O. Box 9010 Addison, Texas 75001 Telephon.: (9721 450·2871 • Fax: (9721 450-2837 DATE. I'J..-il0 1IJOB NO. ATTENTION RE' ArtJ<..n61. hu-RJ1 f/f1pu ///I I , I i GENTLEMAN: WE ARE SENDING YOU Ji(Attached o Under separate cover via ______ the following items: o Shop Drawings o Prints o Plans 0 Samples 0 Specifications 0 _________________________o Copy of letter o Change order COPIES I DATE NO. THESE ARE TRANSMITTED as checked below: o For approval 0 Approved as submitted o Resubmit ____ copies for approval i& For your use 0 Approved as noted o Submit copies for distribution o As requested o Retumed for corrections o Return corrected prints o For review and comment 0 o FOR BIDS DUE __________ 1,,____ o PRINTS RETURNED AFTER LOAN TO US COPY TO ___________________ 􀁓􀁉􀁇􀁎􀁅􀁄􀀺􀀭􀁴􀁾􀁾􀁾􀁾􀁾__-------------If enclosures are not as noted, please noli Jim Pierce From: Randy Moravec Sent: Friday, December 13, 2002 4:54 PM To: Jim Pierce Subject: RE: Belt Line/Quorum/Midway Intersection Improvements -Project #62301 Jim, As I mentioned to you today, go ahead and use the amount you have. Randy --Original Message---From: Jim Pierce Sent: Thursday, December 05,200210:48 AM To: Randy Moravec Cc: Bryan Langley; Michael Murphy Subject: Belt Line/QuorumlMidway Intersection Improvements -Project #62301 Randy: Back in July you brought to our attention that this project had an account deficit of $144,044. I tried to get with Sandra and work on this before she left but we were not able to connect. There is more than enough money that DART has programmed, but nct yet paid, in the DART account This project is now complete and there will be no more charges. If you will give me the final amount needed to zero out Project # 62301, I will request a check from DART, and then ask them to transfer any remainder to another project. Thanks, Jim Pierce, P.E. Assistant Public Works Director P.O. Box 9010 Addison, TX 75001-9010 972-450-2879 1 Re: ]?Arr 􀁾!C-vYl5 FlA.Yl.ci, rtf 􀁁􀀺􀁰􀀮􀁯􀀱􀀯􀁾f I o Original in mail 0 Per your request o FYI 0 Call me Comments: att.utJ.. h a .lettz; M--4><. TOWN OF ADDIsoN To: .JJ ke_ pod rlj Je:3 Company: U A-F21 FAX #:. 􀁾􀁉􀀧􀁦􀀭􀁝L{-.q;... 3 "70 Date: 􀀱􀀱􀀭􀁾􀁬􀁬􀁾􀁯􀀿􀀭# of pages (including cover):--.!:/: PUBLIC WORKS From: Jim Pierce, P.E. Asst. Public Wks. Dir. Phone: 972/450-2879 "FAX: 972/450-2837 jpierce@ci.addison.tx.us 16801 Westgrove P.O.Box 9010 Addison, TX 75001-9010 ® September 10, 2002 Mr. Trip Brizell PUBLIC WORKS DEPARTMENT (972) _2871 FAX (972) 45lJ..2837 Post om« Box 9010 Addison, Tex•• 75001·9010 16801 Westgrove Capital Programming Senior Manager Dallas Area Rapid Transit . P.O. Box 660163 Dallas, TX 75266-0163 Re: Addison LAPICMS Funding Applications Dear Mr. Brizell: This is to transmit LAP/CMS Funding Applications, to be funded from our FY2003 projected allocation, for the following projects: Project/Application Amount Town Wide Signals Upgrade $155,043 i Arapaho Road, Phase ill .$1,141,986 '1&>3, ::t'5'0 Technical Assistance (Salary Assistance) $ 41.330 " Total $1,337,659 I have attached a resolution by the City Council authorizing filing the applications. 􀁾􀀮􀀠. <'(83/􀀧􀀲􀀮􀁾􀁯􀀠This is also to request payment of $1-,141,26'6 for Arapaho Road, Phase III, (project is in right-of way acquisition phase and under design) and $41,530 for Technical Assistance at this time. Please call me at 972-450-2879 ifyou have any questions. Very truly yours, es c. Pierce, Jr., P. sistant Public Works Director cc: Chris Terry, Assistant City Manager Mike Murphy, Director of Public Works Randy Moravec, Finance Director Bandra Goforth, Accounting Manager Enclosures RESOLUTION NO. R02-oS8 A RESOLUTION BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS, AUTHORIZING TOWN OF ADDISON STAFF TO MAKE APPLICATION FOR DART LOCAL ASSISTANCE PROGRAM/CONGESTION MANAGEMENT SYSTEM (LAP/CMS) FUNDS IN THE AMOUNT OF $1,337,659.00 FOR FY 2003. WHEREAS, the Interlocal Agreement between DART and Addison provides for an allocation of funds to Addison, from DART, based upon return of 15% of the DART sales tax collected from Addison for the previous 12 months; and WHEREAS, this program will continue until 2004 or rail construction begins in Addison, whichever comes first; and WHEREAS, the Town's allocation for FY 2002-2003 is $1,337,659.00; and WHEREAS, the Town has three projects for assistance under this program which will utilize the funds for Town wide signals upgrade, Arapaho Road, Phase 111 and technical assistance; now, therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS: THAT, the City Council does hereby authorize Town of Addison staff to make application for DART Local Assistance Program/Congestion Management System (LAP/CMS) Funds in the amount of $1,337,659.00 for FY 2003. OFFICE OF THE CITY SECRETARY R02-068 I 1 DULY PASSED BY THE CITY COUNCIL OF THE TOWN OF ADDISON, TEXAS, this the 2th day of August 2002. ATTEST: OFFICE OF THE CITY SECRETARY R02-068 I Dollos Area Rapid Transit p.o, 80x 660163 Dallas. Texas 75266-0163 214/749-3278 October 18, 2002 Mr. James Pierce, P. E. Assistant City Engineer Department of Public Works Town of Addison P. 0, Box 9010 Addison, TX 75001-9010 Re: LAP/CMS FY 2002 Fourth Quarter Report Dear Mr. Pierce: Attached is the FY 2002 Fourth Quarter Report for the Town of Addison LAP/CMS programs. This includes the new 2003 allocation in the amount of$1,273,232. Recently, DART's Finance Department began requiring all reimbursement checks be mailed directly from that department. Checks will no longer come directly from the Planning Department as they will be mailed directly to your Finance Department. Also, check stubs will have "LAP/CMS" or "LAP/CAP" for identification ofthe recipient. If r can be of further assistance, please call me at 214/749-2764 or Julie Rodriguez at 214/749-2831. If you have any questions regarding System Checks please call Beverly LaBenske at 214/749-3053. Sincerely, 􀁾􀀠􀁔􀁾􀁂􀁾􀁉􀁥􀀻􀀱􀀠Senior Manager Capital Capital Planning & Development TB:jr Attachments • 􀁾􀀠􀁾􀀠1 I n I 􀁾􀁾􀀠§ 􀁾􀀠I II 􀁾􀀠􀁾􀁾􀀠􀀽􀁾􀀠􀁾􀀠􀁾􀀠I􀁾􀀢􀀧􀀱􀀠I ;,d ! gl • 􀁾􀀠􀁾􀀠8 i 8 ·· ·s􀁩􀁾􀀠I rlgl 􀁾􀀠I• r':8 ,;: • ! 􀁾􀂧􀁾􀀠􀁾􀀠p 􀁾􀁾􀀠􀁾􀀠􀁾􀀠ilil 8 􀁾􀀠il 􀁾􀀠il J! 􀁾􀀠 n III 􀁾􀀠IS II:: '" 2 nill 0 , · h IpU 􀁾􀀠􀁾􀀠,,"! 􀁾􀀮􀀠8 􀁾􀀠􀀬􀀬􀁾􀀠II Ii III I I ! 􀁈􀁾􀀠, 􀁾􀀠I ----I ADDISON LOCAL ASSIS..'f.1iNCEPROGRAMlCONGE.S!!.ON MANAGEMENT 􀁓􀁙􀁓􀀱􀁃􀁍􀀭􀀭􀀭􀀱􀁾􀁥􀁊􀁧􀁍􀁓􀀩􀀠roNOS 􀁉􀁕􀁎􀁐􀁒􀁾􀁾􀁧􀀺􀁌􀁁􀁎􀁾.=. Brookhaven Club Drive IReconstruct/on 0>2_ $59,053.50 -Payment 04""'02 SUliTOTAL TIllS PROJECT $59,053.50 Cotton Bell RR Qulel Zones per OIG!Xll00. IResoIutlon /1010148 10116/01 $695,000.00 SUBTOTAL TIllS PROJECT $695,000.00 _100:1 IAddiSon AoacllExcel Way 08130101 $76,500.00 􀁾􀀮􀀠SUBTOTAL 'IHIS PROJECT m,soo.OO Technical Assistance Program (TAP) for Public Wor1ls Departmenl \11II'mUl1.'Q11 ITrampor1atlon 􀁓􀁡􀁬􀁡􀁾􀁥􀁳􀀠0&'30/01 $41,530,00 Paymenl 09/19/01 SUBTOTAL THIS PROJECT $41,530.00 ITechnlcal Asslstanca Program (TAP) 06112100 $37,750.00 Paymenl 07/07/00 SUBTOTAL THIS PROJECT $37,750.00 -,-IAddlson Road Widening 06112100 $1,229,780.00 Payment 07/07/00 I AddlHonal Funding perTo'Ml 01 Addlson. (Update me with 2·7-01 correspondence ancltoss the 1·2·01 corres.) 02112101 $53,021.00 Ipayment 09119101 AddlUonalfunding per Resolullon 11010148 10116/01 $571,354.00 SUBTOTAL THIS PROJECT $1,8$4, 155.00 Wes.grovelSojoum 􀁉􀁮􀁬􀁥􀁾􀁥􀁣􀁕􀁯􀁮􀀠 Improvements per Slaff Approval. This Is actually a lransfer of funds from Addison RoadlExcel Parkway 0S1:IG<00C(t2 Inlersectlon I'J>ENDITURES TOTALPAJDTD FUNDS NOTYEr: ; FY2fX1l DATE PAID, $0.00 $59,053.50 $59,053.50I I $695,000.00 I $76,500.00 $0.00 $41,530.00 $41,530.00 $0.00 $37,750.00 $37,750.00 $245.956.00 I $29B,9n.00 􀁾􀀱􀀠,555, 17B.00 $53,021.00 $40,000.00 I $40,000.00 SO.OO I $35,993.00 $0.00 $35,993.00 $34,000.00 I $34,000.00 $0.00 $250,000.00 I $350,000.00 $0.00 ---I I ADDIS(JN LOCALASSISTANCEPIIQG..RAMlCONGESTlON MANAGEMENT SYSTE"'_MPICMS--PROG""""""NPROGRAMNED BA1..ARCFUNDS EXPENDfTlJRES EXPENDmJRES EXPENDmJRES EXPENDf1VRES EXPENDf1VRES FUNDS NOT YET􀁅􀁘􀁐􀁅􀁎􀁾􀁾􀀬􀀠EXPENDfTlJRESBYPROJEC1" 􀁔􀁏􀁔􀁾􀀺􀀺􀁩􀁄􀁔􀁏PRMeT ._􀁾􀀮􀀠CAPOIIOO1t7OC11 -,-,Payment SUBTOTAL THIS PROJECT Ampaho RealignmentJExtenslon Per Resolution i970172. Payment Payment Additional funding per Resolution #980076 Payment Payment Additional funding per Resolution #990142 Paymenl Additional funding per Resolution I!'OOO099 Paymenl SUBTOTAL THIS PROJECT Belt Une: Quorum & Midway Inlersecllons Per R9901uUon 1970172. Paymenl Paymenl SUBTOTAL THIS PROJECT Belt Unefrollway (Single Point Urban Inlerchangel Per Resolution #970172 Paymenl Additional funding per Resolution #980076 Paymenl Town 01 Addison refunded tAP/CMS in the amounl 01 $122,522. Qui of this amount, $102,800 Is a refund lor this proJ. which then should be reprogrammed to fund other proJecls per 217/01 correspondence Reprogmm balance 01 $102,800 to help lund other proJecls per Town 01 Adtlison correspondence dated 2nfOl. Reprogram balance 01 $216,200 to help lund other proJecls per Town 01 Addison correspondence daled 2nfOl. SUBTOTAL THIS PROJECT -,-Technical Assistance Program Per Resolution #970172 PaymenlI SUBroTAL TIllS PROlEa 1 Keller SpJingsfQuorum IntelSectlon 􀁾􀀬􀀭Iper Resolution #970172 Payment Per Resolution i980258, Imnsler remaining (Iell over) funds Irom 2 tAP/cMS projecis es shown below. However, there will be no physical transler 01 money between the Town of AcIcIlson and DART. The Town 01 'r:ddlson will keep the money In their NOTE"* own account NrAtI ,Railroad CrosslngfSurvayor; 556,860 $100,000.0009/07/99 1350,000.00 09109J97 5844,592.00 10121fl.l7 5188,918AO 02118198 $676,673.60 $0.00 04/14198 5548.280.57 I 0&'17fl.l8 5110,256.00 $2A97,610.57 07f2!JJ98 $436,024.57 08/10199 51,058,738.00 09/07/99 $1,056,736.00 06112100 $50,000.00 07/07100 $50,000.00 I $2,497,510.571 I I 09l09I97 $850,000.00 I 10121/97 5170,000.00 $622,058.17 $227,941,83 09119/01 $452,056.17 $850,000.00 09109.07 $50,000.00 10121/97 $50,000.00 04/14198 5269,000.00 0&'17198 $52,800.00 $102,800.00 $0.00 02112101 5102,800.00 02112101 ($102,800.001j 02112101 (5216,200.00) 5H12,8Oa.00 09109197 $34,000.00 10121197 $34,000.00 $34,000.00 10.00 $34,ooa.oo 09109197 $250,000.00 10121197 5250,000.00 I 11/10198 ,11/1M8 I ADDlSOlj Lp(:AL ASSISTANCE 􀁐􀁒􀁏􀁇􀀭􀀧􀁾􀁁􀁍􀁉􀁃􀁏􀁎􀁇􀁅􀁓􀀱􀀷􀀰􀁎􀀠􀁁􀁦􀁾􀁦􀁊􀁾􀀮􀁇􀁾􀁅􀁎􀁔􀀠SYSTEM f!.APIC3(S} I 􀁉􀁐􀁒􀁏􀁇􀀡􀀬􀀬􀀺􀁾􀁾􀁕􀁎􀁐􀁒􀁄􀁇􀁒􀁁􀁍􀁬􀁬􀁬􀁅􀁄􀁂􀁁􀁌􀁁􀁎􀁃􀁥􀀠EXPENOITURESFUN DS EXPENDmJRES EXPENDmJRES EXPENDmJRES EXPENDmJRES EXPENDmJRES 􀁔􀁏􀁔􀁾􀀧􀀺􀀧􀁄􀁔􀁏􀀠􀁆􀁕􀁎􀁾􀀺􀀡􀁔􀁙􀁅􀁔I I BY PROJECT" I 􀂣􀁬􀁐􀁅􀁎􀁾􀀽.=. I I , * MldwaylDooley 􀁉􀁮􀁬􀁥􀁲􀁳􀀹􀁃􀁾􀁯􀁮􀀺􀀠$8,954.94 11/10198NO. AclUal lotsl progtammed for this pm/ect: 5315,824.94 Addltlonallundlng per Resolution 1990142 08110199 $44,175.06 $294,176.06 SO.OO Payment 09/07/99 $44,175.06 SUBTOTAL THIS PROJECT $294,17Sl}6 Midway Road & Dooley Intel5ection Improvements per Resolution 3 1#970046 03125197 $135,000.00 Payment 04"",,,7 $135,000.00 SI26,035.00 SO.OO Actusl cost ofthis proJect was $126,035. 71Ie remaining $8,965 will besppled to the Keller Sprlngs/Quorum project per Resolutlon 198t:l258. The Town of Addison fIBs the actual remaining 􀁾􀁹􀀮􀀠($8,965.00) ($8,955.00) -Town of AdCOson refunded LAP/eMS In the amount 01 $122,522. Out 01 this amount, $900. Is a refund lor this proj. which than should be reproglllmmed to lund other projecLs per 2/7101 correspondence 02112101 $900.00 i ! Reprogram $900. to help lund other projects per 217101 Town 01 Addison correspondence 02/12/01 ($900.00) iSUBTOTAL THIS PROTECT $126,035.00 Rall(()8d Crossing Raplacement on 2 Surveyor Rd. 10123196 $100,000.00 SI00.oo0.00 $100.910.00 SO.OO Actusl cost of !hIs proJecr was $43,14a 7hB remalnlng$56,860 will beapplied to me Keller Springs/Quorum project per Resolution #980258. The Town 01 .. AddlsOll hils the sctusl money, AddiUonal lundlng perTolYO or 􀁾􀁣􀁬􀁤􀁬􀁳􀁯􀁮􀀧􀁳􀀠letter dated 02/07101 02/12/01 $910.00 Payment 09/19/01 $910.00 SUBTOTAL THIS PROTECT $100,910.00 Technical Assislance Program 10123196 $34,000.001 $0.00 Payment 11/19/96 $34.000.00 $34.000.00 TOIOII'focIjoc!I: 􀁉􀁾􀀠SO.oo $l69,OOO.00 S2,231 ,872.57 SI.236.906.06 $373.706.00 $536.554.17 $59,053.50 $0.00TOTAL $7,263,512.13 $4.708.892.30 $2,654,619.83 ITorsl OIsbUlHl7llln!$ All Y,ar.l: $4,708,892.30I 􀀮􀁾SUMMARY STATUS REPORT: 9f3a102 FUNDS PROGRAAMIED Funds AJI_d lor FYI 'i11lhru 03 (PIUI) FUndllranlllerTed 10 CMS Irgm CAP (1eN1TotaI Paid 10 Dale (lull) Totallranaf,rTed In>m CMS 10 CAP" AI:counl BalanclI (1eN1 programll\ed Fundi Not Y8I Paid S7.263.512.13 $8.752,010.00 $40.000.00 $4,708.892.30 $330.053.43 53,753.064.27 $l,554.819.83 SI,118.445.00 ® September 10, 2002 Mr. Trip Brizell PUBLIC WORKS DEPARTMENT (972) 450-2871 FAX (972) 450-2837 Post Office Box 9010 AddisoD, Texas 75001·9010 16801 W..tgrove Capital Programming Senior Manager Dallas Area Rapid Transit , P.O. Box 660163 Dallas, TX 75266-0163 Re: Addison LAP/CMS Funding Applications Dear Mr. Brizell: This is to transmit LAP/CMS Funding Applications, to be funded from our FY2003 projected'allocation, for tbe following projects: Project/Application Amount Town Wide Signals Upgrade $155,043 II Arapaho Road, Phase III -$.1,141,986. Qli"3::t5o1Technical Assistance (Salary Assistance) $ 41,330 􀁾􀀠Total , 􀀤􀀱􀀬􀁓􀁓􀀧􀁩􀀧􀀬􀀶􀀵􀁾􀀠'!J, I; nil) h'l.3 􀁾􀀠I have attached a resolution by tbe City Council authorizing filing tbe applications. (f'' , Cf 93, 􀀧􀀱􀀮􀀮􀁾􀁯􀀠 This is also to request payment of $1-,141,281; for Arapaho Road, Phase Ill, (project is in right-of way acquisition phase and under design) and $41,530 for Technic ••. 􀁾􀁾CIf-P \ ( \ \ 􀁾􀀮􀀠􀁾􀁾􀀵􀀠􀁾􀀯􀁦􀁾􀀠. . . E--VLj I 1'1 £>-t? r i nO-_.. 􀁌􀁾􀁐􀁍􀁲􀁣􀀬􀀬􀁾􀁟􀁾􀀠 ... 􀁾􀁾􀁤􀀭􀁙􀁜􀀠 􀁴􀁩􀁾􀁾􀀠􀁰􀁾1L/.m: A-d d I 􀁾UY'. gc\ -Tt. 'rfl(\ '{'S. \.., \....., Y\ 􀁾􀀠Sfruh cAf,t,J PI?J'PC.f:s 􀁲􀀺􀀮􀁮􀁾􀀠10 2/0. co S' /, t;; 12.. Cftf '3bl, 0"3 i ' 􀁾􀀠 􀁤􀀺􀀮􀀬􀁓􀁏􀁾􀀠:)t;3 , B 7 '+1 \1 'I 00'+, '8"'+ _ It \ \ 0 I 􀁌􀀮􀁉􀁾􀀮􀀠CJQ ' 􀁣􀁐􀁾􀁾􀁾􀁾􀀠 -cr 􀀱􀀮􀁺􀁽􀀱􀀧􀁾􀀱􀀠􀁯􀁬􀀱􀁾􀀬􀀠􀁾􀁹􀀮􀀠 Michael Murphy From: Randy Moravec Senr. Friday, JuIy05; 20(}2 to:El-1--(lM To: Michael Murphy; Slade Strickland Cc: Bryan Langley; Sandra-GefefIII; Chris Terry Subject: Second Quarter Capital Project Report Mike-&Slade, Please-fi11d attacl,ed a -PDF tre ot-the capital project-report for the qtJarterendect Marei'] 31 , 2002. The report consists of two pages. The first page is Fund 41 and includes information for the firstandsecondqtJarters. The second-page is-FtJnd-46-forthetwoquarters. Mike, I would like to bring to your attention the $144,044 deficit in project # 62301 Midway/0tlorumfBelt-Line Intersections: What-is the stattlS"of OtJr havingE>-AR'"f aIIocateitmding to "zero out" this project? Also, are there any other expenses yet to be charged to this project? Please provideart tJpdateat-yotJr earliest convenience. , If you have any questions or comments regarding this report, please contact me. Second Quarter 2002 Capital Re ..• • 􀁾􀀠:hnJ ])/H2T 􀁾􀁾􀀠􀁾􀁾􀁾􀀯􀁾􀀠􀁾􀀠􀁦􀁫􀀭􀁾r1t 􀁾􀁾􀀠1 In\\\: or \IHlI ...O'X !'>TRlTT('\I'IT\I,I'fmJr:Od Belt LlrnslMkfway/QUQl'l.Im Addison Rd./EI(OSI AddlsOI1 Road' IITI'Rr.!'>" \':\1) ('11.\'\Cp., 1,\ [HI, \ "'f.'> F,I/' ,h,' i;.,...11 rfill' ;:wllll;': S<1'lu,,"a ,w, !Im! 2e.'300 2002 Palling f FiR Rbhab, 06300 SojoumfNestgto'ltl 15301 Addlsoo CIrcle Phase He Cotton Belt RR Quiet Zones Arapaho Rd. Ph8$e I Addison ,"""""Spectrum Cormec1Joo IWlI$l'Sprfnga{OIJorum Arbfualle Repeta Uablilly (550) (596). (2,655) mnsg 􀁾􀀬􀀠(8,655) (10,450) TOTAl. _,07105m PIJnt&d: 07/05/2002 􀀢􀁾􀀮----••-. 􀀭􀀺􀁾􀀺􀀺􀀺􀀺􀀺􀀮􀀺􀀬􀀷􀀺􀀭􀀧􀀠􀀭􀀭􀀢􀁾􀀬􀀠". TO,,"\: or AIlIJISO\: 2000 C\PIT.\1. PRO.JECT FlT'\i1> I'\DJ\lllli\L I'RO.lECT Rf\E'II'ES. E'\PE'IIlITlRES..\'11l CIL\'1(;ES I'IIIAI.\'!CES For ,,,,, Fi.\('/I/l't'UI' Elldillg Sl'plC'IIl/WI' .W. ]()f)] Number 02300 03500 04300 85301 05301 12302 83300 Pro ect Name Unallocated Bell Line Sireetscape Athletic Club Expansion Midway Road Rehabllitallon Moms Road Spectrum Drive Belt Line /Toll Road SPUI Arapaho Road Phase 111111 TOTAL BeginnIng Balance $ 108,338 12,402 3,269,744 91,979 510,448 300,000 272,073 3,398,577 $ 7,963,561 First Quarter Ended December 31,2001 Revenue Ex endltures Interest/Other Admin.Sal. Prof. Services Ca ital 75,555 (11,455) (3,119) (10,423) (2,201 ) (28,381) (2,748,847) $ 75,555 $ -$ (45,156) $(2,759,270) Budget Ad"ustments $ -Ending Balance $ 183,893 12,402 3,258,289 88,860 500,025 300,000 269,872 621,349 $ 5,234,690 TOW'! OI'\IlIlISO'! woo C\I'IT.\L PRO,IEeT Fl''11l I'WI \ I III ',\ L PRO.l EeT REIT'!I' ES. EXPE'!IlITl' lIES, .\'11l (,IIA'I( ;ES I\: 1\.\ L,\'1CES Fol' lite Fi.H"tll rC'({1" 􀀱􀁾􀀱􀁉􀀨􀁴􀀻􀀯􀁉􀀬􀁾􀀠Scp/I'II/hl'/" 3(J, ]{J02 02300 Belt Line Streetscape 12,402 12,402 03500 Athletic Club Expansion 3,258,289 (127,079) 3,131,210 04300 Midway Road Rehabilitation 88,860 (10,318) 78,542 85301 Morris Road 500,025 (82) (17,941) 482,002 05301 Spectrum Drive 300,000 300,000 12302 Belt Line /Toll Road SPUI 269,872 269,872 83300 Arapaho Road Phase II/III TOTAL Developed: 07/05/02 Printed: 07/05/2002 Dallas Area Rapid Transit p.o. Box 660163 Dallas, Texas 75266-0163 214/749-3278DART July 2, 2002 Mr. James Pierce, p, E. Assistant City Engineer Department of Public Works Town ofAddison P. O. Box 9010 Addison, TX 75001-9010 Re: LAP/CMS FY-2002 Third Quarter Report Dear Mr. Pierce: Attached is the FY-2002 Third Quarter Report for the Town of Addison LAP/CMS programs. I want you to know that Julie Rodriguez has moved over to Area Mobility Programs with Koorosh Olyai's group. However, she will still maintain her position working with me on the LAP/CMS projects. Her telephone number remains the same. If I can be of further assistance, please call me at 2141749-2764 or Julie Rodriguez at 2 J41749-2831. Sincerely,-6J􀁔􀁾􀁂􀁲􀁩􀁊􀁉􀀠Senior Manager Capital Planning & Development TB:jr Attschments Ji 􀁾• •t 5 ;, • 􀁾􀀠􀁾􀀠&• 􀁾􀀠i I .J! • l I 8 I -􀀭􀀭􀀭􀀭􀀮􀁾􀁉􀀫􀀭􀀭􀀭􀀫􀀡􀀭􀀭􀀭􀀪􀀭--􀁴􀀡􀁾􀀠􀁾􀀱􀀱􀀠􀁾􀀠􀁊􀁾􀀠" 􀁾􀀠i 􀁾􀁾􀀠􀁾􀁬􀀠􀁾􀀠.s " 􀁾g!os S 8 8 ! 􀁾􀀠II i i8 : i , : II 􀁾􀀠I 􀁾􀀠jj 􀁾􀀠" II ! I i ! "8 Ii 􀁾􀀠􀁾􀀠8 Ii Ii 1< 􀁾􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠8 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀁾􀀠•" UNPROGRAMMED BALANCE BY PROJECT Drive IReconstruCtion 03f25102 $59,053.50􀁾􀀢􀀢􀀧􀀧􀀧􀀠04/30102 $59,053,50 09020011lO1 IResolUtiOn #010148 10116101 $895,000.00 $695,000.00 􀁾􀀬􀁾􀀠IAddilSon 􀁈􀁯􀁡􀁤􀁬􀁾􀁣􀁥􀁬􀀠wav 08130101 $76,500.00 $76,500.00 (TAP) og;QIITlOOIi ITransportation Salar1es 08130/01 S41,530.00 09/19101 $41,530.00 ""'-ITechnical Assistance Pl'OQram {TAP} 06112100 537,750.00 07107100 $37,750.00 􀁾􀀬􀀭IAcldison Hoad wlaenlnQ 06112/00 $1,229,780.00 07107/00 02112101 553,021.00 09119/01 Resolution 10/16101 $571.354.00 51,854,155.00 Intersection per Staff Approval. a transfer 01 funds :1JExcel Parkway is a LAP/CAP thIS new project 02128/00 S40,000.00 04/17100 $40,000.00 per Resolution 􀁾􀀬􀀭1#990142 08110/99 $35,993.00 09/07/99 $35,993.00 #980076, transfer 􀁾􀁥􀁲􀁡􀀠leyear 64,084.43 in 04/14/98 Resolution 09II219S1OaJ 1#9800fti 04/14/98 534,000.00 " 06117/98 SUBTOTAL THIS PROJECT $34,000.00 (LAP/CMSJ $0.00 $59,053.50 $59,053.50 I $895,000.00 I 518,500.00 $0.00 $41,530.00 $41,530.00 $0.00 $37,750.00 537,750.00 $245,956.00 $1,555,178.00I $288,977.00 $53,021.00 50.00 I S40,OOO.00 $40,000.00 I $35.993.00 $0.00 $35,993.00 $34,000.00 534,000.00 I 50.00 pe' Il$IPOfWWf 􀁉􀁴􀀱􀁑􀁓􀁏􀁉􀁕􀁬􀁉􀁏􀁏􀀪􀁾􀁜􀁊􀁕􀀯􀁢􀀠per Resolution funding par RasoMoo rBTOTAL THIS PRO}ECI' Quorum & Midway os Per ResolutIon 􀁾􀀱􀀤􀀮􀀧􀁉􀁴􀁏􀁬􀀠j#97Q1n. OSIO:;lIffiOOo1 Iintart;rtangaj t"er HeSOltlUOn #970172 "'''SUBTOTAL rms PRO}ECI' "",04114/98 $2so.ooo.oo 06t17198 􀀰􀀸􀁴􀀱􀁾􀀠$100.000.00 09/07199 $35(),()(J().(J(J 09/09197 5844,592,00 1Drl1197 0211_ 0411_ S$48,28O.57 00!17198 07129198 00110199 $1,058,736,00 09I07J99 0\ll121OO 07107100 $2,497,610.61 _ANNllD BALANCE BYPROJECT $250,000.00 I $350,000.00 I SM. $100,000.00 $1SS.918.40 $675,673.60 $0.00I $110.256,00 1$2.497,610.57 $436.024.57 $1,056,738.00 $50.000.00 09/09/97 10121197 $170.000.00 $622,058.17 i $221,941.83 09/19101 II $452:,059.17 $860,OOfMJO 09/09197 $50,000,00 10fl1197 $50,000.00 04114/98 $269.000.00 I 06/17/98 $52:.800.00 $102.600,00 02112101 $102,eoo.oo 02112101 02112101 09l09I''' 10121197 134,000.00 $34,000,00 09l09I97 NOTE" • $$S.6&> of Addison refunded LAP/eMS amountof$122,522.0uto! amount, $900. Is a refund for ,........ proj. ....tJ.lch then should be irepJOgrammed to fund other projects !per2ll/01 correspondence !Aeprogram $900. to help ft iprojects per 217101 TOwn of joorraspondenca SUBTOTAL THIS PROJECT \Rallroad Crossing Replacement on 􀁩􀁓􀁾􀁁􀁤􀀬2 􀀺􀁔􀁑􀀯􀀻􀀡􀁯􀁉􀁾􀁮􀀠:roTAL 10121/97 11110198 11/1019$ 11/10J98 0011_ 09J07199 03'''''97 04/23/97 02112101 02112101 $44,175.06 S90 􀁾􀀠t{-35/0 1-2=33 .. NE UMQIJN' 59053.50 0.00 59053.50 , 'J/, -􀀵􀁾􀀰􀀵􀀳􀀮􀀵􀀰􀀠0.00 59053.50 WARNING. THIS 􀁄􀁏􀁃􀁕􀁍􀁾􀀠T HAS UV FIBERS CHEMICAL STAIN VOID AND A TRUE WATERMARK -OLD UP TO THE LIGHT TO V RIFY _ or t.MIIillICA 56167 W:l.chi 􀁴􀀮􀁾􀀠􀀱􀀢􀀢􀀧􀀬􀀱􀀮􀀮􀀱􀀬􀁾􀀬􀀠Te)(ae Dallas Area Rapid Transit P.O. Box 660163 VOID AFTER 􀁾􀀠0 DAYSDallas, Texas 75266-7222 DATE 04/26/02 AMOUNT PAY FIFTY-NINE THOUSAND FIFTY-THREE AND 􀀵􀀰􀀯􀀱􀀰􀀰􀂷􀀺􀂷􀁾􀀭􀀭􀀭􀂷􀂷􀂷􀂷􀀭􀀭􀀮􀀭􀀭􀀭􀀭􀂷 􀀭􀀭􀀭􀀭􀂷􀂷􀂷􀂷􀂷􀀠.i·S9,06·3.50 TOTHE. TOWN'OF ADDISON ORDER .' P.O. Box 9010 OF ADDISON TX 75001-9010 --_.. . .-------.--_. II' Sf, lob 711' .: lolol.qO 10:102': 0010 2 51,81,0 1'1811' PUBLIC WORKS DEPARTMENT (972) 450·2871 FAX (972) 450.2837 􀁾􀁾􀁾􀁾􀁾􀂮􀀠Post Office Box 9010 Addison, Texas 75001-9010 16801 Westgrove March 26, 2002 Mr. Trip Brizell Capital Programming Senior Manager Dallas Area Rapid Transit P.O. Box 660163 Dallas, TX 75266·0163 Re: Brookhaven Club Drive Restoration Dear Mr. Brizell: Fanners Branch has awarded a construction contract for the above referenced project, part ofwhich will be built in The Town ofAddison. The Town has agreed to pay for its share ofthe cost out ofDART LAP/CMS funds. Accordingiy,this is to request a 'check for our portion ofthe project in the amount of $59,053.50 that was set up with our recent funding application. Your attention to this matter will be most appreciated. Very truly yours, 􀁔􀁟􀀺􀁾􀁾􀀠es C. Pierce, Jr., P.E. ......... 􀀬􀁾􀀮􀁳􀁩􀁳􀁴􀁡􀁮􀁴􀀠Public Works Director cc: Chris Terry, Assistant City Manager Michael E. Murphy, P.E" Director ofPublic Works Sandra Goforth, Accounting Manager FUNDING APPLICATION FOR DART's LAP/CMS PROGRAM LAP/CMS Project No. (for DART use only) 01 -00'1 -owe1 city no. project type project no. GENERAL INFORMATION Date Submitted February 8, 2002 • Applicant City: Town ofAddison City CIP No. ________ • Project Eligibility Type: (see list, reverse side) Roadway Improvements i-Project Name: Brookhaven Club Drive Reconstruction •• BoundarieS/short description Brookhaven Club Drive from Golfing Green to Marsh Lane I-Approx. BeginlEnd Dates: from March 2002 to December 2002 FUNDING PROJECTED COST DISTRlBUTION Current LAP/CMS Request $ 59,053.50 PlanningfEnvironmental Studies $ Previously Approved LAP/CMS Date (s) $ EngineeringlDesign .. $ Federal (ifapplicable) $ Right-of-way $. State (if applicable) $ Construction $ 59,053.50 • Local (ifapplicable) $ TestinglInspection $ i Other (ifapplicable) $ OperationslMaintenance $ TOTAL $ 59,053.50 TOTAL $ 59,053.50 DETAILED PROJECT DESCRIPTION (List/Explain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fund transfers, reprogramming requested ifapplicable.) . Reconstruction ofBrookhaven Club Drive from east leg ofGolfmg Green Drive to 500' east of Marsh Lane. The portion ofthe project east ofMarsh Lane is in Addison. This project will improve the westbound left tum lane and enhance the handicap accessability at the intersection ofMarsh Lane and Brookhaven Club Drive. The portion west ofMarsh Lane is in Farmers Branch. This is a cooperative project with Farmers Branch. Farmers Branch has designed and will bid the project. This project affects Bus Route 322 . •Request $59,053.50 be transferred from Addison RoadlExcel Way Project to this new project. . Date I FUNDING APPLICATION FOR DART's LAP/CMS PROGRAM LAP/CMS Project No. (for DART use only) .....:'0",,-,-1--OD'] -D1-{)Dl city no. project type project no. GENERAL INFORMATION Date Submitted Feb 8,2002 • Applicant City: Town ofAddison City CIP No.,________ • Project Eligibility Type: (see list, reverse side) Roadway Improvements • Project Name: BrQokhaven Club Drive Reconstruction • Boundaries/short description Brookhaven Club Drive from Golfmg Green to Marsh Lane • Approx. BeginlEnd Dates: from March 2002 to December 2002 FUNDING PROJECTED COST DISTRIBUTION Current LAP/CMS Request $ 59,053.50 PlanninglEnvironmental Stndies $ Previously Approved LAP/CMS Date (s) $ Engineering/Design $ , Federal (if applicable) $ Right-of-way $, , State (if applicable) $ Construction $ 59,053.50 Local (ifapplicable) $ Testing!Inspection $ Other (if applicable) $ OperationslMaintenance $ TOTAL $ 59,053.50 TOTAL $ 59,053.50 DETAILED PROJECT DESCRIPTION (ListlExplain bus routes affected, intersections to improve, project scope, phases, etc. Attach project justification as needed.) (List/explain fimd transfers, reprogramming requested ifapplicable.) Reconstruction of Brookhaven Club Drive from east leg ofGolfing Green Drive to 500' east of Marsh Lane. The portion of the project east of Marsh Lane is inAddison. This project will improve the westbound left tnrn lane and enhance the handicap accessability at the intersection ofMarsh Lane and Brookhaven Club Drive. The portion west ofMarsh Lane is in Farmers Branch. This is a cooperative project with Farmers Branch. : Farmers Branch has designed and will bid the project. 'This project affects Bus Route 322. Request $59,053.50 be transferred from Addison RoadIExcel Way Project to this new project. Director of Public Works Title Date Date Dallas Area Rapid Transit P.O. Box 660163 Dallas. Texas 75266-0163 2141749-3278 March 11,2002 Mr. James Pierce, P. E. Assistant City Engineer Department of Public Works Town of Addison P. O. Box 9010 Addison, TX 75001-9010 Re: LAP/CMS FY 2002 Second Quarter Report Dear Mr. Pierce: Attached is the FY 2002 Second Quarter report for the Town of Addison LAP and LAP/CMS programs. If! can be of further assistance, please call me at 2141749-2764 or Julie Rodriguez at 2141749-2831. Sincerely, 􀁾􀀯􀁲Trip Brizell Senior Manager Capital Planning & Development TB:jr Attachments • ....,." IReSOlution #010146 SUBTOTAL THIS PROJECT OII021ClilOa (TransPOrtation salaries --(TeChnIcal As&iStance Progmm(fAP) --IAddlson Road wtdeninQ funding per ResoIulion 10116101 08130/01 08130101 09/19101 0611:2100 07107100 00I12JOO 07107100 02112.1)1 09119101 10116101 per ResollJUon I»l1IOOOOt 1#990142 nl SUBTOTAL 7H1S PROJECT ITechnh::al Assistance per Resolution--, SUBTOTAL THlS PROJECT =100 Q.4117toO 08nOl9tl (}9107199 04/14198 04/14198 06117198 $895,000.00 􀀤􀁾􀀹􀀵􀀮􀀰􀀰􀀰􀀢􀁏􀁏􀀠$76,500.00 $78.5!i0.OO $41,530.00 $41,530.00 $31,750.00 $37,750.00 $53,021.00 $571,354.00 $1,B54.155.00 $40,000.00 $4D,OOO.OO $35,993.00 􀀤􀀳􀁾􀀹􀀹􀀳􀀮􀀰􀀰􀀠$34,000.00 $34,000.00 I $695,000.00 $11>,500.00 $0.00 $41,530,00 $41.530.00 $0.00 $37,750.00 $37.750,00 $245,956.00 I$298,977.00 $53,021,00 $40,000.00 I $40,000.00 I $0.00 I $35,993.00 I $0.00 $35.993.00 $34,000.00 $34,000.00 $0.00 -------i 􀁾􀀬􀀮􀀠PROJECT NAME OATEAPPROVE,IJ ......1'11(1(0 ......,lg/l»l. -,,-w-Keller 􀁓􀁰􀁾􀁁􀁤􀁤􀁩􀁳􀁯􀁮Road 􀁉􀁮􀁴􀁥􀁲􀁳􀁥􀁣􀁴􀁩􀁯􀁮􀁾􀁶􀁥􀁭􀁥􀁮􀁬􀀤􀀠per Resolution 076 Paynumt 􀁾􀀬􀁮􀁡􀁬funding per Resolution 142 Payment SUBTOTAL THIS PROTECT Arapaho 􀁾􀁮􀁭􀁥􀁮􀁴􀁬􀁅􀁸􀁬􀁥􀁮􀁳􀁬􀁯􀁮Per Resolution tI9 172. Payment Paymenl Additlorutl funding per 􀁾􀁴􀁩􀁏􀁮􀀠#980076 PaytJ'!$I1{ Payment Atk:Utlanal funding per Resol1,lNOt'l 1#900142 Payment ddltiooal funding per Resolution I1000099 Payment SUBTOTAL THIS PROJECT Belt 􀁬􀁉􀁮􀁥􀁾􀀠Quorum & Midwaytmersedkms Per ResOlution #970172• Payment Paymenl SUBTOTAl. THIS PROJSCI' Belt UI'IOIToUway {Single Point Urban Interchange) Per ResoIUllon #970172 Payment Addltional funding per Resolution #980076 Payn'l(lnt Town of Addison reftmded lAPJCMS 1n the amount (If $122,522. OUt of this amount, $102,800ls a refund for this pro). which Ihen should be 􀁦􀁥􀁾􀁲􀁮􀁭􀁭􀁡􀁤to fund other projectS per 101 COfTespondence R:rogram balMetl of $102.800 to h p fundothetprojeds per To'NOof Addison correspondence d31ed 217/01. Reprogram balallCEl of $216,200 10 hafp fund other projocts per Town of AddIS01'l correspondence dated 217101. SUBTOTAL THIS PROTECT Technical Assistance Program Per Resolution #970172 Payment SUBTOTAl. l"HlS PROJECT Keller 􀁓􀁰􀁬􀁩􀁮􀁾􀁑􀁵􀁯􀁲􀁵􀁭􀀠Inteructl oo iPer Res.olu on #970112 04114198 06f11J98 08110199 09107199 09i09i97 10121197 02118198 04114198 06111198 07129J98 08110199 09107/99 0011:1100 07107/00 O9/09J97 10121/97 09Ji9J01_7 10121197 04/14198 00/17/98 02112101 02112101 021121n1 09109197 10121197 09f09191 A.QDISON J.QCALASSlS!4NCE P _ noN MA r SYSTEM A UNPROGFlAMfrlED E.XPENOITiJRES EXPENOrrURES EXP'ENDlTURES TOTAL PAID TO FUNDS NOT YET""NOS BAI.ANCE BYPROJECT PIJRING FY,7 DURJNG FY'8 􀁾􀁗􀁣􀁦􀁾􀁕􀀺􀀠::=lJ¥r::I1 􀀶􀁲􀁾􀁾􀁾P/WSRAMIdED DURING FYSi PAl.DATE $250.000.00 $100,000.00 $'1_.00 _.592.00 $$46.280.57 $1.056,736.00 $50.000.00 $2,497,610.57 $850.000.00 $860,000.00 $50.000.00 $269.000.00 $102,SOO.OO ($1{)2,OOO.OO 1$216.200.00 $102,800.00 $34.000.00 $34,000.00 $250,000.00 $250.000.00 $0.00$350,000.00 $100,000.00 $168.918.40 $675.673,00 $0.00 $110,256.00 $2,497,610.57 $436,024,57 $1,056,738.00 S50.ooo,oo 1170.000.00 $622,058,17 $227,941.83 $452,0S8.17 $50.000.00 152.aoo.OO $102,800.00 $0.00 $34.000.00 134.000.00 10.00 I Crossing/Surveyor. $56,860 3 2 TOTAL $0.00 i $269,000.00 $2.231.672.57 $1,236.906.06 $313,70MO 5536,554.17 $4.649,831UIlI I$2,564,619.83 UNPROGRAMMED BALANCE BY PROJECT $250,000.00 $44,175.06 $135,000.00 $126,035.00 ,,,,,965.00) $100,000.00 $100,910.00 $0,00 $910.00 $0,00$34,OOC)'OO $34.000,00 10121197 11/10198 11/10196 11/10198 08110/99 09107/99 03n5!97 04123197 02112101 02112101 10J:!3/96 02}12J(11 091191(11 10123196 11/19/96 $4,649,838.80 SUMMARY STA"IUS REPORT: "J(J1Ift1. FtJNDS PROGRAMMED 􀁆􀁵􀁮􀁤􀁡􀁾􀁦􀁏􀁴FY.91tb", 02 {I>tu.} Fllnd. tran.hlmtd to eMS from CAP {....} Total Paid to DIM (Iu'i Total 􀁾􀀱􀁲􀁯􀁭CMSta CAP" A««>IItI.tB.1MCAI (Ian) ProarMl'lll"!odFIlr"idl Hot yet Paid 􀁕􀁾􀁭􀁭􀁾􀁓􀀮􀁦􀀮􀁉􀁬􀁏􀀨􀁴􀀨􀁡􀁬􀁭􀁭􀁕􀁹􀀮􀁶􀀮􀀯􀁬􀁬􀁬􀁢􀀯􀁥􀀩􀀠FUTURE 2003 I'tojected 􀁁􀁬􀁦􀁯􀁣􀁾􀀺􀀠$1.337.659.00 $7.204.456.63 $7,478,m.oo S40.000.00 $4.649,838.80 $330.053.43 $2.538.685.77 $2.554.619.83 ($15.'i34.08) 􀁾􀁾􀀮􀀠............ HH'IE ""'" 􀁾􀂭""... -''''''''''􀁾􀀠$89.201),1)0 $24,572.00 $4.61:t93 &4S2,nsa.11 􀀤􀁭􀁾􀁾􀀺􀁧􀁧􀀠$110.00 $3,nM,OO $1li!,92il 00 55U.0e4.42 $8.12S.OG $3.m.1$ iWfiVDS '" dUl'il6f8vo:tgffJOtId tolhe K.uat 􀀧􀁔􀁾􀁐􀁲􀁯􀁪􀁍􀁴􀀠""""""'" 02l12lftl Q2Ill1l)l S2(!,4QO 00 """''' OU12!iU OQl1lWl $1,020.00 $B,$OMO sae,QSS,19 $14,163.23 $1,R13.95II,.."". -----------n.tNClIIl«)l'l'lf't rtEMOGIllU.lW£ro ___ 􀁾__􀁾􀁾􀁉􀁾􀁬􀁾􀀡􀀻􀁴􀁾􀀠􀁃􀁁􀁾􀁉􀁊􀁟􀁾􀀢􀀧􀁟􀁾􀁾􀁾􀁉􀁾􀁾􀁎􀁃􀁅􀀠PROGRAM _.􀁾􀀠I!lU"I!:NPrt\II't1!B EXl"EHPITIJ1lI!8 EXPENPITIJ1lI!8 EXPEIIPrTlJIIWI 􀁾􀀱􀁬􀁉􀀡􀀸􀀠􀁾Ie.xPIIHPI'l'UIU!8 I!.lI'I"fIiOITIIRIiIl PJlfJCPm,111E8 􀁾􀀠-PURINO DU!'!iH(I ""...MiOlJKI' PAlP• 􀁾􀀬􀁐􀁒􀁏􀁊􀁦􀀮􀁣􀀺􀁮􀁷􀀮􀁾􀀠􀁾=: 􀁾􀁊􀀠􀁾􀀠tI:a 0:;:. 􀁾􀁡􀀠􀁾􀁉􀀨􀁉􀀠.,.... """" """. PERI'fIO.AIC'f -"'"""""""􀁾􀁭􀀠-'" "'" "" 􀀽􀁾􀀢􀁏􀁾􀀽􀀽􀁾􀁾􀀷􀀲􀁰􀁥􀁴Tom R an: 􀁒􀁾􀁭$13,40HI4 ,Into Iho Ampaho Rood ROIIliQl1ITIOI1I proJ(IGl. Projor.1 (I) (lIIft1lIll1 eIosed, 􀁩􀁾􀁉􀁊􀀮􀀴􀀰􀀱􀀮􀀵􀀴 ,.ro,," t1M91.)$ .", 􀁏􀀺􀁬􀁩􀁴􀀷􀁦􀁜􀁬􀀳􀀮􀁾􀀱􀀶􀁬􀁽􀀻􀀡􀀡􀁯􀁯􀀺􀂮􀀠$iO,!llO.OOPI)'I'fIOI'II $to,OOO.ilO p., RO$oCIlutloro tl0101n, IIlP!'; tho 􀀽􀀺􀁾􀀬􀀬􀁾􀁾􀁾􀁾􀁾􀁭􀁾􀀩􀁯􀁤􀀺􀀠􀀽􀀺􀁾􀁾􀁾􀁴􀁶􀁴1108 • Of "I"j4Il;:l PQf JOn,-.....,, 􀁾􀀠􀁻􀀤􀁩􀁾􀁾􀁧􀀺􀀽􀀬􀀠"''' lSELOWA'Y IN £2:,025.00􀁾􀁾􀁬􀀠 !W17m $2.l125.00 􀁉􀁐􀁦􀁉􀁦􀁾􀀱􀁦􀁦􀁬􀀱􀀰􀀱􀀱� �􀀬􀁾􀁭􀀠 􀁬􀁬􀀨􀁉􀁾􀁾􀁐􀀢􀀧􀀩􀁯􀁣􀁬􀀺􀀠 R_indtI! of 􀁾􀁷􀁭b&Mded by 􀀰􀁤􀁍􀁾􀀬􀀠pmjodporJlm {S112,015.00 ${I,oron,.....-swroTAL THlS . """"" 􀁾􀁩,.""", WVIfI3 $11,290,00 $4,280.00 􀁐􀀮􀁲􀁾􀀣􀀹􀀱􀁇􀀱 􀁮􀀬GpfIly thtt 􀀽􀀭􀁾􀁾􀁾􀁾􀁾􀁾􀁾􀀺􀀠 􀀽􀀺􀁭􀁾􀁰􀀡􀁑􀁣􀀽􀁲􀁾􀁾􀁾􀁾􀀠 (S7(I.12IHIC SO,OOPI-. llUIITOT,U 􀁬􀁈􀁬􀁾􀀮􀁬􀁒􀁑􀀱􀁆􀀮􀁃􀁔􀀠S4.l8O,1KI """" Addltk:oMl Flund. 􀀰􀀸􀁊􀁾􀀴􀀱􀀰􀀴􀀠$250:000:00 03J"I1193 $10,500.00...""" "ro",,, S635,52e.00 $5-,525.00 03J14f9G "'''-􀀰􀀴􀀯􀀱􀁾􀀠$86,845.21"',.....,. "',.....,. PlI)1I'I'lIItlIond =oomplllllld.􀁒􀁾􀁬􀁬􀁉􀁭􀁦􀁃􀁭􀁯􀁬􀀠bolllnco per QI "'\lor 11)'21100 $11.1S3.tl1 $158,S40.14 "'" Uso 1M 􀁲􀁯􀁾􀁲􀁡􀁭􀁭􀁏􀁏􀀠I'I'IQl'lllr ..􀁴􀁯􀁡􀁲􀁤􀁾􀁏􀀠_hAbnllOl0 12,... TomR : 􀁒􀁯􀁾􀁭􀀤􀀴􀀱􀀬􀀤􀁓􀀰􀀮􀁏􀁏􀀠 Into 11m Aropui'lo Romt RoAl!IJnmotIl projetl. PtoJIIct to r_tn ekilOO. ($.41.359.8<1 """"" !T.:>Wnof ruklboo rnfuMd forlhhl PI», 􀁩􀁾Ihoo.ho1Ad bo 􀁾􀁭􀁭􀀮􀁭􀁏􀁤􀀠 􀁩􀁾􀁭􀀺􀁾􀁾􀁰􀀶􀀨􀀠1 02H2IOI $212.00 iRo:lpmgmm $212'. I.:> ht'1$> fwd othOf ip!VJilctl pw"2f1l1)1 lowe ()f AtkI/AtkI/ion OZ!tZ}G1 􀁾􀁗􀁲􀁲􀁯􀀺􀁬􀁾􀁾􀁁􀁉􀀠nns vnOIlOC'T 􀀤􀀱􀁾􀀻􀁾, 􀁾􀁾􀁾􀀠 􀁾􀁾􀁾􀀠ENGINl!ERlPlANN!.!R p<>s:mON 􀁉􀁾􀀦􀀧􀀻􀁮􀀠$8;101.00 "-10i$ S(I.,10U')O SO.CO 􀀬􀀬􀁾􀀧􀀢􀀠=, 􀁾􀁮􀁾􀀠"'-sero1JW 􀁾􀀠0$111193 $:)3,1$0.01) $39,466.00 $0.00 􀀬􀁾􀀠 11101100 n,niO,OIl (l2Jll!ft)1 $1,96&.00 􀁩􀀽􀁦􀀺􀀡􀀮􀁾􀀽􀁾􀁾􀀠iPoymool l)QilQ/G1 $I,98EI,QO 􀀱􀀳􀁴􀀬􀀴􀀸􀁟􀀶􀀬􀁾􀀠􀁾􀁾􀁾􀁾i . 􀁾􀁭􀀬􀀮􀀢􀀠"'" '""0"'" -------.. SELT UNElDAllAS NORTH ---------TOLlWAV INTERSECTION Oor.!2fa3 $262,000,(10 P4ymoot 11fOIJOO $13,710..00 $3,&71).00,.",..,.,,,,,'" 1)4/11J95 $120.00 """"" $236,2tU2 􀁾􀁾􀁏􀁾􀁮􀁤ProJu.;t Complel«l pur '0I22l00 ,."...... 04lt41\1(l $6,ltn.za $262,842.00 􀁾􀁾􀁲􀀽􀁾􀁂􀁲􀀺􀁾􀀹􀁉􀁧􀁾􀀠02107/1)1 SS42.00 ""IPSVlnnnl 09110/(11 $S42J)O !·U , " , __ 􀀮􀁓􀁙􀀺􀁾􀀡􀁬􀁾􀀺􀁾􀁾" 􀁋􀁅􀁾􀁌􀁅􀁒􀀠SPRINGSIDAlLAs NORTH -------TOLLWAY INTERSeCTION: 􀀡􀀲􀀲􀀰􀀬􀀱􀁾􀁉􀁕􀀧􀁏􀀠 I- ---ADDISON CAPITAL ASSISTANCE PROGRAM , UPEHDlTURES 􀁾I!XI"£lI)mIRI!s PPEHCllTlJItls UPEHDrru!U!S EXPaItIrTURa 􀁾􀁄􀁉􀁔􀁜􀁉􀁒􀁅􀀮􀁥􀀠E»'ENOITURfS EJl'EHDITURES 􀁾􀀠-,􀁭􀀧􀁾􀀭􀁾􀀠,-, -, ,-, ,-, ..... 􀁾􀀭􀀮DURINO 􀁾􀀠􀁾􀀠􀁾􀀬􀁾􀁾􀁾􀀠-, m" FUND=:YET􀁾􀁣􀁲􀁟􀀠nEPROGRA.IIUED ''''"." ,-􀁾􀀠􀁾􀁾􀀠􀁾􀀠 􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀠􀁾􀀬􀁾􀁭􀀠􀁾􀁾􀁣􀁲􀀠= -Mdrk:nal hnis lransfenn!d from e"R 􀁕􀁮􀁾􀁏􀁉􀀱􀁬􀁦􀁯􀁲􀁴􀀠and Bell Line! Addison Rd. PItIjao:ta 04111195 $tI9,2OS.47 Paymanl 03114100 $232,043.44 paK::nllllnd Project Complelad 10122100 $21,487.03 5295,(130.47 $0.00 Add 􀁮􀁡􀁬􀁬􀁵􀁮􀁤􀁬􀁾􀁰􀁥􀁲􀁔􀁯􀁷􀁮􀁯􀁬􀀠Addison's r.,tter tad 02107101 02/12101 $.276.00 09119101 $275.00 Payment SUBTOTAL 11-rU; PROJECT $295.630.47 ",',' TOLLWAV TO MARSH LANE PHASE I Paymant 02110/04 $255,000.00 $450,105.00 $0.00 Additional funding perTo;rwn of Addlson'.larler dalad 02/07/01 02112/01 $195,105.00 09119101 $195,105.00Paymanl !'lURTOTAT. THIR. PROTECT M50,105.00 SI5.570.00 Paymen1 04/11195 􀀧􀁴􀁉􀁾􀁡􀁮􀁴􀀠 ""',.. $93.958.00 Paymen1 03114196 $16.492.11 $3,123.22􀁾􀀺􀁲􀀧􀀺􀁾􀁾􀁾􀀺􀁾􀁾􀀽􀂷􀁬􀁥􀁴􀁴􀁡􀁲􀀮􀀠 10122100 $129,143.99 SO.OO U .... lho r:1mmmad monrr 􀁡􀁥􀁥􀁯􀁲􀁤􀁾􀀠10 osoluUon #970 72 per Tom fI. om: Ropn;>grom $45,856,01 Into theAnapaho Road Realignmonl project PooJed to romllin 􀁃􀁾􀀨􀀩􀁜􀁅􀁃􀁔􀀠0Q/09/9T 􀁾􀁾􀀺􀁦􀀧􀁊􀁧􀁧􀀠'0"""'􀁾􀁾􀀧􀁆􀁕􀁮􀁤􀀵􀀠 OW13iQ4 sfoo:OOo:oo AddHlonal Funds 10f01194 900,000.00 Paymonl 04/11/95 $184,715.00 03114/00 S9.500.00 􀁌􀁾􀁾􀀧􀁆􀁵􀁮􀁤􀁳􀀠10101195 $620,559.00 Paymant 05120196 $553.492.70 􀁁􀁤􀁤􀁾􀁬􀁯􀁮􀁡􀁬􀀠Funds per ROIIOlutlon 􀁾􀀹􀀷􀀰􀀱􀀷􀀲􀀠 09XJQ/97 S263,I38.22 Tm",,'arrocl $139,170 from tho Mldwal'!'ndborg projeo;l 10 fund this 􀁾􀁁􀁭􀁃􀀺􀀠)proj8CI. per Resolution 91 172 OQ/OOi9T $139.170.00 Tmnslerred $42,075 from the 􀁍􀁩􀁤􀁗􀁡􀁾􀁥􀁬􀀡􀁷􀁡􀁹􀀠projaet 10 fund 􀁴􀁨􀁾 LAmpe )project per R-=olutlon 970172 09/09197 542,075.00 Tronsl8ITod S70.120 lrom tha 􀁍􀁫􀁬􀁷􀁡􀁾􀀢􀀬􀁡􀁮􀁨􀁬􀁬􀁬􀀠pn>ject to fund thls 􀁾􀁾􀁊􀁦􀀱􀀲) project per RasoluLlon OQ/OQ/97 $70,720.00 Conl/nlled on LAPJCMS with e prognunmad amOl/nt ofSIUof,592. 09XJ9I97 Payment 09112197 SI.014.825.oo Tm""fnrlrom eaH Llna/Mamh Ln. project per Rosol. 􀁾􀀹􀀷􀀰􀀱􀀷􀀲􀀠 $41.359.8609'_'􀁾􀁪􀁾􀁥􀁾􀁾􀁾􀁏􀀺􀁆􀁾􀁾􀁏􀁉􀁾􀁲􀁊􀁯􀁵􀁭􀀠 ,....., $45.856.01 TmnsfM from Sldowalk Bus 88f1ch Pads project per Raso1.1I970172 09109197 $3,211.70 Tmnllfer from AddlsonIWaslllrova project per Rasol.1iI970172 09l0Q/97 $13,407.64 $4,162,497.43 $0.00 Paymont 02116100 $2,396,964.73 SUBTOTAL TIllS PROJECT $04.162497.43 AddHlonal Furids 06114194 SSO:OOO:OO Payment 10/04/94 1225.000.00 04112195 S25,000.00 $331,763.00 SO.OO􀁾􀁤􀁾􀀺􀀺􀀧􀁊􀁦􀁾􀁾􀀠􀁐􀁾􀁾 􀁾􀁮􀁭􀁴􀀯􀁡􀁜􀁡􀀩􀀠Addison's lettar'!i'ated 02107101 02/12/01 $81,163.00 09119101 $81,763.00Pllymanl SUBTOTAL iHIS PROTF.CT $331,763.00 ". 􀀮􀁾􀀬􀀮􀁯􀀬􀀮􀀧􀁾􀀮􀀧􀀧􀀧􀀧􀀠S7433 741.00TOTAL DJSBURSEMENrS ALL Y£ARS Pr£IIDI'TI»t!3 􀁾DPeIOfMU:I 􀁾51IP6N1)fJVIIES. ElG'£HIIITlIIIU I!.lI:'PI!.NtII'TI.IUi.!iI 􀁾􀁳􀀠"""',...... -􀁾--, ,." ....." "'" ""'" -"""'" _0 DURING "=" ,􀁾􀀠....... ....... ...... 􀁾􀁦􀀧􀁁􀁉􀁏􀀠􀁾􀁎􀁏􀁔􀁭_U. ....." 􀀭􀁾􀀠REPIIKlGAANalIID 􀁾􀀠􀁾􀀬􀁾􀀠-􀁾􀀠-"'" ...,.. 􀀺􀀺􀁡􀀽􀀺􀀺􀀭􀁾􀁾􀀽􀁾􀀱􀀱􀀱􀀱􀀺􀀺􀀺􀀮􀀮􀁾_ _CIoq; ...IIwI. ""'" ......., ... "''',," -" I,!\pmvllm..nt.) per 􀁾􀁏􀁏􀁏􀀱􀁑􀀴􀀠'''''''' 1534&,000.00-.. ""'." $fiO.l!OO.OO $OO,ZOO.OO 􀁾􀁾􀁾􀁾􀁲􀁾􀁓􀀴􀀰􀀬􀁏􀁏􀁏􀁴􀁯􀀠mn' 􀁷􀁥􀁭􀁑􀁲􀁯􀁾􀀩􀁬􀁬􀀮􀁬􀁭 lntllll!tJClkm 􀀭􀁾􀀠-,,., 0"""" LS:::::::S1JlI'lUTAL TIilS PROrtC't S23tl 000.00 I'ERTtfT.ilJ'fJl.CCOl! PAVEMENT MG.MT. & THOROUGH__ PlAN $18.712,'10 $24,512,00 STAFF SAl.A.I'UES 12itlMSQ $5,6SlUlO Pnljlld 􀁣􀀮􀀻􀁾􀁁􀁬􀀮THIS PROJECT HliOllllO $:l4,157:2.0:0 $24,512.00 "''' HELP FUND $Al...ARYFOR CITY ENGINEER ,"".., SoI,e72.93 $0\,612.93 $4,fl11.ro SO.'". ProJeet 􀁾􀁭􀁰􀀡􀁦􀁴􀁴􀁯􀁤􀀠S 4.S1U13 . M lill" QI,IQI1JI1iMIdway 􀁢􀁬􀀡􀁾􀁮􀀡􀀭PASS PROJECT ,.,""BoIIlJlieJQoorum "''''''' $101,000.00 SO" $161',OOOJ)() Boll. U1elMklwllY ,.,,.. 􀁾􀀺􀀽􀀠.... $lli1.00e.OO Rlghl..-:>f.Wuy ACql.lh\lk)M 1)4111/95 $$5,941.(13 F.,..rn '''B...OTAL THI' ""'lEer {Kt/1G/C11 i4511,(Q,11 S4S2,05iU't 􀀤􀁔􀁮􀁾􀀠., ADolTlOfW. FUNDS 􀀧􀀧􀀧􀀧􀀧􀁾􀀮􀀢􀀧􀀠􀀱􀁦􀁮􀁾􀀱􀀠􀀤􀁾􀁾􀀺􀁾􀀠F,_ 03111103 􀀤􀁾􀁁􀁾􀀺􀁭􀀺􀁾""HKtti83""'''/l'''' $1101lG PP:ljOQt Comp\ellM Uo:Ier Budge! 􀀡􀁬􀀱􀀶􀀱􀀮􀁓􀀴􀀰􀁾􀀠$D.oo and funde truMl1!rod I<> the K!!PCiI' Sprll'l\'l",!N, OIOIkis TokayPm.Ioot '"",.. iS31,(l41.04 􀁾􀁾􀁾􀁾􀁲􀁾􀁾􀁾􀀽􀁾􀀠211ml $3,1lIoI.00 """''' 09119101 ",704.00 SUlMuTAt. TI11$ PROJECT !l101JW&)Q '.".--, ' .",. 􀀢􀀧􀀾􀀼􀁾􀀢􀀠03111193 StEl,'Om.OO 􀁾􀀠OV10Jf1.01 $SII.OO«Z"10<1'. SIiI,lM.eo-W11196 $3,1r12.16 􀁴􀁾􀁷􀁾􀁜􀁏􀁕􀁾􀁾􀁬􀁊􀀡􀁉􀁉􀁡􀁬􀁬􀁤􀀠SpriflgllolN, 0aIIa& Toltf.osy ProJISl "'"",. {S37,25S,1 587,741.83 SMO Town ofAddl\on Rriunded lM'/CMS In 􀁬􀁊􀀬􀀢􀁾􀁭􀁑􀁜􀁉􀁑􀁴􀁯� �􀀤􀁩􀁮􀁍􀀺􀀬􀀠O\Jtofthlt. an!Duni. $1B,il'lQ btI .. ..tund 1Qrlhlt.J:roJ. whlch !ben!lOOUid b6 􀁾􀁾􀁾􀀽􀀽􀁰􀁲􀁯􀁬􀁡􀁤􀁲􀀮􀀠1l2l12f01 $18.610,0(1 􀀽􀁮􀁡􀀮􀀺􀁲􀁾􀀧􀁬􀁾􀀺􀁮􀁮􀀺􀁲􀁾􀁥􀁲􀀠COII'Mpor>dOt'l el'l O2llZXh (S1S.61ILOO SIJSTO'rAL nus PROJECT $&114U3 􀁉􀁾􀁾",1GWl: IMPROIIEMe;I\1!$ ib/WOO: ....""= s:ro.400.00 i􀁾􀁾􀁾􀁾􀀴􀀱􀀹􀀴􀀠10104104 Wl.400,{j(I .." 520,440.00 .',,' Pn:oJed Campildod u...r", 6vdlilol 􀁾􀁾􀁾􀀠􀁾􀀧􀀮􀀧􀁗􀁗􀀠􀁾􀀺􀀳􀀶􀀴􀀺􀀳􀁻􀀩􀀠m,S1UO "'''' 􀁾􀀺􀀧􀁾􀀽􀁾􀀽􀀷􀀲􀀠r TQmR '$$3,2H.ro'lnto11\11 Aropaho R(;ISld fU'l1"nt project. Project to rolTllll" , ,..",., {»'211.10 􀁾􀁲􀀧􀁦􀁵􀁍􀁾􀁰􀁯􀁲􀁔􀁯􀁷􀁮􀁯􀁦fu.on'Q kd.tw 􀀺􀁥􀁤􀁾􀀱􀀱􀀰􀀱􀀠02112/0j Sl,02G.OO Payment 􀁾􀀠TInS PROlECT OQlittlOl $1,Q2e.00 􀀤􀀳􀁓􀀮􀁾􀁗􀀤􀁏􀀠, .. ,It' ::= 􀁏􀁖􀁅􀀬􀀬􀀬􀁾􀀬􀀬� �􀀬􀀮􀀠03J171f13 ....,.""04111/95 $8e,Q5.5.11i1..,.,.. 03(14196 $U,1C3.2:i PaymMlanO project (t)mplWId. 􀁒􀀢􀁐􀀢􀀢􀁉􀁩􀁭􀁭􀁬􀀺􀁷􀁬􀁾􀁰􀁯􀁲􀀰􀁬􀀲􀀷􀀱􀁏􀁏􀀱􀁥􀁴􀁴􀀸􀁲􀀠,...$un.9lo S111,592,30 SO.OO p!ro'EIU)m.lRBtlURIMQ D!.-o _ DUROOl ""'.., $10,630.00 -$l,I'I2S.00 $4,lr;(),OO 􀀺􀁊􀀺􀁴􀁾􀁧􀁧􀀠􀀤􀀵􀁾􀀵􀀢􀁏􀁏􀀠$$Il,e4;S,27 DPtHDr'I'URa eJI'OIDr'I'URa EXKliDntlRES $11,1.5::1.01'''''''' OWOO/01 $&,101.00 􀀤􀀳􀀬􀀱􀁾􀁊􀁘􀁬􀀠"""""" O$(llWt $1;9&6.00 .,.,.., S13,nQ.oot11011fJ3 -am_ $3.sro.oo 0011195 '"• .00 $:2J!!,211."f2:~= 03114100 $6,022.28",""" OZlO1f01 $842.00WIMU ""'" 􀁡􀁾􀀠􀀮􀁾􀀠II II 􀁾􀀠Ii c! 􀁾􀀠i !; 11 • il 8 ! ill S Ii I il􀁾􀀠• III 􀁾􀀠;"•g 􀁾􀀠i gi!j 􀁾􀀠 ----RR Quiet Zones per _1001 IResoluUon #010148 10116101 $695,000.00 SUBTOTAL TlUS PROJECT $695,000,00 _